Page 1: Humphreys.gary

EVMSThe Principles, Best Practices and Benefits

Gary C. HumphreysHumphreys & Associates, Inc.

NASA PM Challenge 2010

Used with Permission

Page 2: Humphreys.gary

PART 1

Overview, Earned Value Management

1NASA PM Challenge 2010

Page 3: Humphreys.gary

What is EVM?

• Earned Value Management (EVM) is an integrated project management process for assessing, understanding and quantifying what a contractor or in-house project is achieving with program/project dollars

– Integrates technical, cost, and schedule with risk management

– Allows objective assessment and quantification of current project performance

– Helps predict future performance based on trends

EVM is simply good project management!

“Management 101” “EVM 101”

Plan Organize

Organize Plan & Budget

Staff Account for Costs

Direct Analyze

Control Incorporate Changes

2NASA PM Challenge 2010

Page 4: Humphreys.gary

EVM enhances the chances of program/project success

• To Succeed, you must Manage

• To Manage, you must Measure

• To Measure, you must Define

• To Define, you must Understand

So why use EVM?

3NASA PM Challenge 2010

Page 5: Humphreys.gary

NASA EVM Policy & Requirements

• NASA EVM requirements are found in NPR 7120.5, NASA Program and Project Management Processes and Requirements and NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements. Policy is contained in NASA FAR Supplement (NFS) 1834.201. NASA EVM requirements are predicated on the principles and guidelines in ANSI/EIA-748, Industry Guidelines for Earned Value Management Systems.

• NPR 7120.5 requires the project EVM approach to be in place by Key Decision Point (KDP) C (the conclusion of Preliminary Design Review (PDR)) and implemented in Phase C (Final Design and Fabrication) through KDP E [Flight Readiness Review (FRR) or Launch Readiness Review (LRR)].

• Additionally, project performance reporting must begin within 60 days after the start of Phase C. To meet this timeline, it is highly recommended that projects begin implementation planning during Phase B (Preliminary Design and Technology Completion).

4NASA PM Challenge 2010

Page 6: Humphreys.gary

NPR 7120.5 Guidance

• NPR 7120.5 also requires that NASA programs and projects use EVM on projects and contracts that meet the following criteria:

1. For projects with a total anticipated final value of $20 million or more, EVM principles should be applied, as defined by ANSI/EIA-748, Earned Value Management Systems.

a. If the project's primary NASA Center has a validated EVMS, the project uses that system rather than the EVM principles application approach.

2. For development contracts and subcontracts valued at or between $20M and $50M, the contractor is expected to have an EVMS that complies with the 32 guidelines in the ANSI/EIA-748 Standard.

3. For development contracts and subcontracts valued at $50M or more, the contractor is required to have an EVMS that has been formally validated by the Government.

4. EVM is not required on contracts for non-developmental engineering support services, steady state operations, basic and applied research, and routine services such as janitorial services or grounds maintenance services. In these cases, application of EVM is at the discretion of the Program/Project Manager (PM).

• NASA projects that do not have a validated EVMS will use the seven management principles that are contained in ANSI/EIA-748 standard.

5NASA PM Challenge 2010

Page 7: Humphreys.gary

1. Plan all work scope for the project to completion.

2. Break down the project work scope into finite pieces that can be assigned to a responsible person or organization for control of technical schedule and cost objectives.

3. Integrate project work scope, schedule, and cost objectives into a performance measurement baseline plan against which accomplishments may be measured. Control changes to the baseline.

4. Use actual costs incurred and recorded in accomplishing the work performed.

5. Objectively assess accomplishments at the work performance level.

6. Analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and all remaining work that must be performed.

7. Incorporate Earned Value Management in the project decision-making and review processes.

Seven EVM Principles (ANSI/EIA-748-B-2007)

6NASA PM Challenge 2010

Page 8: Humphreys.gary

• Organization (5 guidelines)– Define contractual effort and assign responsibilities for the work. Integrate planning,

scheduling, work authorization, and accounting systems.

• Planning, Scheduling and Budgeting (10 guidelines) – Plan, schedule, budget and authorize the work. Establish and maintain a time-phased

budget baseline.

• Accounting Considerations (6 guidelines) – Accumulate costs of work and material.– Report on progress/accomplishments to date.

• Analysis & Management Reports (6 guidelines)– Compare planned, earned and actual costs, analyze variances. Develop revised

estimates at complete. Identify managerial actions.

• Revisions and Data Maintenance (5 guidelines)– Execute timely incorporation of contractual changes. Maintain traceability from original

budgets.

Guideline Categories

32 EVM Guidelines (ANSI/EIA-748-B-2007)

7NASA PM Challenge 2010

Page 9: Humphreys.gary

Earned Value Management Process

Scheduling & Resource Allocation Systems

Informed ManagementDecisions

Risk Monitoring

AccountingSystem

Technical Performance Measurement

Earned Value Mgmt System(Progress)

Progress

8NASA PM Challenge 2010

Page 10: Humphreys.gary

Features of a “Good” EVM system

• Thorough up-front planning based on a detailed product-oriented Work

Breakdown Structure (WBS), incorporating Risk Management

– Timely Performance Measurement Baseline (PMB) establishment and control

– Information broken down by product, as well as by organization or function

• Objective measurement of technical accomplishment against the plan at

levels where the work is being performed

• Reporting consistency and discipline – a structured process and methodology− Summarized data reporting to higher management (performance metrics) for use

in effective decision making

− Provides for analysis of significant variances and their impact on the project

− Facilitates proper management actions to mitigate risk and manage technical, cost and schedule performance

9NASA PM Challenge 2010

Page 11: Humphreys.gary

PART 2

EVMS Terms and the Performance Measurement Baseline

10NASA PM Challenge 2010

Page 12: Humphreys.gary

Basic EVM Terms

• Budgeted Cost for Work Scheduled (BCWS)– The sum of the time-phased budgets established for all effort (including in-

process work) scheduled to be accomplished within a given time period

• Budgeted Cost for Work Performed (BCWP)– The sum of the time-phased budgets for work actually completed during a

specified time period

– BCWP is the budgeted value for the work actually accomplished

– Earned value can only be determined after the performance (or scheduled performance) of work

• Actual Cost of Work Performed (ACWP)– The costs (taken from the Accounting System) actually incurred (or in some

cases estimated) and recorded, in accomplishing the work performed within a given time period

11NASA PM Challenge 2010

Page 13: Humphreys.gary

• Budget At Completion (BAC)– The budgetary goal (excluding MR) for accomplishment of all authorized work

• Estimate At Completion (EAC)– Actual direct and indirect costs allocable to the contract, plus the estimate of all

costs for authorized work remaining

– Estimated cost to complete the entire project scope of work

– Supported with a rationale

– Best case, worst case, most likely

Basic EVM Terms (continued)

12NASA PM Challenge 2010

Page 14: Humphreys.gary

• Total Allocated Budget (TAB)– Total Allocated Budget is the sum of all budgets allocated by the contractor

against which contract performance is to be measured and reported

• Contract Budget Base (CBB)– Contract Budget Base is the negotiated contract cost plus the estimated cost of

authorized unpriced work

• Authorized Unpriced Work (AUW)– Contract work authorized by the contracting officer, not yet negotiated, aka not

yet definitized work

Basic EVM Terms (continued)

13NASA PM Challenge 2010

Page 15: Humphreys.gary

Contract Price (Project Price)

Total Allocated Budget (TAB) Contract Fee/Profit

Contract Budget Base (CBB) or Project

Budget Base (PBB)

Authorized Unpriced Work (AUW)

Performance Measurement Baseline (PMB) Management Reserve (MR)

Over Target Baseline (OTB)

Distributed Budget Undistributed Budget (UB)

Control Account (CA) Summary Level Planning Package (SLPP)

Work Package (WP) Planning Package (PP)

Contract/In-house Project –PMB Relationship

MR – Held for known unknowns but in-scope future effort. Not used to cover cost overruns.

UB – Temporary holding place for allocation to control accounts not to exceed two accounting periods following negotiations.

Total of all authorized work, both negotiated and un-negotiated

The total is also called Budget at Completion (BAC)

14NASA PM Challenge 2010

Page 16: Humphreys.gary

The Performance Measurement Baseline (PMB) –Is all the work planned?

• A time-phased budget plan against which contract performance is measured

• Developed by the contractor and jointly reviewed with the customer within six months of contract award

• Based on the anticipated flow of work and outcomes• Incorporates dynamic, authorized project changes

What is the PMB?

15NASA PM Challenge 2010

Page 17: Humphreys.gary

Establishing the PMB is a 3-step process:

PMB Development

1. DEFINE THE WORK

2. SCHEDULE THE WORK

3. ALLOCATE BUDGETS100

40

60

15

25

3030

$

CONTRACT BUDGET BASE

MR

TIME

PMB – Time-phased, budgeted plan where contract performance can be measured.

• Statement of Work (SOW)• Work Breakdown Structure (WBS)• Organizational Breakdown

Structure (OBS)• Responsibility Assignment Matrix

(RAM)

• Work Authorization System • Control Account Plan (CAP)• Work Packages (WP) &

Planning Packages (PP)

Integrated Master Schedule (IMS)• Master Schedule• Intermediate Schedule• Detailed Schedules

16NASA PM Challenge 2010

Page 18: Humphreys.gary

Work Breakdown Structure (WBS)

• A product-oriented hierarchical division of the hardware, software, services, and data required to produce the project’s end product(s)

• Should not be functional or organizational oriented• Should reflect the total project scope of work• Structured according to the way the work will be performed• Reflects the way in which project costs, schedule, technical and risk data

are to be accumulated, summarized, and reported• WBS is the most important data item in defining and controlling the

contracted technical scope• Summary level WBS must be the sum of all lower level WBS hierarchical

in nature• Supports historical cost collection necessary for future costing activities of

similar scoped products

“It’s the WHAT that is Going to Be Done”

17NASA PM Challenge 2010

Page 19: Humphreys.gary

Properly Structured WBS

Product Oriented

Standard Level 2’s

Clear WBS Titles

Center Breakout at Appropriate Level

18NASA PM Challenge 2010

Page 20: Humphreys.gary

Responsibility Assignment Matrix (RAM)

The Responsibility Assignment Matrix (RAM) Integrates WBS with OBS. The intersecting points are the Control Accounts.

CA

1.0

1.1 1.2 1.3

1.1.1 1.1.2 1.1.3 1.1.4

1.1.2.1 1.1.2.2 1.1.2.3 1.1.2.4 1.1.2.5

Elec

Mec

hSW

ENG

Contract Work Breakdown Structure (WBS)

Org

aniz

atio

n B

reak

dow

n St

ruct

ure

(OB

S)

Work Packages

RAM

Control Account• Task Description• Perform. Measure• Work Authorization• Cost Accumulation• Work Package, Schedules,

& Budget

WBS Reporting Level

CWBS Extension

Func

tiona

l Org

19NASA PM Challenge 2010

Page 21: Humphreys.gary

Control Account (CA)

• The CA forms the hub of the technical, cost and, schedule management focus

• Virtually all elements of planning and control come together at the CA level including work authorization, schedules, budgets, earned value, cost collection (actuals), problem identification/variance analysis and estimate to complete

• Consists of:– Work Packages (WPs) – near term work that is well defined.– Planning Packages (PPs) - more far term effort used for budgeting and

scheduling purposes. A vehicle for planning at a higher level when details may not yet be well defined. Planning packages must also reflect horizontal integration with assignment of predecessors and successors.

• SCOPE• SCHEDULE• BUDGET

Control Account BUDGET – 150

1010

1520

20WORK

PACKAGES

PLANNING PACKAGES

4530

20NASA PM Challenge 2010

Page 22: Humphreys.gary

• Using the WBS:– Develop a logic network schedule for all contractual activities, including

technical performance parameters/outcomes

– Scheduling is a process of changing work scope into defined tasks:• WBS oriented• Defined time duration (phased over the total life of the program)• Logically connected to all other related tasks

– Determine resources required to complete scheduled activities• Labor

– Direct Labor– Civil Service Labor (when applicable)– Support Contractors

• Material• Contracts/Subcontracts• Other Direct Costs• Indirect Costs

Schedule Development

21NASA PM Challenge 2010

Page 23: Humphreys.gary

Horizontal & Vertical Schedule Integration (VSI)

The Scheduling System: Consists of an integrated, multi-tiered hierarchy of schedule levels. With a complete Logic Network Schedule, the time-phased PMB will be accurate, allowing for the identification of the true critical path(s).

Master Schedule(Contract Summary)

Intermediate Schedule(Logic Network

Schedule)

Detailed Schedules(Control Accounts)

VER

TIC

ALIN

TEG

RAT

ION

HORIZONTAL

INTEGRATION

INTEGRATED MASTER SCHEDULE (IMS)

22NASA PM Challenge 2010

Page 24: Humphreys.gary

Schedule Considerations

• Is the schedule logic (activity sequence) established and valid?• Are the schedule milestones compatible with the schedule logic?• Is the critical path analysis valid?• Are durations reasonable compared with other project’s history?• Are resources used to their maximum?• Are parallel activities reasonable or risky, i.e., flight hardware being

built before qualification is complete?

23NASA PM Challenge 2010

Page 25: Humphreys.gary

• Is the plan fully defined?

• Is the plan realistic?

• What are the risky areas of the plan?

Understanding the Baseline

How can we understand and assess inherent risk in the plan?

24NASA PM Challenge 2010

Page 26: Humphreys.gary

• How is Earned Value determined?

– When planning work three basic classifications are used:• Discrete Work – Definable end product• Level of Effort (LOE) – End product not defined• Apportioned Effort – Budgeted based on a percentage of another (base)

related task (e.g., Quality Assurance)

– Earned Value must be taken in the same manner in which the work was planned

Determining Earned Value

25NASA PM Challenge 2010

Page 27: Humphreys.gary

Discrete Earned Value Techniques

Milestone

• Identifiable milestone

• Milestone weighting should correlate to the resources required to accomplish the task –1 milestone per month

• 3 or more accounting periods

Percent Complete

• Least desirable

• Somewhat subjective

• If used, apply quantitative back-up data

50/50 Method

• No more than 2 accounting periods

• 50% EV at start

• 50% EV at complete

0/100 Method

• 1 accounting period

• No EV at start

• 100% EV at completion

26NASA PM Challenge 2010

Page 28: Humphreys.gary

• Work that is dependent on or related to the performance of other discrete effort in direct proportion (i.e., Quality Control effort in production)

• Percentage and base task must be identified

• Take the percentage of the AE for the base task, and that is what is earned

Earned Value Techniques

Apportioned Effort (AE)

Production Effort

Inspection Effort

27NASA PM Challenge 2010

Page 29: Humphreys.gary

• Contract effort that does not produce any definable end product(s)– General or supportive activities; i.e., management, administrative, etc.

• Used when no other EV method is applicable

• Over-use will distort project performance measurement

• Budget is spread over the scheduled period of performance

• Value of work is earned based on passage of time

• Planned Work Budget (BCWS) = Earned Value (BCWP) – Never a Schedule Variance

Level of Effort (LOE)

Earned Value Techniques

28NASA PM Challenge 2010

Page 30: Humphreys.gary

Characteristics of a “Good” Milestone

• Tied to a specific product or event

• Within the authority of the person who will perform the work

• Clear, objective criteria for measuring accomplishment

• Directly related to the control account statement of work

• Weighted in relationship to the time-phased budget

• Expressed in calendar dates and identified to control account and

summary schedules

29NASA PM Challenge 2010

Page 31: Humphreys.gary

What are some potential causes of deviations from a Project Plan?

• Poor beginning estimates

• Poor understanding of requirements

• Lack of risk assessment/planning

• Requirements creep

• Poor management

• Unforeseen technology difficulties

• Jumping to conclusions about causes

30NASA PM Challenge 2010

Page 32: Humphreys.gary

• Estimate At Completion (EAC)– Actual direct and indirect costs allocable to the contract + the estimate of all

costs for authorized work remaining, or Estimate to Complete (ETC).

– Estimated cost to complete the entire scope of work

– Supported with a rationale

– EAC trends usually do not reverse

– Best case, worst case, most likely required in the CPR

• Comprehensive Estimate at Completion

– Bottoms-up estimate reviewing all remaining work and a thorough estimate of that work

– Required annually

Future Performance Predictors

31NASA PM Challenge 2010

Page 33: Humphreys.gary

EVM - Key Data Elements

Actual Cost Actual Cost of Work Performed (ACWP)

Performance MeasurementBaseline (PMB)

Budget atCompletion (BAC)

$ Planned ValueBudgeted Cost for Work

Scheduled (BCWS)

Earned Value (Accomplished)Budgeted Cost for Work Performed

(BCWP)

Estimate At Completion (EAC)

Estimate to Complete (ETC)

Time Now

Contract or Project Budget Base

Management Reserve (MR)

CompletionDate

CostVariance

ScheduleVariance

StartDate

Variance atCompletion

For ProjectedSlippage (check

schedule)

OverBudget

32NASA PM Challenge 2010

Page 34: Humphreys.gary

PART 3

Performance Reporting, Variance Analysis and Data Usage

33

NASA PM Challenge 2010

Page 35: Humphreys.gary

• First we need to analyze current trends (current performance indicators)– What are our problem areas?

– What are the causes of our problems?

• Forecast the future based on performance to date– How can we stay on plan?

– What are the impacts to the project?

– Any technical, cost, or schedule surprises?

– When will we finish all the work?

– What is the estimated cost at completion?

– Is it achievable?

• Indicate areas for management action– What should we do now to mitigate problems?

Where are we headed?

34NASA PM Challenge 2010

Page 36: Humphreys.gary

Project Data Trace (Storyboard)

Page 2 Organizational Owner

WBS #

Pro

ject

M

anag

er

Req

uire

men

ts

Des

ign

Dev

elop

men

t

Test

Pac

kagi

ng

Tech

nica

l S

uppo

rt

1.2.7 x1.2.8 x1.2.9 x1.3.1 x1.3.2 x1.3.3 x1.3.4 x1.3.5 x1.4.1 x1.4.2 x1.4.3 x1.4.4 x

IMS(Resource Loaded)

WBSDictionary

wInsight

Mgmt Reporting & Data Analysis

Planned(BCWS) &

Accomplished (BCWP)

Actuals(ACWP)

SOW

WBS

OBS

Time / AccountingSystem

RAM

CAPs

WAD

CPR

EVMSystem

XML

Contractor Example

35NASA PM Challenge 2010

Page 37: Humphreys.gary

• Cost Variance (CV): The difference between BCWP and ACWP

– CV = (BCWP - ACWP)– Favorable is positive (Cost underrun)– Unfavorable is negative (Cost overrun)

• Cost Variance Percent (%): The CV divided by the Earned Value times 100

CV% = (BCWP - ACWP)

• Schedule Variance (SV): The difference between BCWP and BCWS– SV=BCWP-BCWS

– Favorable is positive (Ahead of schedule)

– Unfavorable is negative (Behind schedule)

• Schedule Variance Percent (%): The SV divided by the BCWS times 100SV% = (BCWP - BCWS)

Variance Calculations

BCWPX 100

BCWSX 100

36NASA PM Challenge 2010

Page 38: Humphreys.gary

• Variance at Completion (VAC): The difference between BAC and EAC– VAC = BAC - EAC

– Compares what the work was budgeted (BAC) to what it is currently estimated to cost (EAC)

– Favorable is positive (Forecasted under run)

– Unfavorable is negative (Forecasted over run)

• Variance at Completion Percent (%): The VAC divided by the BAC times 100

Variance Calculations (conclusions)

BAC X 100VAC % = VAC

37NASA PM Challenge 2010

Page 39: Humphreys.gary

─ A clear explanation of the cause

─ A comprehensive impact assessment

─ A corrective action plan

─ A revised Estimate at Completion (EAC)• Cost

• Schedule

Variance Analysis Objectives

38NASA PM Challenge 2010

Page 40: Humphreys.gary

“Root Causes” of Cost Variances

Cost Variance

Labor

Material &

Equipment

Other Direct Cost

(ODC)

Rate Variance(Earned Value-Actual Rate) x Actual Hours

Usage (Efficiency) Variance(Earned Hours – Actual Hours) x Earned Rate

Price Variance(Earned Price – Actual Price) x Actual Quantity

Usage Variance(Earned Quantity – Actual Quantity) x Earned Price

Price Variance(Earned Price – Actual Price) x Actual Quantity

Usage Variance(Earned Quantity – Actual Quantity) x Earned Price

39NASA PM Challenge 2010

Page 41: Humphreys.gary

Analysis Considerations

Favorable and unfavorable variances should be carefully evaluated. The project analyst should examine and understand the reasons for underruns, as well as overruns because they could be masking a serious problem.• Establishing Thresholds for Reporting and Analysis

– Establish threshold reporting based on risk and tailored to WBS by specific dollar amount and/or variance percentage

– Identification of threshold reporting should also consider program phase, risk and WBS criticality • Good Variance Analysis Identifies

– The Problem – Cause of the Problem – Impact to the Program (Cost, Schedule and Technical) – Corrective Action – Get well date

• Areas to Address– Poor initial planning or estimating – Technical breakthroughs or problems – Cost (or usage) of labor, material, or Other Direct Costs higher or lower than planned – Inflation and new labor contracts – Front-end loading

• Reconciliation Analysis– Other budget/funding documentation – Labor resource planning documentation – Schedules

40NASA PM Challenge 2010

Page 42: Humphreys.gary

EVM Reporting

Contains Five Reporting Formats:

• Format 1 – Work Breakdown Structure

• Format 2 – Organizational Categories

• Format 3 -- Baseline

• Format 4 – Staffing

• Format 5 – Explanations and Problem Analysis– Total contract

– Cost & schedule variance analysis

– Other analyses (6 topics)

– OTB & OTS (as applicable)

Contract Performance Report (CPR) - Required EVM data report on contracts where full EVMS compliance is required

41NASA PM Challenge 2010

Page 43: Humphreys.gary

• Cost Performance Index (CPI): The average cost efficiency with which work has

been performed to date

– Formula: CPI = BCWP / ACWP

– If CPI > 1.0, Effort is under-running budget

– If CPI < 1.0, Effort is over-running budget

• Schedule Performance Index (SPI): The ratio of the budgeted value of work performed to the budgeted value of work scheduled

– Formula: SPI = BCWP / BCWS

– If SPI > 1.0, Effort is ahead of schedule

– If SPI < 1.0, Effort is behind schedule

– Is only an indicator

– More important early in the project

Performance Indicators

42NASA PM Challenge 2010

Page 44: Humphreys.gary

Current Status Indicators

• How much of the program SHOULD have been accomplished at this point?– Percent Scheduled = (BCWS / BAC) X 100

• How many of the forecasted funds have been SPENT at this point?– Percent Spent = (ACWP / BAC) X 100

• How much of the program has been ACCOMPLISHED to this point?– Percent Complete = (BCWP / BAC) X 100

• What is the budgeted value of the work remaining?– Work Remaining = BAC - BCWP cum

43NASA PM Challenge 2010

Page 45: Humphreys.gary

• To-Complete Performance Index (TCPI):

– Cost (CPI) efficiency required to complete the remaining work

– TCPIEAC= (BAC-BCWP) / (EAC-ACWP)

• Performance Indicator Comparison

– CPI versus TCPI– Cost efficiency to date compared to cost efficiency to complete the

work remaining

– Note spread point when more than 20% complete

– Thoroughly evaluate all point degradations, e.g. 1.42 versus .67

– Very helpful in reviewing EAC rationales

Performance Forecasting

44NASA PM Challenge 2010

Page 46: Humphreys.gary

Independent Estimate At Completion (IEAC)

• There are many ways to calculate an IEAC

• An example: Independent Estimate At Completion (IEAC)

– IEAC = Actuals + (Work Remaining/Performance Factor)

• EAC = ACWP + [(BAC-BCWP)/Performance Factor]

– SPI as an indicator of EAC is better in first 50% (early stages) of a project

– There is no substitute for GOOD program information

• Common Performance Factors

– Cost Performance Index (CPI)

– Schedule Performance Index (SPI)

– WEIGHTED (80/20 or some other ratio)

Future Performance Predicators

45NASA PM Challenge 2010

Page 47: Humphreys.gary

Using EVM Data as a Predictor *

• When a contract is more than 15% complete & more than 10% over-run:– The over-run at completion will be more than the over-run incurred to date

• The final cost variance (in dollars or as a percentage) will be worse than

the cost variance at the 20% completion point.

* Based on OSD database of more than 500 major DOD contracts since 1977

46

NASA PM Challenge 2010

Page 48: Humphreys.gary

PART 4

Summary

47

NASA PM Challenge 2010

Page 49: Humphreys.gary

EVM Process Overview

Define the Work Plan the Work Collect Results

Measure Workin Process

Analyze Variances

Internal ChangesExternal Changes

Change Control

Changes

Risk?

Work the Plan

Implement CorrectiveActions

(Earned Value)

An iterative process used throughout the life of a contract.

PMB

(Schedule/Budget)

48NASA PM Challenge 2010

Page 50: Humphreys.gary

• Provides Project Management with objective, accurate and timely data for effective decision making (much more than plan versus actuals)

• Early warning of issues

• Allows more efficient use of management resources, by identifying and

focusing on problem areas

– Detail planning at levels where work is performed allows management attention

to be directed to areas where significant problems are indicated

• Provides better capability to trace problems to their source

• Provides better historical performance data

• EVM is an “Industry Best Practice” for project management (ANSI/EIA-748 – Earned Value Management Systems)

Benefits of using EVM

49NASA PM Challenge 2010

Page 51: Humphreys.gary

Conclusions about EVM

• An integrated management process for gaining valuable insight into project performance.

• Only management process that effectively integrates technical, cost, schedule and risk.

• Provides valuable quantifiable performance metrics for forecasting at-completion cost and schedule.

• Promotes early visibility to cost and schedule variance sooner than any other practice---reduces the ‘shock syndrome’

• Focuses on significant technical, cost and schedule problems---avoids swatting mosquitoes while the elephants charge on by

• Establishes funding authority’s confidence in program management

50NASA PM Challenge 2010

Page 52: Humphreys.gary

Questions?

51NASA PM Challenge 2010