BORNEO OSH CONFERENCE & EXHIBITION 2019 29 & 30 Apr 2019 Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 1 1 PRESENTED BY : ABDUL RAHMAN KADIR, Safety and Health Manager Lebuhraya Borneo Utara Sdn. Bhd. --------------------------------------- TITLE : HSET @PAN BORNEO HIGHWAY SARAWAK : OUR JOURNEY AND CHALLENGES HSET@PAN BORNEO HIGHWAY SARAWAK OUR JOURNEY AND CHALLENGES Presentation by Abdul Rahman Kadir, Health and Safety Manager BORNEO OSH CONFERENCE AND EXHIBITION 2019 2
27
Embed
HSET@PAN BORNEO HIGHWAY SARAWAK 11 HSET@PAN BORNE… · Projek Lebuhraya Pan Borneo Sarawak. 13th April 2018 (Friday) Dewan SJK Chung Hua, Serian 6 Public engagement and Community
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 5
HSE POLICY
HEALTH, SAFETY & ENVIRONMENT POLICY
LBU is committed to: • Establish and maintain (HSE) management systems. • Comply with all applicable HSE statutory. • Take appropriate actions to prevent accidents,
occupational illnesses and environmental degradation. • Promote active engagement of employees, work
package contractors, supervision consultants and the public in all HSE programmes.
• Continually improve our HSE management and performance through the implementation of HSE objectives and targets.
• Employ competent and committed employees with continual training and awareness to embrace best work practices.
“PROTECTING OUR PEOPLE AND THE ENVIRONMENT”
HSET ROADMAP
Aims for Effective HSET Management During
Construction
• Ensure safety of workers & road users during construction
SAFETY OF ALL
• Ensure Contractors implement approved Traffic Management Plan during construction.
• Ensure implementation of good practices in HSET
IMPLEMENTATION
• Ensure minimum disruption to road users during construction
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 9
HEALTH AND SAFETY AWARENESS PROGRAM AND CAMPAIGN
HEALTH AND SAFETY PLAN AND PROGRAM FOR PAN
BORNEO HIGHWAY SARAWAK
HEALTH AND SAFETY PLAN AND PROGRAM FOR PAN
BORNEO HIGHWAY SARAWAK
PUBLIC - ROAD USER - STUDENT
02
03
04
05 06
07
08
01
WORK PACKAGE CONTRACTORS
PROJECT DELIVERY PARTNER
LOCAL LEADERS - TUAI RUMAH - PENGHULU
WORKERS - OPERATOR - LORRY
DRIVER - GENERAL
WORKERS - -
AUTHORITY & GOVERNMENT AGENCIES - DOSH - NREB - JKJR - JPJ - POLICE - HEALTH
DEPT
LOCAL AUTHORITIES - MAJLIS DAERAH - MAJLIS
PERBANDARAN
RESIDENT ENGINEER TEAM (RET)
PARTY INVOLVES IN HEALTH AND
SAFETY PROGRAM AND
CAMPAIGN
These are the objective of the program i) Promote and encourage the
safe use of public road by all classes of road users through the circulation of advice, information and knowledge.
ii) Promote awareness and better understanding on the current construction work activities and explain what the hazard associate with the construction work.
iii) Create close relationship with local community for better understanding the problems and solutions arise while construction in progress.
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 17
QHSET AUDIT MANAGEMENT SYSTEM [PDP’S QHSET System – Overview]
AUDIT
AUDIT, CONTROL OF NON-CONFORMITY & CORRECTIVE
ACTION PROCEDURES
ISO 19011:2011—Guidelines for Auditing Management Systems An audit is a “systematic, independent and documented process for obtaining audit evidence
[records, statements of fact or other information which are relevant and verifiable] and evaluating it objectively to determine the extent to which the audit criteria [set of policies,
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 19
Maintain Safe Working Area : Ref: OSHA 1995, Section 15 “(1) It shall be the duty of every employer and every self-employed person to ensure, so far as is practicable, the safety, health and welfare at work of all his employees.”
BEFORE AFTER
Unsafe Act - Improper storing of generator set. Creating hazard - Falling object, risk of crush by falling object.
1. Generator Set is place on the ground and cover with canvas. 2. The issue was highlighted in the weekly mass toolbox talk to all
contractors.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – HEALTH AND SAFETY
AUDIT
Maintain safe Stepladders/ ladders for access and no obstruction : Ref: OSHA 1995, Section 15, FMA [BOWEC] Regulations 1986, Part X)
BEFORE AFTER
Unsafe Condition Landing bay for ladder not install at ever level of scaffolding. Landing bay area shall be installed for every level of scaffolding.
1. Ladder landing bay area had been installed for every level. 2. Fully decked scaffold with no gaps between working platform.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – HEALTH AND SAFETY
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 20
Maintain Safe Working Area : Ref: OSHA 1995, Section 15 “(1) It shall be the duty of every employer and every self-employed person to ensure, so far as is practicable, the safety, health and welfare at work of all his employees.”
BEFORE AFTER
Unsafe Act Electric cable laid on the ground and unattended.
1. Ladder landing bay area had been installed for every level. 2. Fully decked scaffold with no gaps between working platform.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – HEALTH AND SAFETY
AUDIT
Maintain Safe Working Area : Ref: OSHA 1995, Section 15 “(1) It shall be the duty of every employer and every self-employed person to ensure, so far as is practicable, the safety, health and welfare at work of all his employees.”
BEFORE AFTER
Unsafe Condition Bore pile holes not protected, risk of falling into the bore hole.
1. Temporary barricade installed at bore pile holes before concreting work at Sg. Bakas Bridge.
2. The issue was highlighted in the weekly mass toolbox talk to all contractors.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – HEALTH AND SAFETY
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 21
41
CATEGORY SOIL EROSION AND SEDIMENTATION AND RIVERBAN K STABILIITY: COA ITEM 3(e) - Erosion and sediment control measures are proposed at the discharge points of the drainage i.e. before discharge into waterways, to prevent excessive muddy runoff. Location of the control measures shall be indicated in the Environmental Management Plan (EMP) when detailed engineering design is finalized.
BEFORE AFTER
Damaged silt fence barrier barrier of Sg Sembawang at CH55+400 (LHS) – Bintulu Section.
Maintenance of damaged silt fence barrier of Sg Sembawang at CH55+400 (LHS) – Bintulu Section.
AUDIT
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – TRAFFIC MANAGEMENT
Maintain Safe Working Area : Ref: OSHA 1995, Section 15 “(1) It shall be the duty of every employer and every self-employed person to ensure, so far as is practicable, the safety, health and welfare at work of all his employees.” REAM & Road Safety Audit Report .
BEFORE AFTER
Material and Storage ( Near to Existing Road ) CH 3+600 Material storage should be located more than 9 meter from the existing road or continues concrete barrier should be provided.
1. Contractor replace plastic barrier to concrete barrier. 2. This matter is included in weekly mass toolbox briefing.
Sarawak Regional Group Occupational Safety & Health And Environment Practitioner's Association (SWKRG-SHE) 22
CATEGORY TRAFFIC MANAGEMENT : ATJ 2C/85 – 4.3.1 (b) The standard marking planned for the road should be in-place before opening a new facility to traffic. Also, if revised lane patterns are
planned for the work zone, temporary markings should be placed before the traffic changed.
BEFORE AFTER
Misleading existing white line marking should be removed or painted over with black paint.
Existing white line road marking has been removed and painted with temporary road line marking.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – TRAFFIC MANAGEMENT
AUDIT
Location : CH1000 @ Package 4
CATEGORY TRAFFIC MANAGEMENT : GOOD PRACTICE
BEFORE AFTER
Installation of Plastic Barrier along verge is too far from edge of pavement (road marking). This creates a potential hazard to grass cutting activities. Currently no guidelines stated in ATJ/Ream on correct location to install Barriers along the verge.
Re-location of Plastic Barriers by CMT 04 to edge of pavement eliminates hazard to grass-cutting activities in line with OSHA 1994 requirements to manage safety “as far as practicable”.
SAMPLE - PHOTOGRAPHS OF DISPOSITIONS – TRAFFIC MANAGEMENT