Top Banner
Arlington Parks & Recreation August 12, 2013 Hugh Smith/East Arlington Library Assessment
8

Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Jan 11, 2015

Download

Education

Buddy Blue

 
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Arlington Parks & Recreation

August 12, 2013

Hugh Smith/East Arlington Library

Assessment

Page 2: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Budget: $130,000 2008 Bond Funds

Page 3: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Purpose of the Project

• Condition assessment for Hugh Smith• Programmatic assessment for both facilities• Evaluation of site alternatives• Feasibility of co-locating facilities • Evaluate alternatives for senior services• Identification of aquatic needs

Page 4: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

History of Facilities

Hugh Smith Recreation Center & Pool

• Originally built in 1963 by the YMCA• Transferred ownership to city in 1972• 25,000 SF two story building• 25 yard, 5 lane pool

Page 5: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

History of Facilities

Senior Center

• Constructed in 1994• 10,000 SF building

East Arlington Library

• Opened in 1970, first branch library• In 2000 renovated/expanded building to10,000 SF

Page 6: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Status Update

• Architect has completed a visual assessment of buildings

• Council approval of 14 member citizen committee 6-18-13

• First committee meeting held July 30th

• First public meeting held August 3rd • Architect compiling information from public

meeting

Page 7: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Schedule

2nd Committee Workshop    August 28, 2013 2nd Public Meeting Sept 7, 2013Review of Design Options  Sept 10-18th

City Council & Park/Library Board Committee    October 1-22nd

3rd Committee Workshop     October 29, 2013 City Council & Park/Library Board approval November 1 - 28th

Draft Report December 4, 2013Final Report                        February 5, 2014 

Page 8: Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

Questions?