Page 1: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

How to Get Better Lighting with Less MoneyHow to Get Better Lighting with Less MoneyEuropean Commission DG JRCEuropean Commission DG JRC

Trezzano RosaTrezzano Rosa

INTEL 2003INTEL 2003

Milan, 21 May 2003Milan, 21 May 2003

Page 2: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 22

Trezzano RosaTrezzano Rosa

Trezzano Rosa3.904 resident population (31.03.03)

MilanoMilano

Page 3: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 33

Energy SavingsEnergy Savingswith TPFwith TPF

Third Party FinancingThird Party Financing

Energy Savings on Public Lighting

Page 4: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 44

ProceduresProcedures

Public contract

Call for bids

Page 5: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 55

Scheme TPFScheme TPF

TiescoTiesco

AUDIT

FEASIBILITY STUDY

CONTRACT DRAFTING

PLANNING

INSTALLATION

MONITORING

MAINTENANCE

SAVINGS

MunicipalitMunicipalityy

Page 6: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 66

SAVINGSSAVINGS

before duringcontract

after theend of

contract

Municipality

Tiesco

Utility

Page 7: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 77

FINANCIAL FLOWSFINANCIAL FLOWS

MunicipalitMunicipalityy

SuppliersSuppliersTiescoTiesco

Medium term Medium term loansloans

Performance service

Pay-back on savings

Payments

Repayments

Technology

Loans

Page 8: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 88

AdvantagesAdvantages to Municipality to Municipality

• No investments• Guaranteed and shared savings• Guaranteed technologies• Joint management of energy and future

implementations

Page 9: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 99

Baseline LightingBaseline Lighting

Luminaire 1 Luminaire 2 Luminaire 3 Luminaire 4 Luminaire 5 Luminaire 6

Type of lamps HP Mercury HP Mercury HP Sodium HP Sodium HP Sodium HP SodiumNb. of lamps 126 249 18 96 13 26

Power of single lamp 80 125 70 150 250 400

Type of ballast magnetic magnetic magnetic magnetic magnetic magneticLuminaire reflector aluminised aluminised aluminised aluminised aluminised aluminised

Baseline Lighting

Page 10: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1010

BeforeBefore

Page 11: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1111

Post-installation LightingPost-installation Lighting

Luminaire 1 Luminaire 2 Luminaire 3 Luminaire 4

Type of lamps HP Sodium HP Sodium HP Sodium HP SodiumNb. of lamps 334 164 4 26

Power of single lamp 70 100 150 400

Type of ballast magnetic magnetic magnetic magneticLuminaire reflector aluminised aluminised aluminised aluminised

Post-installation Lighting

Page 12: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1212

After - 1After - 1

Page 13: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1313

After - 2After - 2

Page 14: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1414

Lighting increaseLighting increaseBaseline Lighting

Power Lamps 80 125 70 100 150 250 400 Lumen per lamps 3.600 6.200 6.600 10.500 14.000 25.000 47.000 N. lamps 126 249 18 - 96 13 26

Total Lumen 453.600 1.543.800 118.800 - 1.344.000 325.000 1.222.000 5.007.200

Post Installation Ligthing

Power Lamps 80 125 70 100 150 250 400 Lumen per lamps 3.600 6.200 6.600 10.500 14.000 25.000 47.000 N. lamps - - 334 164 4 26

Total Lumen - - 2.204.400 1.722.000 56.000 - 1.222.000 5.204.400

+ 197.200 lumen+ 197.200 lumen

Page 15: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1515

Economic ResultsEconomic Results

Economic Savings:Economic Savings:– 112.944 kWh/yr of electric energy112.944 kWh/yr of electric energy

– 17 KW/yr of contractual power17 KW/yr of contractual power

– Elimination of penalties for low power factor (cosElimination of penalties for low power factor (cos<0.9)<0.9)– From “Management on call” to “Programmed Management”From “Management on call” to “Programmed Management”

16.657 €/year16.657 €/year

248.855 € in 15 years248.855 € in 15 years

Page 16: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1616

Environmental ResultsEnvironmental Results

Environmental Savings:Environmental Savings:

– Reduction of sky pollutionReduction of sky pollution

(LR 17/00 Regione Lombardia)(LR 17/00 Regione Lombardia)

– Reduction of atmospheric pollutionReduction of atmospheric pollution

82,3 t CO82,3 t CO22/yr, … NOx, … SOx, …/yr, … NOx, … SOx, …

(Kyoto Protocol, …)(Kyoto Protocol, …)

Page 17: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1717

IPMVPIPMVP

International Performance MeasurementInternational Performance Measurement

&&

Verification ProtocolVerification Protocol

to defineto define

Energy SavingsEnergy Savings

Polo Tecnologico

per l’Energia

Trento

Page 18: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1818

Fernando Savorana

ComuneComunedidi

Trezzano RosaTrezzano RosaI.P.O

.

Page 19: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 1919

Environmental FundEnvironmental Fund

ENERGY SAVINGSENERGY SAVINGSTiescoTiesco

MunicipalitMunicipalityy

PrivatePrivate

BusinessBusiness

ENERGY SAVINGSENERGY SAVINGS

ENERGY SAVINGSENERGY SAVINGS

Page 20: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 2020

Trezzano RosaTrezzano RosaGreenLight GreenLight Award 2003Award 2003

Page 21: How to Get Better Lighting with Less Money European Commission DG JRC Trezzano Rosa INTEL 2003 Milan, 21 May 2003.

Luciano BurroLuciano Burro Municipality of Trezzano RosaMunicipality of Trezzano Rosa 2121

ContactsContacts

Comune di Trezzano RosaComune di Trezzano Rosa

Assessorato all’AmbienteAssessorato all’Ambiente