PUCT Staff September 19, 2011
PUCT StaffSeptember 19, 2011
Current Status
Advanced Metering System 1.6 million smart meters deployed
Smart Meter Texas portal deployed
Meter accuracy was validated by PUCT/Navigant Consulting
Benefits achieved 1.5 million meters being read for billing electronically
1.4 million service orders completed electronically
Average electronic service order execution time is 30 minutes
1,500 HAN devices deployed and functioning
About 150 direct and 400 indirect jobs have been created/retained as of Q2 2011
Project is on Schedule $200M DOE grant accelerated project completion from 2014 to 2012
2.2 million meters will be deployed by mid-2012
2
How are we doing?
● Deployment of Smart Meters is on schedule (73 percent complete)
● Design of Advanced Distribution Management System is underway
● Installation of Intelligent Grid infrastructure is underway with work in
six substations and installation of 186 switching devices complete
● Invoiced $190M and received $190M in reimbursement from our
$200M Department Of Energy Smart Grid Investment Grant
● Recognized globally as a leader in smart metering3
$200M DOE Stimulus Grant
DOE Grant Awarded – December 24, 2009
Advanced Metering System (AMS)
Accelerate installation of 2.2 million AMS meters from 2014 to 2012
Moved from 44,000 meters/month to 80,000 meters/month
Moved from 120 cell relays/month to 200 cell relays/month
Impact of DOE grant was incorporated into our surcharge reconciliation,
reducing the cost of AMS to end-use consumers
Intelligent Grid (IG)
Automate 226 distribution circuits and 29 distribution substations
Install software systems to monitor and control the smart grid
Establish bi-directional communication network to support IG, by leveraging
the AMS communications system
4
• Our Energy InSight Center has hosted nearly 700 tours with local, state,
national, and international guests
Delegations from many countries (France, Germany, Brazil, Canada,
Russia, South Africa, UK) visited our facilities in the past year
Three FERC commissioners made site visits
Representatives of the Department of Energy spent three days on site
We participated in a US delegation to Russia on behalf of US Energy
Association
• A successful audit by the Inspector General of the Department of Energy was
conducted in December
• A media celebration was held in February commemorating the 1,000,000th
meter installed, with widespread coverage by media channels
• A press conference with DOE Deputy Secretary Poneman was held in July to
announce consumer adoption of HAN devices with widespread coverage by
media channels
Global Recognition
5
Components of our Advanced Metering System (AMS)
Combined with back office computer systems and integration, our AMS provides:
Daily register reads
Daily 15 minute interval reads
Remote connect / disconnect / on-demand reads
Access to data via Smart Meter Texas portal6
Data Collection
Engine
(Itron DCE 3.0
SP1)
Digital
Communications
Backhaul
Meter Data
Management
System
(eMeter MDM 6.2)
Legacy
Systems
Wireless Communications
Environment
(GE WiMax with GSM
Backup)Smart Meter
Texas PortalExisting
Recently
Deployed
Legend
Itron Open Way
HW 2.0 SR 3.0
Some Components of our
Intelligent Grid (IG)
Combined with back office computer systems, our IG technology, when fully
deployed, will automatically identify the location of power outages, isolate faulted
sections of the main feeder portion of the network and re-route power from other
sources, essentially “healing” the system.7
Consumer benefits of smart meters
Available NOW
Remote meter reading
Faster, automated move-in/out, switching
Pre-paid service, time-of-use rates
15-minute usage data to promote
energy conservation
Easier integration of distributed generation and renewables
Available SOON
Automatic outage notification
Available in the FUTURE
Energy analysis and cost comparison tools
Support for plug-in hybrid electric vehicles
Consumer remote control of thermostats and appliances (HAN)
Energy management systems
Ability to participate in Demand Response programs
71 percent of participants in CNP’s
In-Home Display pilot program
indicated that they have…”changed
their electric consumption behavior…”
as a result of the information available.
Consumer benefits of intelligent grid
Initial Benefits
More precise identification of outage
locations, resulting in faster
restoration of electric service
Reduction in time required to perform
circuit switching to isolate fault
Long-term Benefits
Improved reliability and faster
restoration, especially during major
weather events
Enhanced and improved customer
communications and notifications
The Customer Benefits in a
More Robust Electricity Market
Educate
consumers about
electricity usage
Help consumers
save money on
utility bills
Facilitate
Distributed
Generation and
Renewables
Encourage
demand
response
Improve
reliabilityEnhance customer
service 10
The following initiatives involve direct customer engagement:
• 2011
Residential Energy Feedback R&D Project - Approx. 800 IHDs
In-Home Display REP Pilot Program - Approx 1,500 IHDs
“Smart Partners” R&D Project
– Residential Direct Load Control Demand Response – (39 thermostats, 104 Switches)
– Residential/Small Commercial Standby Generator Demand Response – (3 Homes)
• 2012
Energy Efficiency Ambassador Program: Community-based outreach to
educate customers on energy conservation, smart meters and PEVs
Retail Electric Provider (REP) Pilot Program - $3.5 MM¹ set aside
program for the REPs: structured as a cafeteria plan to pick participation
Energy Efficiency (EE)Customer Engagement Programs
In-Home Displays (IHDs) Time-of-Use Rates (TOUs)
Direct Load Control A/C Tune Ups
Load Management (1) 2012 Budget could include 25K IHDs or 18K DLC/LM or
70K Tune Ups depending on participation from REPs11
What’s Next?Smart Meters Are Just The Beginning
Price control / load control
Micro Grids
Storage
Advanced Self-Healing Grid
Aggregated Demand Management
Electric vehicles
2010 20202014201320122011
HAN Devices Smart Appliances
Smart Meters
Intelligent Grid
Phase 1:
Customer
Insight
Phase 2:
Customer
Engagement
Phase 3:
Customer
Co-Creator
of Value
Intelligent Load Shed
12
Per the DOE Grant Agreement,:
“If you publish or otherwise make publicly available the results of the work conducted under
the award, an acknowledgment of Federal Support and a disclaimer must appear in the
publication of any material, whether copyrighted or not, based on or developed under this
project, as follows:”
Acknowledgment: “This material is based upon work supported by the Department of Energy
under Award Number [DE-OE0000210]”
Disclaimer: “This report was prepared as an account of work sponsored by an agency of the
United States Government. Neither the United States Government nor any agency thereof,
nor any of their employees, makes any warranty, express or implied, or assumes any legal
liability or responsibility for the accuracy, completeness, or usefulness of any information,
apparatus, product, or process disclosed, or represents that its use would not infringe
privately owned rights. Referenced herein to any specific commercial product, process, or
service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute
or imply its endorsement, recommendation, or favoring by the United States Government or
any agency thereof. The views and opinion of authors expressed herein do not necessarily
state or reflect those of the United States Government or any agency thereof.”
DOE Acknowledgement and
Disclaimer
13