Horace Mann School New Construction
Overall Site Plan
• 2 Story Building • Basement
Subterranean Parking • Building B
61,651 SF • 27 Classrooms • 1 Multipurpose
Room • 2 Science Labs • 1 Art Lab • 3 Staff Rooms
Horace Mann School New Construction
Subterranean Parking
• 49,843 SF • 65 Total Parking Spots • 4 ADA Parking Spots
Horace Mann School New Construction
First Floor Plan
• Total - 38,387 SF • Multipurpose Room • Boys and Girls Locker
Room • 15 Classrooms • 2 Science Labs • 2 Staff Lounges • Synthetic Turf
Playfield
Horace Mann School New Construction
• Total – 19,656 SF • 12 Classrooms • 1 Art Lab • 2 Staff Lounges • 4 Pa?os
Horace Mann School New Construction
Second Floor Plan
Horace Mann School New Construction
August 2014
October 2014
February 2015 April 2015
Progress Pictures
CONSTRUCTION SCHEDULE
Horace Mann School New Construction
!
! month! 1! 2! 3! 4! 5! 6! 7! 8! 9! 10! 11! 12! 13! 14! 15! 16! 17! 18! 19! 20! 21! 22! 23! 24!! ! !
! !
Jul%14!
Aug%14!
Sep%14!
Oct%14!
Nov%14!
Dec%14!
Jan%15!
Feb%15!
Mar%15!
Apr%15!
May%15!
Jun%15!
Jul%15!
Aug%15!
Sep%15!
Oct%15!
Nov%15!
Dec%15!
Jan%16!
Feb%16!
Mar%16!
Apr%16! May%16! Jun%16!
! ! !
!MOBILIZE! !! !! !!
! ! ! ! ! ! ! ! ! ! !!!
! ! ! ! ! ! ! ! ! ! ! !
!DEMO!!
!!! !!
! ! ! ! ! ! ! ! ! ! !!!
! ! ! ! ! ! ! ! ! ! ! !
!MASS!EXCAVATION!
! ! !!! !!
! ! ! ! ! ! ! ! !!!
! ! ! ! ! ! ! ! ! ! ! !
!GARAGE!
! ! ! !!! !! !! !! !! !! !! !! !!
!!!
! ! ! ! ! ! ! ! ! ! ! !
!
BUILDING!STRUCTURE!
! ! ! ! ! ! ! ! ! ! ! !!! !! !! !!
! ! ! ! ! ! ! ! ! ! !
!BUILDING!SHELL!
! ! ! ! ! ! ! ! ! ! ! ! ! !!! !! !! !! !!
! ! ! ! ! ! ! !
!INTERIOR!BUILD!OUT!
! ! ! ! ! ! ! ! ! ! ! ! ! !!! !! !! !! !! !! !!
!SUBSTANTIAL!COMPLETION!
4/2016! !
!SITE!/!LANDSCAPE!
! ! ! ! ! ! ! ! ! ! ! ! ! !!!
! !!! !! !! !!
! !
!PUNCH!&!CLOSE!OUT!
! ! ! ! ! ! ! ! ! ! ! ! ! !!!
! ! ! ! ! !!! !!
PROJECT!COMPLETION!6/9/16!
Phase 3
Building A Renovation: First Floor Plan Complete interior and exterior renovation of original HMS Building with interior reorganization to include Administration, Library, Cafeteria, Music Rooms, Computer Labs, Kindergarten, and other instructional support spaces.
Music / Special Educa?on
Cafeteria / Food Service
Administra?on Office / Main Entry
Library / Computer Lab Kindergarten / Community PTA Room
Computer Lab
Horace Mann School Building A Modernization
Phase 3
Building A Renovation: Second Floor Plan Complete interior and exterior renovation of original HMS Building with interior reorganization to include Administration, Library, Cafeteria, Music Rooms, Computer Labs, Kindergarten, and other instructional support spaces.
Horace Mann School Building A Modernization