1 How do Vestas manufacture Nacelles
67

How Do Vestas Manufacture Nacelles - PE Rev3

Nov 28, 2015

Download

Documents

tpzuniga
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: How Do Vestas Manufacture Nacelles - PE Rev3

1

How do Vestas manufacture Nacelles

Page 2: How Do Vestas Manufacture Nacelles - PE Rev3

2

V52

V52 – 850 kW – Pitch/Optispeed – 14.00 to 31.40rpm

Weight

Nacelle: ≈22 ton

Rotor: ≈ 10 ton

Sum: ≈ 32 ton

Nacelle factories:

Italy: Taranto V52

Hub factories:

Italy: Taranto V52

_ = Primary factory: Prototype, Working instruction

Page 3: How Do Vestas Manufacture Nacelles - PE Rev3

3

V82

V82 – 1,65 MW – Active-Stall – 14.4 rpm (1 speed generator)

V82 – 1,65 MW(900kW) – Active-Stall – 14.4/10.8 rpm (2 speed generator)

Weight

Nacelle: ≈52 ton

Rotor: ≈ 43 ton

Sum: ≈ 95 ton

Nacelle factories:

Spain: Viveiro V82

India: Chennai V82

Hub factories:

Denmark: Skagen V82

India: Chennai V82

_ = Primary factory: Prototype, Working instruction

Page 4: How Do Vestas Manufacture Nacelles - PE Rev3

4

V80-V90

V80 – 2 MW – Pitch/Optispeed – 9 to 19 rpm

V90 – 1,8-2 MW – Pitch/Optispeed – 9 to 14.9 rpm

V80 – 1,8 MW – Pitch/Optislip – 15.5 to 16.8 rpm

Weight

Nacelle: ≈67 ton

Rotor: ≈ 37 ton

Sum: ≈ 104 ton

Nacelle factories:

Denmark: Viborg V80 2MW

Spain: Leon V80 2MW

China (2007): Tianjin V80 2MW

Hub factories:

Denmark: Ringkøbing V80 2MW

China (2007): Tianjin V80 2MW

_ = Primary factory: Prototype, Working instruction

Page 5: How Do Vestas Manufacture Nacelles - PE Rev3

5

V90

V90 – 3 MW – Pitch/Optispeed – 8.6 to 18.4 rpm

Weight

Nacelle: ≈70 ton

Rotor: ≈ 41 ton

Sum: ≈ 111 ton

Nacelle factories:

Denmark: Ringkøbing V90 3MW,

Hub factories:

Denmark: Ringkøbing V90 3MW,

_ = Primary factory: Prototype, Working instruction

Page 6: How Do Vestas Manufacture Nacelles - PE Rev3

6

Nacelles Value Chain

Foundries Machining

Generators

Vestas Nacelles Value Chain

Assembly and test

Page 7: How Do Vestas Manufacture Nacelles - PE Rev3

7

Vestas Nacelles production facilities

Denmark, Norway, Sweden, Germany, Italy, Spain, India and China

Page 8: How Do Vestas Manufacture Nacelles - PE Rev3

8

Vestas Castings

Vestas Castings:Magdeburg, components up to 11 tonKristianssand, components up to 20 tonsGuldsmedshyttan components up to 40 ton

Page 9: How Do Vestas Manufacture Nacelles - PE Rev3

9

Vestas Machining - Lem

•Ca. 20,100 m2

Page 10: How Do Vestas Manufacture Nacelles - PE Rev3

10

Vestas Generator - Lübeck

Page 11: How Do Vestas Manufacture Nacelles - PE Rev3

11

Pictures from Ringkøbing

Page 12: How Do Vestas Manufacture Nacelles - PE Rev3

12

Pictures from LeonViveiro

V82

LeònV90 2MW

Page 13: How Do Vestas Manufacture Nacelles - PE Rev3

13

Pictures from Viveiro

Page 14: How Do Vestas Manufacture Nacelles - PE Rev3

14

Pictures from Taranto

Page 15: How Do Vestas Manufacture Nacelles - PE Rev3

15

Pictures from Chennai

Page 16: How Do Vestas Manufacture Nacelles - PE Rev3

16

Pictures from Tianjin

BeijingTianjin

Shanghai

GuangzhouShenzhen

TEDA WEST

Page 17: How Do Vestas Manufacture Nacelles - PE Rev3

17

Pictures from Tianjin

Land approx. 50.000 sqm

Buildings approx. 13.000 sqm.

Page 18: How Do Vestas Manufacture Nacelles - PE Rev3

18

Pictures from Viborg (1)

Page 19: How Do Vestas Manufacture Nacelles - PE Rev3

19

Factory Viborg

Operation 0100Main foundation Yaw beamYaw gear

Operation 0200Crane column

Operation 0300GearMain shaft/bearingHydraulic station

Operation 0700Assembling of main foundation and rearCrane finish Cables

Operation 0800Final test

Operation 0900Glass fiber cabinReady for shipment

Operation 0400Rear sectionGenerator

Operation 0500Control cabinetTransformer

Operation 0600CablesGenerator finish

Front

Rear

LEAN-Production in Viborg (15-18 turbines/week):

6 step (2x3 parallel + 3) 1 step takes 6 hours. Target is 4 hours

Page 20: How Do Vestas Manufacture Nacelles - PE Rev3

20

Pictures from Viborg (2)

Page 21: How Do Vestas Manufacture Nacelles - PE Rev3

21

Pictures from Viborg (3)

Page 22: How Do Vestas Manufacture Nacelles - PE Rev3

22

Pictures from Viborg (4)

Page 23: How Do Vestas Manufacture Nacelles - PE Rev3

23

Pictures from Viborg (5)

Page 24: How Do Vestas Manufacture Nacelles - PE Rev3

24

Pictures from Viborg (6)

Page 25: How Do Vestas Manufacture Nacelles - PE Rev3

25

Pictures from Viborg (7)

Page 26: How Do Vestas Manufacture Nacelles - PE Rev3

26

Pictures from Viborg (8)

Page 27: How Do Vestas Manufacture Nacelles - PE Rev3

27

Pictures from Viborg (9)

Page 28: How Do Vestas Manufacture Nacelles - PE Rev3

28

Pictures from Viborg (10)

Page 29: How Do Vestas Manufacture Nacelles - PE Rev3

29

Pictures from Viborg (11)

Page 30: How Do Vestas Manufacture Nacelles - PE Rev3

30

Pictures from Viborg (12)

Page 31: How Do Vestas Manufacture Nacelles - PE Rev3

31

Pictures from Viborg (13)

Page 32: How Do Vestas Manufacture Nacelles - PE Rev3

32

Pictures from Viborg (14)

Page 33: How Do Vestas Manufacture Nacelles - PE Rev3

33

Pictures from Viborg (15)

Page 34: How Do Vestas Manufacture Nacelles - PE Rev3

34

Pictures from Skagen (1)

Page 35: How Do Vestas Manufacture Nacelles - PE Rev3

35

Pictures from Skagen (2)

Page 36: How Do Vestas Manufacture Nacelles - PE Rev3

36

Pictures from Skagen (3)

Page 37: How Do Vestas Manufacture Nacelles - PE Rev3

37

Responsibility

Page 38: How Do Vestas Manufacture Nacelles - PE Rev3

38

Drawing system

Drawing system: Pro/EArchives system: Intralink

• 3D Assembly drawing

• 3D Part drawing

Page 39: How Do Vestas Manufacture Nacelles - PE Rev3

39

Drawing system

• Assembly drawing

• Production drawings

Page 40: How Do Vestas Manufacture Nacelles - PE Rev3

40

Structure

Level 1 (Nacelle)

Level 2 (Main module)

Level 3 (Sub module)

Level 4-x (Assembly)

Main foundation mod

Rear foundation mod

Generator mounted

Generator module

Slip-ring module

Yaw module

Nacelle cover module

Mainshaft-gear mod.

Mainshaft module

Gearbox brake offl.filt.

Rotating transfer mod.

Torquearm module

Torquearm left

Torquearm right

V80 - 76 Variants:V80/V90, 50 Hz/60Hz, Ral 7035/9010, VCS/VRCC etc.

Page 41: How Do Vestas Manufacture Nacelles - PE Rev3

41

Certificate

A turbine can’t be erected without a certificate.Certificates can be issued by GL, DNV and TÜV based on documentation from Vestas. Guidelines and standards: IEC 61400, DS 472, NVN 11400, GL, DIBt etc.

Three elements in the certificate: - Design assessment. Verification of the design and engineering documents. Turbine management and safety. Load calculation.Strength calculation.

- Quality management ISO 9001 covers the majority of the requirements .

- Prototype testValidation of the calculations.Turbine management.Performance.Noise.Grid compatibility.

Page 42: How Do Vestas Manufacture Nacelles - PE Rev3

42

Operational Loads

Wind Loads etc. (Flex5)Gravity (9,82 N/kg)Horizontal acceleration - Extreme: ≈5 N/kg – Fatigue: ≈1 N/kg (m=5, n=10^7)

Loads based on GL category 1A Extreme wind speed for 80 m V = 70 m/sAnnual average for 80 m V = 10 m/sTurbulence intensity for category A1 = 18 %

(3. december 1999 51,4 m/s)(“Katrina Hurricane” 2005 77,8 m/s)

Extreme moment at blade flange V80: ≈6000kNm = 1000kg at 600m

Page 43: How Do Vestas Manufacture Nacelles - PE Rev3

43

Transport Loads

-Transport

Page 44: How Do Vestas Manufacture Nacelles - PE Rev3

44

Certificate – Main parts

Component Approval Issue

Hub Loads: Flex 5Strength: FEM

Fatigue and static strengthDeformations by the bearings.

Machine frame Loads: Flex 5Strength: FEM

Fatigue and static strength

Rear section Loads: Flex5 + AnalyticStrength: Analytic + FEM

Fatigue and static strengthWelded component

Drive train Loads: Flex5 + AnalyticStrength: FEM

Fatigue and static strengthWelded component

Crane with traverse

Loads: AnalyticStrength: Analytic + FEM

Static strengthWelded component

Page 45: How Do Vestas Manufacture Nacelles - PE Rev3

45

Certificate – Main parts

Page 46: How Do Vestas Manufacture Nacelles - PE Rev3

46

Certifikate – Small parts

Component Approval Issue

Bearings Loads: Flex 5Strength: Approved by supplier

Fatigue and static strength

Main bearing housing

Loads: Flex 5Strength: FEM

Fatigue and static strength

Rotor lock Loads: Flex 5Strength: Approved by supplier

Static strength

Coupling and breake

Loads: Flex 5Strength: FEM / Supplier

Fatigue and static strength

Gear box torque arms

Loads: Flex 5Strength: FEM / Supplier

Fatigue and static strength

Page 47: How Do Vestas Manufacture Nacelles - PE Rev3

47

The rest

• ≈ 1000 drawings of different parts for one Turbine

For example:

Tread platesGlass fiber cabinet/nose cone supportSupport for hydraulic and electrical partsCoolersLaddersAnemometerCover platesHatchesEtc.

Page 48: How Do Vestas Manufacture Nacelles - PE Rev3

48

Standards - Why?

The components shall be produced global without problems.Knowledge to standards and GPS (Geometrical product specification) is therefore important

Chinese supplier

Page 49: How Do Vestas Manufacture Nacelles - PE Rev3

49

Design - PE

Add standards:

Not add better requirements than necessary!

Not all requirements are mentioned on the drawings. Remember to check the bill of material in INFOR

Page 50: How Do Vestas Manufacture Nacelles - PE Rev3

50

Design - PE

Drawing head - assembling:

Bulk items in the BOM: Georoil etc:

Accessories not separate in the BOM: Cable Stripper, lock oil etc

Page 51: How Do Vestas Manufacture Nacelles - PE Rev3

51

Design - PE

Verdana 12 pt, font colour white

Drawing head - part:

Page 52: How Do Vestas Manufacture Nacelles - PE Rev3

52

Design - PE

Verdana 12 pt, font colour white

Make it cheaper –

The redesign displayed below gives savings of 10.000 DKK/week in Viborg

Page 53: How Do Vestas Manufacture Nacelles - PE Rev3

53

Design - PE

Improve assembling.

Page 54: How Do Vestas Manufacture Nacelles - PE Rev3

54

Design - PE

Improve drawings - GPS

Page 55: How Do Vestas Manufacture Nacelles - PE Rev3

55

Design - PE

Improve drawings – GPS – 3D measuring (Tolerance 0,003)

Page 56: How Do Vestas Manufacture Nacelles - PE Rev3

56

Design - PE

Improve drawings – GPS Lasertracker

Page 57: How Do Vestas Manufacture Nacelles - PE Rev3

57

Design - PE

Verdana 12 pt, font colour white

See failures before they occur

Fatigue crack

Page 58: How Do Vestas Manufacture Nacelles - PE Rev3

58

Remember: Fatigue

Verdana 12 pt, font colour white

Page 59: How Do Vestas Manufacture Nacelles - PE Rev3

59

Remember: Fatigue

Page 60: How Do Vestas Manufacture Nacelles - PE Rev3

60

NCR - PE

BP 04.03.00.This procedure is valid for the handling of non-conformity items/products detected during Vestas' manufacturing, storage, transport, installation and commission activities until the after sales system/procedures takes over.

Page 61: How Do Vestas Manufacture Nacelles - PE Rev3

61

NCR - PE

Page 62: How Do Vestas Manufacture Nacelles - PE Rev3

62

Surface treatment

Verdana 12 pt, font colour white

Inside Nacelle: C3Hot dip galvanizing acc. ISO 1461:1999 minimum local thickness 45 µm Thermal spraying acc. ISO 2063:2005 (ISO 14919:2001 ZnAl15) 70 µm Thermal spraying acc. ISO 2063:2005 (ISO 14929:2001 ZnAl 15) 50 + S3.17

Indvendig Inside Hub: C4Hot dip galvanizing acc. ISO 1461:1999 minimum local thickness 85 µm Thermal spraying acc. ISO 2063:2005 (ISO 14919:2001 ZnAl15) 110 µm Thermal spraying acc. ISO 2063:2005 (ISO 14929:2001 ZnAl 15) 100 + S4.20

Outside Nacelle: C5MHot dip galvanizing acc. ISO 1461:1999 minimum local thickness 170 µm Thermal spraying acc. ISO 2063:2005 (ISO 14929:2001 ZnAl 15) 100 + S7.02

Page 63: How Do Vestas Manufacture Nacelles - PE Rev3

63

Documentation

Documentation demand, see BP 08.16.00 Work instruction, Purchase specification, Quality Specification, Control instruction, Inspection scheme, Supplier approval

A-item are items where defects affect theQuality of the product, Environment, SafetyAssuranceLegislation prescribes calculations, safety evaluations, production documentation

 B-item are items (including catalogue items), that defects only marginally affect the Product quality, EnvironmentSafety The defect will be detected in the prescribed inspections Only capable of affecting processes and reliability of supply briefly. Items not classified as A-item, which are designed by Vestas and must be purchased, are classified as B-items. 

U-item are items where defect not affectsEnvironmentProduction qualityDefects and lacks will bee corrected before use.

Page 64: How Do Vestas Manufacture Nacelles - PE Rev3

64

Material - Welding - Cast

Quality requirements - WeldingDepending on consequence and use (Loads etc). See nacelle notes guideline

QS 993667 (Elementary quality requirements)QS 993665 (Comprehensive quality requirements)

If there is a reference to TPS 901529 or TPS 901530 it is allowed to manufacture the item in an substitute material for example Chinese standardized steel.

TPS 901528: Casting quality requirements

TPS 901529: Parts - Certified components (Approved by DNV, GL etc.) / Component which are important for the safety of the turbineThe substitute material has at least the same strength as the specified material.

TPS 901530: Parts - Non certified components / Non-important components. The substitute material may be weaker than the specified strength of the parent material:Strength of steel S355 (EN 10025) may be reduced with max. 10%Strength of steel S235 (EN 10025) may be reduced with max. 5%Strength of stain less steel is min. 150 MPaStrength of aluminium may be reduced with max. 20%Strength of other materials may be reduced with max. 10%

Page 65: How Do Vestas Manufacture Nacelles - PE Rev3

65

Temperature

Production stop:Alarm 19: Ambient temperature too low    :  -30 °CAlarm 83: Gear oil temperature too low    :  -10 °CAlarm 94: Nacelle temperature too low     :  -15 °C

Page 66: How Do Vestas Manufacture Nacelles - PE Rev3

66

Tower

Page 67: How Do Vestas Manufacture Nacelles - PE Rev3

67

Local content percentage distribution

on componentsName of component NDRC

[%]Possible NDRC [%]

Tower 16.9 9.0

Electrics in Wind Farm 7.2

Nacelle cover 4.4 4,0

Generator 7.4 8.0

Blade 22.5 19.0

Gearbox 15.4 15.0

Main shaft, (incl. Bearings, coupling) 3.4 4.0

Hub (incl. Pitch regulated system) 4.2 7.0

Yaw system 1.3 5.0

Central control and monitoring system 3.5 3.0

Electrical control sys. (SCADA) incl. inverter 3.5 16.0

Hydraulic system 2.2 2.0

General assembly 3.0 3.0

Spareparts 1.0 5.0

Others 4.1

SUM 100.0 100.0