8/7/2019 Hoover Dam Final
1/16
THE HOOVER DAM
By Group no 5
Aniket Banarjee -05Sachin Desai -15
Sunil Kale -25
Prashant Mali -35
Darshan Pimple -45
Sunil Naryani -55
8/7/2019 Hoover Dam Final
2/16
8/7/2019 Hoover Dam Final
3/16
HOOVER DAM
Concrete arch-gravity dam in the BlackCanyon of the Colorado River
Constructed between 1931 and 1936during the Great Depression
Impounds Lake Mead and is located nearBoulder City, Nevada
Construction cost $49 million
Major tourist attraction
8/7/2019 Hoover Dam Final
4/16
BACKGROUND RESOURCES
Improvement in electric power transmissiontechnology
Edison Electric (EE) surveyed had potential ofbuilding a 40-foot (12 m) rock dam which couldgenerate 10,000 horsepower (7,500 kW)
Limit of transmission of electric power was 80 miles(130 km)
Reclamation Service finally rejected the proposal
8/7/2019 Hoover Dam Final
5/16
PLANNING & DESIGNING
Fall-Davis report & Federal concerns
Interstate compact
Concrete arch-gravity dam
The wedge-shaped dam would be 660 ft (200 m) thick atthe bottom, narrowing to 45 ft (14 m) at the top
Winning bid to build the dam was submitted by aconsortium called Six Companies, Inc.
8/7/2019 Hoover Dam Final
6/16
DESIGN
Height - 726.4 ft (221.4 m)
Length - 1,244 ft (379 m)
Crest width - 45 ft (14 m)
Base width - 660 ft (200 m)
Volume 3,250,000 cu yd. (2,480,000 m3)
Impounds Colorado River Type of spillway 2 x controlled drum-gate
Spillway capacity 400,000 cu ft/s (11,000 m3/s)
8/7/2019 Hoover Dam Final
7/16
LABOR FORCE
Company hired large numbers of workers, more
than 3,000 on the payroll by 1932
Employment peaking at 5,251 in July 1934
On August, 1937 first strike took place and secondlabor action took place in July 1935
8/7/2019 Hoover Dam Final
8/16
RIVER DIVERSION
River needed to be diverted away
Four diversion tunnels - two on the Nevada sideand two on the Arizona side
Tunnels were 56 feet (17 m) in diameter. Their
combined length was nearly 16,000 ft or more
than 3 miles (5 km).
8/7/2019 Hoover Dam Final
9/16
CONCRETE
The first concrete was poured into the dam on June 6,1933, 18 months ahead of schedule
Used steel buckets 7 feet (2.1 m) high and almost 7 feet
(2.1 m) in diameter
A total of 3,250,000 cubic yards (2,480,000 m3) ofconcrete was used
In addition, 1,110,000 cubic yards (850,000 m3) were usedin the power plant and other works.
More than 582 miles (937 km) of cooling pipes were placedwithin the concrete.
8/7/2019 Hoover Dam Final
10/16
OPERATION OF THEPLANT
8/7/2019 Hoover Dam Final
11/16
POWER PLANT AND WATER DEMANDS
Excavation completed in late 1933
Filling of the lake began on February 1, 1935
In the later half of 1936, water levels of Lake Meadwere high enough to permit power generation, and thefirst three generators began operating
By September 1939, the dams power plant hadbecome had become the largest hydroelectricityfacility in the world
8/7/2019 Hoover Dam Final
12/16
POWER PLANT AND WATER DEMANDS
(CONTINUED)
The final generator came to service only in 1961
The average annual generation ofHoover Dam is 4.2Terawatt-Hour / Year
Water released from the Dam irrigates over 400,000
ha of land
8/7/2019 Hoover Dam Final
13/16
RO ROADWAY
There are two lanes for automobile traffic across
the top of the dam, which formerly served as
Colorado River crossing
The Hoover Dam Bypass opened on October 19,
2010. With the opening of the bypass, traffic is no
longer allowed over Hoover Dam
8/7/2019 Hoover Dam Final
14/16
TOURISM
Hoover Dam was opened to the tourists since its
completion in 1937
The has dam remained closed only on a few days
since then and more than a million people visit the
dam every year
8/7/2019 Hoover Dam Final
15/16
ENVIRONMENTAL IMPACT
For almost six years after the construction ofHoover
Dam, while Lake Mead filled up, virtually no water
reached the mouth of the river
The dam eliminated the natural flooding of River
Colorado, which imperiled many species adapted to
flooding, including plants and animals
Some species of fishes native to the Colorado River
are currently listed as endangered
8/7/2019 Hoover Dam Final
16/16