Anne Inman, P.E. Air Permits Division Texas Commission on Environmental Quality Environmental Trade Fair 2013 Hot Topics Federal Standards for the Oil and Gas Industry
Feb 12, 2016
Anne Inman, P.E.Air Permits Division
Texas Commission on Environmental QualityEnvironmental Trade Fair 2013
Hot Topics Federal Standards for the
Oil and Gas Industry
New◦NSPS OOOO
Revised◦NESHAP HH and HHH
Proposed August 23, 2011 Final Published August 16, 2012 Effective Date October 15, 2012
New and Revised Federal Requirements
Affected Facilities◦Natural gas well completions◦Storage vessels◦Compressors◦Pneumatic controllers◦Glycol dehydrators ◦Gas plants fugitives and treatment units
NSPS OOOO, NESHAP HH AND HHH
Focuses on reducing VOCs from hydraulically fractured natural gas wells during the flowback period. Phased Requirements for Green
Completions Exceptions for Wildcat, Delineation,
and Low Pressure Wells Includes Pre-completion Notification
and Annual Reporting Requirements
Fracked Natural Gas Wells
Jurisdiction? Any New Guidance? How Do I Notify?
Well Completion/Flowback Notification is now done through e-mail using a form that can be found on our website.
Well Completion / Flowback Notification
Common Questions
Well Completion/Flowback Notification Form
Applicable Statewide or Just at the Wellhead?
Temporary Tanks(<180 days)
After Controls?Potential to Emit (PTE) is on a Per Tank
BasisOnce In – Always In?
Common Tank Questions
Centrifugal & Reciprocating Compressors (Manufactured, Initially Installed but Not Relocated)
New and Replacement Pneumatic Controllers From Gas Wells to Processing Plants
Additional Requirements Summary
Sweetening Units & Fugitives at Gas Plants Glycol Dehydrators (Small and Large at
Major Sites)
Additional Requirements Summary
(cont’d)
August 23, 2011 Applicability Based on New or Modified
August 23, 2011 ApplicabilityBased on New or Modified
Hydraulically Fractured Natural Gas Well Completion (Flowback)
Tanks
Centrifugal Compressors With Wet Seals
Reciprocating Compressors
Small and Large Dehydrators
October 15, 2012 Applicability
Reciprocating Compressors Rod Packing Tracking
o 3-year, or
o 26,000 run-time hours
Continuous Bleed Pneumatic Controllers at Gas Plants With No Bleed Controllers
October 15, 2012 Applicability
Well Flowback Emissions to Flare (or Voluntary to REC)
Centrifugal Compressors (Wet Seals) Controlled 95%
October 12, 2012 Applicability (cont’d)
Fugitives at Gas Plants LDAR (500 ppm)
Sweetening Units at Gas Plants (Up to 99.9%)
New Small Dehydrators (Value)
New Large Dehydrators (95%)
ALL No Exceptions for Start-up, Shut-downs, or Malfunctions (VOC and SO2)
October 15, 2013 Applicability
October 15, 2013 Applicability
Continuous Bleed Pneumatic Controllers at Wellhead to Gas Plants With Low Bleed Controllers
Tank VOC Reduction 95%
January 15, 2015 Applicability
January 15, 2015 Applicability
Gas Well Flowback Emissions to REC and Flare (100% Capture/Control)
October 15, 2015 Applicability
October 15, 2015 Applicability
Existing Small Dehydrators (Value)
Existing Large Dehydrators (95%)
If New Site/New EquipmentShow compliance with or non-applicability of NSPS OOOO in application using PI-7-CERT or APD-CERT
If Existing Site/EquipmentUse APD-CERT to show compliance with or non-applicability of NSPS OOOO
Applicability Forms
Enforceable Limit Control/Destruction Efficiency Claims Operating Hours
Why/When Do I Need to Certify?
www.texasoilandgashelp.org [email protected] Air Permits Main line: (512) 239-1250 Small Business and Environmental
Assistance: 1-800-447-2827 or www.TexasEnviroHelp.org
Where to Find More Information