Top Banner

of 16

Hoover Dam Final

Apr 08, 2018

Download

Documents

trunal1
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/7/2019 Hoover Dam Final

    1/16

    THE HOOVER DAM

    By Group no 5

    Aniket Banarjee -05Sachin Desai -15

    Sunil Kale -25

    Prashant Mali -35

    Darshan Pimple -45

    Sunil Naryani -55

  • 8/7/2019 Hoover Dam Final

    2/16

  • 8/7/2019 Hoover Dam Final

    3/16

    HOOVER DAM

    Concrete arch-gravity dam in the BlackCanyon of the Colorado River

    Constructed between 1931 and 1936during the Great Depression

    Impounds Lake Mead and is located nearBoulder City, Nevada

    Construction cost $49 million

    Major tourist attraction

  • 8/7/2019 Hoover Dam Final

    4/16

    BACKGROUND RESOURCES

    Improvement in electric power transmissiontechnology

    Edison Electric (EE) surveyed had potential ofbuilding a 40-foot (12 m) rock dam which couldgenerate 10,000 horsepower (7,500 kW)

    Limit of transmission of electric power was 80 miles(130 km)

    Reclamation Service finally rejected the proposal

  • 8/7/2019 Hoover Dam Final

    5/16

    PLANNING & DESIGNING

    Fall-Davis report & Federal concerns

    Interstate compact

    Concrete arch-gravity dam

    The wedge-shaped dam would be 660 ft (200 m) thick atthe bottom, narrowing to 45 ft (14 m) at the top

    Winning bid to build the dam was submitted by aconsortium called Six Companies, Inc.

  • 8/7/2019 Hoover Dam Final

    6/16

    DESIGN

    Height - 726.4 ft (221.4 m)

    Length - 1,244 ft (379 m)

    Crest width - 45 ft (14 m)

    Base width - 660 ft (200 m)

    Volume 3,250,000 cu yd. (2,480,000 m3)

    Impounds Colorado River Type of spillway 2 x controlled drum-gate

    Spillway capacity 400,000 cu ft/s (11,000 m3/s)

  • 8/7/2019 Hoover Dam Final

    7/16

    LABOR FORCE

    Company hired large numbers of workers, more

    than 3,000 on the payroll by 1932

    Employment peaking at 5,251 in July 1934

    On August, 1937 first strike took place and secondlabor action took place in July 1935

  • 8/7/2019 Hoover Dam Final

    8/16

    RIVER DIVERSION

    River needed to be diverted away

    Four diversion tunnels - two on the Nevada sideand two on the Arizona side

    Tunnels were 56 feet (17 m) in diameter. Their

    combined length was nearly 16,000 ft or more

    than 3 miles (5 km).

  • 8/7/2019 Hoover Dam Final

    9/16

    CONCRETE

    The first concrete was poured into the dam on June 6,1933, 18 months ahead of schedule

    Used steel buckets 7 feet (2.1 m) high and almost 7 feet

    (2.1 m) in diameter

    A total of 3,250,000 cubic yards (2,480,000 m3) ofconcrete was used

    In addition, 1,110,000 cubic yards (850,000 m3) were usedin the power plant and other works.

    More than 582 miles (937 km) of cooling pipes were placedwithin the concrete.

  • 8/7/2019 Hoover Dam Final

    10/16

    OPERATION OF THEPLANT

  • 8/7/2019 Hoover Dam Final

    11/16

    POWER PLANT AND WATER DEMANDS

    Excavation completed in late 1933

    Filling of the lake began on February 1, 1935

    In the later half of 1936, water levels of Lake Meadwere high enough to permit power generation, and thefirst three generators began operating

    By September 1939, the dams power plant hadbecome had become the largest hydroelectricityfacility in the world

  • 8/7/2019 Hoover Dam Final

    12/16

    POWER PLANT AND WATER DEMANDS

    (CONTINUED)

    The final generator came to service only in 1961

    The average annual generation ofHoover Dam is 4.2Terawatt-Hour / Year

    Water released from the Dam irrigates over 400,000

    ha of land

  • 8/7/2019 Hoover Dam Final

    13/16

    RO ROADWAY

    There are two lanes for automobile traffic across

    the top of the dam, which formerly served as

    Colorado River crossing

    The Hoover Dam Bypass opened on October 19,

    2010. With the opening of the bypass, traffic is no

    longer allowed over Hoover Dam

  • 8/7/2019 Hoover Dam Final

    14/16

    TOURISM

    Hoover Dam was opened to the tourists since its

    completion in 1937

    The has dam remained closed only on a few days

    since then and more than a million people visit the

    dam every year

  • 8/7/2019 Hoover Dam Final

    15/16

    ENVIRONMENTAL IMPACT

    For almost six years after the construction ofHoover

    Dam, while Lake Mead filled up, virtually no water

    reached the mouth of the river

    The dam eliminated the natural flooding of River

    Colorado, which imperiled many species adapted to

    flooding, including plants and animals

    Some species of fishes native to the Colorado River

    are currently listed as endangered

  • 8/7/2019 Hoover Dam Final

    16/16