HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009 S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related WP’s First priorities worked out : Separation from TI2 tunnel (ODH risk) Handling means (PR632 crane repair, BA7 door) Survey scanning of TTC6 and WANF Area Preparation of tendering documents for WANF dismantling Planning Agenda
10

HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

Dec 27, 2015

Download

Documents

Lambert Dean
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area

October 29 2009S. Evrard

1

• WG2&3 meeting organization• Preliminary WBS for related WP’s• First priorities worked out :

– Separation from TI2 tunnel (ODH risk)– Handling means (PR632 crane repair, BA7 door)– Survey scanning of TTC6 and WANF Area– Preparation of tendering documents for WANF dismantling

• Planning

Agenda

Page 2: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : WG2&3 meeting organization

October 29 2009S. Evrard

2

• Weekly coordination meeting every Friday at 15.30• Dino as secretary, agenda on Indico• Core team (EN-MEF): Ans, Dino, Hubert, Ilias, Michael,

Nicolas, Sebastien• Invited on request :

Meeting organization

Safety E. Paulat C. Pividori Y. Algoet L. Ulrici N. Conan H. Vincke

Transport A. Calderone S. Pelletier J-P Granchelli Y. Bernard P. Brunero I. Ruehl

CoolingVentilation

M. Nonis P. Pigne J. Lehtinen   S. Deleval B. Bannister

Electricity G. Le Godec G. Gros J-C Guillaume F. Tarita WP resp.

Access D. Vaxelaire

Civil eng. R. Morton

Page 3: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : WG2 – WANF Dismantling

October 29 2009S. Evrard

3 Work packages - tasks

Page 4: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : WG3 – Irradiation Area

October 29 2009S. Evrard

4 Work packages - tasks

Page 5: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat . Workpackages EN-HE

October 29 2009S. Evrard

5 Work package description

Detailed discussion with EN-HE for transport issues, to be followed next week by EN-CV for cooling and ventilation issues.

Page 6: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : First priorities worked out

October 29 2009S. Evrard

6 Separation from TI2 tunnel (ODH risk)

PPG_TI2 at BA7 reinforced to sustain a pressure up to 35mbar plus some sealing around cables and beam pipe

Started from scratch

Page 7: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat Project : First priorities worked out

October 23 2009S. Evrard

7 Handling means (PR632 crane repair, BA7 door)

• First inspection in January 09.• Not operated for more than 10

years.• A lot of components to be changed

(3 speed variators, remote control, 3 motors….)

• As expected repair cost > 100 k, price enquiry needed delays.

• Cost & delay saving approach : dismount the crane for repair at the surface (EHN1)

• Goal : back and operational underground in early 2010

• EN-HE will start dismounting it end of next week after cleaning-up by ASN under

RP team monitoring. 13 subsets identified.• BA7 motorized door to be refurbished by the end of the year.

Page 8: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat Project : First priorities worked out

October 23 2009S. Evrard

8 Survey scanning of TTC6 and WANF Area

• Suggested by Integration team

• Will save time in Integration studies

• Will help a lot regarding ALARA principles

• Can be carried out within one week before Xmas shutdown

• Detailed discussion tomorrow with survey responsible.

Page 9: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat : First priorities worked out

October 29 2009S. Evrard

9 Preparation of tendering documents for WANF dismantling

• Material inventory weight/volume OK (T1 and T9 targets).

• Other plants (CV, EL,…) in progress

• Movies T1 and T9 available.• Detailed RP survey available• Dismantling procedure worked

out with RP and transport

Page 10: HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October 29 2009S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.

HiRadMat Planning

October 29 2009S. Evrard

10 Planning