High level overview of HUB upgrade and market release strategy June 2010. Two Versions of the MPCC MPCC 15.1 (existing test W2000 machine, but with Schema 8 installed on it) MPCC 16.0 (new W2003/XP machine with schema 8). IPT Process. IPT Strategy. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: High level overview of HUB upgrade and market release strategy June 2010

High level overview of HUB upgrade and market release

strategy

June 2010

Page 2: High level overview of HUB upgrade and market release strategy June 2010

Two Versions of the MPCC

– MPCC 15.1 (existing test W2000 machine, but with Schema 8 installed on it)

– MPCC 16.0 (new W2003/XP machine with schema 8)

Page 3: High level overview of HUB upgrade and market release strategy June 2010

IPT Process

Page 4: High level overview of HUB upgrade and market release strategy June 2010

IPT Strategy

• To replicate the to-be situation , at least one MP is required to run IPT using MPCC 15.1 and, at the same time, at least one will use MPCC 16.0

This is a change to the process that was briefed at the November IGG

Page 5: High level overview of HUB upgrade and market release strategy June 2010

Schema Release

• March 19th. Dispatch upgraded schema 8 and two CDs to each MP.

– CD1 MPCC 15.1 – CD2 MPCC 16.0

Page 6: High level overview of HUB upgrade and market release strategy June 2010

MPCC 15.0

MPCC 15.1

MPCC 16.0

Liv

eT

es

t N

ew

(2

b L

ive

)N

ew

(2

b T

es

t)Pre-IPT IPT Go-Live Post Go-Live

Live IP/Cert

MPCC 16.0

CD1

CD2

MPCC 15.1

CD1

Live IP/Cert

MPCC 16.0

Retire Machine

Retire Machine

MPCC 16.0

Test IP/Cert

Live IP/Cert

Build from scratch as per 2blive above, when required

Mar 22-27 Mar 29-Apr 16 May 17 – Jun 11

MPCC 15.1

CD1 CD2= MPCC 16 + Schema 8.0

Test IP/Cert

Test IP/Cert

Apr 19-23

MPCC 15.1

Test IP/Cert Test IP/Cert

Jun 26-27 Before 2 July

= Schema 8.0 for MPCC 15.1

= Comms Test or Link

Page 7: High level overview of HUB upgrade and market release strategy June 2010

MPCC 15.0

MPCC 15.1

MPCC 16.0

Liv

eT

es

t N

ew

(2

b L

ive

)N

ew

(2

b T

es

t)

Pre-IPT IPT Go-Live Post Go-Live

MPCC 16.0

CD1

CD2

MPCC 15.1

CD1

Live IP/Cert

MPCC 16.0

Retire Machine

Retire Machine

MPCC 16.0

Test IP/Cert

Live IP/Cert

Build from scratch as per 2blive above, when required

Mar 22-27 Mar 29-Apr 16 May 17 – Jun 11

MPCC 16.0

Test IP/Cert

CD1 CD2= MPCC 16 + Schema 8.0

Test IP/Cert

Test IP/Cert

Apr 19-23 Jun 26-27 Before 2 JulyLive IP/Cert

= Comms Test or Link= Schema 8.0 for MPCC 15.1

Page 8: High level overview of HUB upgrade and market release strategy June 2010

MPCC 15.0

MPCC 15.1

MPCC 16.0

Liv

eT

es

t N

ew

(2

b L

ive

)N

ew

(2

b T

est)

Pre-IPT IPT Go-Live Post Go-Live

MPCC 16.0

CD1

CD2

MPCC 15.1

CD1

Live IP/Cert

MPCC 16.0

Retire Machine

Retire Machine

MPCC 16.0

Test IP/Cert

Live IP/Cert

Build from scratch as per 2blive above, when required

Mar 22-27 Mar 29-Apr 16 May 17 – Jun 11

MPCC 16.0

Test IP/Cert

MPCC 15.1

OR

CD1 CD2= Schema 8.0 for

MPCC 15.1= MPCC 16 + Schema 8.0

Test IP/Cert

Test IP/Cert

Apr 19-23

MPCC 15.1

Test IP/Cert Test IP/Cert

= Comms Test or Link

Jun 26-27 Before 2 JulyLive IP/Cert

Page 9: High level overview of HUB upgrade and market release strategy June 2010

Cutover

Page 10: High level overview of HUB upgrade and market release strategy June 2010

• By Thursday June 24th - Formal go/no-go confirmation from CER

• Friday June 25th – 13.00 - Confirmation from RMDS– 18.00* - Market Participants are asked not to

send in any Market Messages after this point

• Saturday June 26th

– Morning* - Application of changes– Afternoon* - Connectivity testing

• All communications will be via RMDS over the cutover weekend

* Times subject to validation through dress rehearsals

Page 11: High level overview of HUB upgrade and market release strategy June 2010

Contingency/Rollback

Page 12: High level overview of HUB upgrade and market release strategy June 2010

• Go/No-Go Decision prior to weekend• Hub Upgrade will precede the Market

Release• Planned to involve TSO and MP1 in

testing the hub upgrade• Therefore will require rollback plans for

both their backend systems • On success, apply SAP transports to

Central Market System – point of no return

Hub Upgrade

Page 13: High level overview of HUB upgrade and market release strategy June 2010

• Consists of SAP IS-U transports, RMP Extranet changes and MPCC 15.1 upgrade

• Any issues with the Market Release will be addressed through fixing forward i.e. application of corrective transport

Market Release

Page 14: High level overview of HUB upgrade and market release strategy June 2010

• Fallback is to switch production IP back to MPCC 15.1 in the event of a problem with MPCC 16.0

MPCC 16.0 upgrade

Page 15: High level overview of HUB upgrade and market release strategy June 2010

• Questions?