How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning
26

How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

Jan 17, 2016

Download

Documents

Damon George
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

How to Have a Successful Retrocommissioning Project

Karl Stum, PEPortland Energy Conservation Inc. (PECI)

Successful Retrocommissioning

Page 2: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

2

Successful Retrocommissioning

What We Will Cover--

• Definitions

• Planning phase activities

• Investigation and implementation phases

• Hand-off phase

Page 3: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

3

Successful Retrocommissioning

Retrocommissioning

• Existing equipment

• Seeks low-cost operational improvements

• Likely won’t get done with a conventional performance contract

Page 4: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

4

Successful Retrocommissioning

Phases of the Process

• Planning

• Investigation

• Implementation

• Hand-off

Page 5: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

5

Successful Retrocommissioning

Building Selection

• Enthusiastic facility staff

• Facility staff have time

• Owner has money to put into project

• High energy users?

Page 6: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

6

Successful Retrocommissioning

Objectives

• System verification (RCx)

• Energy savings

• Problem areas

• What systems? HVAC Lighting Controls Specialty

Page 7: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

7

Successful Retrocommissioning

System Verification

• Systematic testing of systems

• Like new construction testing

• Report card

Page 8: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

8

Successful Retrocommissioning

Energy Savings

• Focus on big energy using equipment

• Comfort?

• IAQ?

• Capital improvements?

• Energy-only may not be compatible with std. RCx

Page 9: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

9

Successful Retrocommissioning

Problems Areas

• Comfort

• System control

• IAQ

Page 10: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

10

Successful Retrocommissioning

Satisfy All Stakeholders

Page 11: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

11

Successful Retrocommissioning

Satisfy All Stakeholders

• Owner

• Utility

• Energy manager

• Facility manager

• Facility engineer/operator

Page 12: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

12

Successful Retrocommissioning

Types of Implementation

By Whom:

• All by owner

• CP oversees

• CP implements

When:

• Along the way

• After full finding report

Page 13: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

13

Successful Retrocommissioning

Selecting a Provider

• Done it before

• Experienced with your issues TAB Design Equipment Energy Troubleshooting Controls

• References

• Approach

Trust me….

Page 14: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

14

Successful Retrocommissioning

Scope of Work

• Don’t promise the farm

• Be explicit

• Consider phasing the project--investigation / implementation

Page 15: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

15

Successful Retrocommissioning

Scope of Work

• All but insist that you do some implementation or follow-up

• Allow enough time for implementation

• Leave documentation for facility staff

Page 16: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

16

Successful Retrocommissioning

Expectations

• Understand them

• Manage them

• Document

Page 17: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

17

Successful Retrocommissioning

Budgeting

• Be realistic

• Many projects are scoped to a budget rather thanthe opposite

• Typical 100k - 500k sf, typical energy projects:

$20k-$50k for investigation, and $10k-$30k for implementation of

findings

Page 18: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

18

Successful Retrocommissioning

Cx Plan

• Clear

• Complete

• Include a schedule

Page 19: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

19

Successful Retrocommissioning

INVESTIGATION & IMPLEMENTATION PHASE

Page 20: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

20

Successful Retrocommissioning

Kick-Off Meeting

• Team building

• Communicate objectives

• Communicate process

• Clear up questions

Page 21: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

21

Successful Retrocommissioning

Staff Issues

• Managers support staff Time Appropriate staff resources Allocate budget to implement

• Commissioner respect staff Don’t take their whole day Don’t make staff look bad

(call a spade a heart? Or is the glass half empty or half full?)

Page 22: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

22

Successful Retrocommissioning

Communication

• Document all scope directives and changes

• Keep parties informed of progress

• Meet to go over findings

Page 23: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

23

Successful Retrocommissioning

Communication

• Provide clear findings and recommendations

• Make report accessible--use summary tables

Page 24: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

24

Successful Retrocommissioning

Remaining on Track

• Remember to please all stakeholders

• Revisit your budget often

• Don’t go too deep in one area

• Leave enough for analysis and implementation

Page 25: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

25

Successful Retrocommissioning

Implementation

• Consider interactions of recommendations

• Plan for verification, if required

• Identify that all players are satisfied

• Document

Page 26: How to Have a Successful Retrocommissioning Project Karl Stum, PE Portland Energy Conservation Inc. (PECI) Successful Retrocommissioning.

26

Successful Retrocommissioning

HAND-OFF PHASE

• Provide a clear / accessible report

• Leave staff with guidance in writing

Implementation plan Optimum operating parameters Updated sequences of control Recommissioning plan Energy accounting plan