Thomas Lienhard 17 November 2010 High Maturity Heresy! Doing Level 5 Before Level 4 Without Data? Copyright © 2010 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a registered trademark of Raytheon Company.
29

High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Feb 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Thomas Lienhard17 November 2010

High Maturity Heresy!

Doing Level 5 Before Level 4 Without Data?

Copyright © 2010 Raytheon Company. All rights reserved.Customer Success Is Our Mission is a registered trademark of Raytheon Company.

Page 2: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 211/18/2010

Where Do We Get Our High MaturityKnowledge?

CMMI

The CMMI•Upfront material•Infamous page 80

Training Courses•CMMI Overview•Understanding CMMI High Maturity Practices•Six Sigma

Training Courses

Conferences

Conferences

Experiences

Experiences Appraisals

Appraisals•Leads•Mini Team partners

Others

Others•Consultants•“Experts”

Page 3: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 3

Where Do We Get Our High MaturityKnowledge?

Page 4: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 411/18/2010

[My] Evolution of High MaturityUnderstanding

Evolution of a High Maturity practitioner

SW CMM Six Sigma BlackBelt

SW CMMI CMMI Understand HighMaturity Practices

Understand BusinessObjectives

peer reviews

analysis of variation

peer review defect density

control charts

?identify what

REALLY matters

predict performance

Page 5: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 511/18/2010

Achieved SW CMM Level 5 in 2001 Did not see the “promised” 8:1 ROIWhat went wrong?

Is it about finding an iterative process to collect data so SPC can be applied? Is it about hanging a sticker on the wall? Is it about appeasing the SEI to avoid an audit? Or is it about meeting your primary business objectives?

Needed to understand our business and business objectives Needed to understand which processes had the greatest impact on business objectives

Nirvana at Level 5?

When you think you have it right, talk with those responsible for cost and schedule

Page 6: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 611/18/2010

Understanding What’s Critical to Our Business

Production is where opportunity abounds

Page 7: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 711/18/2010

Changing Our Approach

How to move from a Business that…

Understands Product

Requirements

Designs A Product

Determines Suppliers

Decides Where To

Build

Evaluate For Affordability Redesigns

UnderstandsThe Use Of

The Product

Makes Requirements

Capability Trades Around

Affordability

Determines A Build Strategy

Identifies Where To Buy

From

Designs To Maximize This

Strategy

To a Business that

Page 8: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 811/18/2010

High Maturity Timeline

Planning Development Manufacturing Field

1950–1970s

1980s–Present

RMS

HW

SW/SE

Pre-Concept

Models

Statistical techniques SPC

Org Objectives

Balance performance with producibility and affordability

Page 9: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 911/18/2010

High Maturity Timeline

Planning Development Manufacturing Field

1950–1970s

1980s–Present

RMS

HW

SW/SE

Pre-Concept

Models

Statistical techniques SPC

Org Objectives

Would you ever implement QPM before you have a contract?

Balance performance with producibility and affordability

Page 10: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1011/18/2010

High Maturity Timeline

Planning Development Manufacturing Field

1950–1970s

1980s–Present

RMS

HW

SW/SE

Pre-Concept

Models

Statistical techniques SPC

Org Objectives

How can you be confident something can be built,

if it has never been “invented”?

Balance performance with producibility and affordability

Page 11: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1111/18/2010

Brain Shift

SW SE HWSW SE HW

SW SE HWSWSEHW

SyDeSystDeve

System Development

Page 12: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1211/18/2010

Remember, What is Critical to the Business Production over Development

– Production is where cost and time are either minimized or super-inflated– The organization is willing to invest more in development in order to streamline

production Production

– Software Hit control C Rarely impacts development decisions

– Hardware Extremely complex Very much impacts development decisions

Primary focus is HW/SE/SW (System Development) The life cycle includes:

- pre-concept- development- manufacturing- fielding

Leveraging our capabilities to be innovative, fast, and effective

Page 13: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1311/18/2010

Profound Shift in Focus

DevelopmentSW

Page 14: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1411/18/2010

Profound Shift in Focus

DevelopmentSWSE

Page 15: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1511/18/2010

Profound Shift in Focus

DevelopmentSWSEHW

Page 16: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1611/18/2010

Profound Shift in Focus

DevelopmentSW 1st

SE 2nd

HW 2nd

Page 17: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1711/18/2010

Profound Shift in Focus

Pre-Concept Development Production Field/MaintSWSEHW

Page 18: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1811/18/2010

Profound Shift in Focus

Pre-Concept Development Production Field/Maint1st SWSEHW 2nd 1st 1st

Page 19: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 1911/18/2010

High Maturity “Epiphany”

Plan Req Design Imp Test

SW/SE

Finding “defects” earlier saves $

Page 20: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2011/18/2010

Finding “defects” earlier saves $

High Maturity “Epiphany”

Plan Req Design Imp Test

P R D I T Manufacturing FieldPre-Concept

Page 21: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2111/18/2010

Modeling Throughout the Lifecycle

Page 22: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2211/18/2010

Breaking the Paradigm – Level 5 Before 4 Without “Data”

Results Driven - Product Centric – Full Life Cycle – Multifunctional Approach

Start with business goals and drivers Establish objectives for entire lifecycle (pre-concept through delivery)

Predict success prior to design

Take a product centric,multi-discipline approach

Page 23: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2311/18/2010

EXAMPLE

Page 24: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2411/18/2010

Business Objective –Increase Margin Profit Cost of Poor Quality is Too High

– Cost and schedule need to be reduced

– Rework, scrap and support costs need to be reducedProduction Rework Costs

0

50000

100000

150000

200000

250000

300000

350000

400000

450000

500000

2002 2003 2004 2005 2006 2007 2008

Year

Hou

rs

$0

$5

$10

$15

$20

$25

$30

$M

Rework Hours ($M)

Improving production yields greatly reduces costs, schedule, rework, and scrap

Page 25: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2511/18/2010

Case Study Multiple projects using a common seeker have an Average Unit Production Cost

(AUPC) objective Sensitivity analysis showed which subprocess was the significant cost driver EOSPA predictive cost model was created to characterize the process

performance based on organizational historical baseline data Prediction showed the current process was incapable of achieving the AUPC

objective Causal analysis was done Process was characterized:

– Process steps– Touch points/hours – Parts – Effort

Improvements were identified and implemented– Eliminated non-value added process steps– Reduced number of touch points and touch hours– Reduced cycle time and touch labor– Eliminated parts– Substituted processes with new processes which

had reduced touch points/hours

Page 26: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2611/18/2010

Probability of Noncompliance (PNC): Probability of exceeding either lower or upper specification limits

Distribution fitted PNC = 30% Predicted estimated cost of scrap: $XXM Annually

Predictive Analysis Revealed:– Out of Control conditions will occur– Out of Spec conditions will occur – Mean was too close to lower limit –

need to center the distribution– Variance was too large –

identify / reduce sources of variation

Predictive Analysis

Low yields predicted as a result of poor process capability 180 out of 600 units would be scrapped

Page 27: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2711/18/2010

Results Resulted in 59% fewer process steps

45% fewer parts

44% less time

78% improved throughput

Predicted yields increased to over 90%

Predicted rework reduced by over 50%

Predicted scrap reduced by over 40%

Initial inspection costs reduced by over 50%

Warranty costs expected to be reduced by over 25%

Discipline, compliance, predicted performance and continuous improvement

Tech support? My predictive analysis is giving the wrong answer again – can you please fix it?

Page 28: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2811/18/2010

Summary

To meet business objectives, engineering must be more predictable

– Need to characterize process and product performance prior to implementation

– Need to establish and track design metrics that relate to business objectives (production yield and cost)

– MUST balance affordability and producibility as well as technical performance

Design for cost and producibility has become part of our DNA

Page 29: High Maturity Heresy! · [My] Evolution of High Maturity Understanding. Evolution of a High Maturity practitioner. SW CMM Six Sigma BlackBelt SW CMMI CMMI Understand High Maturity

Page 2911/18/2010

Questions