REKAPITULASI ENGINEER ESTIMATE (E.E NAMA KEGIATAN : PERENCANAAN & PENGAWASAN GEDUNG PEMERI PEKERJAAN : PEMBANGUNAN GEDUNG TYPE B KANTOR KELUR LOKASI : KOTA SURABAYA TAHUN : NO. URAIAN PEKERJAAN PEKERJAAN KANTOR BARU A LANTAI 1 I PEKERJAAN PERSIAPAN II PEKERJAAN TANAH III PEK. BETON (BEKESTING, BESI, BETON) IV PEK. PASANGAN & PLESTERAN V PEK. LANTAI DAN KERAMIK VI PEK. KUSEN DAN PENGGANTUNG VII PEK. PLAFOND VIII PEK. PENGECATAN IX PEKERJAAN TANGGA X PEK. INSTALASI LISTRIK XI PEK. SANITARY XII PEK. TANDON AIR, SEPTICTANK DAN RESAPAN B LANTAI 2 I PEK. BETON (BEKESTING, BESI, BETON) II PEK. PASANGAN & PLESTERAN III PEK. LANTAI DAN KERAMIK IV PEK. KUSEN DAN PENGGANTUNG V PEK. PLAFOND VI PEK. PENGECATAN VII PEKERJAAN ATAP VIII PEK. INSTALASI LISTRIK IX PEK. SANITARY PEKERJAAN KANTOR LAMA I PEK. KERAMIK DAN BATU KLINGKER II PEKERJAAN AKHIR J U M L A H P P N 10 % J U M L A H T O T A L D I B U L A T K A N TERBILANG
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REKAPITULASI ENGINEER ESTIMATE (E.E)
NAMA KEGIATAN : PERENCANAAN & PENGAWASAN GEDUNG PEMERINTAH, PEMERINTAH DAERAHPEKERJAAN : PEMBANGUNAN GEDUNG TYPE B KANTOR KELURAHAN BULAKLOKASI : KOTA SURABAYATAHUN :
NO. URAIAN PEKERJAANJUMLAH HARGA
(Rp.)PEKERJAAN KANTOR BARU
A LANTAI 1I PEKERJAAN PERSIAPAN Rp 6,100,027.80 II PEKERJAAN TANAH Rp 23,580,129.34 III PEK. BETON (BEKESTING, BESI, BETON) Rp 302,170,164.88 IV PEK. PASANGAN & PLESTERAN Rp 71,516,977.63 V PEK. LANTAI DAN KERAMIK Rp 44,315,785.36 VI PEK. KUSEN DAN PENGGANTUNG Rp 17,133,391.00 VII PEK. PLAFOND Rp 17,670,475.38 VIII PEK. PENGECATAN Rp 7,666,898.14 IX PEKERJAAN TANGGA Rp 30,498,624.83 X PEK. INSTALASI LISTRIK Rp 12,187,542.50 XI PEK. SANITARY Rp 6,337,227.10 XII PEK. TANDON AIR, SEPTICTANK DAN RESAPAN Rp 16,613,603.67 B LANTAI 2I PEK. BETON (BEKESTING, BESI, BETON) Rp 115,249,104.21 II PEK. PASANGAN & PLESTERAN Rp 83,113,011.19 III PEK. LANTAI DAN KERAMIK Rp 32,501,731.16 IV PEK. KUSEN DAN PENGGANTUNG Rp 30,720,126.04 V PEK. PLAFOND Rp 24,270,830.30 VI PEK. PENGECATAN Rp 15,690,839.61
VII PEKERJAAN ATAP Rp 151,607,584.49 VIII PEK. INSTALASI LISTRIK Rp 47,621,327.50
IX PEK. SANITARY Rp 11,690,585.30 PEKERJAAN KANTOR LAMA
I PEK. KERAMIK DAN BATU KLINGKER Rp 17,486,218.33 II PEKERJAAN AKHIR Rp 2,851,380.00
J U M L A H 1,088,593,585.77 P P N 10 % 108,859,358.58 J U M L A H T O T A L 1,197,452,944.35
D I B U L A T K A N 1,197,452,000.00
TERBILANG :
Surabaya, CV.GRIYA TEKNIKA
AGUS CAHYANTO., S.T.Direktur
RENCANA ANGGARAN BIAYA
NAMA KEGIATAN : PERENCANAAN & PENGAWASAN GEDUNG PEMERINTAH, PEMERINTAH DAERAH
NAMA PEKERJAAN : PEMBANGUNAN GEDUNG TYPE B KANTOR KELURAHAN BULAK
LOKASI : KOTA SURABAYA
TAHUN :
NO JENIS PEKERJAAN VOL SAT. HARGA SATUAN JUMLAH
(Rp.) (Rp.) PEKERJAAN KANTOR BARU
A LANTAI 1I PEKERJAAN PERSIAPAN
1 Pembongkaran atap dan penutup atap tidak dipakai lagi 136.20 m2 Rp 4,515.00 Rp 614,943.00 2 Pembongkaran plafond dan rangka tidak dipakai kembali 112.50 m2 Rp 4,515.00 Rp 507,937.50 3 Pembongkaran dinding tembok dengan pembersihan 48.96 m3 Rp 45,150.00 Rp 2,210,544.00 4 Pembongkaran Beton 3.15 m3 Rp 70,554.00 Rp 222,245.10 5 Pembuatan bouwplank (Uitset) 28.50 m1 Rp 72,565.00 Rp 2,068,102.50 6 Uitset dengan waterpass & teodolit 291.60 m2 Rp 1,633.25 Rp 476,255.70
SUB TOTAL Rp 6,100,027.80 II PEKERJAAN TANAH
1 Galian Tanah 109.04 m3 Rp 40,635.00 Rp 4,430,956.21 2 Pengangkutan tanah keluar proyek 128.92 m3 Rp 26,725.00 Rp 3,445,447.93 3 Pengurugan tanah kembali 90.75 m3 Rp 13,545.00 Rp 1,229,179.63 4 Pengurugan pasir padat bawah poer & sloef t=10cm 11.37 m3 Rp 151,400.00 Rp 1,721,425.57 5 Pengurugan sirtu 72.00 m3 Rp 102,250.00 Rp 7,362,000.00 6 Pembuatan lubang strouss 70.00 ttk Rp 77,016.00 Rp 5,391,120.00
SUB TOTAL Rp 23,580,129.34 III PEK. BETON (BEKESTING, BESI, BETON)
1 Lantai kerja bawah poer & sloef t = 5 cm 5.69 m3 Rp 490,554.45 Rp 2,788,814.31 2 Pekerjaan beton strouss (Beton K225, Besi 109Kg) 19.78 m3 Rp 2,009,875.58 Rp 39,759,358.72 3 Beton PT1 (Beton K225, Besi 210Kg) 8.06 m3 Rp 3,602,867.70 Rp 29,053,525.13 4 Beton PT2 (Beton K225, Besi 342Kg) 2.02 m3 Rp 4,892,853.54 Rp 9,863,992.74 5 Sloof S1 30/50 (Beton K225, Besi 113Kg) 13.85 m3 Rp 2,894,441.06 Rp 40,095,244.78 6 Sloof S2 20/40 (Beton K225, Besi 194Kg) 2.40 m3 Rp 3,686,023.28 Rp 8,846,455.87 7 Sloof S3 20/30 (Beton K225, Besi 193kg) 0.42 m3 Rp 3,676,250.66 Rp 1,525,644.02 8 Kolom K1 30/40 (Beton K225, Besi 170kg) 6.97 m3 Rp 4,516,492.90 Rp 31,488,988.50 9 Kolom K2 25/25 (Beton K225, besi 215 kg) 2.24 m3 Rp 4,956,260.80 Rp 11,102,024.19
10 Kolom praktis 12/12 KP 66.40 m1 Rp 60,105.36 Rp 3,990,995.90 11 Balok B1 30/60 (Beton K225, Besi 151kg) 6.05 m3 Rp 4,548,155.62 Rp 27,507,245.19 12 Balok B2 20/40 (Beton K225, besi 187kg) 0.78 m3 Rp 4,899,969.94 Rp 3,841,576.43 13 Balok B3 20/40 (Beton K225, besi 154kg) 2.02 m3 Rp 4,577,473.48 Rp 9,228,186.54 14 Plat lantai tebal 12 cm (Beton K225, besi 189 kg) 15.91 m3 Rp 4,745,802.68 Rp 75,515,212.24 15 Balok latei 10/20 78.70 m1 Rp 96,097.84 Rp 7,562,900.30
SUB TOTAL Rp 302,170,164.88 IV PEK. PASANGAN & PLESTERAN
1 Pas. bata 1 : 4 286.76 m2 Rp 76,385.00 Rp 21,903,857.06 2 Plesteran dinding 1 : 4 t = 1,5 cm 428.65 m2 Rp 32,679.00 Rp 14,007,918.71 3 Acian 428.65 m2 Rp 18,705.00 Rp 8,017,935.66 4 Benangan 703.20 m1 Rp 30,252.00 Rp 21,273,206.40 5 Expose beton 337.56 m2 Rp 18,705.00 Rp 6,314,059.80
SUB TOTAL Rp 71,516,977.63 V PEK. LANTAI DAN KERAMIK
1 Urugan Pasir bawah lantai 10 cm 14.49 m3 Rp 151,400.00 Rp 2,193,786.00 2 Rabat lantai t = 5 cm 7.25 m3 Rp 490,554.45 Rp 3,554,066.99 3 Pas. Keramik 40 x 40 Motif (Ruangan & teras) 127.20 m2 Rp 113,506.28 Rp 14,437,998.82 4 Kol - kolan keramik 10x40 cm (ruangan & teras) 110.00 m1 Rp 19,330.00 Rp 2,126,300.00 5 Pas. Keramik 20x20 (toilet) 20.55 m2 Rp 118,185.00 Rp 2,428,701.75 6 Pas. Keramik 20x25 (Toilet) 144.86 m2 Rp 135,130.00 Rp 19,574,931.80
SUB TOTAL Rp 44,315,785.36
NO JENIS PEKERJAAN VOL SAT. HARGA SATUAN JUMLAH
(Rp.) (Rp.) VI PEK. KUSEN DAN PENGGANTUNG
1 Kusen Aluminium 4" 104.60 m1 Rp 84,961.50 Rp 8,886,972.90 2 Pemasangan daun pintu, jendela slimar alumunium 3/8" 12.30 m1 Rp 93,211.50 Rp 1,146,501.45 3 Pemasangan jalusi (hollow alumunium 2x4cm) P1 & P2 16.00 m1 Rp 61,300.00 Rp 980,800.00 4 Pas. Kaca mati rayban 5mm 26.79 m2 Rp 97,827.25 Rp 2,621,202.90 5 Kunci tanam 2x putar (pintu) 9.00 bh Rp 124,344.00 Rp 1,119,096.00 6 Engsel pintu 13.50 stel Rp 30,230.50 Rp 408,111.75 7 Engsel jendela 8.00 stel Rp 30,251.50 Rp 242,012.00 8 Grendel jendela 8.00 bh Rp 41,814.00 Rp 334,512.00 9 Hak angin lurus 8.00 stel Rp 24,614.00 Rp 196,912.00
10 Pintu PVC toilet 3.00 bh Rp 399,090.00 Rp 1,197,270.00 SUB TOTAL Rp 17,133,391.00
VII PEK. PLAFOND1 Plafond Calciboard rangka hollow 132.45 m2 Rp 105,127.40 Rp 13,924,124.13 2 List gypsump 132.03 m' Rp 28,375.00 Rp 3,746,351.25
SUB TOTAL Rp 17,670,475.38 VIII PEK. PENGECATAN
1 Cat Dinding 555.21 m2 Rp 10,936.90 Rp 6,072,298.12 2 Cat plafond 145.80 m2 Rp 10,936.90 Rp 1,594,600.02
SUB TOTAL Rp 7,666,898.14 IX PEKERJAAN TANGGA
1 Balok bordes 20/40 (Beton K225, besi 239kg) 0.34 m3 Rp 5,408,146.18 Rp 1,817,137.12
2 3.44 m3 Rp 5,556,930.14 Rp 19,110,227.18
3 Pas. Keramik Tangga 40 x 40 cm motif kasar 19.09 m2 Rp 113,506.28 Rp 2,167,232.16 4 Pas. Step nosing keramik tangga 5x40 cm 31.05 m1 Rp 27,230.00 Rp 845,491.50 5 Kol - kolan keramik 10x40 cm 25.74 m1 Rp 19,330.00 Rp 497,554.20 6 Pas. Dinding Sandaran 1 Pc : 5 Ps 6.50 m2 Rp 74,643.00 Rp 484,880.93 7 Pas. Ringbalk pd. Sandaran 8.12 m1 Rp 96,097.84 Rp 780,314.49 8 Pas. Kolom praktis 12/12 cm 3.20 m1 Rp 60,105.36 Rp 192,337.15 9 Plesteran tembok 1 Pc : 5 Ps Dinding Sandaran 52.70 m2 Rp 31,513.00 Rp 1,660,672.07
10 Cat (Dinding Sandaran, plat tangga) 68.35 m2 Rp 10,936.90 Rp 747,580.86 11 Benangan sudut 30.30 m1 Rp 30,252.00 Rp 916,635.60 12 Acian 52.70 m2 Rp 18,705.00 Rp 985,716.09 13 expose beton 15.66 m2 Rp 18,705.00 Rp 292,845.48
SUB TOTAL Rp 30,498,624.83 X PEK. INSTALASI LISTRIK
1 Pemasang instalasi lampu 18.00 titik Rp 499,850.00 Rp 8,997,300.00 2 Lampu TL 20 Watt dengan fitting glass 11.00 bh Rp 40,000.00 Rp 440,000.00 3 Lampu SL 14 Watt dengan fitting glass 7.00 bh Rp 32,000.00 Rp 224,000.00 4 Saklar Ganda 7.00 bh Rp 49,392.50 Rp 345,747.50 5 Saklar tunggal 5.00 bh Rp 41,342.50 Rp 206,712.50 6 Stop kontak 8.00 bh Rp 204,342.50 Rp 1,634,740.00 7 Panel MCB 1.00 titik Rp 339,042.50 Rp 339,042.50
SUB TOTAL Rp 12,187,542.50 XI PEK. SANITARY
1 Pas. Closed Jongkok 3.00 bh Rp 376,100.00 Rp 1,128,300.00 2 Pas. Avour lantai metal 3.00 bh Rp 30,000.00 Rp 90,000.00 3 Pas. Kran air 6.00 bh Rp 46,950.00 Rp 281,700.00 4 Pas. Pipa PVC 3/4" (air bersih) 24.10 m' Rp 25,359.50 Rp 611,163.95 5 Pas. Pipa PVC 3" (air kotor) 28.70 m' Rp 45,964.50 Rp 1,319,181.15 6 Pas. Pipa PVC 4" (air Kotoran) 25.00 m' Rp 57,632.00 Rp 1,440,800.00 7 Pas. Wastafel 3.00 bh Rp 488,694.00 Rp 1,466,082.00
SUB TOTAL Rp 6,337,227.10
XII PEK. TANDON AIR, SEPTICTANK DAN RESAPAN
a. PEK. TANDON AIR
1 Galian tanah 15.94 m3 Rp 40,635.00 Rp 647,681.27 2 Lantai kerja t=5cm 0.38 m3 Rp 490,554.45 Rp 186,165.41 3 Plat beton t=15cm, besi 102kg 2.63 m3 Rp 2,547,424.74 Rp 6,692,084.79 4 Keramik 20x20 16.55 m2 Rp 118,185.00 Rp 1,955,961.75 5 Pek. Water profing tandon air 16.55 m2 Rp 28,808.75 Rp 476,784.81
1 Galian tanah 8.58 m3 Rp 40,635.00 Rp 348,648.30 2 Pek. Pas. Bata (1sm : 5ps) 20.80 m2 Rp 74,643.00 Rp 1,552,574.40 3 Pek. Plasteran (1sm : 5ps) 23.12 m2 Rp 31,513.00 Rp 728,580.56 4 Plat beton penutup t=15cm, besi 147kg 0.64 m3 Rp 2,987,192.64 Rp 1,922,258.46 5 Pek ring balok 2.60 m' Rp 96,097.84 Rp 249,854.39 6 Pipa sirkulasi PVC 3' 3.00 m' Rp 45,964.50 Rp 137,893.50
c. PEK. RESAPAN
1 Galian tanah 6.59 m3 Rp 40,635.00 Rp 267,947.19 2 Lantai kerja t=20cm 0.09 m3 Rp 490,554.45 Rp 46,210.23 3 Pek. Pas. Batu merah kosongan 1.08 m3 Rp 480,078.50 Rp 520,069.04 4 Pek. Urugan pasir 0.08 m2 Rp 151,400.00 Rp 11,647.20 5 Pek. Urugan kerikil 3.63 m3 Rp 156,970.00 Rp 569,283.10 6 Plat beton penutup t=15cm, besi 102kg 0.12 m3 Rp 2,547,424.74 Rp 299,959.26
SUB TOTAL Rp 16,613,603.67
B LANTAI 2I PEK. BETON (BEKESTING, BESI, BETON)
1 Kolom K3 30/40 (Beton K225, Besi 174kg) 6.72 m3 Rp 4,555,583.38 Rp 30,613,520.31 2 Kolom K2 25/25 (Beton K225, besi 215 kg) 3.48 m3 Rp 4,956,260.80 Rp 17,235,892.56 3 Kolom praktis 12/12 KP 56.00 m1 Rp 60,105.36 Rp 3,365,900.16 4 Balok B3 20/40 (Beton K225, besi 154kg) 4.76 m3 Rp 4,577,473.48 Rp 21,801,590.69 5 Plat lantai tebal 12 cm (Beton K225, besi 189 kg) 4.64 m3 Rp 4,745,802.68 Rp 22,039,507.65 6 Parapet atap (Beton K225, besi 146 kg) 1.34 m3 Rp 4,325,580.02 Rp 5,787,626.07 7 Balok latei 10/20 149.90 m1 Rp 96,097.84 Rp 14,405,066.78
SUB TOTAL Rp 115,249,104.21 II PEK. PASANGAN & PLESTERAN
1 Pas. bata 1 : 4 329.20 m2 Rp 76,385.00 Rp 25,146,094.77 2 Plesteran dinding 1 : 4 t = 1,5 cm 578.32 m2 Rp 32,679.00 Rp 18,899,050.00 3 Acian 578.32 m2 Rp 18,705.00 Rp 10,817,550.42 4 Benangan 816.80 m1 Rp 30,252.00 Rp 24,709,833.60 5 Expose beton 189.28 m2 Rp 18,705.00 Rp 3,540,482.40
SUB TOTAL Rp 83,113,011.19 III PEK. LANTAI DAN KERAMIK
1 Rabat lantai t = 5 cm 7.20 m3 Rp 490,554.45 Rp 3,531,992.04 2 Pas. Keramik 40 x 40 Motif 115.80 m2 Rp 113,506.28 Rp 13,144,027.22 3 Kol - kolan keramik 10x40 cm 125.00 m1 Rp 19,330.00 Rp 2,416,250.00 4 Pas. Keramik 20x20 (toilet) 21.90 m2 Rp 118,185.00 Rp 2,588,251.50 5 Pas. Keramik 20x25 (Toilet) 80.08 m2 Rp 135,130.00 Rp 10,821,210.40
SUB TOTAL Rp 32,501,731.16 IV PEK. KUSEN DAN PENGGANTUNG
1 Kusen Aluminium 4" 156.40 m1 Rp 84,961.50 Rp 13,287,978.60 2 Pemasangan daun pintu, jendela slimar alumunium 3/8" 97.70 m1 Rp 93,211.50 Rp 9,106,763.55 3 Pemasangan jalusi (hollow alumunium 2x4cm) P1 & P2 12.80 m1 Rp 61,300.00 Rp 784,640.00 4 Pas. Kaca rayban 5mm 39.23 m2 Rp 97,827.25 Rp 3,838,173.89 5 Kunci tanam 2x putar (pintu) 8.00 bh Rp 124,344.00 Rp 994,752.00 6 Engsel pintu 12.00 stel Rp 30,230.50 Rp 362,766.00 7 Engsel jendela 16.00 stel Rp 30,251.50 Rp 484,024.00 8 Grendel jendela 16.00 bh Rp 41,814.00 Rp 669,024.00 9 Hak angin lurus 16.00 stel Rp 24,614.00 Rp 393,824.00
10 Pintu PVC toilet 2.00 bh Rp 399,090.00 Rp 798,180.00 SUB TOTAL Rp 30,720,126.04
V PEK. PLAFOND1 Plafond Calciboard rangka hollow 184.50 m2 Rp 105,127.40 Rp 19,396,005.30 2 List gypsump 171.80 m' Rp 28,375.00 Rp 4,874,825.00
SUB TOTAL Rp 24,270,830.30 VI PEK. PENGECATAN
1 Cat Dinding 555.21 m2 Rp 10,936.90 Rp 6,072,298.12 2 Cat plafond 145.80 m2 Rp 10,936.90 Rp 1,594,600.02 3 Pelapisan water proofing toilet 21.90 m2 Rp 28,808.75 Rp 630,911.63 4 Pengecatan besi 165.60 m2 Rp 44,643.90 Rp 7,393,029.84
NO JENIS PEKERJAAN VOL SAT. HARGA SATUAN JUMLAH
(Rp.) (Rp.) SUB TOTAL Rp 15,690,839.61
VII PEKERJAAN ATAP1 Kuda kuda WF.150.75.5.7 847.00 kg Rp 20,744.00 Rp 17,570,168.00 2 Gording CNP.125 1,103.40 kg Rp 20,744.00 Rp 22,888,929.60 3 Ikatan angin besi 16 72.62 kg Rp 20,744.00 Rp 1,506,362.90 4 Penggantung gording besi 12 52.80 kg Rp 20,744.00 Rp 1,095,283.20 5 Angkur diameter 16 44.24 kg Rp 20,744.00 Rp 917,714.56 6 Baut kuda-kuda 24.70 kg Rp 20,744.00 Rp 512,293.82 7 Plat plendes t=12mm 118.69 kg Rp 20,744.00 Rp 2,462,146.85 8 Plat pemyambung t=10mm 204.00 kg Rp 20,744.00 Rp 4,231,814.90 9 Plat rib t=6mm 74.18 kg Rp 20,744.00 Rp 1,538,841.78
10 Dudukan gording L.40.40.4 32.19 kg Rp 20,744.00 Rp 667,666.38 11 Batang tarik besi dia.16 77.42 kg Rp 20,744.00 Rp 1,606,000.48 12 Jarum keras 140.00 kg Rp 20,744.00 Rp 2,904,160.00 13 Baut gording 100.80 kg Rp 20,744.00 Rp 2,090,995.20 14 Hak talang L.40.40.4 165.53 kg Rp 20,744.00 Rp 3,433,712.83 15 Pek. Pasang usuk reng galvalum 165.60 m2 Rp 284,325.00 Rp 47,084,220.00 16 Pas. Genteng karang pilang 165.60 m2 Rp 136,410.00 Rp 22,589,496.00 17 Pas. Bubungan karang pilang 18.00 m1 Rp 91,589.00 Rp 1,648,602.00 18 Pek. Waterproofing plat atap 38.70 m2 Rp 28,808.75 Rp 1,114,898.62 19 Pek. Talang Pembuluh pipa 4' 112.00 m' Rp 77,624.53 Rp 8,693,947.36 20 Pas. Talang Tritisan BJLS 30 (lebar 90cm) 18.00 m' Rp 181,005.00 Rp 3,258,090.00 21 Pas. List plank 3/30 36.00 m' Rp 105,340.00 Rp 3,792,240.00
SUB TOTAL Rp 151,607,584.49 VIII PEK. INSTALASI LISTRIK
1 Pemasang instalasi lampu 17.00 titik Rp 499,850.00 Rp 8,497,450.00 2 Lampu TL 20 Watt dengan fitting glass 13.00 bh Rp 40,000.00 Rp 520,000.00 3 Lampu SL 14 Watt dengan fitting glass 4.00 bh Rp 32,000.00 Rp 128,000.00 4 Saklar Ganda 5.00 bh Rp 49,392.50 Rp 246,962.50 5 Saklar tunggal 2.00 bh Rp 41,342.50 Rp 82,685.00 6 Stop kontak 8.00 bh Rp 204,342.50 Rp 1,634,740.00 7 Panel MCB 1.00 titik Rp 339,042.50 Rp 339,042.50 8 Pas. Penangkal Petir 2.00 bh Rp 16,086,223.75 Rp 32,172,447.50 9 Pas. Pompa air 2.00 unit Rp 2,000,000.00 Rp 4,000,000.00
SUB TOTAL Rp 47,621,327.50 IX PEK. SANITARY
1 Pas. Closed Jongkok 2.00 bh Rp 376,100.00 Rp 752,200.00 2 Pas. Avour lantai metal 2.00 bh Rp 30,000.00 Rp 60,000.00 3 Pas. Kran air 6.00 bh Rp 46,950.00 Rp 281,700.00 4 Pas. Pipa PVC 3/4" (air bersih) 38.30 m' Rp 25,359.50 Rp 971,268.85 5 Pas. Pipa PVC 3" (air kotor) 11.30 m' Rp 45,964.50 Rp 519,398.85 6 Pas. Pipa PVC 4" (air Kotoran) 11.30 m' Rp 57,632.00 Rp 651,241.60 7 Pas. Wastafel 4.00 bh Rp 488,694.00 Rp 1,954,776.00 8 Pas. Tandon almunium air kap. 1000L 2.00 bh Rp 3,250,000.00 Rp 6,500,000.00
SUB TOTAL Rp 11,690,585.30
PEKERJAAN KANTOR LAMAI PEK. KERAMIK DAN BATU KLINGKER
1 Urugan Pasir bawah lantai 10 cm 5.18 m3 Rp 151,400.00 Rp 784,252.00 2 Rabat lantai t = 5 cm 2.59 m3 Rp 490,554.45 Rp 1,270,536.03 3 Pas. Keramik 40 x 40 Motif (Ruangan & teras) 51.80 m2 Rp 113,506.28 Rp 5,879,625.30 4 Pas. Batu klingker 32.25 m2 Rp 296,180.00 Rp 9,551,805.00
SUB TOTAL Rp 17,486,218.33 II PEKERJAAN AKHIR
1 Pembersihan Akhir 383.25 m2 Rp 7,440.00 Rp 2,851,380.00 SUB TOTAL Rp 2,851,380.00
NO DESCRIPTION UNIT W H L RATE QTY TOTAL REMARKS
(lebar) (tinggi) (panjang)
m m m pcs
(a) (b) (a x b )
A LANTAI 1
I PEKERJAAN PERSIAPAN1 Pembongkaran atap dan penutup atap tidak dipakai lagi m2 9.08 15 136.20 1 136.20
2 Pembongkaran plafond dan rangka tidak dipakai kembali m2 7.5 15 112.50 1 112.50
20.01.01.05.05.03 Batu Pecah Mesin 1/2 cm 0.8100 m3 254,000.00 205,740.00Besi Beton (polos/ulir) 154.0000 Kg 9,772.62 1,504,983.48
Kawat Ikat Beton 3.0000 Kg 15,350.00 46,050.00
20.01.05.02.04.06 Kayu meranti bekisting 0.3200 m3 2,400,000.00 768,000.00Kayu kamper balok 3/5 0.1400 m3 6,000,000.00 840,000.00Dolken kayu gelam dia 8-10 cm, panjang 4m 4.0000 Batang 0.00
NOMOR URAIAN KEGIATAN KOEF. SATUAN HARGA HARGA
SATUAN
Plywood tebal 9 mm 2.8000 Lembar 95,000.00 266,000.00Paku usuk 3.2000 Kg 12,000.00 38,400.00Minyak bekesting 1.6000 ltr 4,800.00 7,680.00
20.01.01.05.05.03 Batu Pecah Mesin 1/2 cm 0.0200 m3 254,000.00 5,080.00Besi Beton (polos/ulir) 4.7999 Kg 9,772.62 46,907.60
Kawat Ikat Beton 0.0667 Kg 15,350.00 1,023.84
20.01.05.02.04.06 Kayu meranti bekisting 0.0040 m3 2,400,000.00 9,600.00Paku usuk 0.0267 Kg 12,000.00 320.40
Jumlah: Rp 70,147.44
NOMOR URAIAN KEGIATAN KOEF. SATUAN HARGA HARGA
SATUAN
Nilai HSPK : Rp 96,097.84
D PEKERJAAN DINDING
24.04.01 Dinding & Plesteran
24.04.01.8 Pemasangan Batu Merah 1 Pc : 4 Ps (tabal 1/2 bata) m2
Upah:
23.06.01.01.04 Mandor 0.0150 O.H 65,000.00 975.0023.06.01.01.01 Kepala Tukang Batu 0.0100 O.H 60,000.00 600.0023.06.01.03.01 Tukang Batu 0.1000 O.H 55,000.00 5,500.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.3000 O.H 41,900.00 12,570.00
Jumlah: 19,645.00
Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.2300 Zak 55,000.00 12,650.0020.01.01.04.03 Pasir Pasang 0.0430 m3 130,000.00 5,590.0020.01.01.21.03 Batu Bata Merah uk 22 x 11 x 4.5 cm 70.0000 Buah 550 38,500.00
Jumlah: 56,740.00
Nilai HSPK : 76,385.00
24.04.01.11 Pemasangan Batu Merah Kosongan m3
Upah:
23.02.03.01.02 Mandor 0.0495 O.H 65,000 3,217.50
23.02.03.01.01 Kepala Tukang Batu 0.0330 O.H 60,000 1,980.00
23.02.03.01.04 Tukang Batu 0.3300 O.H 55,000 18,150.00
23.02.03.01.05 Pekerja/Buruh Tak Terampil 0.9900 O.H 41,900 41,481.00
Jumlah: 64,828.50
Bahan:
20.01.01.18.02 Batu Bata Merah uk 22 x 11 x 4.5 cm 755.0000 Buah 550 415,250.00
Jumlah: 415,250.00
Nilai HSPK : 480,078.50
24.04.01.9 Pemasangan Batu Merah 1 Pc : 5 Ps (tebal 1/2 bata) m2
Upah:
23.06.01.01.04 Mandor 0.0150 O.H 65,000.00 975.0023.06.01.01.01 Kepala Tukang Batu 0.0100 O.H 60,000.00 600.0023.06.01.03.01 Tukang Batu 0.1000 O.H 55,000.00 5,500.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.3000 O.H 41,900.00 12,570.00
Jumlah: 19,645.00
Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.1936 Zak 55,000.00 10,648.0020.01.01.04.03 Pasir Pasang 0.0450 m3 130,000.00 5,850.0020.01.01.21.03 Batu Bata Merah uk 22 x 11 x 4.5 cm 70.0000 Buah 550 38,500.00
Jumlah: 54,998.00
Nilai HSPK : 74,643.00
24.04.01.22 Pembongkaran Dinding Tembok Dengan Pembersihan m2
23.06.01.01.04 Mandor 0.0100 O.H 65,000.00 Rp 650.00 23.06.01.01.01 Kepala Tukang Batu 0.0100 O.H 60,000.00 Rp 600.00 23.06.01.03.01 Tukang Batu 0.1000 O.H 55,000.00 Rp 5,500.00 23.06.01.04.04 Pekerja/Buruh Tak Terampil 0.2000 O.H 41,900.00 Rp 8,380.00
Jumlah: Rp 15,130.00
Bahan:
20.01.01.02.02 Semen portland (50 kg) 0.0650 Zak 55,000.00 Rp 3,575.00 Jumlah: Rp 3,575.00
Nilai HSPK : Rp 18,705.00
24.04.02 FINISHING DINDING
24.04.02.01 Pemasangan Batu Klingker m2
Upah:
23.06.01.01.04 Mandor 0.0350 O.H 65,000.00 2,275.0023.06.01.01.01 Kepala Tukang Batu 0.0350 O.H 60,000.00 2,100.0023.06.01.03.01 Tukang Batu 0.3500 O.H 55,000.00 19,250.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.7000 O.H 41,900.00 29,330.00
Jumlah: 52,955.00
Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.2350 Zak 55,000.00 12,925.0020.01.01.04.03 Pasir Pasang 0.0350 m3 130,000.00 4,550.0020.01.01.05.06.02 Batu Klingker 52.5000 m2 4,300 225,750.00
Cat meni kayu 0.1500 Kg 30,400.00 4,560.00Plamir 0.3000 kg 33,700.00 10,110.00Cat Kayu 0.2000 kg 48,067.00 9,613.40Cat penutup 0.3000 kg 37,500.00 11,250.00
Jumlah: 35,533.40
Nilai HSPK : 44,643.90
E PEKERJAAN LANTAI
24.05.01 Lantai
24.05.01.01 Pemasangan Tegel Keramik 20x20 cm m2
Upah:
23.06.01.01.04 Mandor 0.0350 O.H 65,000.00 Rp 2,275.00 23.06.01.01.01 Kepala Tukang Batu 0.0350 O.H 60,000.00 Rp 2,100.00 23.06.01.03.01 Tukang Batu 0.3500 O.H 55,000.00 Rp 19,250.00 23.06.01.04.04 Pekerja/Buruh Tak Terampil 0.7000 O.H 41,900.00 Rp 29,330.00
Jumlah: 52,955.00
Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.2080 Zak 55,000.00 11,440.0020.01.01.02.05 Semen Berwarna Yiyitan 1.6200 Kg 8,000.00 12,960.0020.01.01.04.03 Pasir Pasang 0.0450 m3 130,000.00 5,850.0020.01.01.38.02.02 Tegel Keramik 20 x 20 Cm (bermotif) 1.0600 m2 33,000.00 34,980.00
Upah:23.06.01.01.04 Mandor 0.0350 O.H 65,000.00 Rp 2,275.00 23.06.01.01.01 Kepala Tukang Batu 0.0350 O.H 60,000.00 Rp 2,100.00 23.06.01.03.01 Tukang Batu 0.3500 O.H 55,000.00 Rp 19,250.00 23.06.01.04.04 Pekerja/Buruh Tak Terampil 0.7000 O.H 41,900.00 Rp 29,330.00
Jumlah: Rp 52,955.00 Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.1960 Zak 55,000.00 10,780.0020.01.01.02.05 Semen Berwarna Yiyitan 1.3000 Kg 8,000.00 10,400.0020.01.01.04.03 Pasir Pasang 0.0450 m3 130,000.00 5,850.0020.01.01.38.02.05 Tegel Keramik 40x40 (motif/warna gelap) 1.0608 m2 31,600.00 33,521.28
Jumlah: 60,551.28Nilai HSPK : 113,506.28
24.05.01.07 Pemasangan Tegel Keramik 20x25 cm (Dinding) m2
Upah:23.06.01.01.04 Mandor 0.0450 O.H 65,000.00 2,925.0023.06.01.01.01 Kepala Tukang Batu 0.0450 O.H 60,000.00 2,700.0023.06.01.03.01 Tukang Batu 0.4500 O.H 55,000.00 24,750.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.9000 O.H 41,900.00 37,710.00
Jumlah: 68,085.00Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.1860 Zak 55,000.00 10,230.0020.01.01.02.05 Semen Berwarna Yiyitan 1.9400 Kg 8,000.00 15,520.0020.01.01.04.03 Pasir Pasang 0.0180 m3 130,000.00 2,340.0020.01.01.38.02.01 Tegel Keramik 20 x 25 Cm (dinding) 1.0500 m2 37,100.00 38,955.00
Jumlah: 67,045.00Nilai HSPK : 135,130.00
24.05.01.10 Pemasangan Tegel Plin Dinding Keramik uk. 10x40 cm m'
Upah:23.06.01.01.04 Mandor 0.0050 O.H 65,000.00 325.0023.06.01.01.01 Kepala Tukang Batu 0.0090 O.H 60,000.00 540.0023.06.01.03.01 Tukang Batu 0.0900 O.H 55,000.00 4,950.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.0900 O.H 41,900.00 3,771.00
Jumlah: 9,586.00Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.0228 Zak 55,000.00 1,254.0020.01.01.02.05 Semen Berwarna Yiyitan 0.0250 Kg 8,000.00 200.0020.01.01.04.03 Pasir Pasang 0.0030 m3 130,000.00 390.0020.01.01.38.02.08 Tegel Plint Keramik warna/motif 0.2500 Buah 31,600.00 7,900.00
Jumlah: 9,744.00Nilai HSPK : 19,330.00
24.05.01.10 Pemasangan step nosing uk 5x40 m'
Upah:23.06.01.01.04 Mandor 0.0050 O.H 65,000.00 325.0023.06.01.01.01 Kepala Tukang Batu 0.0090 O.H 60,000.00 540.0023.06.01.03.01 Tukang Batu 0.0900 O.H 55,000.00 4,950.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.0900 O.H 41,900.00 3,771.00
Jumlah: 9,586.00Bahan:
20.01.01.02.02 Semen PC (Portland Cement) 50 kg 0.0228 Zak 55,000.00 1,254.0020.01.01.02.05 Semen Berwarna Yiyitan 0.0250 Kg 8,000.00 200.0020.01.01.04.03 Pasir Pasang 0.0030 m3 130,000.00 390.0020.01.01.38.02.08 Tegel Plint Keramik warna/motif 0.5000 Buah 31,600.00 15,800.00
Jumlah: 17,644.00Nilai HSPK : 27,230.00
F PEKERJAAN ATAP
24.06.01 Rangka Atap
24.06.01.04 Pekerjaan Kuda kuda WF kg
Upah:Mandor 0.0030 O.H 65,000.00 195.00
Pemasangan Tegel Keramik 40x40 cm (Motif/Warna Gelap)
NOMOR URAIAN KEGIATAN KOEF. SATUAN HARGA HARGA
SATUAN
Kepala Tukang 0.0060 O.H 60,000.00 360.00Tukang Las 0.0600 O.H 55,000.00 3,300.00Pekerja/Buruh Tak Terampil 0.0600 O.H 41,900.00 2,514.00
Jumlah: 6,369.00Bahan:Besi profil WF 1.1500 kg 12,500.00 14,375.00
Upah:23.06.01.01.04 Mandor 0.0300 O.H 65,000.00 1,950.0023.06.01.01.03 Kepala Tukang Kayu 0.2000 O.H 60,000.00 12,000.0023.06.01.03.05 Tukang Kayu 2.0000 O.H 55,000.00 110,000.0023.06.01.04.04 Pekerja/Buruh Tak Terampil 0.6000 O.H 41,900.00 25,140.00
Jumlah: 149,090.00Bahan:Daun Pintu PVC 1.0000 bh 250,000.00 Rp 250,000.00
Jumlah: 250,000.00Nilai HSPK : 399,090.00
24.07.02 Instalasi Listrik
24.07.02.01 Pemasangan Titik Stop Kontak Gedung TitikUpah:
23.06.02.01.03 Kepala Tukang Listrik 0.0500 O.H 60,000.00 3,000.0023.06.02.03.04 Tukang Listrik 0.2000 O.H 55,000.00 11,000.0023.06.01.02.01 Pekerja Terampil 0.0010 O.H 42,500.00 42.50
Jumlah: 14,042.50Bahan
20.03.06.05.01.01 Stop Kontak (broco) 1.0000 Buah 17,500.00 Rp 17,500.00 20.03.06.01.01.08 Kabel NYA 500 Volt 2 x 2,5 mm2 10.0000 m1 16,400.00 Rp 164,000.00 20.05.04.01.02.01 Pipa Pralon 5/8 1.0000 Lonjor 6,600.00 6,600.0020.05.01.05.13 T Doos Pvc 1.0000 Buah 2,200.00 Rp 2,200.00
Jumlah: 190,300.00Nilai HSPK : 204,342.50
24.07.02.02 Pemasangan Titik Lampu Gedung TitikUpah:
23.06.02.01.03 Kepala Tukang Listrik 0.0500 O.H 60,000.00 3,000.0023.06.02.03.04 Tukang Listrik 0.5000 O.H 55,000.00 27,500.0023.06.01.02.01 Pekerja Terampil 0.3000 O.H 42,500.00 12,750.00
Jumlah: 43,250.00
BahanIsolator 4.0000 Buah 32,750.00 Rp 131,000.00 Kabel NYA 500 Volt 2 x 2,5 mm2 10.0000 m1 16,400.00 Rp 164,000.00 Pipa Pralon 5/8 1.0000 Lonjor 6,600.00 Rp 6,600.00 T Doos Pvc 1.0000 Buah 2,200.00 Rp 2,200.00 Fiting Plafon 1.0000 Buah 152,800.00 Rp 152,800.00 Las Doof 1.0000 bh 5,000.00 Rp 5,000.00
Jumlah: 456,600.00Nilai HSPK : 499,850.00
24.07.02.03 Pemasangan Saklar Tunggal TitikUpah:
23.06.02.01.03 Kepala Tukang Listrik 0.0500 O.H 60,000.00 3,000.00
Nilai HSPK : 588,210.0024.07.02.04 Pemasangan Penangkal Petir Unit
Upah:23.06.01.01.04 Mandor 0.0050 O.H 65,000.00 325.0023.06.02.01.03 Kepala Tukang Listrik 0.0500 O.H 60,000.00 3,000.0023.06.02.03.04 Tukang Listrik 0.2000 O.H 55,000.00 11,000.0023.06.01.02.01 Pekerja Terampil 0.0010 O.H 42,500.00 42.50
Jumlah: 14,367.50Bahan
23.06.01.02.01 Head Penangkal Petir modern non radio aktif R 132m 1.0000 bh 450,000.00 450,000.0023.06.01.02.01 Down Conductor Ericor Cable BC 50 mm 1.0000 m1 84,981.25 84,981.2523.06.01.02.01 Dudukan Tiang Openangkal Petir 3.0000 bh 2,675,812.50 8,027,437.5023.06.01.02.01 Lighting Strike Counter 1.0000 bh 4,775,812.50 4,775,812.5023.06.01.02.01 Obstruction Lamp 1.0000 bh 1,319,625.00 1,319,625.0023.06.01.02.01 Grounding Penangkal Petir 1.0000 bh 1,414,000.00 1,414,000.00
Jumlah: 16,071,856.25Nilai HSPK : 16,086,223.75
No Namadan Spesifikasi Satuan Harga(Rp) Keterangan
1 2 3 4 5
I MATERIAL.
Air (Biaya air tawar) ltr Rp 13.00 Aluminium 4\" M1 Rp 62,500.00 Aluminium coklat uk. 3x7,5, profil 3" M1 Rp 55,000.00 Aluminium putih uk. 3x7,5, profil 3" M1 Rp 52,500.00 Batu kali pecah15/20 m3 Rp 130,100.00 180.00 Batu pecah mesin 1/2 m3 Rp 254,000.00 Batu pecah mesin 2/3 m3 Rp 160,000.00 200.00 Batu Kali Pecah 5/7 M3 Rp 120,000.00 200.00 Batu Kerikil M3 Rp 120,600.00 Bata merah (kelas 1) Bh Rp 550.00 650.00 Besi beton polos/ulir Kg Rp 9,772.62 8,750.00 Besi Profil WF Kg Rp 12,500.00 9,000.00 Cat Genteng kg Rp 100,000.00 30.00 Cat tembok luar Kg Rp 30,000.00 35.00 Cat dasar (dempul tembok) Kg Rp 13,660.00 Cat Meni Besi Kg Rp 39,900.00 20.00 Cat Meni Kayu Kg Rp 30,400.00 20.00 Cat Kayu Kg Rp 48,067.00 45.00 Cat Penutup Kayu Kg Rp 37,500.00 20.00 Closed Jongkok Porselain bh Rp 142,800.00 Closed Duduk Porselain bh Rp 450,000.00 800,000.00 Daun pintu PVC bh Rp 250,000.00 Engsel Kuningan ARCH u Pintu Stel Rp 20,400.00 Engsel Kuningan ARCH u Jendela Stel Rp 23,700.00 20.40 Fitting Plafond Bh Rp 152,800.00 9,750.00 Glass Blok bh Rp 12,000.00 Grendel Biasa Kecil bh Rp 32,700.00 7,000.00 Grendel Tanam bh Rp 67,100.00 10,000.00 Kalsiboard EG Uk. 240 x 120 x 9mm Lembar Rp 46,000.00 60,000.00 Hakangin Lurus kuningan bisa disetel maju/mundur bh Rp 15,500.00 25,000.00 Isolator Bh Rp 32,750.00 5,000.00 Kawat Bendrat Kg Rp 15,350.00 Kayu Kamper Balok (6/15) m3 Rp 3,400,000.00 6,500,000.00 Kayu Kamper balok 8/12 m3 Rp 7,500,000.00 6,500,000.00 Kayu Kamper 3/30 cm m3 Rp 8,000,000.00 6,500,000.00 Kayu Kamper 1/5cm m1 Rp 6,000,000.00 3,000.00 Kayu kamper (slimar) m3 Rp 6,750,000.00 Kayu Kamper Usuk m3 Rp 6,500,000.00 Kayu Kamper reng (balok 3/5) m3 Rp 6,000,000.00 Kayu Meranti Balok 8/12 m3 Rp 3,400,000.00 5,500,000.00 Kayu Meranti Usuk 4/6dan5/7 m3 Rp 3,100,000.00 5,500,000.00 Kayu Meranti Usuk balok 5/7 m3 Rp 6,500,000.00 5,500,000.00 Kayu Meranti (Bekisting) m3 Rp 2,400,000.00 5,500,000.00 Kayu Meranti papan 2/20 m3 Rp 3,500,000.00 5,500,000.00 Keramik 20x20cm motif m2 Rp 33,000.00 37,100.00 Keramik dinding 20x25 m2 Rp 37,100.00 Keramik 40x 40cm (motif/warnagelap) m2 Rp 31,600.00 43,100.00 Keramik tegel plint warna/motif 7,5x20 M1 Rp 4,900.00 25,000.00 Kertas gosok No. 150 Lbr Rp 2,500.00 Kertas gosok No. 280 Lbr Rp 2,500.00 Kran air Ex Import Bh Rp 27,900.00
Kuas Bh Rp 7,500.00 Kunci Tanam besar 2x putar kuningan Bh Rp 95,500.00 Kaca Reyben t = 5 mm m2 Rp 80,000.00 65,000.00
No Namadan Spesifikasi Satuan Harga(Rp) Keterangan
1 2 3 4 5Kabel NYA 500 volt 2x 2,5 Mm2 m Rp 16,400.00 11,500.00 Las Doof bh Rp 5,000.00 1,000.00 Lampu TL 18 Watt bh Rp 40,000.00 12,500.00 Lampu SL 14 Watt bh Rp 32,000.00 Lampu Tempel hias SL 18 Watt bh Rp 130,000.00 Lapis triplek 0,4cm lbr Rp 49,000.00 Lem kayu kg Rp 25,000.00 10,000.00 Lem PVC bh Rp 11,650.00 6,000.00 List plafond Gypsum bh Rp 12,500.00 Minyak Cat (Afdunner) Ltr Rp 7,500.00 Minyak Bekisting Ltr Rp 4,800.00 Minyak pelumas Ltr Rp 24,400.00 Metal stud M2 Rp 4,262,050.00 70,000.00 MCB MG 10A bh Rp 325,000.00 50,000.00 Paku kayu Kg Rp 14,500.00 Paku reng Kg Rp 12,500.00 Paku usuk Kg Rp 12,000.00 skrup Bh Rp 3,700.00 250.00 Paku sumbat Bh Rp - Paku triplek/eternit Kg Rp 14,000.00 Paku Asbes Kg Rp 14,500.00 Pasir Cor m3 Rp 14,500.00 180,000.00 Paku Klem (No.4) kg Rp 14,500.00 Paku Klem (No.4) doz Rp 27,100.00 Paku Biasa 2"-5" kg Rp 12,500.00 Pasir Pasang m3 Rp 130,000.00 160,000.00 Pasir Urug m3 Rp 115,000.00 140,000.00 Pipa paralon 5/8\" m Rp 6,600.00 Pewarna sct Rp 900.00 Pipa Galvanis Ø 2" BT Rp 93,200.00 Pipa PVC Ø1/2\ "Type AW batang Rp 25,450.00 Pipa PVC Ø3/4\ "Type AW batang Rp 30,850.00 Pipa PVC Ø1\ "Type AW batang Rp 38,750.00 Pipa PVC Ø11/2\ "Type AW batang Rp 71,550.00 57,000.00 Pipa PVC Ø3\ "AW panjang 6 mtr ljr Rp 194,500.00 90,000.00 Pipa PVC Ø4\ "AW panjang 4 mtr ljr Rp 283,400.00 140,000.00 Pipa PVC Ø5\ "AW panjang 4 mtr ljr Rp 446,900.00 200,000.00 Pipa PVC Ø2\"C LJR Rp 42,500.00 25,000.00 Pipa PVC Ø4\"C batang Rp 80,500.00 55,000.00 Pipa PVC Ø3\"C batang Rp 62,550.00 35,000.00 Pipa PVC Ø5\"C batangPipa PVC Ø6\"C ljrPlamur Tembok kg Rp 104,100.00 15,000.00 Plamur Kayu kg Rp 33,700.00 17,500.00 Plywood tebal 9mm lbr Rp 95,000.00 105,000.00 Saklar Tunggal Bh Rp 27,300.00 15,000.00 Saklar Ganda Bh Rp 35,350.00 25,000.00 Shanding kg Rp 55,000.00 Rangka Galvalum m2 Rp 237,400.00 220,000.00 Semen Pc 50kg Zak Rp 55,000.00 Semen Pc 40kg Zak Rp 48,000.00 48,500.00 Semen berwarna yiyitan kg Rp 8,000.00 Serat fiber m2 Rp 9,000.00 6,000.00 Sirtu m3 Rp 75,000.00 140,000.00 Slimar Alumunium3/8" m1 Rp 70,000.00 Sealent tube Rp 70,300.00 22,000.00 Stop Kontak Broco Bh Rp 17,500.00 T doos PVC Bh Rp 2,200.00 Triplek uk. 110x244 t=4mm Lbr Rp 49,000.00 Triplek uk. 110x244 t=4mm Lbr Rp 38,000.00 Teer Kg Rp 7,000.00 Thinner A ltr Rp 21,600.00 Tiang Pancang 20/20 M Rp 142,500.00
No Namadan Spesifikasi Satuan Harga(Rp) Keterangan
1 2 3 4 5Tiang Pancang 25/25 m Rp 142,500.00 180,000.00 Tiang Pancang30/30 m Rp 142,500.00 220,000.00 Wastafel Besar Warna bh Rp 298,700.00 Waterproofing kg Rp 37,075.00 50,000.00 Besi Hollow 2/4 m1 Rp 13,800.00 Got talang R25 (1/2 lingkaran) bh Rp 25,000.00 40,000.00 Besi pipa putih (steinless)SCH 40 welded bh Rp 95,300.00 Head Penangkal Petir modern non radio aktif R 13 bh Rp 450,000.00 5,000,000.00 Down Conductor Ericor Cable BC 50 mm m1 Rp 84,981.25 Dudukan Tiang Openangkal Petir bh Rp 2,675,812.50 Lighting Strike Counter bh Rp 4,775,812.50 Obstruction Lamp bh Rp 1,319,625.00 Grounding Penangkal Petir bh Rp 1,414,000.00 tandon air plastik kapasitas 1000 liter Rp 1,500,000.00 tandon air stanles kapasitas 1000 liter bh Rp 3,250,000.00 Urinoir bh Rp 350,000.00 Sunscreen m2 Rp 275,000.00 Pompa air submersible unit Rp 2,000,000.00 Avour lantai metal bh Rp 30,000.00
II TENAGA
Mandor hr Rp 65,000.00 Surveyor Geodesi hr Rp 60,000.00 KepalaTukang Batu hr Rp 60,000.00 KepalaTukang Besi hr Rp 60,000.00 KepalaTukang Cat hr Rp 60,000.00 KepalaTukang Kayu hr Rp 60,000.00 KepalaTukang Listrik hr Rp 60,000.00 KepalaTukang Pipa hr Rp 60,000.00 Tukang Batu hr Rp 55,000.00 Tukang Besi hr Rp 55,000.00 Tukang Cat hr Rp 55,000.00 Tukang Kayu hr Rp 55,000.00 Tukang Las hr Rp 55,000.00 Tukang Listrik hr Rp 55,000.00 Tukang Pipa hr Rp 55,000.00 PekerjaTerampil hr Rp 42,500.00 Pekerja/ BuruhTakTerampil hr Rp 41,900.00
III. PERALATAN
Sewa Compresor Jam Rp 35,000.00 Sewa Concreate Mixer 0.50m3 (min 3jam) Jam Rp 50,000.00 Sewa Concreate Pump (min 3 jam ) Jam Rp 25,000.00 Sewa Concreate vibrator Jam Rp 15,000.00 Sewa Crane 30ton-min8jam (termasuk mob/demob.Opertor, BBM) Jam Rp 225,000.00 Sewa Hammer tiang pancang-min8jam (termasukmob/demob,operator, BBM) Jam Rp 185,000.00 Sewa Bucket dan crane/draglin scraper Jam Rp 80,000.00 Sewa Motor Grader125-140Pk (min5jam) Jam Rp 270,000.00 Sewa PhenumaticTire Roller (min5jam) Jam Rp 155,000.00 SewaTruck Tangki Air (min 5 jam) Jam Rp 250,000.00 Sewa Vibrator Roller (min 5 jam) Jam Rp 135,000.00 Sewa Excavator 6m Jam Rp 130,000.00 SewaTheodolit set Rp 100,000.00 Sewa Welding Set (min 5 jam) hari Rp 30,000.00 Sewa Alat Bantu (1 set@3alat ) jam Rp 1,000.00 Sewa Dump truck 6T min(5jam) jam Rp 65,000.00 Sewa Dump truck 5T min(5jam) jam Rp 65,000.00 Sewa Dump truck 3,5T min(5jam) jam Rp 65,000.00 Sewa alat bantu strouss pile jam Rp 10,000.00