7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
1/62
1
EIE 329 E-TOOL
FINAL REPORT
Distributed to EIE-agency and E-TOOL partners
Legal disclaimer:
The project Energy-toolset for improving the energy performance of existing buildings (E-TOOL) is supported by the European Commission through theIntelligent Energy Europe Programme (Grant agreement number EIE/04/239/S07.38676). The sole responsibility for the content of this publication lies withthe authors. It does not necessarily reflect the opinion of the European Communities. The European Commission is not responsible for any use that may bemade of the information contained therein.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
2/62
2
LIST OF CONTENT
1 Summary............................................................................................................................................32 Objectives...........................................................................................................................................63 The scope of the project report...........................................................................................................64 The project partners............................................................................................................................75 Project flow chart...............................................................................................................................96 Tool configuration............................................................................................................................117 Description of the E-TOOL software...............................................................................................118 Bench marking of the energy consumption......................................................................................159 Accessibility of the input data..........................................................................................................16
10 Energy saving measures...............................................................................................................2011 Top 10 energy saving measures in 6 EU countries...................................................................2712 Investment costs of energy saving measures................................................................................2813 Energy performance (bench mark) after energy retrofitting........................................................3414 Quality of the E-TOOL rating......................................................................................................4115 Accuracy of results - questionnaire..............................................................................................4416 Description of the contribution to advancement on the state of the art........................................4617 Feasibility and impact of E-TOOL...............................................................................................46
17.1 Feed-back from workshops, training seminars........................................................................4717.2 Feed-back from the market actors............................................................................................4817.3 Training/instruction for using E-TOOL ...................................................................................48
17.4 Time required for completing the carry out E-TOOL certification.........................................4917.5 Reproducibility.........................................................................................................................5017.6 Comparison of rating methodologies E-TOOL operational rating to assessment rating.........50
18 Support of the implementation of energy savings in building by E-TOOL energy rating...........5118.1 Criteria for the evaluation of the implementation....................................................................5118.2 Acceptance of results by clients...............................................................................................5218.3 Accuracy of the results.............................................................................................................54
19 Overall evaluation of E-TOOL for energy rating.........................................................................5520 E-TOOL energy rating - discussion and recommendations.........................................................5821 Reduction of barriers and support to policy implementation.......................................................5922 Resume of achieved results..........................................................................................................59
23 Lessons learned............................................................................................................................6124 Recommendations........................................................................................................................61
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
3/62
3
1 Summary
Operational rating of the energy performance of existing buildingsThe overall objectives of the proposed action is to promote the implementation of the EU building performancedirective (2002/91/EF, 16th December 2002) by developing a simple and practical energy-toolset, which on aEuropean level can support the implementation of the directive in relation to existing domestic, commercial andpublic buildings.
The E-TOOL project developed a simple and practical "E-TOOL", which can increase the efficiency of energyperformance rating of existing buildings. The criteria for developing E-TOOL are:
Energy certification shall be carried out within 2-3 man hours; The results of the energy certification shall be communicated at the survey to the house owners in an
easy understandable way.
The E-TOOL shall efficiently support the energy consultants in making the energy performancecertificates.
The E-TOOL
The input data for E-TOOL are: General data of the building, owner, type etc. - energy consumption data -general characteristics of the building, including: Heating, cooling, domestic hot water system, lightning andthermal envelope.
For out put data, see below:
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
4/62
4
E-TOOL can be down loaded from: www.e.tool.org, including the E-TOOL handbook.
Testing the E-TOOL
The evaluation criteria for the regional testing of E-TOOL were: User friendliness (functional aspects) of the tool- time required completing the rating and clients report - acceptance of the results by client - accessibility of thedata needed for the tests - improvements to the tool (with respect to local building practice and climate).
The tests were carried out for: Slovenia, 500 residential buildings and 50 public buildings - Bulgaria, 600residential buildings - Greece,100 public buildings - Austria, 50 commercial buildings - Spain,100 publicbuildings - Denmark, 1.000 residential buildings.
Evaluation criteria Results "Mark"
Bench marking of energy
consumption
Specific benchmark data are in general not available,
therefore benchmarking is not implemented in the E-TOOL
rating.
To be
improved
Accessibility of input data Positive feed-back AcceptableGuidelines for energy saving
measures
Top 10 energy measures identified, U-values etc. are fixed,
output for investment costs and energy savings acceptable
for standard buildings
Good for
typical
buildings
Energy performance after
implementing energy savings
Acceptable results when comparing with energy audits Acceptable
Accuracy - compare with energy
audit
Acceptable for energy saving measures and energy
performance after implementing energy saving measures
Acceptable
Need of education Small need of education Good
Time required Around 2/3
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
5/62
5
Accuracy of results 80% good/acceptable. Acceptable
The operational energy rating, e.g. E-TOOL rating, could be the optimum rating, providing theobjective is cost efficiently to identify potential energy saving measures.
The best results with E-TOOL rating are achieved on buildings with regular structure and where thedata are transparent and representative.
Impact of operational rating of the energy performance of existing buildings
With a limited input of resources it has been possible to develop the E-TOOL to a level, where it hasgot positive evaluation results, e.g. on users acceptance of the results.
The experience has shown that 90% of the on-site ratings can be performed within 1-2 hours withacceptance of the results from 60% of the clients.
With the combination of measured energy consumption and a simple rating tool, the rating can beperformed by experienced persons after short training in the use of E-TOOL.
The results from the workshops carried show that the among market actors, there is a interest for the E-TOOL being seen as an efficient tool to support the implementation of energy saving measures in theexisting building stock.
The E-TOOL project has experienced a large difference in access to transparent and reliable buildingdata in the European countries, from regions with almost zero data to regions with high valuable data.
Recommendation for European energy performance ratingIs it recommended to introduce both an operational tool and and calculated rating tool in the nationalcertification scheme and then leave it to the experts to decide or set up some rules for which rating toolto use under particular conditions.
The partners
Naturgas Midt-Nord DK), energy supply company, (Coordinator). CENER, Centro Nacional de Energas Renovables (ES), scientific institution.
Upper Austria Energiesparverband (AU), regional energy agency. Thessaloniki Metropolitan Development Agency, Natural Gas of Macedonia S.A.(GR), regional publicauthority.
SIGMA Consultants Ltd (GR), private consultant company. Building and Civil Engineering Institute ZRMK (SI), research institute. Sofia Energy Centre (BU), private consultant company. Deuca Energia S.L. (ES), private consultant company.
For more information:www.e.tool.org
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
6/62
6
2 Objectives
Overall objectives on European level
The overall objectives are to promote the implementation of the EU building energy performancedirective (2002/91/EF, 16th December 2002) - with focus on developing an operational and simple toolwell suited for practicable application - with the energy consultants as the main target group. Theseobjectives have within the project been translated into:
Energy certification shall be carried out within 2-3 man hours
The results of the energy certification shall be communicated at the survey to the house ownersin an easy understandable way.
The E-TOOL shall efficiently support the energy consultants in making the energy performancecertificates.
Specific objective of the E-TOOL project
The energy-toolset was developed with a special focus on buildings in the southern/south-eastern part
of the Europe Union.
The E-TOOL project developed a simple and practical toolset, with the purpose of increase theefficiency of energy performance rating of existing buildings. The saving measures were calculated onthe basis of the actual energy consumption operational rating and on basis of benchmarks for energyconsumption for different categories of buildings.
3 The scope of the project report
This report is supported by the Intelligent Energy Europe (IEE-2004/239)-project, E-TOOL (Energy-toolset for improving the energy performance of existing buildings) is to be considered as a stand-aloneand result-oriented report. The main project results are described as well as the lessons learnt and themain results that have been achieved. The scope of the final report therefore is therefore to describe,how the E-TOOL supports the improvement of the energy performance of existing buildings, referringto the results of the project.
The general guideline of the methodology that has been applied, for the E-TOOL-rating of energyperformance is based on the methodology of measured (operational) energy rating. In contrast, otherrelated projects are based on the methodology of calculated (asset) energy rating.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
7/62
7
The energy performance certification is being implemented all over the EU. In this context, the resultsand findings of this report are important and to be considered in the perspective that this project andresults are based on measured energy rating. The results are recommended to be taken into account inimplementing at the EU-level, the energy performance building directive.
The background for carrying through the project under the coordination of the Danish Naturgas Midt-Nord is in particular the experience from the Danish energy performance certification system, based onthe methodology of calculated energy rating, and the energy supply companies experience with energyrating of existing buildings using the measured energy methodology.
Based on these experiences, it was determined that the calculated energy rating is costly and has notproved to have the expected effect in terms of documented implementation of rational use of energy inexisting buildings. In contrast, the measured energy rating methodology has shown to be cost efficientand to support rational use of energy in existing residential buildings.
4 The project partners
The proposed action is covering main parts of Europe: The north (Denmark), the south-west with arelatively wealthy region (Spain), the middle-central (Austria) and the south-east (Greece, Slovenia andBulgaria) and by that has a European dimension. The proposed action can give a substantial support tothe implementation of the EU Building Directive on a European scale. The partners cover thesedifferent regions of Europe and different types of relevant experience and know how:
Partner Name Acronym Activity Country1 Naturgas Midt- Nord NGMN Energy supply company Denmark2 Fundacin Cener-Ciemat CENER Scientific institutions Spain3 Ober-sterreich Energiesparverband ESV Regional/local authority Austria4 Thessaloniki Metropolitan Development Agency TMDA Regional/local authority Greece5 Sigma Consultants Ltd SIGMA Consultants - Energy experts Greece6 Sofia Energy Centre SEC Scientific institutions Bulgaria7 Building and Civil Engineering Institute ZRMK Scientific institutions Slowenia8 Deuca Energia DEUCA Consultants - Energy experts Spain
Figure 1: Project partners
The partners can be described briefly as follows:
Partner 1: Naturgas Midt/Nord (Denmark)
Naturgas Midt-Nord (NGMN) is a public owned gas utility, owned by 74 municipalities in the Northernpart of Denmark.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
8/62
8
Partner 2: Cener (Spain)
CENER is the Renewable Energy National Centre of Spain. It is a technological centre oriented andspecialized in renewable energies. CENER is integrated in the CENER-CIEMAT Foundation.
Partner 3: Upper Austria Energiesparverband (Austria)
O.. Energiesparverband (ESV) is the regional energy agency of Obersterreich/Upper Austria, anindustrial region in the Northern part of Austria.
Partner 4: Thessaloniki Metropolitan Development Agency (Greece)
Thessaloniki Metropolitan Development Agency Natural Gas of Macedonia S.A. (TMDA NGM) isan Intermunicipal Public Commercial Organisation whose shareholders are the Municipality of
Thessaloniki and the Municipalities of the widest region of Thessaloniki
Partner 5: SIGMA (Greece)
SIGMA Consultants Ltd (SIGMA) is an engineering and consultancy firm with a long standing activityin the Greek and European market.
Partner 6: Building and Civil Engineering Institute ZRMK (Slovenia)
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
9/62
9
Building and Civil Engineering Institute ZRMK, l.t.d., Ljubljana, Slovenia, (short name BCEI ZRMK)is a daughter company of ZRMK Holding, j.s.c., founded in 2003 for R&D and consultancy in buildingand civil engineering.
Partner 7: Sofia Energy Centre (Bulgaria)
Sofia Energy Centre (SEC) has been established as a successor of EC (DG XVII) Energy Centre Sofiaand it has gained a lot of experience in the field of promotion, dissemination and market penetration ofnovel EU energy technologies in Bulgaria.
Partner 8: Deuca Energia S.L. (Spain)
The Spanish Company is constituted in Girona in 1996 as Engineering and Consultancy Company.
Main activities are in the planning, promotion and realization of energy projects.
5 Project flow chart
The following flow-chart represents the different tasks that have been completed within the E-TOOL
project.
Data collection: Necessary to obtain all input data for energy consumptions, prices and buildingcharacteristics
Tool Development: Based on the requirements of the data collection, the tool was developed with theresult of the energy consumptions before and after the implementation of the energy saving measures,pay-back times, investments, CO2 savings and a certificate.
Test preparation: Important step for the application of the tool, including training of energy auditors.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
10/62
10
Regional testing and evaluation: Testing of different kind of buildings (public, private, hotels, ..) in thedifferent partner countries and evaluation of the tests
Handbook: Guide for users and energy experts with indication of the practical aspects of the tool.
Dissemination: Inform about the project results on workshops, training seminars, conferences,
Homepagewww.e-tool.org.
Data collection Tool development
Regional testingand evaluation
Handbook Dissemination
Preparation oftesting
Figure 1: Project structure
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
11/62
11
6 Tool configuration
Through the description of the E-TOOL configuration is it the intention to give an introduction and
overview of how the E-TOOL works, the main components of the tool - and to evaluate, based on the
findings of the project, if E-TOOL elements work accordingly to, what is the intention.
The E-TOOL consists of 3 main components, which will be described and evaluated:
Bench marking of the energy (heating/cooling) consumption of different main buildingcategories.
Guidelines for typical energy saving measures, including cost estimations and pay-back-time.
Output in terms of energy consumption after carrying out the proposed energy saving measures
E-TOOL provides data about the impact produced by the implementation of some energy saving
measures in existing buildings, quantifying, not only the energy and CO2 emission savings, but also the
expected payback time.
Three fundamental premises have been taken into account when choosing the most representative
saving measures:
The effective energy savings produced by these measures should be measurable and calculable
independently of the orientationand shadowing of the studied building.
The cost of the saving measures should be easy to calculate by experts in each country.
The measure should be applicablein most buildings.
7 Description of the E-TOOL software
The E-TOOL is described in: "e-tool - handbook, manual for energy rating of existing buildings,
December 2006, and it can be down loaded from: www.e-tol.org. Here will be made a short
introduction, also to give background information for the section of the Final Report concerning the
feasibility of the E-TOOL.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
12/62
12
The E-TOOL was developed by Cener, Navarra, Spain, in close cooperation with especially Naturgas
Midt-Nord of Denmark. Cener prescribes its right to the E-TOOL, in the sense that parties, who want to
use the tool, shall contact Cener to ask about permission.
The E-TOOL confirm with CEN standards TC89/prEN wi 1+3+4, when possible.
The E-TOOLSET methodology has three main parts:
E-TOOL User Data Sheets E-TOOL Process E-TOOL Report
E-TOOL User - Data Sheets
Data Collection Saving Measures Selection
1.-General Data Building
2.-Data Consumption
Location
CategoryShape and physicaldata
Fuel typeAnnual consumConsumption included
-Heating-Cooling-Domestic Hot Water-Lighting
-Envelope
E-TOOL PROCESS
DATA BASE
-Energy saving coefficients for saving
measures.-Correlations to calculate energy savings
depending on measures characteristics.
INPUTS FOR EACH COUNTRY
-Prices of saving measures.-Average consumption value depending onthe type of building and the climatic zone.
-Energy prices and annual rate of increase.-CO2 emissions.
E-TOOL Report
Potential savings, initial investments, pay-back times, CO2 savings for all saving measure initially selected.
Total potential savingsTotal investment cost of energy saving measures
Payback time of the energy saving measuresTotal CO2 savings
Initial E -Tool BenchmarkFinal E-Tool Benchmark
Best five energy saving measures selection
Figure 2: Flow Diagram of the E-TOOL software
Input data
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
13/62
13
The types of input data are: General data of the building, owner, type etc. Energy consumption data - screen picture, if relevant General characteristics of the building, including:
o Heatingo Coolingo Domestic hot water systemo Lightningo Thermal envelope
Figure 3: Front pages of E-TOOL version 1 and E-TOOL version 5
Output data
Summary for each potential energy saving measure: Potential savings, (kWh/year) Initial investment (EURO) Payback in years CO2 savings (kg)
Cost-effective analysis summary: Total potential, kwh/year Total investment costs
E-TOOLSET
Goes to:
Page 1
Page 2
Page 3
1- CLIMATIZATION SYSTEMS
1.1- HEATING 1.1-SAVING MEASURES Page 3
1.2- COOLING 1.2- SAVING MEASURES Page 4
2- DOMESTIC HOT WATER
2.1- SAVING MEASURES Page 5
3- LIGHTING
3.1- LIGHTS / REGULATION 3.1- SAVING MEASURES Page 6
4- USAGE
4.1- OCCUPANCY, HEATING-COOLING SCHEDULES 4.1 SAVING MEASURES Page 7
5- THERMAL ENVELOPE
5.1- INSULATION 5.1- SAVING MEASURES Page 8
5.2- OPENINGS 5.2- SAVING MEASURES Page 8
Page 9
CONSUMPTION DATA
SUMMARY- Benchmarking
2.1- EQUIPMENT/ RENEWABLE ENERGY
GENERAL CHARACTERISTICS OF THE BUILDING
GENERAL DATA OF THE BUILDING
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
14/62
14
Payback time CO2 savings Initial E-TOOL bench mark (measured), kWh/m2 Final E-TOOL bench mark (with energy savings), kWh/m2
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
15/62
15
Figure 4: Certificate format
8 Bench marking of the energy consumption
Why bench marking?
One of the ideas behind the E-TOOL methodology is to identify groups of similar buildings with asimilar energy (in climates with over-heating problems heating also includes cooling) consumption. If itis possible to identify these groups, it can be derived what energy consumption could be expected in agiven building and then compare this with the actual energy consumption - and thereby get a goodindication of the energy standard of the building. This information can be used for looking for typicalpotential energy savings measures, which could lead you to an energy performance of the building to beexpected, when having a rational use of heat.
To identify such groups of building you need statistic data on energy consumption of the existingbuilding stock.
Sources for data for bench marking of the energy consumption of existing buildings
The benchmark data have been obtained during the data collection process in the partner countries thathad these data available, such as Denmark, as well as during the realization and evaluation of the testsfor the same type of buildings that have been tested with E-TOOL.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
16/62
16
In Denmark there exist statistic data from the heating and electricity consumption of 46,000 singledwellings, which have been rated for energy certificates using the calculated methodology.
Of other sources for statistic data on energy consumption can be mentioned the IEE-projects: EP-Label,
enper-exist and e-impact. EUROSTAT is another source of information. The data of these projects havebeen taken into consideration to get an orientation and a general impression of energy consumptions ofbuildings as reference data in the general evaluation of the E-TOOL project within the frame of theEPBD Building Platform.
Bench marking of energy consumption
Bench marking of the energy consumption of the existing building stock in typical building categoriesis intended to be a support for energy experts making building energy performance rating. But in mostcountries there is a lack of reliable data. This means that the use of bench marking of the energy
consumption has not had the extend as expected in the project proposal.Not using bench mark data as an integrated part of the E-TOOL methodology did not mean that theenergy expert carrying out the energy performance rating did not compare an actual measured heatingconsumption with what could be expected of heating consumption for a typical building of the typecertified. Experience from the tests has shown that many experts have their own experience to draw on.An alternative is also to use the numbers of the actual building code for when the building was erected,if the building code included maximum heating/energy consumption.
Recommendations
It would be recommended to support the establishment a European data-base for energy consumptionfor existing EU-building stock, also to be able to follow the development of the energy standard of theexisting building stock.
9 Accessibility of the input data
Introduction
As the overall E-TOOL methodology is based on measured energy rating, is the accessibility of the dataof the actual energy consumption of the building of importance.
Besides these consumption data, further input data are needed for carrying out an E-TOOL certification,such as:
General data of the building, age, type etc. Energy consumption data General characteristics of the building, including:
o
Heating system
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
17/62
17
o Coolingo Domestic hot water systemo Lightningo Thermal envelope
The energy experts carrying out the regional testing of the E-TOOL have been questioned about theaccessibility of the data needed.
Accessibility of input data for E-TOOL certification
Denmark
For the operational rating is the access to transparent and reliable data for the energy consumptionimportant.
In less than 10% of the tests have improvements of the access to data been proposed.These are mainly the tests where it has been difficult to calculate how much of the energy consumptionfor heating have been covered with firewood or biomass,
Austria
Although it is in some cases challenging to obtain the building data for completing the e-tool, it is a
useful instrument to assess building qualities and to show the building owner the potential of energyefficiency measures.
For the success of the e-tool it is crucial that only qualified advisers use it.
Greece
The evaluation of the accessibility of data in Greece can be taken from following column diagram:
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
18/62
18
Figure 5: Accessibility of data
Slovenia
The evaluation of the accessibility of data in Slovenia can be taken from following column diagram:
Figure 6: Accessibility of data
Spain
The main draw-back is the dependency of the E-TOOL on the energy consumption data andinformation on building characteristics (constructive plans, boiler data, etc.).
The evaluation of the accessibility of data in Spain can be taken from following column diagram:
Accessibility of the data
needed for the tests
0
5
10
15
20
25
30
35
VERY EASY EASY MEDIUM DIFFICULT VERY
DIFFICULT
respons
e
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
19/62
19
Accessibility of data for the tests- Spain
0
20
4060
80
Very
good
Good Medium Difficult Very
difficult
Percentage
[%]
Figure 7: Accessibility of data
Bulgaria
Good accessibility of data was registered in 80% of the tests; fair availability of data was registered in18% of the tests and in 2% of the tests significant data was missing. Missing data is in most casesconnected to the energy consumption: missing bills for electricity or heat energy.
Accessibili ty of the data neede d for the tests
424
97
6
0
50
100
150
200
250
300
350
400450
Good Fair Improve
Figure 8: Accessibility of data
Building can be assessed as a whole with regard to the heat energy consumption, as there is availabledata from the district heating companies. But it is not possible to have such data for consumption ofelectricity as each flat has its own electrical meter.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
20/62
20
Conclusion and recommendations on accessibility of input data
No general conclusions at a European level can be made on the accessibility of data for the E-TOOLrating using the measured data. In some countries, e.g. Denmark, the accessibility of accounted
consumption is good. In other countries are such data not present for different reasons.To use the E-TOOL measured rating methodology it will in many cases be necessary to compromise onthe quality of the input data on measured energy consumption using estimates, e.g. based on what thebuilding owner remembers about the size/level of energy bills or simply estimates based on the energyexperts' experience.
Even if the energy expert does not know the exact energy consumption of an existing building, it is stillpossible on the site to identify the potential energy saving measures and make a calculation of thepotential energy savings that can be obtained by implementing these measures. This is the mostimportant part of the E-TOOL rating, which can be carried through, even with estimates on actual
energy consumption of the building being energy rated.If energy savings shall be implemented into the existing building stock of EU, then the problem of lackof information about the actual energy consumption of the buildings shall be solved, e.g. by demandingthe energy supply companies to register the energy consumption. This will in the future provide theenergy authorities with information about the development of the energy consumption.
10 Energy saving measures
Introduction
For the E-TOOL based on the methodology of measured rating, are the guidelines for energy savingmeasures, including costs estimated and information about potential energy savings, key elements. Thiselement of the tool is where the tool actually carries out calculations - on investment costs, energysavings and thereby cost savings.
The overall idea is to be able to identify a relatively limited number of cost efficient energy savingmeasures, which can be described sufficiently precise to be able to estimate the potential energy savingmeasures for a specific building. The investment costs, energy and money savings are transformed into
standard figures per m2
for each specific energy saving measure for each country/region.
The data on energy saving measures are specific for each country and are put into a price matrix of theE-TOOL, from which the tool draws information for calculations. The E-TOOL differs from energyrating tools based on calculated rating basically by using default for U-values of walls and other basisstructure. Taking into account the inaccuracy related to real effect in terms of obtained energy savingsdue to in-complete data of the existing building, e.g. the thickness of the insulation, then this element ofthe E-TOOL is not considered to have major influence on the overall rating accuracy.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
21/62
21
Energy saving measures have been identified
For the 6 involved countries: Austria, Bulgaria, Denmark, Greece, Slovenia and Spain have been
identified the "top 10 energy saving measures" and as result, it has shown up to be to a very high degreethe same energy saving measures.
The criteria for selecting the measures have been to select the most common measures within thecountry. Results from each country.
Austria:
Most of the buildings tested were built after 1970, the average heated area is around 1430 m. Theaverage indicator is about 175 kWh/ma and could be reduced to 117 kWh/ma after renovation. Onaverage 76,877 kWh savings could be achieved annually by implementing the suggested measures,
which would require investment costs of about 20,400 in the average.
The figure below shows the percentage of different energy saving measures for all types of buildings(offices, hotels and shops). The most attractive measures were the insulation of external walls, walls tounconditioned space, followed by the exchange of windows. The installation of a new boiler togetherwith a change of the fuel to biomass, the installation of a solar collector system, the insulation of pipesand the substitution of conventional lights by low consumption lights are other measures named quiteoften.
Other measures named for the prospected buildings were the installation of a modern boiler, theinstallation of presence detectors, a change to a gas boiler, the cleaning of the boiler, sealing of windowair leaks, the reduction of the heating set point and the installation of a water saving system.
Percentage of different energy saving measures
0
2
4
6
8
10
12
14
16
18
Insulate
externalw
alls
(externally)
Insulate
walls
touncon
ditione
dspace
Change
windo
w
Chan
getobiomassbo
iler
Installs
olar
collct
orsystem
Chan
gelight
sto
lowconsum
ption
Insula
tethepipes
Installthe
rmostat(he
ating)
Installm
odernboile
r
Installp
rescen
cedetectors
Chan
getogas
boiler
Clea
nthebu
rner
Sealingwind
owairleaks
Redu
ceheatingsetp
oint
Installw
ater
saving
%
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
22/62
22
Figure 9: Distribution of energy saving measures
When the energy saving measures at the different types of examined buildings are evaluated, it can befound that there are some measures that are important for all types of buildings, such as insulation ofexternal walls and walls to unconditioned space, as well as the change of windows but there are alsosome differences.
Energy saving measures in hotels
In hotels, the most frequently suggested measures were the insulation of external walls, walls tounheated space and the roof, followed by the exchange of windows. Another very important measure isthe installation of a solar collector system, because of the high hot water consumption in hotels.
Further suggestions were the change of lights to low efficient ones, the insulation of pipes, the changeto a biomass boiler and the installation of thermostats.
Percentage of different energy saving measures in hotels
0,00%
5,00%
10,00%
15,00%
20,00%
25,00%
Install
mod
ernbo
iler
Change
tobiomassb
oile
r
Chan
getogas
boile
r
Clea
nthebu
rner
Insulate
thepipes
Installthe
rmostat(he
ating)
Redu
cehea
tingsetp
oint
Install
water
saving
Install
solarc
ollct
orsystem
Chan
gelight
sto
lowconsum
ptio
n
Install
prescen
cedetectors
Insula
teexte
rnal
walls(externally)
Insula
tewalls
tounconditione
dspace
Sealin
gwind
owairlea
ks
Chan
gewin
dow
Figure 10: Distribution of energy saving measures
Energy saving measures in shops
Similarly, in shops the most frequently suggested measures are the insulation of external walls, walls tounheated space and the roof, followed by the change of windows. Other measures are the installation ofa biomass boiler, a solar collector system, the change of lights to low consumption and the installationof presence detectors.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
23/62
23
Percentage of different energy saving measures in shops
0,00%
5,00%
10,00%
15,00%
20,00%
25,00%
Installm
odernboile
r
Change
tobiomassboile
r
Change
togas
boiler
Cleanthebu
rner
Insulate
thepipes
Installthe
rmostat(he
ating)
Reduce
heatingsetpoint
Installw
ater
saving
Install
solar
collct
orsystem
Change
light
sto
lowconsum
ption
Installp
rescence
detectors
Insulateexternal
walls
(externally)
Insulat
ewalls
tounconditionedspace
Sealingwindow
airle
aks
Change
window
Figure 11: Distribution of energy saving measures
Energy saving measures in offices
In offices, the insulation of external walls and walls to unconditioned space, as well as the exchange ofwindows are measures that are named very often. Especially in offices the change of lights to lowconsumption is an attractive measure for energy savings with a share of around 12 % compared to 4,5
% in shops and 7,5 % in hotels. The installation of a biomass boiler and the insulation of the pipes arealso very important.
Percentage of different energy saving measures in offices
0,00%
5,00%
10,00%
15,00%
20,00%
25,00%
Install
modernbo
iler
Change
tobiom
assb
oiler
Change
togas
boiler
Clea
nthebu
rner
Insulat
ethepipes
Install
thermostat(he
ating)
Reduce
heatingsetp
oint
Installw
ater
saving
Install
solarcollctor
system
Chan
gelight
sto
lowconsum
ption
Install
prescence
detectors
Insulate
externalw
alls
(exte
rnally)
Insulat
ewalls
touncon
ditionedspace
Sealing
windowairleaks
Chan
gewindow
Figure 12: Distribution of energy saving measures
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
24/62
24
Bulgaria
Top 10 energy saving measures in Bulgaria (for multi dwelling buildings erected before 1999):
Figure 13: Distribution of energy saving measures
Denmark
Most frekvent measures for single dwellings
0%
5%
10%
15%
20%
25%
30%
35%
Insulation Windows Air filtrat. Temp.Ctr. Boiler Pump
Frequency
%
Figure 14: Distribution of energy saving measures
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
25/62
25
Greece
Distribution of Energy Saving Interventions
0
2
4
6
8
10
12
14
16
18
20
Cleaning
Burner
Installing
modernboiler
ChangeFuel Oil
toGas. Install
GasBoiler
InsulatingPipes Changing
Glazing-
Windows
Insulating
external Walls
InsulatingWalls
incontactto
unconditioned
premises
Reducing
HeatingSet
Point
Increasing
CoolingSet
Point
Changinglights
tolow
consumption
Installing
presence
detectors
InstallingHVAC
VRV
InstallingWater
Saving
Systems
InstallingSolar
Collectors
Installing
Reflective
Curtains
(Heating)
Installing
Reflective
Curtains
(Cooling)
Installing
Awnings
Improve
Windows
Inflitrations
Intervention
%
Figure 15: Distribution of energy saving measures
Slovenia
0
2
4
6
8
10
12
14
16
18
20
INSTALL MODERN
BOILER
INSULATE THE PIPES REDUCE HEATING SET
POINT
INSTALLING A SOLAR
COLLECTOR SYSTEM
CHANGING ALL LIGHTS
TO LOW
CONSUMPTION
INSULATING
EXTERNAL
WALLS(outer side of the
wall)
CHANGE WINDOWS INSULATING WALLS
CLOSE TO
UNCONDITIONED
SPACES
INSULATING ROOF
Frequency[%]
Figure 16: Distribution of energy saving measures single dwellings
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
26/62
26
0
5
10
15
20
25
INSTALL MODERN
BOILER
INSULATE THE PIPES REDUCE HEATING SET
POINT
INSTALLING A SOLAR
COLLECTOR SYSTEM
CHANGING ALL LIGHTS
TO LOW
CONSUMPTION
INSULATING
EXTERNAL
WALLS(outer side of the
wall)
CHANGE WINDOWS INSULATING WALLS
CLOSE TO
UNCONDITIONED
SPACES
INSULATING ROOF
Frequency[%]
Figure 17: Distribution of energy saving measures block of dwellings
0
5
10
15
20
25
INSTALL MODERN
BOILER
INSULATE THE PIPES REDUCE HEATING SET
POINT
INSTALLING A SOLAR
COLLECTOR SYSTEM
CHANGING ALL LIGHTS
TO LOW
CONSUMPTION
INSULATING
EXTERNAL
WALLS(outer side of the
wall)
CHANGE WINDOWS INSULATING WALLS
CLOSE TO
UNCONDITIONED
SPACES
INSULATING ROOF
Frequency[%]
Figure 18: Distribution of energy saving measures schools
Spain
With respect to the public schools and libraries that have been visited, following energy savingmeasures are considered to be the most common ones:
Windows: changing of frames without thermal bridges
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
27/62
27
Windows: changing from single to double glazing Walls: External insulation Heating system: changing of boilers (>20 years old) Heating system: installation of regulation system Heating system: installation of thermostats Water: installation of water saving systems (WC) Hot water: installation thermal panels for hot water production (kitchens of the public schools) Electricity: installation of presence detectors (corridors) Electricity: install low consumptions lamps (all)
Distribution of Energy Saving Interventions
0,00
5,00
10,00
15,00
20,00
25,00
Installation new
boiler
Changing lights
low consumption
Installation
presence detector
Insulation external
wall
Insulation internal
wall
Changing window Reduction heating/
increase cooling
set point
Solar panel DHW
%
Figure 19: Distribution of energy saving measures Spain
11 Top 10 energy saving measures in 6 EU countries
The top 10 energy saving measures have been made a trans-national comparison, because this hasimportance for which measures to include into the tool.
As a general approach for the project has comparisons between the different involved countries, e.g. ofenergy consumption, not been carried out., The differences in climate, building traditions, utilization ofbuildings, different numbers of housing area per resident etc. makes it too complex to evaluate withinthis project scope.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
28/62
28
Ranking of measureMeasure
AU BG DK GR SI ES Priority
Insulation outer walls 1 1 3 4 2 2 HighInsulation of roofs 6 - 3 HighInsulation, uncond.spaces 1 5 5 HighInsulation of pipes 7 10 6 LowChange windows 3 2 2 6 1 1 HighReducing/stop airfiltration
7 4 9 Medium
Temperature control 8 8 6 2 7 4 Medium
Energy efficient pump 4 Medium
Install presence detector 10 3 7 Medium
Energy efficient light 6 3 1 8 8 LowIncrease cooling set point 5 LowChange to biomass boiler 4 - Mediu
mChange to gas boiler 7 Mediu
mChange to efficient boiler 9 1 8 4 3 Mediu
mClean burner 10 Low
Install solar collector 5 9 6 LowWater savings 4 5 Low
12 Investment costs of energy saving measures
Introduction
For each of the energy saving measures included in the E-TOOL is the identified national (regional)
investment costs based on inputs from the partners of the project. For some of the common energysaving measures have been carried out trans-regional comparison of costs to give some ideas about thelevel of investment costs in the different parts of EU. The results are shown below. The specific costsfor a building will depend on the specific conditions and also on the terms of defining costs, but thefigures can give some indication of level of costs in different countries.
The following energy saving measures are included: Insulation of wall/floor/roof Changing windows / glass Installing biomass boiler Installation of more energy efficient oil boiler Installation of more energy efficient gas boiler
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
29/62
29
New control for the energy system Solar collector
The following table gives an overview of selected investment cost of energy saving measures and
shows the wide variety of the costs:
Region Wall insulation(16 cm)
/m2
Double glazingwindows
(1.2 W/mK )/m2
New biomassboiler
(50 kW)/kW
Insulation ofpumps and pipes
/m
Slovenia 43 - 76 130 - 208 70 - 300 1 -6Austria 60 - 80 250-450 300 - 400 2 - 5Bulgaria 28 - 40 19 - 120 48-200 3Denmark 170 250 400 7
Spain 15-20 130-150 190-215 5-10Greece 35-40 176-220 - 12
The collected data of the investment cost are entered in the development of the E-TOOL to calculate thecost of selected energy saving measures with the E-TOOL.
The following figures show the average investment costs for different energy saving measures in therespective countries. The underlying data for the investment costs can be found in the Annex.
Average investment costs for insulation of wall, floor and roof
De
nmark
Denmark
Denmark
Denmark
DenmarkA
ustria
Austria
Austria
Austria
Austria
Slovenia
Slovenia
Slovenia
Slovenia
Slovenia
Bulgaria
Bulgaria
Bulgaria
Bulgaria
Bulgaria
Spain
Spain
Spain
Spain
Spain
Greece
Greece
Greece
Greece
Greece
0
20
40
60
80
100
120
140
160
180
Wall (8 cm) Wall (16 cm) Floor (10 cm) Roof (10 cm) Roof (20 cm)
[/m2]
Denmark Austria Slovenia Bulgaria Spain Greece
Figure 20: Average investment costs
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
30/62
30
The average investment costs for the insulation of the wall (8 and 16 cm), the insulation of the floor (10cm), and the costs for roof insulation (10 and 20 cm) are shown. The costs to insulate the walls are veryhigh in Denmark, followed by Austria and Slovenia. Greece has the highest prices concerninginsulation of floors.
Average investment costs for windows
Denmark
Denmark
Austria
Austria
Slovenia
Slovenia
Bulgaria
Bulgaria
Spain S
pain
Greece
Greece
0
50
100
150
200
250
300
350
400
450
Double glazing (1.2 W/m2K) Triple glazing (0.8 W/m2K)
[/m
2]
Denmark Austria Slovenia Bulgaria Spain Greece
Figure 21: Average investment costs
In Austria the average investment costs for windows with double- and triple glazing are the highestamong the different countries.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
31/62
31
Average investment costs for new biomass boilers
Denmark
Denmark
Denmark
Austria
Austria
Austria
Slo
venia
Slovenia
Slovenia
Bulgaria
Bulgaria
Bulgaria
Spain
Spain
Spain
0
50
100
150
200
250
300
350
400
450
< 50 kW 50-100 kW 100-500 kW
[/kW]
Figure 22: Average investment costsThe average investment costs for smaller biomass boilers 50 kW inevery country. Biomass boilers up to 50 kW are most expensive in Denmark and Austria, between 50 -100 kW and 100 500 kW we have the highest investment costs in Austria and Slovenia.
Average investment costs for a new oil boiler
Denmark
Denmark
Denmark
Denmark
Austria
Austria
Austria
Austria
Slovenia
Slovenia
Slovenia
Slovenia
Bulgaria
Bulgaria
Bulgaria
Bulgaria
Spain
Spain
Spain
Spain
0
50
100
150
200
250
< 50 kW 50-100 kW 100-500 kW >500 kW
[/kW]
Figure 23: Average investment costs
Oil boilers up to 100 kW have the highest average investment costs in Denmark, followed by Austria.
The costs for a new oil boiler are almost the same for every capacity in Bulgaria and Spain.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
32/62
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
33/62
33
The average investment costs for a new control system are much cheaper in Bulgaria and Spain,especially for heating systems >100 kW. Overall the costs for the installation of a new control systemare the highest in Austria and Greece.
Average investment costs for a solar collector system
Denmark
Denmark
Austria
Austria
AustriaS
lovenia
Slovenia
Slovenia
Bulgaria
Bulg
aria
BulgariaS
pain
Spain
Spain
Greece
Greece
Greece
0
100
200
300
400
500
600
700
800
900
8 m2 30-100 m2 >100m2
[/m2]
Denmark Austria Slovenia Bulgaria Spain Greece
Figure 26: Average investment costs
The average investment costs for the installation of a solar collection system up to 100 m2 are thefewest in Greece (around 100 /m2) and Denmark (around 200 /m2), for systems above 100 m2 therehave been no data for Denmark. For solar collector systems of 8 m2 there is not much difference in theaverage costs, only in Spain the installation is more expensive.
Results from Austria
In Austria the costs of energy savings in shops, offices and hotels have been compared.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
34/62
34
Average savings and costs of energy saving measures
0
20.000
40.000
60.000
80.000
100.000
120.000
Shops Office Hotel
[][kWh]
Costs ()
Savings (kWh)
Figure 27: Average savings
Payback time for energy saving measures in Bulgaria:
Thermal insulation of external walls 8 years; Thermal insulation of roof (water-proofing of roof excluded) 4,5 years Thermal insulation and water-proofing of roof 15,5 years Thermal insulation of basements ceiling 9 years Repair and draught-proofing of windows and external doors 4 years Replacement of windows 20 years Installation of local heating (change of fuel) 11 years.
13 Energy performance (bench mark) after energy retrofitting
It is very simple to derive to the energy performance (bench mark) after retrofitting of the buildingimplementing the energy saving measures - by taking the actual measured heating consumption anddeduct the estimated energy savings through implementing the energy saving measures.
The energy performance can then be compared to what should be the energy consumption of thebuilding, e.g. compared to the standard of the actual building code, or rating the building according tothe national certification energy performance categories.
Because bench mark of the energy consumption after retrofitting is very dependent on the regionalconditions there has not been made a trans-regional comparison.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
35/62
35
Results from Austria on commercial buildings
This figure shows the benchmarks for the different building types before and after energy savingmeasures. The greatest difference between the benchmark before and after renovation was discovered athotels. The results are from Austria.
Benchmarks before and after energy saving measures
0,00
20,00
40,00
60,00
80,00
100,00
120,00
140,00
160,00
180,00
200,00
Shops Office Hotel
kWh/m2a
Indicator before
Indicator after
Figure 28: Benchmarks
Most of the buildings tested were built after 1970, the average heated area is around 1,430 m. Theaverage indicator is about 175 kWh/ma and could be reduced to 117 kWh/ma after renovation. Onaverage 76,877 kWh savings could be achieved annually by implementing the suggested measures,which would require investment costs of about 20,400 in average.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
36/62
36
Results from Bulgaria
Results from Denmark
Comparison of DK-certificates and E-TOOL
Single Dwellings - energy consumption before and after savingLeft collum DK certificates - Right collum E-TOOL
0
50
100
150
200
250
00-20 20-40 40-60 60-70 70-80 80-00
Year of construction
kWh/m2
Before
After
%
pay-back
BeforeAfter
%
pay-back
Figure 29: Comparison E-TOOL to energy audit
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
37/62
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
38/62
38
225,4
255,8
209,4
231,5
155,5164,2
141,8151,6
0,0
50,0
100,0
150,0
200,0
250,0
300,0
BLOCK OF DWELLINGS SCHOOLS MUNICIPAL BUILDINGS SINGLE DWELLING
[kWh/m2]
INITIAL E-TOOL BENCHMARK
FINAL E-TOOL BENCHMARK
Figure 31: Benchmark Slovenia
Block of dwellings
0
50
100
150
200
250
300
350
400
2 10 19 28 37 46 55 64 73 82 91 100 109 118 127 136 145 154 163 172 181 190
Energyconsumption[kWh/m2
]`
0
10
20
30
40
50
60
Paybacktime[year]
ENERGY CONSUMPTION BEFORESAVING MEASURESENERGY CONSUMPTION AFTER SAVINGMEASURESPAYBACK TIME OF THE ENERGY SAVINGMEASURES
Figure 32: Benchmark Slovenia
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
39/62
39
0,0255
0,01900,0202
0,0289
0,0165
0,0103
0,0129
0,0175
0,0000
0,0050
0,0100
0,0150
0,0200
0,0250
0,0300
0,0350
BLOCK OF DWELLINGS SCHOOLS MUNICIPAL BUILDINGS SINGLE DWELLING
[kWh/m3*DD]
INITIAL E-TOOL BENCHMARK
FINAL E-TOOL BENCHMARK
Figure 33: Benchmark Slovenia
Single dwelling
0
100
200
300
400
500
600
1 10 19 28 37 46 55 6473 82 9110010911
8127
13614515416317
218119
0199208217
22623
524425
326227128028
9298307
Energyconsumption[kWh/m2]`
0
10
20
30
40
50
60
Paybacktime[year]
ENERGY CONSUMPTION BEFORESAVING MEASURESENERGY CONSUMPTION AFTER SAVINGMEASURESPAYBACK TIME OF THE ENERGY SAVINGMEASURES
Figure 34: Benchmark Slovenia
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
40/62
40
Results from Spain
Overview tested buildings Spain
0
100
200
300
400
500
600
700
Schools Office
building
Library -
Music school
Social
services
Museums Sport Bus station-
Market hall
En
ergyconsumption[kWh/m2]
[kWh/m2 before]
[kWh/m2] afer
Figure 35: Benchmark Spain
Conclusions on bench mark after implementing energy saving measuresThe following energy savings are obtained from the national values on energy consumption before andafter implementing the energy saving measures. It has to be taken into account that it is different typesof buildings etc., but the numbers give some indications about the potential for energy savings.
Country Type of buildings Energy savings, %
Shops 38%Offices 20%
Austria
Hotels 38%Bulgaria Dwellings, blocks 46%
Denmark Dwelling, blocks and single 25%Greece Public 20%
Slovenia Dwellings and public 33%Spain Public 40%
The E-TOOL calculates the energy performance of the building (after implementing the energy savingmeasures proposed) and show the result as a part of the E-TOOL energy performance rating.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
41/62
41
14 Quality of the E-TOOL rating
Introduction
A key issue in evaluating the E-TOOL rating is to be able to answer the simple question. What is thequality of the E-TOOL rating?
With the approach used in this project the focus of the certificate is to make estimations of potentialenergy savings - in existing buildings. So this has been the criteria for evaluating the performance of theE-TOOL. This is also the central point with regard to implementation of energy savings in the existingbuilding sector - and therefore should also be the central point for promoting the implementation of theenergy performance building directive.
Two methods have been used for evaluating the quality of the E-TOOL energy rating:
Compare E-TOOL/energy audit's proposals for energy saving measures - in Denmark andSlovenia
Questionnaire to energy experts about the accuracy of results based on the energy expert'sexperiences - carried out in Denmark, Slovenia and Spain
Compare E-TOOL/energy audit certificate's proposals for energy saving measures
A pragmatic approach of looking into the results of using the E-TOOL methodology and compare itwith the use of other certification methodologies with respect of identification of potential energysaving measures. Does the E-TOOL identify the same potential energy saving measures.
Results from Denmark
The results from Denmark include also a comparison with energy audit (calculated) rating, which ingeneral comes to higher energy consumption than the measured (operational) rating.For energy saving measures the calculated rating has identified energy savings measures of around thesame size as the E-TOOL
Results from Slovenia
Comparison of the E-tool results with an energy audit of a block of dwellings, built in 1980.
The building characteristics are: 50 apartments with totally 100 residents Heated floor area 3.100 m2 External wall area 1.940 m2
Uwall values of approx. 0,8 W/(m2
K)
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
42/62
42
Windows 640 m2 Uwindow value 3,0 W/(m
2K) with high air leakage
Recommended measures: Additional thermal insulation of outer wall with 15 cm thick polystyrene layer. Installation of energy efficient windows with low-e double glazing (Uw=1,1W/m
2K) Additional insulating roof (TI=25cm) Additional insulating walls close to unheated spaces (TI=12cm) Improvement of boiler house and install modern boiler
POTENTIAL SAVINGS
POTENTIAL
SAVINGS
INITIAL
INVESMENT
INITIAL
INVESMENT PAY-BACK PAY-BACK CO2SAVINGS CO2SAVINGS
E-tool Energy Audit E-tool Energy Audit E-tool Energy Audit E-tool Energy Audit
Investment measure [kWh/a] [kWh/a] [] [] [year] [year] [kg/m2] [kg/year]
improvement of boiler
house and install modern
boiler 130.357 85.500 86.000 92.000 11,6 19,0 26.071 17.100
additional insulating walls
close to unheated spaces
(TI=12cm) 17.827 5.230 15.070 7.840 13,7 27,7 3 .565 1.046
change windows from 3,0 to
1,1 [W/m2K] (640 m2) 124.319 163.800 146.286 157.084 20,6 17,6 24.863 32.760
additional insulating
external walls (TI=15cm,
faade) 117.107 76.000 68.953 94.125 9,6 22,0 23.421 15.200 additional insulating of roof
(TI=25cm) 23.263 18.300 17.056 8.175 11,8 10,5 4.653 3.660
Comparison E-TOOL with Energy Audit Slovenia
Comparison between E-TOOL and Energy AuditImprovement of boiler house and install modern boiler
-
20.000
40.000
60.000
80.000
100.000
120.000
140.000
E-TOOL Energy Audit
POTENTIAL SAVINGS [kWh/a]
INITIAL INVESTMENT []
CO2 SAVINGS [kg/year]
Figure 36: Comparison E-TOOL with Energy Audit Slovenia
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
43/62
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
44/62
44
Comparison between E-TOOL and Energy Audit
Additional insulating walls close to unheated spaces (TI=12cm)
-
5.000
10.000
15.000
20.000
25.000
E-TOOL Energy Audit
POTENTIAL SAVINGS [kWh/a]
INITIAL INVESTMENT []
CO2 SAVINGS [kg/year]
Figure 40: Comparison E-TOOL with Energy Audit Slovenia
15 Accuracy of results - questionnaire
Results from Denmark
E-TOOL evaluation (DK)Result of questionnaires
0
20
40
60
80
100
Survey Function Access Client
Answerin%
Fair
Good
Improve
Figure 41: Result of questionnaires
Results from Slovenia
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
45/62
45
Figure 42: Result of questionnaires
Results from Spain
Accuracy of the results: Satisfied 60% Accepted 30% Not sufficient (improvements necessary) 10%
Conclusion concerning the accuracy
Evaluation Denmark Slovenia Spain Average
Good 27% 40% 60% 42%Sufficient 34% 40% 30% 38%
In-sufficient 39% 20% 10% 20%
Time required to complete the
survey and the report
0
5
10
15
20
25
less than
30
minutes
30 - 60
minutes
1 - 2
hours
2 - 3
hours
more than
4 hours
Other
response
Accurancy of results based
on your experiences
0
5
10
15
20
25
EXCE
LENT
VERY
GOOD
GOOD
SUFF
ICIENT
INSU
FFICIENT
response
Accessibility of the data
needed for the tests
0
5
10
15
20
25
30
35
VERY EASY EASY MEDIUM DIFFICULT VERY
DIFFICULT
response
Acceptance of results by client
0
5
10
15
20
25
30
35
EXCE
LENT
VERY
GOOD
GOOD
SUFF
ICIENT
INSU
FFICIENT
response
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
46/62
46
The average figure of 80% of energy experts expressing that the E-TOOL rating is good or sufficientmust be said to be satisfactory.
Conclusion on the quality of the E-TOOL rating
In general and overall terms based on evaluation of comparison with energy audits and evaluation byenergy experts the E-TOOL rating seems to be of a satisfactory quality.
16 Description of the contribution to advancement on the state ofthe art
Focus of E-TOOL development on Southern Europe and East/Southern part of Europe
The energy audits and the implementation of energy saving measures are more advanced in theNorthern part of Europe, such as in the partner countries Denmark and Austria.
One of the motivations of starting-up E-TOOL was to use these long-term experiences and to transferthem to other countries. In this sense, it has to be underlined that that e-tool was developed withSpecial focus on buildings in Southern Europe and East/Southern part of Europe. It means that E-tool needs modification or improvements to be used in Northern climate, as here the energy savingmeasures are more precise and not only of general character.
17 Feasibility and impact of E-TOOL
Introduction
In this context is focused on the feasibility and the impact of the E-TOOL in relation to the objectivesdefined for the tool. By "feasibility" is meant E-TOOL's ability of fulfilling the functional objectivesdefined. By "impact" is meant E-TOOL's ability of making an impact in terms implementing energysavings in the building sector of existing buildings. The objectives for the functionality of the E-TOOLare:
Operational/simple/practicable. Promote the implementation of the energy performance building directive. Promote the implementation of energy savings in the building sector.
The feasibility and impact have first of all been evaluated by the energy experts testing the tool. Inconnection to the testing activities the energy experts have filled out questionnaires concerning:
Applicability of the tool, giving characters of: Good/fair/improve. User (energy expert) friendliness, giving characters of: Good/fair/improve.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
47/62
47
Accessibility of the data needed for the tests, giving characters of: Good/fair/improve. Acceptance of the results by the client, giving characters of: Good/fair/improve. Time required for completing the survey and the reporting. Improvements of the tool.
17.1 Feed-back from workshops, training seminars
The feasibility and impact of E-TOOL have also been evaluated through the regional workshops carriedout with attendance of regional energy experts, who haven given their feed back on the performance ofthe tool etc. Supplementary to the workshops have been carried out interviews with energy experts, e.g.from energy companies, with evaluation of the tool.
The aim of the training seminars was to explain the usage of the E-TOOL to the energy auditors,technicians of public administration and energy companies. The main tasks therefore have beenfulfilled, as a large number of implied and qualified people were reached and the philosophy and thepractical aspects of the present project could be demonstrated.
The two regional workshops aimed at the dissemination of the project results and the discussion mainlyof the practicable aspects when applying E-TOOL. In the case of Demark and Slovenia, a special pointof discussion was the comparison of E-TOOL to the national certificates.
The general feed-back of the auditors that used E-TOOL was positive, despite of the fact that this toolcould not cove all different aspects of the particular buildings in each partner country.
For example, in the case of large building complex as public buildings, the user influence is importanton the total energy consumption. This is especially important to sport complex building with highenergy consumptions where it is worth to reduce the energy consumption from very high to lowerlevels.
The interaction between the data collection, default values and software is in general a major factor forthe accuracy of the rating. The operational and calculated rating methods have identified the same costefficient saving measures, but the calculated savings and pay-back time are different. It was concludedthat the differences could be caused by calculation models and default values. The difference betweenthe metered and the calculated consumption is often seen by the danish experts and it could be
explained with the software for calculated rating did not take the surplus energy from indirect sourcesinto account.
It was the general opinion that the simple structure of E-TOOL has maintained its reproducibilitycompared to the more detailed structure of the DK-software and reporting. In comparison with morecomplex and advanced rating tools using calculated rating has E-TOOL shown a shorter rating time andhas identified the same potential for cost efficient energy savings in the buildings.
The efficiency of the rating in time is depended on how detailed the examination and registration of thebuilding is required. The calculated rating will in most cases require more data than the operationalrating. The E-TOOL rating took about 1-2 hours for survey and reporting, whereas with calculated
rating takes the process 3-4 hours and it is not feasible at all, because of the low fee, if not the energy
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
48/62
48
rating is combined with a condition rating of the building. The impact of E-TOOL compared with theDK-certificates is difficult to evaluate.
E-TOOL has been developed with focus on Southern European buildings and modified to adapt the
regional differences in climate and buildings. The experts draw the attention to the uncontrolled airfiltration through building joints walls and roofs and other examples characteristic for the Northernclimate.
It was the experts opinion that the surveyor must have a good and broad knowledge about buildingsand installations, combined with experience from the building industry. The more advanced andcomplex rating tool the better qualifications and training. Technical data about the building in form ofdrawings and other as-built documentation are rare available.
The energy performance of a building depends on in general on climate envelope, efficiency of heatinginstallations and use of buildings.
The results of E-TOOL rating depend on representative and transparent data about building andaccounted energy consumption. With regards to the experts acceptance of E-TOOL as a comprehensivetool for energy rating of existing buildings in comparison with the obligatory DK-certification it wasthe opinion, that for smaller, regular buildings as flats, apartments ect.The use of E-TOOL will be limited where a detailed data acquisition is required and nonerepresentative data for energy consumption are available. With additional modifications could E-TOOLmeet the requirements to a additional rating tool for buildings in Northern Europe.
17.2 Feed-back from the market actors
The E-TOOL software was developed to be a simple and practicable tool that could be used by theenergy auditors prior to training and instruction. The efficient tool is in general accepted from themarket actors, such as energy auditors, public administration and private households as end user, as theresults are clear and the proposed implementation of the energy saving measures are given also with aneconomical point of view. Therefore, the inclusion of the investment and pay-back time in the resultsand not only a certificate is important for the real implementation of the measures.
17.3 Training/instruction for using E-TOOL
An important indication if the E-TOOL is simple is that it is easy for energy experts to use the tool withlittle education or training activities. Nevertheless, it has to be underlined that the results depends on thequalification of the auditor.Prior to the Testing with the E-TOOL in the 6 involved partner countries, training activities of theenergy experts were carrying out. Each partner decided on his own how to train the experts and tochoose the necessary academic background of the auditors.
Country Education activity
Austria Training seminars were carried out for 50 energy experts in energy management
and cooling of commercial buildings. As part of the seminars E-TOOL was
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
49/62
49
presented.Bulgaria Training seminar for 15 energy experts presenting the E-TOOL methodology and
software.Denmark The experts involved in testing the E-TOOL had brief instructions, and they were
able to use it directly. They were instructed, if they had any questions.Greece Mini seminars were carried out instructing the energy experts in the software and
methodology of E-TOOLSlovenia Short training instruction of energy experts - no problems for using E-TOOL is
registeredSpain The testing of E-TOOL was carried out by energy experts from the local region.
The public administration technicians of the local government as end users and alocal company that is responsible for the implementation of the energy savingmeasures that are proposed for the public buildings were trained additionally.
From the experience of the regional training activities in connection to preparing regional testingactivities it can be concluded that education of energy experts in using the E-TOOL can be made with ashort instruction for one day or less. This is a clear indicator that the E-TOOL is a simple tool - forenergy experts with experience in energy rating.
17.4 Time required for completing the carry out E-TOOL certification
The time used for completing an E-TOOL certification including survey and reporting to the end-user(house owner) gives a good indication, if the tool is simple and practicable. The time required is also animportant success criteria defined for the E-TOOL, with a maximum of 2-3 hours for a standarddwelling.
As part of the regional testing activities the energy experts carrying out the testing of the E-TOOL wereasked to answer a question of: "Time required for completing the survey and the reporting".
Denmark
For Denmark, a typical value is to perform the test and survey on single dwellings was done within 1-2hours in 95% of the cases.
Greece
In Greece, the time effort is reasonably higher due to the additional time effort for the data baseestablishment as well as due to the fact that more complex buildings were tested.
Spain
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
50/62
50
In Spain the energy rating only included public buildings, most of them larger buildings with a poordata base that had to be established expressively for the project. Therefore, the target of E-TOOL ratingwithin 2-3 hours can't be satisfied. The time spent was up to 7 hours with possibility of reducing to 5hours by improving efficiency.
General overview
From the testing activities it can be concluded, taking the limited number of tests into account, whichthe E-TOOL is able to carry out energy rating within the objective of 2-3 man hours. This only countsfor "standardised buildings".
Nevertheless, the comparison between the countries does not give a representative picture. The mostimportant factor is the availability of the input data and the complexity of the building on the time that
has to be spent for the complete test procedure.
The following table gives an overview on the time spent in some representative partner countries.
Time DK Slovenia ES Greece
0,5 - 1 2 28 0 19
1- 2 95 43 15 22
2 -3 2 17 40 30
3 - 4 1 10 40 22
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
51/62
51
other national certifications. This comparison gives an indication on the quality of the developed toolwithin the frame of the present contract as a simple and user-friendly tool.
The results of E-TOOL rating of single dwellings in Denmark and Slovenia indicate a good consistencyin the overall picture and trends of the two different rating methodologies calculated rating andoperational rating.
Most notable is the difference between the metered and the calculated consumption, the same resultscan be seen from other comparisons in DK of the calculated and metered consumption, they also showsa lower metered consumption than calculated. For both ratings is it clear that the eldest buildings havethe largest saving potential and shortest pay-back time.
Comparison of E-TOOL rating and DK-certificates
Single Dwellings - energy consumption before and aftersaving
Left collumn DK (calculated) - Right collumn E-TOOL (metered)
0
50
100
150
200
250
00-20 20-40 40-60 60-70 70-80 80-00
Year of Contruction
kWh/m
0
10
20
30
40
50Before
After
% saving
pay-back
Before
After
% saving
pay-back
E-TOOL
DK-certif.
Figure 44: Comparison of E-Tool results with assessment audit Single Dwellings (Denmark)
In the case of Slovenia, the E-TOOL results were compared with respect to the calculated energysavings.
18 Support of the implementation of energy savings in buildingby E-TOOL energy rating
18.1 Criteria for the evaluation of the implementation
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
52/62
52
The overall objective of the project has been to develop a tool, which can promote the implementationof the EU building performance building directive. This objective has been "translated" into developinga tool, which can be applied for efficient energy rating of existing buildings.
Above has been described how the E-TOOL performs in relation to: Accessibility of input data Generation of proposals for energy saving measures Generating bench marks of energy consumptions after implementing energy saving measures Need for education of energy experts Time required for the E-TOOL rating
Additionally to these evaluations of the single elements of the E-TOOL has also been carried out anevaluation of the overall performance of the tool in relation to:
Acceptance of results by the clients Accuracy of results - based on the energy experts' experiences.
The evaluation has been carried through the energy experts carrying out the tests of the tool filling out aquestionnaire.
18.2 Acceptance of results by clients
On important aspect in the evaluation process of the E-TOOL project is the acceptance of the outcomeof the results and the functioning of the tool by the experts. In general terms, it can be concluded thatthe clients acceptance of the results is good.
Acceptance Denmark Greece Slovenia Spain
Good 75% 52% 38% 90%Fair 22% 32% 55% 5%
In-sufficient 3% 16% 7% 5%
Results of clients acceptance of the results
In the following, some examples are given that were supplied by the project partners.
Greece
The main reason of the E-Tools relative high acceptance from its users, is the simplicity of the tool andthe fact that the completion of an audit does not require as many working hours like other morecomplex software do, demanding the input of data relative to energy use, geometrical features andbuildings use. Such methodologies aim in simulating the buildings operation and usually do not
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
53/62
53
incorporate any data related to the financial evaluation of the buildings operation and the measuresproposed for the improvement of its energy behaviour. Thus E-Tool proved to be in advance, providingvery useful information regarding the pay-back period of the measures proposed by the auditors,helping the financial directors of the services to have draft estimation on the economics of theinterventions. The presentation of the financial appraisal for a number of occasions proved to be astrong motivation to the clients to take into strong consideration E-Tools results. The relative highlevel of the tools acceptance is presented at the following graph.
Figure 45: Results from questionnaires with experts evaluation (Greece)
Slovenia
External experts from ENSVET energy advisory network that tested E-TOOL in their ever day workexpressed their opinion about the tool. As and additional feature, the partners from Slovenia developed
an own new webpage that was used to collect the experts opinion. This is an important aspect to beconsidered.
Spain
Satisfied 90%
Accepted 5%
Not sufficient (improvements necessary) 5%
The E-TOOL and the corresponding activities are highly accepted by the client. Acceptance of theresults by client was mostly very acceptable like a clearness of results too. The end user, in this case thelocal municipality, was generally spoken satisfied with the results of the E-TOOL. Nevertheless, themain draw-backs came from the availability of the input data. In some buildings it was very time-intensive to get all the needed data. In some cases (special buildings) E-TOOL was considered not to besufficient enough and it was considered to be a too simple tool.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
54/62
54
18.3 Accuracy of the results
In this context, the evaluation is not made by actually carrying out precise energy audits to compare theE-TOOL energy rating. In stead is used a "subjective" evaluation method based on the energy expert'sexperience. The "audit-evaluation" has been made by comparing energy audits and E-TOOL ratings,mentioned previously in the report.
In the case of Slovenia, the external experts from ENSVET energy advisory network that tested E-TOOL in their ever day work expressed their opinion about the tool and as well on the accuracy of theobtained results.
For this purpose, the web-site http://www.gi-zrmk.si/EU_projekti/E-tool was used to collect the expertsresults of testing and their opinions.
Topics: Scope and work programme General invitation to experts to participate in testing Pole (to submitted via internet)
A general overview that came out of the questionnaire and the opinion of the experts are summarized infollowing table.
Accuracy Denmark Greece Slovenia Spain
Good 42% 65% 39% 60%Fair 22% 24% 39% 30%
In-sufficient 36% 11% 22% 10%
Overview on the accuracy of results
The evaluation of the accuracy of the results obtained by E-TOOL is not scope of the work of thepresent project. In order to precise an absolute comparison of the obtained results by E-TOOL based onthe operational rating method with other methods or national certification standards based onassessment rating, it is recommended in further studies within the frame of the EU network to definethe criteria on the accuracy of the results.
The experts that used in the different countries the E-TOOL expressed their singular and subjectiveoption on the tool based on their own experiences while working with other methods and came to theconclusion that the results that have been obtained are within a representative margin and thereforewere considered to be accurate.
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
55/62
55
19 Overall evaluation of E-TOOL for energy rating
Introduction
Above has been described the results of the evaluation of E-TOOL for energy rating with respect todifferent specific evaluation criteria. In this section it is the intention to summarize the results ofevaluation, to discuss the results and to make recommendations on the utilization of E-TOOL, and ingeneral the measures (operational) rating methodology for energy rating of existing buildings.
Summarization of evaluation of single elements.
Evaluation criteria Results "Mark"
Bench marking of energyconsumption
In general specific bench mark data are not available,therefore bench marking is not included in E-TOOL
To beimproved
Accessibility of input data Positive feed-back AcceptableGuidelines for energy savingmeasures
Top 10 energy measures identified, U-values etc. arefixed, output for investment costs and energy savingsacceptable for standard buildings
Good fortypical
buildingsEnergy performance after
implementing energy savings
Acceptable results when comparing with energy audits Acceptable
Accuracy - compare with energyaudit
Acceptable for energy saving measures and energyperformance after implementing energy savingmeasures
Acceptable
Need of education Small need of education GoodTime required Around 2/3
7/29/2019 Http-__WP 1 - D 3.3 Final Publishable Report
56/62
56
Often the results have to be interpreted. The energy experts shall have the know-how and experience toclarify about or assess data, eventual not correct calculations, inter etc. For doing that a high level ofknow-how and experience is required. For the success of the e-tool it is crucial that qualified energyexperts use it.
Therefore a focus was put on the qualification of the advisers. The training seminars organised weresuccessful and ensured that a number of experts are able to use the e-tool.
Bulgaria
The real energy consumption in multi-dwelling buildings in Bulgaria is not relevant for testingthe building, as many households do not heat the whole dwelling or maintain very lowtemperature in the rooms. When using the data from the energy bills it appears that the building
does not need any improvement. This is because we assess not the building, but the userbehaviour For energy certification in Bulgaria we have to assess the whole building, its qualities and
energy characteristics. It is not possible to make this assessment flat by flat. It is very difficult to collect the data regarding the energy consumption. There is always
something missing (either invoices for heating or for electricity) Building can be assessed as a whole with regard to the heat energy consumption, as there is
available data from the district heating companies. But it is not possible to have such data forconsumption of electricity as each flat has its own electrical meter.
The E-TOOL is very useful at the beginning of the refurbishment process, as different energy
saving measures can be easily assessed. The E-TOOL is also useful for public buildings as schools and hospitals were the indoor
temperature should reach a minimal required comfort and the building is managed by oneorganisation.
Denmark
The energy