Top Banner
High Gradient tests at the KEK Nextef Facility Shuji Matsumoto On behalf of Nextef Group Accelerator Laboratory, KEK WE08 XB-10 22/05/13 1 XB-10 Cockcroft Institute
49

High Gradient tests at the KEK Nextef Facility

Feb 06, 2016

Download

Documents

luisa

WE08 XB-10 . High Gradient tests at the KEK Nextef Facility . Shuji Matsumoto On behalf of Nextef Group Accelerator Laboratory, KEK. Contents. Three topics I will report today are as follows. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: High Gradient tests at the KEK Nextef Facility

High Gradient tests at the KEK Nextef Facility

Shuji MatsumotoOn behalf of Nextef Group

Accelerator Laboratory, KEK

WE08XB-10

23/04/22 1XB-10 Cockcroft Institute

Page 2: High Gradient tests at the KEK Nextef Facility

ContentsThree topics I will report today are as follows

1) Review of two X-band high power stations in KEK; Nextef, the 100MW X-Band test station and KT-1, 50MW.

2) Recent high power test results of TD18_Disk#2 (a CLIC prototype structure with HOM damping slots).

3) A overview of our on-going programs such as the pulse compression system of Nextef as well as the future plans of X-band study.

23/04/22 2XB-10 Cockcroft Institute

Page 3: High Gradient tests at the KEK Nextef Facility

Mission

Nextef facility

•Nextef was proposed in 2006 and was constructed in 2007 as a reassembled facility of GLCTA to be a 100MW high power station for the X-band accelerating structure tests. •Since 2008, the facility runs for the development of CLIC prototype high gradient accelerator structures (of 100MV/m or beyond). The collaboration program is ongoing.

Nextef stands for NEw X-band TEst Facility.

KT-1

•A 50MW facility originally started as an X-band klystron test station in 2006.•Small experiments utilizing the klystron power are performed.

23/04/22 3XB-10 Cockcroft Institute

Page 4: High Gradient tests at the KEK Nextef Facility

Nextef100MW X-Band station in KEK

y/m2007/8 Start operation2007/12 Commissioning Power production went upto 100MW2008/1 Start Retest of KX032008/9 Start test of T182009/7 Start TD18Quad#5 test.2009/12 Starts TD18Disk2 test.2010/11 T24Disk installed. Ready to start testing

Features•Combined power of klystrons to produce 11.424GHz RF of peak power above 100MW (maximum power available depends on the pulse width). •Use of PPM klystrons (originally developed for GLC project).

•Associated with a concrete shield (Shield-A) which is fully equipped for the structure high power tests.•No beam available.

Nextef facility

23/04/22 4XB-10 Cockcroft Institute

Page 5: High Gradient tests at the KEK Nextef Facility

Nextef station configuration

A: ModulatorB: KlystronsC: Low Loss Power Transfer Line D: Accelerating structure under test in Shield-A (5m W x 3m D x 2m H)

• The modulator drives two 50MW PPM klystrons.• The combined power is transferred into Shield-A.• Local control room (not shown in this picture).

Nextef facility

23/04/22 5XB-10 Cockcroft Institute

Page 6: High Gradient tests at the KEK Nextef Facility

Plan View inside Shield-A observables along beam axis

ACC str: Structure under test FC: Faraday Cup, PM: Profile Monitor, AM: Analyzer magnet, GV: Gate Valve.

Comment: Some of the details are incorrect. The drawing should be updated.

Nextef facility

23/04/22 6XB-10 Cockcroft Institute

Page 7: High Gradient tests at the KEK Nextef Facility

•  24Hr operation is possible due to the linkage with KEKB Linac operation. (The linac operation=6000Hr/year.)

•  Local control as well as a remote control through Linac control system.

•  Possible to store / handle the operation data as well as experimental data through Linac control system (LINUX and EPICS).

Specifications

Frequency 11.424GHz

Max power production 100MW

Max power for test * 75MW

Pulse width 400ns

Repetition rate 50pps

* Measured Transmission Loss is 25%.

PerformanceNextef facility

23/04/22 7XB-10 Cockcroft Institute

Page 8: High Gradient tests at the KEK Nextef Facility

What we have achieved : Nextef•Continuous run established (Total RFON time is more than 20000hrs from 2006) .

•Maximum power 70MW, 250ns, 50pps for recent structure tests.

•The maximum power production is about 100MW. It is practically determined by the performance of one of the klystrons: Frequent Klystron gun breakdowns occur in one of the klystrons at the cathode voltage above 460kV. Below this voltage klystrons are stable.

Nextef facility

23/04/22 8XB-10 Cockcroft Institute

Page 9: High Gradient tests at the KEK Nextef Facility

KT-1 : 50MW X-band test station(y/m)2006/ 5 Start operation (as an X-band klystron test stand)2006/6 Klystron test (PPM6A)2007/1 Started to run for “small experiments”2008/5 Narrow waveguides (SUS003 followed by CU005) testing.2009/9 Testing RF Loads

Features

•Use of a single PPM klystron, 11.424GHz RF of peak power of 50MW, 400ns is available. This station runs for small-size experiments such as a narrow waveguide and RF component test (e.g. RF load).

•The current klystron sitting at KT-1 is old (constructed in 2003, repaired 2004) but it has been healthy so far.

•24Hr operation is possible.

•This station is rather crucial for Nextef, since sometimes we need to check the performance of the high power devices before their installation.

Nextef facility

23/04/22 9XB-10 Cockcroft Institute

Page 10: High Gradient tests at the KEK Nextef Facility

Test done at KT-1, an example.Test of CERN Cinel load and KEK Waveguide valve

CERN CINEL High power RF Load

KEK Waveguide valve

RF

2009.10.28

Lead Box(It is opened at this moment)

Nextef facility

23/04/22 10XB-10 Cockcroft Institute

Page 11: High Gradient tests at the KEK Nextef Facility

We are operating two X-band high power stationsKT-1 (50MW)

Klystron test, small experiments (in Lead shield box) or component tests

Test area in the bunker(Sheild-A)

Nextef (100MW)

Modulator and twin ppm klystrons

Nextef facility

23/04/22 11XB-10 Cockcroft Institute

Page 12: High Gradient tests at the KEK Nextef Facility

Klystrons

Spec of Nextef klystron: originally designed as a 75MW klystron for GLC project.

Frequency 11.424GHz

Peak Power 75MW

Pulse width 1.s

Repetition 150Hz

Cathode Voltage 480kV

Cathode Current 266A

Perveance 0.8uK

Efficiency >55%

Main Focus PPM

Max B / period 0.32T / 30mm

Magnet Material NdFeB

We have two(at Nextef)+one(at KT-1) ppm klystrons in operation and one spare.(“ppm” stands for “periodic permanent magnets”.)

Nextef facility

23/04/22 12XB-10 Cockcroft Institute

Page 13: High Gradient tests at the KEK Nextef Facility

X-band klystrons

We usually operate it at 50MW 400ns 50pps maximum. One tube has frequent gun breakdowns when it is operated more than at ~460kV. The performance of our X-band ppm focus klystron has a limit in available peak power and pulse width by RF instability. So far the tubes are good enough for our purposes.

Nextef facility

0.010.020.030.040.050.060.070.080.090.0

350.0 400.0 450.0 500.0 550.0Cathode Voltage (kV)

Pow

er

(MW

) /

Eff

. (%

)

PowerEfficiency

Result of high power testing. PPM4 (2003).

-50

-40

-30

-20

-10

0

10

20

30

-0.5

-0.4

-0.3

-0.2

-0.1

0

0.1

0.2

0.3

0 1 2 3 4 5

Pulse Waveforms

Volts

Volts (RF Power Signal)

time (micro sec)

Cathode Voltage

RF Power

Cathode Current

Collector Current

38.4MW @ 439kV

23/04/22 13XB-10 Cockcroft Institute

Page 14: High Gradient tests at the KEK Nextef Facility

Structure Test Procedure:How the research Collaboration works

Design for CLIC

(CERN)

Fabrication of parts (KEK)

Bonding (SLAC)

CP (SLA

C)

VAC bake (SLAC)

High power test

(NLCTA-SLAC)

High power test (Nextef-

KEK)

Two structures are made and treated as the twin for the evaluation.

TD18 Test

23/04/22 14XB-10 Cockcroft Institute

Page 15: High Gradient tests at the KEK Nextef Facility

T18_Disk_#2 TD18_Disk_#2

Test structures made as twinsTD18 Test

23/04/22 15XB-10 Cockcroft Institute

Page 16: High Gradient tests at the KEK Nextef Facility

Unloaded 100MV/mT18 TD18

0 2 4 6 8 10 12 14 16 180

50

100

150

200

250

iris number

P [

MW

] (b

lack

), E

s (

gre

en),

Ea (

red

) [M

V/m

],

T

[K

] (b

lue)

, S

c*50

[MW

/mm

2 ] (m

agen

ta)

8.1 12.5

148

232

2.7

4.4

76

126

53.0

37.4

Pinload = 53.0 MW, P

outload = 37.4 MW

Eff = 0.0 % tr = 0.0 ns, t

f = 0.0 ns, t

p = 100.0 ns

P (M

W),

Es

(MV

/m),

Ea

(MV

/m),

T

(C),

Sc*

50 (

MW

/mm

2)

Iris number

P

Ea

Sc

Es

T

T18 unloaded 100MV/m

0 2 4 6 8 10 12 14 16 180

50

100

150

200

250

iris number

P [

MW

] (b

lack

), E

s (

gre

en),

Ea (

red

) [M

V/m

],

T

[K

] (b

lue)

, S

c*50

[MW

/mm

2 ] (m

agen

ta)

29.1

47.0

155

226

3.2

4.4

79

120

57.5

34.3

Pinload = 57.5 MW, Pout

load = 34.3 MW

Eff = 0.0 % tr = 0.0 ns, tf = 0.0 ns, tp = 100.0 ns

P (M

W),

Es

(MV

/m),

Ea

(MV

/m),

T

(C),

Sc*

50 (

MW

/mm

2)

Iris number

P

Ea

Sc

Es

T

TD18 unloaded 100MV/m

TD18 Test

23/04/22 16XB-10 Cockcroft Institute

Page 17: High Gradient tests at the KEK Nextef Facility

Processing of damped structuresTD18_Disk_#3 tested at SLAC

0 100 200 300 400 500 600 700 800 900 10000

20

40

60

80

100

120

Accumulated rf process time (hr)

BDR (1/hr)

<G> for regular cell (MV/m)

Pulse Width (divided by 10 ns)

0

1000

2000

3000

Total # BD

RF-ON period (hrs)

Pul

se w

idrh

(ns

)/10

E

acc

(MV

/m)

TD18_Disk_#2 tested at KEK

Big difference in ramping speed.(may be partially due to the difference in

processing procedure)Both reached 100MV/m 240ns.

TD18 Test

23/04/22 17XB-10 Cockcroft Institute

Page 18: High Gradient tests at the KEK Nextef Facility

Breakdown rate T18 vs TD18

Undamped vs DampedSLAC vs KEK

Sensitive to Eacc (Es, Hs) ~ X10 / 5 (MV/m)BDR(damped) ~ 100 X BDR (undamped)

Damped structure: High pulse temperature rise? Any other mechanism?

Single-cell SW test also shows tight correlation of BDR to pulse temperature rise.

Helps if reducing temperature rise?

See the result of TD24 to be tested in several months.

TD18 Test

23/04/22 18XB-10 Cockcroft Institute

Page 19: High Gradient tests at the KEK Nextef Facility

TD18_#2 all BDR versus Eacc

It seems difficult to get a smooth curve as function of Eacc by collecting all data points scattered in time and in operation parameter space.

Usually we get a smooth curve by measuring intentionally with focusing to take data of BDR vs Eacc!?

TD18 Test

23/04/22 19XB-10 Cockcroft Institute

Page 20: High Gradient tests at the KEK Nextef Facility

Breakdown rate versus width or T

T18_Disk_#2BDR versus pulse width

Tight correlation with pulse width.

TD18 Test

TD18_Disk_#3 BDR versus T (pulse temperature rise)

Undamped

Damped

Tight correlation with pulse temperature rise. Same at 100MV/m but pulse length T Same T 83~84 degC but diff. Eacc

23/04/22 20XB-10 Cockcroft Institute

Page 21: High Gradient tests at the KEK Nextef Facility

TD18_#2 Evolution of breakdown rateTD18 Test

23/04/22 21XB-10 Cockcroft Institute

Page 22: High Gradient tests at the KEK Nextef Facility

TD18_#2 BDR versus widthat 100MV/m around 2800hr

and at 90MV/m around 3500hr

TD18 Test

The power of the width depends on Eacc. 23/04/22 22XB-10 Cockcroft Institute

Page 23: High Gradient tests at the KEK Nextef Facility

Evolution of dark current till early April in TD18_Disk

Dark current reduced by three order of magnitude. It followed roughly modified F-N formula. reduced from 70 to 40. * Es

max ~ 5~7 GV/m

IPAC10TD18 Test

23/04/22 23XB-10 Cockcroft Institute

Page 24: High Gradient tests at the KEK Nextef Facility

Comparison of dark current

0.01

0.1

1

10

100

50 60 70 80 90100 200

T18_#2  Dark Current evolution081128-081224-090224-090414-090515

FC-Mid [microA] (081128)

FC-Mid [microA] (081224) 

FC-Mid  microA  (253ns, 090225)

FC-Mid  microA  (253ns, 090414)

FC-Mid  microA  090515

FC-Mid microA

Eacc [MV/m]

T18_Disk

TD18_Disk

TD18_Quad

Eacc for peak dark current of 10 A90MV/m 70MV/m 40MV/m

TD18_Quad

Presented to IPAC10TD18 Test

23/04/22 24XB-10 Cockcroft Institute

Page 25: High Gradient tests at the KEK Nextef Facility

Summary of TD18_Disk#2 testing • Testing of TD18_Disk#2 structure is finished successfully.• Breakdown rates were and is being measured. It is 10-

4/pulse/m at 100MV/m at 252nsec. It is fair to conclude that BDR of TD18_Disk#2 is greater than that of T18 by about one-two order of magnitude (depends on Eacc).

• The amount of dark current has been decreasing by a few order of magnitude during the test (over some 2000hrs) and became very similar to that of T18.

• The field enhancement factor, beta, has decreased by factor of 2. The final value is some 40.

• Dark current was initially reduced but recently has been saturated.

TD18 Test

23/04/22 25XB-10 Cockcroft Institute

Page 26: High Gradient tests at the KEK Nextef Facility

•A few attempts to understand the properties of RF breakdowns in the structure were done: operation with RF double pulses, operation with additional eight pulses after an RF reflection interlock and operation with switching RF input power periodically.

•I quickly show the latter two results.

TD18 Test

23/04/22 26XB-10 Cockcroft Institute

Page 27: High Gradient tests at the KEK Nextef Facility

Run 98 switching in three power levels for 46.2 hours

Switching every second among three power levels, controlled by Ushimoto program.

90 – 95 – 100 MV/mRF pulse counts

Inpu

t po

wer

(M

W)

Histogram of pulses in terms of Eacc

Nicely separated with each other.

Input power (MW)

TD18 Test

23/04/22 27XB-10 Cockcroft Institute

Pulse width=252ns

Page 28: High Gradient tests at the KEK Nextef Facility

Run 98

81

43 Higher power pulse makes bigger BDR.

We compare this result to the usual BDR plot…

3.3*10-6 / 2.6*10-5 / 1.4*10-4 [BD/pulse/m]

TD18 Test

23/04/22 28XB-10 Cockcroft Institute

Page 29: High Gradient tests at the KEK Nextef Facility

Relevant data points of BDR vs Eacc

Data points from jumping among three levels

TD18 Test

23/04/22 29XB-10 Cockcroft Institute

Page 30: High Gradient tests at the KEK Nextef Facility

Run 100 at 100 MV/m level Behavior of eight pulses after BD

More than 50% of breakdowns are not accompanied by any consecutive breakdowns.Some are followed by breakdowns. Correlation between number of consecutive breakdowns and the hardness of the initial breakdown should be evaluated.

TD18 Test

23/04/22 30XB-10 Cockcroft Institute

Page 31: High Gradient tests at the KEK Nextef Facility

Vaccum issuesVacuum at low power level

Outgassing is observed at the monitor located at left arm of Acc output port when the power comes down (about a few MW) .Exact location of the outgas has not been identified yet.

Acc Input power

Pressure @IN-WG

We inserted a long waveguide (and put an additional pump) between the structure and the load to “separate” the vacuum. We expect better vacuum due to the added pump but …

TD18 Test

23/04/22 31XB-10 Cockcroft Institute

Page 32: High Gradient tests at the KEK Nextef Facility

6.3E-5

2.5E-7

4.0E-6

1.0E-6

T18

TD18

T24

It does not change so much now. We will watch the behaviour.

opeartion started

TD18 Test

23/04/22 32XB-10 Cockcroft Institute

Page 33: High Gradient tests at the KEK Nextef Facility

Demands for system upgradeFuture plans

There are always demand to improve the performance of a facility.Of course this is true for us..

For example, we have a room to improve the peak power of Nextef by introducing a relevant pulse compressor system, which should be useful for accelerating structure studies. Also from a technical point of view, this should be somewhat important for us to actually handle extremely high power over one hundred MW.

We have started this upgrade work within the same framework of collaboration between three labs.

23/04/22 33XB-10 Cockcroft Institute

Page 34: High Gradient tests at the KEK Nextef Facility

Nextef Pulse Compressor•A pulse compression system (PCS) will be installed in order to improve the peak power of Nextef 100→150MW. 100MW power available for structure tests. •A practical solution to getting higher peak power, necessary for the structure tests in the future.

•Use of single delay line (circular waveguide of phi 80mm). The line partially exists already as a C-band transmission line in Nextef experimental area. The circular polarized TE11 mode in X band is employed to store energy in this line. •The compression gain of 3 expected. Final power of 150MW 150ns pulse width is expected in Phase 1.

PCS INPUT :X-band PPM Klystrons: 25 MW each X2 X 750nsPCS OUTPUT: Gain 3 → 150MW, 150ns.

•In Phase 2 we utilize TE12 mode also to obtain 300ns output pulse while the peak power will be kept.

Future plans

23/04/22 34XB-10 Cockcroft Institute

Page 35: High Gradient tests at the KEK Nextef Facility

Nextef Delay Line Pulse Compressor

Kly

str

on

Acc

eler

ato

r

TE11R

TE11L

750ns → 150nsGain = 3.6 @ 3dB

22m - One ChannelK

lys

tro

nA

ccel

erat

or

1500ns → 300nsGain = 3.3 @ 3dB

TE11R

TE11L

TE12LTE12R

TE11 ModeConverter

TE11-TE12

Reflector (Mode exchanger)

Upgrade possible if we use a higher mode.

25 MW×2 Klyston×gain=3→ 150MW

Phase1

Phase2

Future plans

Tunable reflector

23/04/22 35XB-10 Cockcroft Institute

Page 36: High Gradient tests at the KEK Nextef Facility

C-band RF Source(will be removed.)

22m Delay line Originally constructed as the C-band transmission line in 2009 and will be converted as the X-band delay line for pulse compressor.

Nextef pulse compressor LayoutThe reflector will be put.

X-bandRF Source

PCS header(3dBHybrid+Mode Launcher)

Future plans

A

23/04/22 36XB-10 Cockcroft Institute

Page 37: High Gradient tests at the KEK Nextef Facility

Production of RF components:Kazakov Mode Converter

(Rect TE10→Circ TE01)

Noboru Kudoh

Future plans

23/04/22 37XB-10 Cockcroft Institute

Page 38: High Gradient tests at the KEK Nextef Facility

01020304050607080

0 200 400 600 800 1000 1200 1400 1600

ns

MW

PPM4 2003)(PPM4G2A(2006)

25MW,0.75us pulse compression

50MW,0.25us: current operation point  

Parameter choice / klystron stability

The points reflect the limit of the RF instability

Future plans

pulse compressionPhase 2

23/04/22 38XB-10 Cockcroft Institute

Page 39: High Gradient tests at the KEK Nextef Facility

Improvement Plan for KT-1Demand: There has been some requests on the testing of the cavity structures such as single cell structures, short structures, so on. Those experiments do not require much power and it can be provided by our single klystron.

Problem: However it is difficult to perform these programs at current KT-1 station where only a small lead box is there for small experiments. It is not practical to make a good shield nearby.

Solution:A simple solution is to use Shield-B which locates in next door. This can be done by constructing a new power transfer line.

Future plans

23/04/22 39XB-10 Cockcroft Institute

Page 40: High Gradient tests at the KEK Nextef Facility

Power delivery from KT-1 to Shield-B

We are able to start basic studies with structures using this test setup, though it sacrifices the usual KT-1 klystron activities (=Klystron test) somehow.

This experimental activities should complement the series of high gradient tests on CLIC prototype structures proceeded at Nextef.

Future plans

23/04/22 40XB-10 Cockcroft Institute

Page 41: High Gradient tests at the KEK Nextef Facility

KT-1X-band KT-2

Reflector

Delay line

Shield-B

NextefX-band

Lead Box (now workingfor small experiments)

Future plans

23/04/22 41XB-10 Cockcroft Institute

Page 42: High Gradient tests at the KEK Nextef Facility

Whole Configuration of the Proposed Power Line from KT-1 to Shield-B

The power from the klystron is transmitted through the circular waveguides (40mm diameter) with TE01 Mode. Those circular pipes, bends and vacuum ports are common to those used in the pulse compressor.

Future plans

23/04/22 42XB-10 Cockcroft Institute

Page 43: High Gradient tests at the KEK Nextef Facility

Status Future plans

Components: More than 80% fabricated.

A hole was made through a wall between KT1 and shield-B.

Installation of KT1-B in early next year.

Pulse compression setup will follow KT1-B setup.

23/04/22 43XB-10 Cockcroft Institute

Page 44: High Gradient tests at the KEK Nextef Facility

Nextef and KT-1 as of 2011

A

KT-1toB

B

Nextef with PCS

Future plans

23/04/22 44XB-10 Cockcroft Institute

Page 45: High Gradient tests at the KEK Nextef Facility

Summary: Future plansMost of the components of those lines for Nextef Pulse Compressor and KT-1 to B are in the final stage of the fabrication. The whole parts will be ready for construction soon.

The construction depends on the schedule of the testing in Shield-A and –B. The construction work will start in the end of this year.

We expect the power of more than 100MW * with 150ns pulse width in Nextef as well as that of 35MW *, 400ns in Shield-B available.

* Due to the transmission loss.

23/04/22 45XB-10 Cockcroft Institute

Future plans

Page 46: High Gradient tests at the KEK Nextef Facility

Nextef near future plan revised as of IWLC10

9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2

2010 2011 2012

PPM6B, Component tests, NWG test or serving shield-B, …….

A

B

KT-1

C-band Structure Test

Components fabrication

KT1 B connection

PC commissioning

TD24_Disk #3

X-band basic studies Construction in shield-B

T24_Disk #3TD18_Disk #3

TD24_Disk_R05 ?? ??

PC Construction??

23/04/22 46XB-10 Cockcroft Institute

Page 47: High Gradient tests at the KEK Nextef Facility

ConlusionsNextef, a 100MW X-band power station in KEK, has been running for the test of high gradient structures in last three years. The facility is dedicated for CLIC prototype structure tests in the framework of an international collaboration.

High power test of the structure TD18_Disk, the structure with damping slots has been over. The basic time trend of the BDR is and it is fair to say that its final value is from ten to hundred times higher (the factor depends on Eacc) than that of T18 structure.

Works for the future plans are ongoing to establish the higher peak power at Nextef and to provide a new experimental area (Shield-B) for KT-1.

23/04/22 47XB-10 Cockcroft Institute

Page 48: High Gradient tests at the KEK Nextef Facility

5th Collaboration Meeting on X-band Accelerator Structure Design and Test Program

Date: May 16th to 18th , 2011Place: Seminar hall of 4th building, KEK, Tsukuba, Japan (KEK Homepage: http://www.kek.jp/intra-e/)

Chaired by K.Ueno (KEK).Organized by T.Higo(KEK) S.Tantawi(SLAC) W. Wuensch(CERN).

23/04/22 48XB-10 Cockcroft Institute

Page 49: High Gradient tests at the KEK Nextef Facility

Now we suppose those issues to be covered:

Structure design: electrical and mechanical Manufacturing of parts; disks, couplers and loadsState-of-the-art precision machiningFabrication of quadrant/half structureExperimental study on high gradient performanceBreakdown physics and simulationsOn-going and possible new collaborations …. Others

In this 5th collaboration meeting, we set one day dedicated for the effort to understand and suppress the vacuum breakdowns in addition to the usual collaboration meeting. Especially we try to introduce those activities ongoing in Japan for making perfect or special surface based on the state-of-the-art precision machining technology.

Details and registration procedures will be posted at conference web site soon.See you in Tsukuba in next spring!

23/04/22 49XB-10 Cockcroft Institute