Input Data

Pondasi Tapak Beton Type Bujursangkar

Project :Gedung Utama Rumah Sakit PropinsiClient :Dinas Kesehatan PropinsiEngineerCheckedApproved

NameErick PattiwaelYogaDate6/16/14 9:44

Data Struktur :Pu

Mu1Dimensi Kolomb=400mm bh=400mmMuka TanahType Koloms
Lutfi: Lutfi:konstanta40 = kolom dalam30 = kolom tepi20 = kolom sudut=302Dimensi PondasiB=2.00mhaL=2.00mB = Lht=0.40m3Mutu Beton fc'=21.6836734694Mpaht4Mutu Bajafy'=320Mpa5Besi tulanganD=16Unit Conversion(dipakai)L6BJ Beton c=24KN/m31Mpa=1000KpaL=101.972t/m2Data Tanah :=0.010t/cm2=101971.621kg/m26Daya dukung tanaht=200Kpa=10.197kg/cm27Berat tanaht=17.20KN/m38Tebal tanah diatas ha=1.20mpondasihBData Beban :B = L9Beban P ultimatePult=384KN10Beban M ultimateMult=18.25KNm

b

ResultCek Status Pondasi :

Tegangan yang terjadi pada tanahmaks=139.927531.36Mpamaka

fc'x bxdAs(3)=4fy

9) Jarak tulangan

0.25xphixD2s=SAs terpilih Pilih "s" yang s2xhtterkecil

s450

Cek Kuat Dukung Fondasi

Pu=x0.85xfc'xA.....( = 0,7 )

Syarat :PultPu

Referensi : Asroni, A., Buku Kolom Fondasi & Balok T Beton Bertulang,

hasil perhitunganJob No.Sheet No1

PartJob TitleRefGedung Utama Rumah Sakit PropinsiEnginnerErick PattiwaelDateClient.Dinas Kesehatan PropinsiFileDate/time6/16/14 9:44

Analisaq =Berat Fondasi+Berat Tanah=ht xc+ha xt=0.40x24+1.20x17.20=30.24KN/m2

Cek Fondasi Terhadap Tegangan Izin Tanah

Tegangan yang terjadi pada tanah

PultMultmaks=++qtBxL1/6BxL2

38418.25=++30.242002.00x2.001/62.00x2.002

=96+13.6875+30.24

=139.928105Not Save

PultMultmin=-+qtBxL1/6BxL2

38418.25=-+30.242002.00x2.001/62.00x2.002

=96-13.6875+30.24

=112.553105Not SaveKontrol Tegangan Geser 1 Arah

0.40ds=75+D/2=75+8.00=83.00mm

d=ht-ds=400-83.000.40=317.00

L=2.00a=B/2-b/2-d=1000-200-317.002.00=483.00mm=0.483ma=min+B-axmaks-minb=112.553+2.00-0.483x139.928-112.5532.002.000.4=133.316KN/m2Gaya tekan ke atas dari tanah (Vu)Vu =axBxmaks+a20.4=0.483x2.00x139.928+133.3162=131.977KN0.400.3170.483Gaya geser yang dapat ditahan oleh beton (.Vc)fc'.Vc=xxBxd621.6836734694=0.75
Lutfi: Lutfi:Faktor reduksi (SKSNI)xx2.00x317.0060.317=369.033KN2.00.Vc=369.033>Vu =131.977.........Save!minamaks112.553133.316139.928Kontrol Tegangan Geser 2 Arah (Geser Pons)Dimensi Kolom,b=400h=400b+d=400.00+317.00=717.00mm=0.717mh+d=400+317.00=717.00mm=0.717mGaya Tekan Ke Atas (Geser Pons)maks+minVu=B2-b+dxh+dx2139.928+112.553=2.002-0.717x0.717x2=440.06140464hk400c
Lutfi: Lutfi:rasio dari sisi panjang terhadap sisi pendek pada kolom, daerah beban terpusat/daerah reaksi===1.000Bk400bo=2xbk+d+hk+dbo=2x400+317.00+400+317.00=2868mmGaya geser yang ditahan oleh beton2fc'bodVc1=1+x0.159c6

0.40221.68367346942868317.00Vc1=1+x0.1591.0006

Vc1=2116775.708N=2116.776KN

0.6420.1590.400.1590.6415s
Lutfi: Lutfi:konstanta40 = kolom dalam30 = kolom tepi20 = kolom sudutdfc'bodVc2=2+xbo12

30
Lutfi: Lutfi:konstanta40 = kolom dalam30 = kolom tepi20 = kolom sudut317.0021.68367346942868317.00Vc2=2+x0.317286812

0.083Vc2=1522631.899N2.00=1522.632KN

1Vc3=xfc'bod31minVc3=x21.68367346942868317.00112.553maks3139.928=1411183.80521534N=1411.184KN

Jadi

Vc1=2116.776Vc2=1522.632Diambil yang terkecilVc3=1411.184

Vc=1411.184KN.Vc=0.75x1411.184=1058.388KN

.Vc=1058.388>Vu =440.061.........Save!Hitungan Penulangan Fondasi0.40ds=75+16+8=99.000mm0.099m0.801.00d=ht-ds=0.40-0.099=0.301m0.400.301=301mm0.099Bh2.00x=-222000400x=-22minxmaksx=800mm112.553128.978139.928=0.8mx=min+B-xxmaks-minBx=112.553+2.00-0.8x139.928-112.5532.00`=128.978KN/m3

maks-xMu=0.5xx2+x23139.928-128.978=0.5128.97812+0.823=43.609KNm

MuK=xbxd243608800.000=0.8x1000x3012=0.602Mpa382.5x0.85x600+fy-225x1fc'Kmaks=600+fy2382.5x0.85x600+320-225x0.8521.6836734694Kmaks=600+3202=6.070MpaK31.36Mpamakafc'x bxdAs=...........(R.2)4fy....... SNI 03-2847-2002 (Pasal 12.5.1)

fc' =21.6836734694Pu,k=384.......OK!SKSNI 03-2847-2002

Program Hitung Pondasi Tapak

Desain Penulangan PondasiJob No.Sheet No3

PartJob TitleRefGedung Utama Rumah Sakit PropinsiEnginnerDateClient.Dinas Kesehatan PropinsiFileDate/time6/16/14 9:44

2.002.00D16-152DETAIL PONDASINon Scale

400D16-152400301992000

POTONGAN 1-1Non Scale

SNI 03-2847-2002 (Pasal 17.4.3)SNI 03-2847-2002 (Pasal 17.7)SNI 03-2847-2002 (Pasal 9.7.1)

Program Hitung Pondasi Tapak1

kontrol program75+0

164.6882.52.51.4x bxdfc'x bxdAs(2)=.......(R.1)As(2')=.......(R.2)fy4fy1.4x 1000x3010x 0x0==32040=1316.875mm2=ERROR:#DIV/0!mm2Status :Tegangan yang terjadi pada tanahmaks=139.9275maks=112.5525t=200Kontrol gaya geser 1 arahVu=131.9768218125.Vc=369.0334218659Kontrol gaya geser 1 arahVu=440.06140464.Vc=1058.3878539115