HESSEQUA MUNICIPALITY SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY HESRIV-489 Revision 2.0 AUGUST 2019 PREPARED BY: CLIENT: ASLA DEVCO PO Box 118 GORDONS BAY 7151 MR G PEPLER 22 HEIDELBERG ROAD RIVERSDALE 6670 Tel : (028) 713 4030 Fax : 086 617 4114 Mobile : 083 447 9297 Email : [email protected]
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
1.4.1 Major Systems ..............................................................................................................................6
1.4.2 Minor Systems and Storm water Design ......................................................................................6
1.5 WATER .............................................................................................................................................7
1.5.1 WATER SOURCE AND WTW ......................................................................................................7
3.5.2 WATER DEMAND ........................................................................................................................9
ANNEXURE B : TRAFFIC IMPACT ASSESSMENT ........................................................................... 17
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
ANNEXURE C : TECHNICAL REPORT FOR THE UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS ................................................................................................ 18
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 4
INTRODUCTION
Hessequa Consulting Engineers have been appointed by ASLA Devco for the planning and design of
civil engineering services, on Portion 111 of the Farm Melkhoutfontein No 480, for a Low-Cost Housing
project in Melkhoutfontein in the Western Cape. This report is based on a desk top study and is compiled
on behalf of the Hessequa Municipality for submission to the Department of Human Settlements as part
of the project application for conditional approval of the housing development.
The report will discuss the design criteria and specifications which will apply to civil engineering services
required for the development.
LOCATION AND ACCESS
Melkhoutfontein falls within the demarcated boundaries of the Hessequa Municipality in the Western
Cape and is situated 335km East of Cape Town and 35km South East of Riversdale, the administrative
headquarters of the region. The proposed development site (Portion 111 of the Farm Melkhoutfontein
No 480) is a vacant area adjacent (South) to Divisional Road 1528 known as Suikerbos Road.
One access, from Divisional Road 1528, will be provided opposite an existing intersection to the
Melkhoutfontein Industrial Area.
CIVIL ENGINEERING SERVICES
Proposed designs are based on the design standards of the Guidelines for the Provision of Engineering
Services and Amenities in Residential Township Development as published by the CSIR as well as the
minimum requirements of Hessequa Municipality.
1.1 MASS EARTHWORKS
Very little earthworks will be required to ensure a 2% free draining slope in a South Eastern direction.
Localised depressions will be filled with G7 material from commercial sources and compacted to 93%
MAASTO.
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 5
1.2 ACCESS ROAD
Deca Consulting Engineers was contracted by Asla Devco to carry out a Traffic Impact Assessment on
the proposed single access to the complete development off the DR1528.
The following recommendations were made to ensure that the access comply with safe operating
standards:
An exclusive right turn lane is warrant on the eastern DR1528 approach.
It is suggested that taxi embayment’s be provided at the two community centres in the new
suburb.
A sidewalk be provided along the central north-west/south-east roads through the new
development.
1.3 INTERNAL ROADS
The Minimum Design and Construction Standards for Internal A Grade Engineering Services, as
approved by the Chief Director: Human Settlements, will be applicable for this project. The access road
will consist of a 6,0m wide road within the proposed 13m road reserve (Class 4). Road finishing will
consist of double and single surface treatments with stormwater pipework and inlet- and outlet structures.
The basis of the road and pavement design for the proposed development is set out in the table below:
Table 1 Road Design Criteria
Parameter Local Distributor Residential Access
Loop Residential Access
way (Class 4) (Class 5b) (Class 5d)
Category UB UC UC
Traffic Class E1 E0 E0
Structural Design Traffic 0.05 - 3 x 106 < 0.2 x 106 < 0.2 x 106
Surface Treatment Double surface treatment with 13,2 & 6,7mm aggregate and
single slurry seal
Single surface treatment with 13mm aggregate and two
slurry seals
Single surface treatment with 13mm aggregate and two
slurry seals
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 6
Base and Sub-base from commercial sources
150mm G2 (98% MAASHTO) on 150mm G4 (95% MAASHTO) on 150mm Roadbed prep insitu Material (93% MAASHTO)
100mm G4 (98% MAASHTO) on 125mm G6 (95% MAASHTO) on 150mm Roadbed prep insitu Material (93% MAASHTO)
100mm G4 (98% MAASHTO) on
125mm G6 (95% MAASHTO) on
150mm Roadbed prep insitu Material (93%
MAASHTO)
Sub-grade (Historical geotechnical investigation, close to the site, suggest that the site is essentially underlain from ground surface by Aeolian silty sands which overlie calcarenites, calcareous sands, sands and gravelly soils of the Bredasdorp Group.
- - -
Carriage Way Width 6.0 4.5 4.5
Design Speed 50 km/h 40 km/h 30 km/h
Maximum Gradient 10% over 100m max 16% over 50m max 16% over 30m max
Minimum Gradient 0.5% 0.5% 0.5%
Cross Fall 2% 2% 2%
Bellmouths 8m Radius 8m Radius 8m Radius
1.4 STORMWATER
1.4.1 Major Systems
Two water courses cross the proposed development site. Free drainage of all roads will be in a South
Eastern direction. The lowest drainage point is located in the south eastern corner of the site.
Stormwater will drain, from this point, in a southerly direction to the Olive Grove storage dam.
Stormwater will be released via a Gabion energy dissipating structure, which will disperse stormwater at
a controlled rate thus reducing the risk of erosion. The structure will further trap waste transported from
storm water inlet structures.
1.4.2 Minor Systems and Storm water Design
Stormwater infrastructure will be constructed in accordance with the standard requirements and
specifications as agreed with the Hessequa Municipality.
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 7
Stormwater runoff from the erven will gravitate towards the internal road network. Surface runoff will be
collected via kerb inlet structures and transported via pipe culverts to the lowest point on the site.
Servitudes will be provided for storm water reticulation as required.
Design criteria adopted for the development with regard to stormwater infrastructure is summarised as
follows:
Runoff rates will be determined according to the Rational Method.
Flood recurrence interval : 2 years
Pipe material : Concrete
Pipe class : 75D / 100D
Pipe diameters : min 375mm Ø up to diameter as required
Bedding : Class C
Inlets : Kerb and drop inlets as required
Manholes : Point of deflections on pipes
1.5 WATER
1.5.1 WATER SOURCE AND WTW
Melkhoutfontein is supplied with water from the Melkhoutfontein spring situated in the most Northern
corner of erf 570. A Report on Geohydrological Investigation for the Planned Expansion of the
Melkhoutfontein Village Area was completed by Groundwater Complete in May 2015.
The measured spring discharge records indicate that the minimum spring flow during the monitoring
period was around 9 l/s in January 2015 while the maximum rate was 21 l/s measured in July 2014.
The total discharge of the spring (after the off-take to the farmers of 95 000 m3 per year) over the year of
monitoring was in the order of 440 000 m3, which gives an average discharge of 13.9 l/s for the period.
Important to note from a bulk water supply perspective is that the highest demand period in the year is
through the warm summer and December holiday period when rainfall is at its lowest and the spring
discharge is also the lowest. At current spring flow, especially through December, is unable to supply in
the demand and water is used from storage.
Additional demand will definitely cause water shortages during this period. Although the exact spring
flow for a specific rainfall depth cannot be predicted, with only a year’s data, it is safe to surmise that a
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 8
very dry season (<300 mm of rain) will lead to water shortages for the community at its current water
consumption.
When comparing current supply and demand figures it was very clear that the spring can easily supply
the demand during the cool and rainy winter months, but that demand far outstrips supply during the drier
and hot summer holiday season. The shortage during this period to especially Still Bay East is supplied
from the Olive Grove Dam storage. The dam is also fed by the other spring to the south of
Melkhoutfontein.
The solution for water supply to additional houses at Melkhoutfontein will thus be to develop a sufficient
buffer volume to keep up supply through the dry season or by securing other sources of bulk water supply.
Alternative bulk water sources
Groundwater from boreholes in the area was identified as a viable, cost-effective source as supply
boreholes have been developed in the past for community projects. We know that the aquifers in the
area are reliable since Still Bay West was supplied, prior to the building of the Olive Grove Dam, entirely
by groundwater from boreholes.
A number of boreholes occur in the Melkhoutfontein area that has been tested in the past to determine
the sustainable yield. Two of the boreholes were re-tested to affirm the overall condition of the boreholes
and confirm previous yields. Average sustainable yields were calculated at approximately 10 l/s for
borehole BH01B, while a yield of ± 12 l/s was calculated for borehole BH04. For the proposed housing
development at Melkhoutfontein it is strongly recommended that one or 2 of these boreholes be
commissioned for bulk water supply to augment the supply from the Melkhoutfontein Spring.
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 9
1.5.2 WATER DEMAND
For this preliminary capacity analysis of the Melkhoutfontein water system, the total annual average daily
demand (AADD) and fire flows for the proposed development was calculated as follows:
The proposed new development will have no capacity effect on the existing sewer reticulation system.
The existing Melkhoutfontein PS must be upgraded to a pumping capacity of 20 ℓ/s to accommodate the
existing and proposed development.
1.6.3 SEWER RETICULATION
A waterborne sewer reticulation system comprising of 160mm class 34 PVC sewer mains with solid shaft
fibre cement manholes complete with ductile iron double lipped manhole covers is proposed.
Each new erf will be provided with a 110mm Ø Class 34 uPVC connection with rodding eye and end cap
terminating one meter from the erf boundary. Typical details are shown on drawing HESRIV-489/S01.
1.7 ELECTRICAL SLEEVES
The position of electrical sleeves (110/160mm Class 34 PVC) will be determined in consultation with the
Electrical Engineer.
COST ESTIMATE : MELKHOUTFONTEIN HOUSING
The preliminary estimated cost for the provision of bulk/link services for the proposed development of
585 Low Cost erven is set out in the table below, viz.
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 14
Table 3 : Cost Estimate
Description Costs
Costs associated with the provision of Bulk/link services
Water:
Development of Bore Hole BH01B R 180,000.00
75mm Ø Class 9 pipeline between BH01B and existing Melkhoutfontein Spring Pump Station
R 970,000.00
Link water main : 1160m long 160mm Ø Class 12 uPVC R 995,000.00
Sub-Total - A R 2,145,000.00
Sewer:
Sewage Pump Station (Civil, Mechanical & Electrical) R 550,000.00
Rising Main : 1240m long 110mm Ø Class 9 uPVC R 845,000.00
Upgrading of Existing Sewage Pump Station (20 ℓ/s) R 280,000.00
Sub-Total - B R 1,675,000.00
WWTW:
Extension of Oxidation ponds R 890,000.00
Provision of bypass from Pond 3 to 7 R 25,000.00
Pipe work and site works (including dealing with water) R 100,000.00
Polishing via reed bed system (2,279m²) R 400,000.00
Disinfection facility R 70,000.00
Sludge drying beds (480m²) R 864,000.00
Mobile sludge pump, including pipe work R 450,000.00
Sub-Total - C R 2,799,000.00
Irrigation:
New irrigation pump installation, gravity main, holding tank and power supply to irrigation system.
R 550,000.00
Supply and installation of irrigation system on 28 ha. R 1,120,000.00
Sub-Total - D R 1,670,000.00
External Road widening of DR1528:
Widening of DR1528 R 320,000.00
Sub-Total - E R 320,000.00
Sub-Total (A to E) Carried over R 8,609,000.00
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 15
Sub-Total (A to E) Brought forward R 8,609,000.00
Plus : Preliminary & General @ 20% R 1,722,000.00
Plus : 5% Contingencies R 518,000.00
Plus : Engineering Fees @ 11% (Fees and Recoverable Costs) R 1,194,000.00
Plus : Water Use Licence Application and Geohydrological Study and Modelling R 3,000,000.00
Plus : Recoverable Cost (Survey, Soil Tests, Occupational Health & Safety and Administrative Costs – Excluding any Environmental Reports, Authorisation applications or Management Plans.
R 280,000.00
Total (Excluding 15% VAT) R15,323,000.00
CONCLUSION
We trust that the information provided in this report will provide an understanding with regard to the
required link/bulk infrastructure for the development of 585 low cost housing erven on Portion 111 of the
Farm Melkhoutfontein 480.
GIDEON PEPLER Pr Tech Eng HESSEQUA CONSULTING ENGINEERS
12 August 2019
SERVICES REPORT FOR CIVIL ENGINEERING SERVICES ON PORTION 111 OF THE FARM MELKHOUTFONTEIN NO 480 FOR HESSEQUA MUNICIPALITY
HESRIV-489 SERVICES REPORT -REV 2
P a g e | 16
ANNEXURE A : DRAWINGS
HESRIV-489-BW-01 : BULK WATER LAYOUT
HESRIV-489-BS-01 : BULK SEWER LAYOUT
HESRIV-489-W01 : WATER RETICULATION TYPICAL DETAILS
MELKHOUTFONTEIN LOW COST HOUSING PROJECT TRANSPORT IMPACT ASSESSMENT
1
1. BACKGROUND
Deca Consulting Engineers were appointed by Asla Devco (Pty) Ltd to assess the transport impact of the proposed subsidised housing development on Portion 111 of the Farm Melkhoutfontein No. 480,. The transport impact assessment is submitted as part of the land use planning application. The report is based on the Draft Layout Plan by Urban Dynamics dated 12 February 2019, a copy of which is attached.
Melkhoutfontein is located to the west of the existing town of Melkhoutfontein and to the
north of Melkhoutfontein Primary School, approximately 5 kilometres north of Stilbaai in the Hessequa Municipal area. The town is accessed from the N2 via Main Road (MR) 332 (R305) and Divisional Road (DR) 1528. Minor Road (OP) 4896 serves as the main east-west road through Melkhoutfontein. The location of the development as well as the high order roads in the vicinity are shown in Figure 1.
The settlement was originally established as a fisherman’s village and today serves mainly
as a dormitory town to Stilbaai. There is a school, a clinic, churches, sports fields and small spaza-type shops, but no real commercial or industrial opportunities. Most Melkhoutfontein residents travel to Stilbaai or Riversdale for administrative, shopping and work purposes.
2. DEVELOPMENT PROPOSAL
The attached Site Layout Plan shows that the property will be developed in two phases. The first phase will consist of 253 residential erven, one business erf and one erf each zoned for utility and community use. The second phase will have 332 residential erven, one erf zoned for community use and 4 erven zoned for utilities. Both phases will obtain access via a single point off DR1528.
3. EXISTING ROADS AND TRAFFIC
Important roads that will be impacted by the development include the MR332 (R305; Class 3 Minor Arterial), DR1528 (Class 4 Collector Roads) and OP4896 (Class 5). The RCAM Classification was obtained from the Western Cape Road Network Information website.
Traffic counts were done at the MR332 / DR1528 intersection on Tuesday 11 June 2019.
This intersection is a T-junction with stop control on DR1528. Peak hours were observed between 6:45 and 7:45 in the morning and between 16:30 and 17:30 in the afternoon. The counts show that 10% of the vehicles counted during 12-hour count were minibus taxis and 2% was buses.
The intersection was analysed using SIDRA software. The analysis indicates that all
movements operate at a level of service A during both the morning and afternoon peak hours. The good service levels were confirmed during a site visit. Existing 2019 traffic volumes and service levels are shown in Figure 2.
4. BACKGROUND TRAFFIC
It is expected that both phases will be completed and most homes occupied by the end of 2022. Existing 2019 traffic volumes were increased by 4,4% per annum as per the historical growth rate obtained from the Western Cape Provincial Road Network Information System to calculate Year 2022 baseline traffic volumes. The analysis of the MR332 / DR1528 intersection with the baseline volumes shows that all movements will continue to operate at a level of service A during the morning and afternoon peak hours. See Figure 3.
2
5. DEVELOPMENT TRIPS For the purpose of this report it was assumed that one of the community erven would be
used for a church and the other for a crèche. Trip generation rates for the church and crèche were obtained from the 2013 COTO TMH7 South African Trip Data Manual. It was assumed that only 50% of the crèche trips would be private transport trips, with the remainder being non-motorised or public transport trips. The trip generation rate for the subsidy housing component was obtained from the older South African Trip Generation Rates document, as the newer manual does not give a rate for low income households. Although the rate for the subsidised housing component already takes into account the high public and non-motorised modal share, the 2019 traffic counts for Melkhoutfontein indicate that the private transport trip generation rate for this town is closer to 0,4 trips per residential unit. Based on these rates, it was calculated that the development will have the potential to generate 253 private vehicle trips (65 in, 188 out) during the morning peak hour and 259 trips (175 in, 83 out) during the afternoon peak hour. The trip generation details are shown in Tables 1 and 2.
It was assumed that the majority of trips to and from the creche and church would be from
Melkhoutfontein Village, whereas the most residential trips would be to and from MR332, where it was split 70:30 to the south (Stilbaai) and north (N2), respectively. The trip distribution is shown in Figure 5.
Phase 1 Residential 253 units 0,43 per unit 0,68 0,32 110 75 35
Church 100 seats 0,05 per seat 0,5 0,5 5 3 3
Phase 2 Residential 332 units 0,43 per unit 0,68 0,32 144 98 46
Crèche 80 kids 0,5 per child 0,5 0,5 40 20 20
Total 259 175 83 5. TRAFFIC IMPACT Development trips were added to Year 2022 background traffic volumes. The MR332 /
DR1528 intersection as well as the DR1528 / Development access intersection were analysed with the resultant total traffic volumes. The analysis shows that all movements at both intersections will operate at a level of service A during the morning and afternoon peak hours. It can be concluded that, although the development will generate a considerable number of trips, the traffic impact thereof will be low.
3
Melkhoutfontein
School
Although no improvements will be required at the DR1528 / Development access intersection, an exclusive right turn lane is warranted on the eastern DR1528 approach for safety purposes, based on the Western Cape Provincial Road Access Guidelines warrants.
6. PUBLIC TRANSPORT As stated in paragraph 3, approximately 10% of the vehicles counted on DR1528 were
minibus taxis. Another 2% of the vehicles were buses, presumably school buses. If it is assumed that taxis carry an average of 14 persons, buses carry 60 persons and cars two persons, it means that 29% of people in Melkhoutfontein using motorised transport use taxis, 32% use buses and 39% use cars.
Formal taxi embayments were provided on either side of MR322 just south of the DR1528
intersection during the 2017 reconstruction of MR322. Counts were done at the taxi stops on 11 June 2019. The counts show that only one minibus taxi stopped on the western side of the road during the 12-hour counting period, while ten taxis stopped on the eastern (Melkhoutfontein) side. During the same period, 52 taxis travelled from Melkhoutfontein towards Struisbaai with 55 taxis doing the reverse trip.
It is expected that the new Melkhoutfontein development will generate a considerable
number of public transport trips. Due to the size of the development it is expected that minibus taxis will establish regular routes through the area to pick up and drop off passengers. It is suggested that taxi embayments should be provided at the two community centres in the new suburb.
7. NON-MOTORISED TRANSPORT There is a paved footpath linking Melkhoutfontein to the primary school and MR332. The
new development will be provided directly to the north of the footpath, which means that the new development will also be served by the footpath (See Diagram 1 below). The Site Development Plan shows that provision has been made for pedestrian links to the footpath. There is also a paved sidewalk along the eastern side of MR332 all the way from the Melkhoutfontein footpath to the town of Stilbaai. On the day of the traffic counts, only twelve pedestrians were recorded making use of the footpath from the MR332 side.
Diagram 1: Footpath between MR332 and Melkhoutfontein
4
The existing non-motorised transport infrastructure will be sufficient to accommodate the new development. The only new infrastructure recommended, is a sidewalk along the central north-west / south-east road through the new development.
8. CONCLUSIONS It can be concluded from the study that the proposed low-cost housing development in
Melkhoutfontein will have a low traffic impact. Other important findings are summarised as follows:
The development will consist of residential erven, one business erf and one erf each
zoned for utility and community use. The second phase will have 332 residential erven, one erf zoned for community use and 4 erven zoned for utilities;
The full development will have the potential to generate 253 private vehicle trips (65 in, 188 out) during the morning peak hour and 259 trips (175 in, 83 out) during the afternoon peak hour;
Public transport vehicles account for 12% of the vehicles counted on DR15258, the access road to Melkhoutfontein;
All roads and intersections that will be affected by the proposed development currently operate at excellent service levels and will continue to do so with the addition of development trips;
There are taxi embayments next to MR332 within walking distance from the proposed development;
The development will be located directly north of a paved footpath linking Melkhoutfontein to the primary school and MR332. The Site Development Plan shows that provision has been made for pedestrian links to the footpath.
9. RECOMMENDATIONS It is recommended that the proposed Melkhoutfontein low cost housing development be
approved, on condition that the following recommendations are considered:
An exclusive right turn lane is warranted on the eastern DR1528 approach, based on the Western Cape Provincial Road Access Guidelines warrants;
It is suggested that taxi embayments should be provided at the two community centres in the new suburb;
A sidewalk should be provided along the central north-west / south-east road through the new development.
We trust that you will find this report in order. Kindly contact Liezl du Plooy at telephone number 082 338 6466 should you have any questions. Yours truly Liezl du Plooy M. Eng Pr. Eng Deca
E
x
i
s
t
i
n
g
P
o
w
e
r
l
i
n
e
140
3
0
4
0
120
130
Riversdale
G
o
u
ritz
m
o
n
d
S
t
i
l
b
a
a
i
Main R
oad 332 (U
nder C
onstruction)
Business ±
0.15ha
1
0
m
1
0
m
1
0
m
8
m
8
m
1
0
m
8
m
8
m
8
m
8
m
8
m
D
iv
is
io
n
a
l R
o
a
d
P
1
5
2
8
R
3
0
5
P
e
d
e
s
tria
n
W
a
lk
w
a
y
1
3
m
8
m
8
m
8
m
1
0
m
1
0
m
1
0
m
Community
Facility
± 0.06ha
Community
Facility
± 0.26ha
CLIENT
INDEMNITY
URBAN DYNAMICS MAKES NO WARRANTY OF ANY KIND, EXPRESSED OR IMPLIED, WITH REGARD
TO THE DATA AND SHALL NOT BE HELD LIABLE IN ANY EVENT FOR ANY INCIDENTAL OR
CONSEQUENTIAL DAMAGES IN CONNECTION WITH OR ARISING OUT OF THE USE OF THIS DATA.
THE DATA REMAINS THE SOLE PROPERTY OF THE CLIENT AND MAY ONLY BE USED FOR THE
PURPOSES OF A PROJECT WITH THE PRIOR WRITTEN APPROVAL OF THE CLIENT.
12 Feb 2019
See Linescale
FILE NAME:
PLAN NO.
SCALE
DATE
RESERVED
COPYRIGHT
DRAFT LAYOUT PLAN
MELKHOUTFONTEIN
1
PLEASE NOTE:
All boundary line positions, distances and property sizes need to be verified
by a Professional Land Surveyor.
FAX: (021) 948 1588
TEL: (021) 948 1545
Website: www.udwc.co.za
URBAN DYNAMICS WESTERN CAPE INC REG. No : 95/09962/21
2nd Floor Tygervalley Chambers
Willie van Schoor Avenue
Bellville 7530
PO Box 2445
Bellville
7535
PORTION 111 OF THE FARMMELHOUTFONTEIN No. 480
DRAFT LAYOUT PLAN
FOR DISCUSSION PURPOSES ONLY
Application Area - ±17.87ha
Building Line Setback ±40m
Graves
Contours (0.5m intervals)
PHASE 1
PHASE 2
AutoCAD SHX Text
137/480
AutoCAD SHX Text
RE/63/480
AutoCAD SHX Text
1503
AutoCAD SHX Text
1459
AutoCAD SHX Text
1461
AutoCAD SHX Text
1460
AutoCAD SHX Text
1458
AutoCAD SHX Text
1492
AutoCAD SHX Text
1457
AutoCAD SHX Text
1456
AutoCAD SHX Text
1455
AutoCAD SHX Text
1453
AutoCAD SHX Text
1454
AutoCAD SHX Text
1452
AutoCAD SHX Text
128/480
AutoCAD SHX Text
1490
AutoCAD SHX Text
1491
AutoCAD SHX Text
138/480
AutoCAD SHX Text
RE/14/480
AutoCAD SHX Text
149/480
AutoCAD SHX Text
241/480
AutoCAD SHX Text
RE/15/480
AutoCAD SHX Text
RE/14/480
AutoCAD SHX Text
241/480
AutoCAD SHX Text
1504
PORTION 111 OF THE FARM MEKLHOUTFONTEIN NO. 480LOCALITY PLAN
PO Box 35982 FairwaysTheewaterskloof EstateVilliersdorp6848
Page i 000/00000/0 : Document Number Rev A : 2019-08-05
Disclaimer
This report has been prepared on behalf of and for the exclusive use of ASLA DEVCO, and is subject to
and issued in accordance with the agreement between ASLA DEVCO and iX engineers (Pty) Ltd. ASLA
DEVCO and iX engineers (Pty) Ltd accepts no liability or responsibility whatsoever for it in respect of any
use of or reliance upon this report by any third party.
Copying this report without the permission of ASLA DEVCO and iX engineers (Pty) Ltd is not permitted.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page ii 000/00000/0 : Document Number Rev A : 2019-08-05
EXECUTIVE SUMMARY
ASLA Devco appointed iX engineers for the investigation and compilation of a technical report to qualify the
extent of the upgrading required at the Melkhoutfontein Wastewater Treatment Works (WWTW), in order to
accommodate the sewage to be generated by a proposed new housing development.
The current oxidation pond system has an estimated capacity of 0.15Ml/d. A new low-cost housing
development is planned for 585 erven. The additional flow from these developments will exceed the capacity
of the existing Wastewater Treatment Works and would require upgrading of the works to ensure a treatment
capacity of + 0.45Ml/d.
The proposed upgrade of the WWTW would require an extension of the pond systems in terms of the secondary pond volume (retention) and the tertiary pond volume (retention) as well as final polishing before discharge/re-use. In addition to this, the following infrastructure and treatment processes are recommended for inclusion with the WWTW upgrade:
• Effluent disinfection utilizing a PV panel to provide the required electrical power.
• Provision of sludge drying facilities for the waste sludge periodically withdrawn from the anaerobic ponds
The estimated project cost for the extension to the existing ponds is detailed below:
Estimated Project Cost
Description Cost
Preliminary and General Cost (20 %) R 589,800.00
Extension of oxidation ponds (+ 3000m3 @R80/m3) + lining of + 5000m2 @R130/m2) R 890,000.00
Provision of a bypass from Pond 3 to Pond 7 R 25,000.00
Pipe work and site works (including dealing with water) R 100,000.00
Polishing via a reed bed system (2 279m2) R 400,000.00
Disinfection facility R 70,000.00
Sludge drying beds (480 m2 @R1 800/m2) R 864,000.00
New gravity line, holding tank and pump for irrigation R 150,000.00
Mobile sludge pump (incl pipe work) R 500,000.00
SUBTOTAL R 3,588,800.00
Contingencies (5%) R 179,440.00
Professional fees and disbursements (10%) R 358,880.00
TOTAL R 4,127,120.00
The extension of the pond system as recommended above should be sufficient to provide a final effluent that could be irrigated on a nearby field, however, this can only be confirmed upon completion of the following studies:
• Water Use License Application (18-24 maande)
• Waste Licence Application
• Geohydrological Study including hydrocensus
• Geohydrological Modelling
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
It is then anticipated that the cost associated with the aforementioned studies would be in the order of R3,000,000.00 (excl. VAT). It is understood that the Stellenbosch University may be in the process of conducting studies to investigate Aquifer Recharge within the catchment area of the Hessequa Municipality with funding being provided by the Norwegian Government. This initiative should be explored further and gauged whether the aforementioned investigation could be included within the study.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page iv 000/00000/0 : Document Number Rev A : 2019-08-05
CONTENTS
EXECUTIVE SUMMARY ................................................................................................................................. II
Table 2: Flow estimation based on the planned development ........................................................................ 4
Table 3: Current and Future Treatment Capacity Required ............................................................................ 5
Table 4: Estimated Construction Cost ...........................................................................................................10
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page v 000/00000/0 : Document Number Rev A : 2019-08-05
LIST OF FIGURES
Figure 1: Current layout of the existing Melkhoutfontein WwTW .................................................................... 2
Figure 2: Area available on site and layout of proposed new extensions ....................................................... 6
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 1 000/00000/0 : Document Number Rev A : 2019-08-05
1. BACKGROUND
ASLA Devco appointed iX engineers for the investigation and compilation of a technical report to determine
the extent of the upgrade requirements at the Melkhoutfontein Wastewater Treatment Works (WWTW), in
order to accommodate the additional sewage generated by the proposed new housing development.
Melkhoutfontein falls within the demarcated boundaries of the Hessequa Municipality in the Western Cape
and is situated 335km East of Cape Town and 35km South East of Riversdale.
During conversations with the Hessequa Municipality, it was made clear that the WWTW should also address
the following concerns.
• Effluent disinfection
• Effluent polishing and disposal
• De-sludging of anaerobic ponds, as well as providing drying facilities for the waste sludge
The ensuing report provides context regarding the existing wastewater treatment works as well as the need
and proposed means by which the existing works should be upgraded.
2. DESCRIPTION OF THE EXISTING MELKHOUTFONTEIN WWTW
2.1 CAPACITY AND FLOW VOLUMES
The WWTW has an estimated capacity of 0.15Ml/d (according to the Development Bank of Southern Africa
Status Quo Report) and consist of the following processes:
1. Inlet works with manual screen and grit channels
2. Two anaerobic ponds, 3.5m deep with an approximate volume of 588m³ and 456m³ respectively
3. One primary pond with a surface area of + 8558m²
4. A Secondary pond with a volume of + 1050m3 (depth 0.7m)
5. Three tertiary ponds with a combined volume of + 3155m3 (depth 1.1m)
6. A polishing pond with a volume of + 3987m3 (Depth 1.5m)
An aerial photo of the Melkhoutsfontein WwTW can be seen in Figure 1 below.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 2 000/00000/0 : Document Number Rev A : 2019-08-05
Figure 1: Current layout of the existing Melkhoutfontein WwTW (Oxidation Pond System)
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 3 000/00000/0 : Document Number Rev A : 2019-08-05
2.2 EFFLUENT QUALITY
Effluent quality results received (refer Appendix 1) for June 2019 indicate that the ponds currently provide
sufficient treatment of the sewage flow received. The Conductivity seems to be elevated, however this can
be attributed to the high salinity content of the boreholes supplying the town with potable water. The effluent
quality results are summarized below in Table 1 (also refer Appendix 1). There is however no information
available regarding industries that may discharge to the WWTW.
Table 1: Effluent Quality Results
Based on the Government Notice no. 36820, of 6 September 2013, the effluent quality harvested from a treatment works up to a capacity of 500m3/d that is not discharged in a water course should comply with the following limits:
• pH – not less than 6 or more than 9 pH units;
• Electrical conductivity – not exceed 200 mS/m;
• Chemical Oxygen Demand (COD) – does not exceed 400mg/l, after removal of algae;
• Feacal coliforms – do not exceed 100 000 per 100ml. A comparison with the effluent results in the table above, show consistent compliance with the Limits as listed. Since an oxidation pond process is natural, and subject to influences which are random – weather, and predominant microbiological species, etc – a pond system cannot consistently produce effluent of a precise standard. The introduction of a reed bed polishing step will however improve the quality by approximately 25% while addressing the issue of Contaminants of Emerging Concern. Pond performance is influenced by variations of seasons and climate, for example ammonia removal is usually good in summer but poor in winter. Algal blooms are typically a summertime occurrence, an impact on COD, SS and bacteria levels. Therefore, compliance with General Limit Values (GLV), according to the Government Notice no. 36820, of 6 September 2013, cannot be guaranteed.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 4 000/00000/0 : Document Number Rev A : 2019-08-05
3. NEED FOR UPGRADING OF THE EXISTING WWTW
According to a report entitled Draft Services Report for Civil Engineering Services on Portion 111 of the Farm
Melkhoutfontein No 480 for Hessequa Municipality, February 2019, a new low-cost housing development is
planned for 585 erven. The additional flow from these developments will exceed the capacity of the existing
WWTW.
Given the development that is planned, a few assumptions were made based on values found in literature
in order to obtain figures that can be used to base a design on. Table 1 show the assumptions made.
Table 2: Flow estimation based on the planned development
Planned Residential Development
Type of Dwelling Low Income
Number of units planned 585
People per dwelling 3.5
Effluent per person per day (l) 100
Total effluent per day (kl/d) 204.8
Total existing sewage flow (kl/d) 215
Total future flow (existing + new) (kl/d) 419.75
With the additional flow, the capacity of the works should increase from 0.15Ml/d to 0.42Ml/d.
The above flow figures were also confirmed using the census figures for 2016. During this assessment a
population of 2610 people was indicated. If an estimated additional population of 2047 people (585 new
erven X 3.5 persons/erf) is added, a future population of + 4647 people is calculated. At a sewage flow of
100l/p/d a total estimated future sewage flow of 465 kl/d is envisaged, which correlates with the above
figures.
Furthermore, in terms of the organic- and hydraulic loading, the following assumptions were made:
• BOD load – 0.055 kg/p/d
• 60% organic load reduction achieved in anaerobic ponds. Two separate ponds are preferred in order to
provide flexibility should maintenance be required
• Organic loading rate on the primary pond – 135 kgBOD/ha.d
• Design hydraulic retention time in secondary pond – 10 days
• Design hydraulic retention time in tertiary ponds – 15 days (retention ideally to be provided in 3 separate
ponds (5 days each), or in at least two (2) separate ponds)
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 5 000/00000/0 : Document Number Rev A : 2019-08-05
4. DESIGN CAPACITY REQUIRED
Table 3: Current and Future Treatment Capacity Required
Unit Current Estimated Capacity Future Requirement
(420 Kl/d)
Anaerobic Ponds 1 044m3 (Two ponds: 456m3 and 588m3) 577m3 per pond
Primary Pond 8 558.4m2 10 260m2
Secondary pond 1 050m3 4 197m3
Tertiary Pond 3 155m3 6 000m3
Polishing 3 987m3 3 570m2
Note: The design criteria used to determine the capacity of the individual ponds is based on empirical values,
as indicated above. Thus, although the anaerobic ponds and primary pond seem to be slightly undersized
sufficient retention is provided downstream with the proposed upgrade that this should not negatively impact
the final effluent quality.
The estimated volumes listed above was calculated using the dam depths as provided in the report; Draft
Services Report for Civil Engineering Services on Portion 111 of the Farm Melkhoutsfontein No 480 for
Hessequa Municipality.
5. UPGRADING OF THE MELKHOUTSFONTEIN WWTW
Based on the treatment requirements identified in Section 4 of this report, the design capacity of the various
components comprising the oxidation pond system can be calculated. Several factors determine the choice
of treatment technology to be adopted when considering upgrading of any wastewater treatment works. For
now, the main factors are treatment efficiency with regards to operational input and cost. Considering the
remote location and existing infrastructure or lack thereof (availability of electricity) the most viable option at
this stage is to extend the oxidation pond system to ensure sufficient treatment before final effluent discharge.
The proposed upgrade of the WWTW would require an extension of the pond systems in terms of the
secondary pond volume (retention) and the tertiary pond volume (retention) as well as final polishing before
discharge/re-use.
It is recommended that pond three (3) act a primary pond together with pond two (2), thus an increased
surface area would be available. In order to ensure sufficient secondary pond volume it is proposed to
combine ponds four (4) to six (6) into one pond. With the demolition of the dividing walls between dams four
(4) and five (5) and five (5) and six (6) it is also recommended to deepen this pond to 1.5m and to line this
pond to reduce any possibility of ground water pollution due to infiltration.
Tertiary pond capacity will then be achieved in pond seven (7). An additional pond should be constructed
downstream of pond seven (7) in order to provided additional tertiary capacity.
Finally, it is proposed to provide final polishing via a reed bed, with retention of 1 day. It is anticipated that
the reed bed polishing step will improve the quality of final effluent by approximately 25%.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 6 000/00000/0 : Document Number Rev A : 2019-08-05
Below is the proposed layout including the extensions as recommended.
Figure 2: Area available on site and layout of proposed new extensions (refer Appendix 2 for an A3
version of this layout)
Apart from increasing the oxidation ponds during the upgrading of the works, there are several other aspects
of the existing works that also require attention and should be addressed during the upgrade. The following
infrastructure and treatment processes are also recommended.
• Effluent disinfection utilizing a PV panel to provide the required electrical power.
• Provision of sludge drying facilities for the waste sludge periodically withdrawn from the anaerobic ponds
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 7 000/00000/0 : Document Number Rev A : 2019-08-05
6. EFFLUENT DISCHARGE OPTIONS
As part of the project brief, iX engineers were requested to investigate effluent disposal options. The existing
works do not have a formal effluent disposal mechanism in place and with the anticipated increase in flow
stemming from the proposed development a solution must be found which would address the disposal of
effluent in an environmentally responsible manner.
Several options were discussed with the Hessequa Municipality and various stakeholders and these options
include:
• Irrigation of final effluent on land allocated for such an activity
• Aquifer Recharge
• Discharge to the Goukou River
These options are discussed in further detail below.
6.1 OPTION 1: IRRIGATION OF FINAL EFFLUENT
This option would entail the irrigation of land adjacent to the existing WWTW site. At the time of the report,
an area suitable for such an activity have not been identified by relevant stakeholders. However, the land
adjacent to the WWTW appear to be suitable for such an activity, pending agreement and commitment from
the landowners. It is estimated that an area of approximately 28ha would be required for irrigation of luserne,
which could be used as feed for livestock.
The proposed area is identified in Appendix 3 and based on the information obtained from the Title Deeds
Office, the properties impacted are owned by the Hessequa Municipality. Engagement with the Municipality
would therefore be required. The area, however, may impact on the existing aquifer which is classified as a
Major Aquifer that is considered Most Vulnerable and has a Very High Susceptibility. Refer to Annexure 4
for aquifer location and details.
Should the proposed area not be aligned with current borehole location and abstraction the location for
irrigation may have to be revised. Refer to Appendix 3 for location of the existing boreholes in relation to the
area proposed for irrigation.
It is envisaged that this option would entail the following studies and investigations to confirm that the aquifer
is not negatively impacted by the irrigation activity:
• Water Use License Application (18-24 months)
• Geohydrological Study and Modelling
Based on feedback from GHT Consulting Scientists and Groundwater Africa as well as similar studies
conducted within the Atlantis area the cost associated with the geohydrological investigation is anticipated
to be in the order of R3,000,000.00 (excl. VAT). This would include the construction of specialist boreholes
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 8 000/00000/0 : Document Number Rev A : 2019-08-05
to accommodate inflow as well as monitoring boreholes to determine aquifer properties. In addition, recharge
studies to determine max influx into the aquifer to prevent forming wetlands forms part of the study.
It is understood that the Stellenbosch University may be in the process of conducting studies to investigate
Aquifer Recharge within the catchment area of the Hessequa Municipality with funding being provided by
the Norwegian Government. This initiative should be explored further and gauged whether the
aforementioned investigation could be included within the study.
6.2 OPTION 2: AQUIFER RECHARGE
This option would entail the disposal of final effluent through Aquifer recharge.
• Water Use License Application (18-24 maande)
• Waste Licence Application
• Geohydrological Study including hydrocensus
• Geohydrological Modelling
The same activities associated with Option 1 will apply to Option 2, but since this option entails direct
recharge, the impact on the aquifer may be considered as an increased risk and may require more stringent
effluent quality requirements. If it is found that the water quality stemming from the WwTW for aquifer
recharge is not of an acceptable level the oxidation pond process configuration may have to be replaced by
an Activated Sludge Plant. The cost associated with such a plant is detailed below in Table 4.
Table 4: Project Cost for 0.45Ml/d Activated Sludge WWTW
Description Civil Cost Mechanical Cost
Inlet works R 600,000.00 R 200,000.00
Biological reactor R 1,330,000.00 R 650,000.00
Waste from aerobic basin R - R 100,000.00
Secondary settling tank – 16 m diameter R 500,000.00 R 300,000.00
Chlorine contact channel R 500,000.00 R 120,000.00
Chlorine installation to SANS 10298:2005 standards R 350,000.00 R 280,000.00
Mixed liquor recycle pumps (duty/standby) R - R 250,000.00
RAS pumps (duty/standby) R - R 260,000.00
Sludge drying beds R 800,000.00 R 50,000.00
Control building R 520,000.00 R -
Irrigation pumps (duty/standby) R - R 150,000.00
Automation, scada and security camaras R - R 600,000.00
Electrical installation R - R 750,000.00
Subtotal 1 R 4,600,000.00 R 3,710,000.00
Total Construction (Subtotal 2) R 8,310,000.00
25 % Preliminary and General R 2,077,500.00
10 % Contingencies R 1,038,750.00
Subtotal 3 R 11,426,250.00
Professional Fees R 1,142,625.00
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 9 000/00000/0 : Document Number Rev A : 2019-08-05
Geotechnical investigation R 100,000.00
Disbursements R 300,000.00
Optional Supervision R 600,000.00
TOTAL (Excluding VAT) R 13,568,875.00
VAT R 2,035,331.25
TOTAL (Including VAT) R 15,604,206.25
6.3 OPTION 3: DISCHARGE TO THE GOUKOU RIVER
This option would entail the construction of a pump station and pipeline to discharge to the Goukou River.
The Goukou River in located within the Goukou Estuary. It must be noted that the Goukou Estuary forms
part of the Stilbaai Marine Protected Area (MPA), which includes the area between Noordkapperspunt
(34°23’.964 S, 21°24’.800 E) and Rietvleivywers (34°21’.676 S, 21°30’.976 E), out to approximately 4.2 km
offshore, and includes the estuary of the Goukou River to a point 15 km upstream of the shore. Refer to
Appendix 5 for details of the extent of the Stilbaai MPA.
As per the National Environmental Management: Integrated Coastal Management Act (No. 24 of 2008)
(ICMA) (as amended), the Department of Environmental Affairs (DEA) has the responsibility for regulating
land-derived effluent discharges into coastal waters. In terms of Section 69 of ICMA, no person is permitted
to discharge effluent originating from a source on land into coastal waters except in terms of a GDA or a
Coastal Waters Discharge Permit (CWDP). Discharge into the MPA would not be authorized, however should
the discharge point be located outside of the boundaries of the MPA, an estuarine discharge of this nature
will require the following studies and investigations:
• Water Use License Application (18-24 months)
• Environmental Basic Assessment Process (9-12 months)
• Freshwater Impact Assessment
• Possibly Botanical Impact Assessment Study
• Estuarine Impact Assessment
• Dispersion Modelling
• Coastal Waste Discharge Permit
It is anticipated that the cost associate with the studies will be in the order of R500,000.00 (excl. VAT). In
addition, the construction of approximately 10km of pipeline as well as a pump station would be required in
order to discharge upstream of the Stilbaai MPA and it is anticipated that the construction cost would be in
excess of R5,000,000.00. Based on the complexity of the studies, the lengthy approval process and
associated risk as well as the anticipated cost this option is not considered a viable option for effluent
discharge.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 10 000/00000/0 : Document Number Rev A : 2019-08-05
7. COST ESTIMATE
The cost of construction for the extension to the existing ponds, as well as providing the additional
infrastructure as discussed, is tabled below.
Table 5: Estimated Project Cost
Description Cost
Preliminary and General Cost (20 %) R 589,800.00
Extension of oxidation ponds (+ 3000m3 @R80/m3) + lining of + 5000m2 @R130/m2) R 890,000.00
Provision of a bypass from Pond 3 to Pond 7 R 25,000.00
Pipe work and site works (including dealing with water) R 100,000.00
Polishing via a reed bed system (2 279m2) R 400,000.00
Disinfection facility R 70,000.00
Sludge drying beds (480 m2 @R1 800/m2) R 864,000.00
New gravity line, holding tank and pump for irrigation R 150,000.00
Mobile sludge pump (incl pipe work) R 500,000.00
SUBTOTAL R 3,588,800.00
Contingencies (5%) R 179,440.00
Professional fees and disbursements (10%) R 358,880.00
TOTAL R 4,127,120.00
8. CONCLUSION
Despite the good effluent quality data, it is envisaged that the existing works will not have sufficient capacity
to receive and treat the future estimated wastewater flow. Therefore, given the planned new housing
development, the works will have to be upgraded to provide sufficient treatment capacity for the forecasted
increase in flow rate stemming from the new development.
The extension of the pond system as recommended above should be sufficient to provide a final effluent that
could be irrigated on nearby land for luserne production should this option of re-use be adopted. The size
of the ponds, reed bed and sludge drying beds will not exceed the land area that is currently available at the
site of the existing works.
A number of effluent discharge strategies were discussed under Section 6 and Options 1 and 2 are
considered the most feasible. However, both options would require extensive studies and investigations to
be completed as mentioned. It is envisaged that the same studies will have to be conducted regardless of
which option is preferred, and it is recommended that the following studies proceed in order to determine the
way forward:
• Water Use License Application (18-24 maande)
• Waste Licence Application
• Geohydrological Study including hydrocensus
• Geohydrological Modelling
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) Page 11 000/00000/0 : Document Number Rev A : 2019-08-05
It is then anticipated that the cost associated with the aforementioned studies would be in the order of
R3,000,000.00 (excl. VAT).
The recommendation of retaining the existing oxidation pond system and only extend to ensure sufficient
treatment capacity is attractive regarding the low operational and maintenance requirements it will have.
Thus, the Municipality will not have to train new process controllers or start using external service providers
for major mechanical and electrical works. This approach, however, can only be confirmed once the studies
above have been completed.
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) 000/00000/0 : Document Number Rev A : 2019-08-05
APPENDIX 1 - LABORATORY RESULTS
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) 000/00000/0 : Document Number Rev A : 2019-08-05
APPENDIX 2 - LAYOUT OF PROPOSED EXTENSIONS
X 3799400
E
X
I
S
T
I
N
G
G
R
A
V
E
L
R
O
A
D
E
X
I
S
T
I
N
G
G
R
A
V
E
L
R
O
A
D
5
5
5
5
5
3
5
3
5
3
5
3
5
3
5
3
5
1
5
1
51
5
7
5
5
5
5
55
51
5
1
5
1
5
3
5
3
5
3
5
3
5
3
5
5
57
5
3
55
5
2
5
2
5
2
5
2
5
2
5
4
5
4
5
4
5
4
5
4
5
6
5
6
5
6
5
2
5
2
5
4
5
4
5
4
58
5
7
WATER LEVEL=53.30
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
NEW SLIDING GATE
6
7
8
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
5
5
.0
0
0
5
5
.0
0
0
5
5
.0
0
0
5
5
.0
0
0
A
N
A
E
R
O
B
IC
D
A
M
W
L
=
5
4
.1
9
0
F
L
O
O
R
=
5
1
.2
0
0
E
X
IS
T
IN
G
A
N
A
E
R
O
B
IC
D
A
M
O
U
T
L
E
T
N
E
W
IN
L
E
T
R
E
F
E
R
T
O
D
W
G
H
E
S
R
IV
-4
5
6
-S
0
6
E
X
IS
TIN
G
IN
LE
T
TO
B
E
D
E
M
O
LIS
H
E
D
E
X
IS
T
IN
G
P
U
M
P
L
IN
E
T
O
B
E
R
E
R
O
U
T
E
D
N
E
W
1
1
0
m
m
D
IA
C
L
A
S
S
9
S
E
W
E
R
R
IS
IN
G
M
A
IN
N
E
W
IN
L
E
T
S
T
R
U
C
T
U
R
E
R
E
F
E
R
D
O
D
R
A
W
H
E
S
R
IV
-4
5
6
/S
0
6
55.00
53.60
1.40
1
55.68
54.68
1.00
2
N
E
W
IN
L
E
T
R
E
F
E
R
T
O
D
W
G
H
E
S
R
IV
-4
5
6
-S
0
6
N
E
W
IN
L
E
T
R
E
F
E
R
T
O
D
W
G
H
E
S
R
IV
-4
5
6
-S
0
6
7
3
N
E
W
2
0
0
m
m
D
I
A
C
L
A
S
S
3
4
S
E
W
E
R
G
R
A
V
I
T
Y
M
A
I
N
N
E
W
1
6
0
m
m
D
I
A
C
L
A
S
S
3
4
S
E
W
E
R
G
R
A
V
I
T
Y
M
A
I
N
EXISTING PRIMARY DAM
EXISTING
SECONDARY DAM
EXISTING
TERTIARY DAM
54.42
53.41
1.10
4
54.28
53.14
1.14
5
54.19
53.03
1.16
6
54.27
53.20
1.07
54.09
53.09
1.00
8
54.05
52.91
1.14
9
3
7
.4
6
1
:1
9
7
.1
6
55.84
54.84
1.00
54.19
1:200.70
2
2
.
0
5
1
:
2
0
0
.
4
5
1
:
2
0
0
3
1
.9
6
1
:1
9
9
.7
5
3
.4
8
1
:1
7
4
1
0
.
6
0
1
:
2
0
0
.
7
0
3
4
.
4
1
1
:
1
9
1
.
1
6
515.47m²
V= ±456m³
1
4
0
0
0
7
0
0
0
2
2
2
0
0
2
9
2
0
0
647.9m²
V= ±588m³
SIDE SLOPES 1:2
DEPTH = 3.5m
5
3
0
0
04
2
0
0
0
1
2
6
0
.
0
0
m
²
V
=
±
2
0
0
0
m
³
N
E
W
R
E
E
D
B
E
D
1478.9m²
DEPTH = 0.7m
V= ±1050m³
NEW GATE
2
2
2
6
.
0
0
m
²
V
=
±
0
0
0
m
³
4
2
0
0
0
3
0
0
0
0
8
0
0
0
F
I
N
A
L
E
F
F
L
U
E
N
T
N
E
W
T
E
R
T
I
A
R
Y
P
O
N
D
1
.
5
m
D
E
E
P
1
2
3
4
5
6
7
8558.38m²
V= ±000m³
9
3
2
.
0
m
²
D
E
P
T
H
=
1
.
1
m
V
=
±
1
0
2
5
m
³
9
6
8
.
3
m
²
D
E
P
T
H
=
1
.
1
m
V
=
±
1
0
6
5
m
³
9
6
7
.
9
m
²
D
E
P
T
H
=
1
.
1
m
V
=
±
1
0
6
5
m
³
2658.9m²
DEPTH = 1.5m
V= ±3987m³
TO ACT AS TERTIARY POND
TO BE CONVERTED TO 1 OFF
SECONDARY POND 1.5m DEEP LINED
CHLORINATION
N
E
W
B
Y
P
A
S
S
1
0
0
0
0
8000
3
2
0
0
0
8
0
0
0
8000
8000
1
5
0
0
0
N
E
W
S
L
U
D
G
E
D
R
Y
IN
G
B
E
D
S
8
9
EXISTING
TERTIARY DAM
EXISTING
TERTIARY DAM
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) 000/00000/0 : Document Number Rev A : 2019-08-05
APPENDIX 3 – AREA PROPOSED FOR FINAL EFFLUENT IRRIGATION
RE/57/480
66/480
71/480
RE/73/480
92/480 93/480
146/480
149/480
150/480
RE/14
/480
12/480
13/480
133/480
156/480
157/480
158/480
170/480
172/480
174/480
175/480
177/480
179/480
180/480182/480184/480
185/480
187/4
80189/480
190/480
191/480
192/480
194/480195/480
197/480
199/480200/480
202/480
204/480205/480
207/480
209/480210/480
212/480213/480
214/480215/480
218/480
220/480
221/480
223/480
225/480
226/480
228/480
230/480
232/480
233/480
RE/102/480
147/480
138/4
80
137/4
80
RE/56/480
81/480
9/480
69/480
94/480
103/480
151/48
0
152/4
80
171/480
173/480176/480
178/480181/480183/480
186/4
80188/480193/480
196/480
198/480
201/480 203/480
206/480
208/480
211/480
219/480
222/480
224/480
227/480
229/480231/480
142/480
107/480
111/480
159/480
161/480162/480
163/480164/480160/480
134/480
166/480167/480 216/480
217/480
165/480
168/480169/480
140/480
135/480
48/480
RE/630
245/480 249/480
251/4
8025
2/480
253/4
8025
4/480
RE/102/480
141/480
95/480
129/480
148/480
241/4
801/635
RE/635
25/472
33/472
101/4
80RE/154/480
28/47
2
2/472
118/4
80
518
RE/15
/480
RE/65/480
RE/65/480
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
MELKHOUTSFONTEINTECHNICAL REPORT
PROJECT
SIGNATURE PR No DATE
SIGNATURE DATE
CONSULTING ENGINEER
CLIENT
PRELIMINARYiX engineers retains the copyright in all intellectual property, inluding
designs and/or documents prepared in terms of this appointment for theproject covered by the appointment. The client may use the designs and/ordocuments for the sole purpose of their intended use on this project only
subject to payment for the design having been received. Use for any otherpurpose, whether or not the design and/or documents have been paid for
constitutes an infringement of copyright, and all rights are reserved.
All dimensions must be verified on site before the works commence.Refer any discrepancies to the Engineer. Copyright reserved
No DATE DESCRIPTIONREVISION SCHEDULE CLIENT
CONSULTANT
ASLA DEVCO
PLAN DESCRIPTION
OWNERSHIPINFORMATION
PROJECT PRODUCED CHECKED
DATE SCALE
PLAN NUMBER REV 00
2019/08/05
31 Allen Drive | Loevenstein | Bellville | Cape Town I 7530 I RSATel: +27 (0)21 912 3000 | Website: www.ixengineers.co.za
GPS: -33.884179, 18.613853
¹
05/08/2019 14:49:20 Printed by: reinhardt.b
Path:
G:\0
6_Pr
ojects
\3014
59\01
_mxd
s\Own
ership
.mxd
-
Geo
graph
ic Co
ordina
te Sy
stem:
GCS
Hart
ebee
sthoe
k 199
4
1:20,000
Melkhoutfontein-1
Melkhoutfontein-2
LegendBoreholes
Irrigation AreaFarm RE/154/480ErvenFarm Portions
OWNER: HESSEQUA MUN
POND SITE
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) 000/00000/0 : Document Number Rev A : 2019-08-05
APPENDIX 4 – AQUIFER MAP
ASLA DEVCO UPGRADING OF THE MELKHOUTFONTEIN WASTEWATER TREATMENT WORKS
s:\tanya pillay\melkhout - 5 aug\melkhoutfontein report rev 4.docx (tanya pillay) 000/00000/0 : Document Number Rev A : 2019-08-05