How a Well is Drilled on Land

Mar 09, 2016

Download

Documents

course work
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • How a Well is Drilled on Land

    1

    Step 1: Digging a Cellar

    On land, a majority of wells

    begin with digging a cellar

    from three to fifteen feet in

    depth. The purpose of a

    cellar is to align the

    production Christmas tree at

    ground level, providing easier

    access to the valves,

    chokes, and other equipment.

  • How a Well is Drilled on Land

    2

    Step 2: Running a Conductor

    Pipe

    The first string of pipe used

    in a well is called the

    conductor pipe, or drive pipe.

    The pipe is usually 30-36

    inches in diameter. A large

    diameter hole is drilled to

    a specified depth, usually

    one or two hundred feet, and

    the pipe is driven into the

    ground..

  • How a Well is Drilled on Land

    3

    Step 3: Connecting the BOP

    An adapter flange, or drilling

    flange, is welded to the

    conductor pipe to connect a

    diverter system or a blowout

    preventer system to control

    wellhead pressure.

  • How a Well is Drilled on Land

    4

    Step 4: Running the Surface

    Pipe

    A hole is drilled for the wells

    first string of pipe, the

    surface pipe, and the pipe is

    run in the hole. There may be

    several strings of pipe in a

    well, each run to a different

    depth. The number of strings

    is determined by the number

    of zones being drilled

    through. These can include

    fresh water, salt water, and

    potential production zones.

    Each zone is isolated, or

    cased off, until it is to be

    produced. .

  • How a Well is Drilled on Land

    5

    Step 5: Connecting the

    Surface Pipe

    The surface pipe is

    cemented in place back to

    the surface. This holds the

    pipe in place and seals off

    the zone. A cement plug is

    left in the pipe so that the

    BOP system may be

    disconnected safely. The

    BOP is then removed from

    the adapter flange.

  • How a Well is Drilled on Land

    6

    Step 6: Cutting the Conductor

    Pipe and Surface Casing

    The surface pipe is drained,

    the adapter flange (or drilling

    flange) is cut off, and both the

    conductor pipe and the

    surface casing are cut to the

    proper height to allow the top

    of the completed wellhead

    to be at ground level.

  • How a Well is Drilled on Land

    7

    Step 7: Installing the Casing

    Head Housing and Base

    Plate

    The casing head housing is

    welded in place on the

    inside diameter and the

    outside diameter of the

    surface casing. The

    housing is then tested to

    assure there are no leak

    paths in the welds.

  • How a Well is Drilled on Land

    8

    Step 8: Installing the BOP

    System

    The BOP system is installed

    above the casing head

    housing and then tested. To

    test the BOP system, the test

    plug is made up on the drill

    string and lowered through

    the BOP system onto the

    casing head bowl. Pressure

    is applied from above the

    plug to test the BOP system.

  • How a Well is Drilled on Land

    9

    Step 9: Installing the Casing

    Head Wear Bushing

    A wear bushing is installed to

    protect the interior of the

    casing head from damage

    by drilling equipment.

  • How a Well is Drilled on Land

    10

    Step 10: Installing the

    Intermediate String

    A hole is drilled for the

    intermediate string and the

    casing is run in the hole

    and cemented in place. A

    cement plug is left in the

    intermediate casing, just as it

    was in the surface casing. .

  • How a Well is Drilled on Land

    11

    Step 11: Installing the Casing

    Hanger and Casing Spool

    The intermediate casing is

    suspended from the block

    above the rig floor, the BOP

    is picked up, and the casing

    hanger is installed on top of

    the casing head. Holes are

    cut in the casing to allow the

    drilling fluids to drain out of

    the casing riser. When the

    fluid has drained, the casing

    is cut off to the appropriate

    height and the casing spool

    is installed.

  • How a Well is Drilled on Land

    12

    Step 12: Installing the BOP

    System

    The BOP system is installed

    above the casing spool and

    then tested. To test the BOP

    system, the test plug is made

    up on the drill string and

    lowered through the BOP

    system onto the casing head

    bowl. Pressure is applied

    from above the plug to test

    the BOP system.

  • How a Well is Drilled on Land

    13

    Step 13: Installing the Wear

    Bushing

    The wear bushing running

    tool is made up on the drill

    string and the wear bushing

    installed on the running tool.

    The wear bushing is then

    lowered through the BOP

    system, until it rests in the

    casing spool bowl, then is

    locked into place. The

    running tool is removed and

    drilling resumes.

  • How a Well is Drilled on Land

    14

    Step 14: Running the

    Production Casing String

    The production casing string

    is usually run to the total

    depth of the well. A hole is

    drilled for the production

    casing and the casing is run

    in the hole and cemented

    into place. A cement plug is

    left in the production casing,

    as in the previous steps.

  • How a Well is Drilled on Land

    15

    Step 15: Installing the Casing

    Hanger and Tubing Spool

    The production casing is

    suspended from the

    elevators at the rig floor, the

    BOP is picked up, and the

    production casing hanger is

    installed in the same way as

    the previous casing hanger.

    The tubing spool is installed

    in the same way as the

    casing spool. After the spool

    has been installed, the seals

    and connections are tested,

    and the BOP system is

    reinstalled..

  • How a Well is Drilled on Land

    16

    Step 16: Running the

    Production Tubing

    The production tubing is

    installed inside the

    production casing. Unlike

    casing, the production tubing

    is not cemented in the well

    so it may be removed later, if

    necessary.

  • How a Well is Drilled on Land

    17

    Step 17: Installing the Down

    hole Packer Assembly

    A down hole packer

    assembly (a type of seal

    assembly) is run and

    installed in the

    production casing to seal the

    reservoir from all strings of

    pipe, except the production

    tubing.

  • How a Well is Drilled on Land

    18

    Step 18: Installing the Tubing

    Hanger

    The tubing hanger is installed

    on the tubing at the rig floor,

    then lowered into

    the bowl of the tubing spool.

    The packer seals are tested,

    and a backpressure valve is

    installed in the tubing hanger

    so that the BOP can be

    removed safely. After the

    valve has been installed the

    BOP is removed. .

  • How a Well is Drilled on Land

    19

    Step 19: Installing the Christmas Tree

    The production Christmas tree, sometimes

    called the flow assembly, controls the flow

    of the well. It is made up of a seal flange, or

    tubing head adapter, a series of valves, and a

    choke. The valves are stacked vertically and

    horizontally to provide backup should a

    valve fail. Each Christmas tree has at least

    one actuated surface safety valve to shut

    down the well in an emergency and prevent

    damage to equipment downstream. The

    Christmas tree is connected to a flowline,

    which transports the wells fluid or gas.

    The Christmas tree is oriented properly,

    picked up, lowered over the neck of the

    tubing hanger, and connected to the tubing

    spool. The connections and seals are tested,

    and the well is now ready for production

    testing.