Top Banner
Front block refurbishment Joe Greenway Projects Manager YOUR LEARNING YOUR COLLEGE
22

Huntingdonshire Regional college Refurbishment

Jul 12, 2015

Download

Education

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Huntingdonshire Regional college Refurbishment

Front block refurbishment

Joe Greenway

Projects Manager

YOUR LEARNING

YOUR COLLEGE

Page 2: Huntingdonshire Regional college Refurbishment

Project Manager ?

• Lecturer in Biology - 1980 to 1992

• Section Leader – 1992 to 1995

• Head of Faculty – 1995 to 2001

• Assistant Principal – 2001 to 2003

• Vice Principal – 2003-2008

• Capital Project Manager(!) 2008 to date

Page 3: Huntingdonshire Regional college Refurbishment

New build?

• One of the 140 colleges in the LSC Capital programme debacle

• Plan to build two new campuses in two new locations for c.£50 M

• Involved acquisition of two new sites, sale of two existing sites as well as two new builds.

• Appointed as CPM in August 2008 with AiPsubmitted to LSC in September 2008

Page 4: Huntingdonshire Regional college Refurbishment

What now?

• Work ceased in March 2009

• Work on an alternative property strategy commenced September 2009

• CPM & Estates Manager met with all departments to ascertain alternatives and priorities (Sept to Nov 2009)

• Senior team proposals grafted to front of departmental suggestions

Page 5: Huntingdonshire Regional college Refurbishment

Current campus

Page 6: Huntingdonshire Regional college Refurbishment

Current Campus

Page 7: Huntingdonshire Regional college Refurbishment

Current campus

• 1963

• Concrete frame with pre-cast aggregate fascia panels

• Crittal windows – single glazed

• Flat roofs

Page 8: Huntingdonshire Regional college Refurbishment

The Alternative Property Strategy

• 12 projects identified for the period 2010 to 2013, to be delivered in 3 phases.

• Financial plan worked out for phases 1 and 2 of c. £7 M.

(no financial plan for phase 3; too far in future)

• Approved by Governors January 2010.

Page 9: Huntingdonshire Regional college Refurbishment

Two strands

• Summer works 2010

• Refurbishment of the front block and external approaches with provisional programme July 2011 to December 2011.

Page 10: Huntingdonshire Regional college Refurbishment

Summer works 2010

• Relocation of IT Services to central part of campus & upgrade of servers

• Conversion of Library to a Learning Resource Centre

• Conversion and upgrading of rooms and two corridors to install new fire exits, cable trays, new lighting, doors etc.

• Re-roofing of two areas.

• C. £1 M

Page 11: Huntingdonshire Regional college Refurbishment

Refurbishment of Front block

• Brief written by CPM, Estates Manager & Principal

• QS from aborted project employed to work out a cost from the brief.

• Value Engineering to bring the cost into budget

• Governor approval to proceed to a Feasibility Study (March 2010)

• Saunders Boston Associates appointed

Page 12: Huntingdonshire Regional college Refurbishment

Artists ImpressionArc

YOUR LEARNING

YOUR COLLEGE

Page 13: Huntingdonshire Regional college Refurbishment

• New Entrance and Reception

• New Admissions and Student Services

• Two new classrooms and 3 new seminar rooms

• Large breakout space and social area

• Refurbished Refectory

• Reorganised frontage and car parking spaces

YOUR LEARNING

YOUR COLLEGE

Consists of:

Page 14: Huntingdonshire Regional college Refurbishment

Feasibility outcomes

• £2.66 M project

• 248 m2 new build and 607m2 refurbishment

• Design development July 2010 to June 2011

• On site July 2011 to December 2011

• Financial plan in place to procure

• Governor approved June 2010

• Tender exercise to appoint Architect and QS

Page 15: Huntingdonshire Regional college Refurbishment

Design Team

• Saunders Boston - Architects

– Cunnington Clark - M & E

– Richard Hermann Associates – Structural

• Davis Langdon – QS, Employers Agent, CDMC

• Procurement by 2 stage Design & Build

– Tender Exercise for contractor appointment August 2010

Page 16: Huntingdonshire Regional college Refurbishment

THE GRANT!

• Timescale! – must be complete by by Sept 2011. Programme changed to Feb 2011 to Aug 2011 on site

• Maximise funding – up to £1 M available– Included 2 of the summer works projects in the

application

– Brought forward kitchen/refectory refurbishment from phase 2

• Application submitted on time

Page 17: Huntingdonshire Regional college Refurbishment

September 2010

• £1 M Grant from SFA

• Appointment of ISG Jackson and main contractor

• SFA ‘budget’ £3.041M

• Project budget £2.7 M

Page 18: Huntingdonshire Regional college Refurbishment

October –December 2010

• Design development

• Decanting plan

• Stage D report inc cost plan

• Stage D Project budget £2.84M

• Contract sum agreed with contractor 22 December

• Final budget £2.82M

Page 19: Huntingdonshire Regional college Refurbishment

What does it look like?

• College web site link:

http://www.huntingdon.ac.uk/

Page 20: Huntingdonshire Regional college Refurbishment

January to February 2011

• Decanting of various college departments

– Senior Executive Team, HR, Finance, Marketing, Print Services, Student Services, Admissions, ALS, Caretakers, Reception

Page 21: Huntingdonshire Regional college Refurbishment

February 2011

• On site 21 February

• Due to handover 26 August

• Up to Easter on programme and on budget

• Now encountered structural issues

Page 22: Huntingdonshire Regional college Refurbishment

College/Contractor web-site

http://www.isgjcommunity.com/huntingdonshire/