Helmholtz Centre for Ion Research G. Moritz, Cryogenic Expert meeting, GSI, September 19/20 2007 (courtesy of D. Krämer for the FAIR Design Team) Current Status of the FAIR Project
Jan 16, 2016
Helmholtz Centre for Ion Research
G. Moritz, Cryogenic Expert meeting, GSI, September 19/20 2007
(courtesy of D. Krämer for the FAIR Design Team)
Current Status of the FAIR Project
The Pillars of the FAIR Complex
Antiprotonproduction
100 TmSynchotron
scSIS100
Collector & CoolerRing
AccumulatorRing
Deceleration
Rare isotopeProduction &separator sc
HighEnergy
Storage Ring
HESR&
PANDAnc or sc
NewExperimentalStorage Ring
CompressedBarionicMatter
experiment
NESR
300 TmStretcher
Ringsc
SIS300
From existing GSIUNILAC & SIS18& new proton linac
+ Experiments:E-I colliderNuclear PhysicsAtomic PhysicsPlasma PhysicsApplied Physics
sc
Technical Realization of FAIR
100 m
UNILAC
SIS 18
SIS 100/300
HESR
SuperFRS
NESR
CR
RESR
FLAIR
Radioactive Ion Production Target
Anti-Proton Production Target
Existing facility: provides ion-beam source and injector for FAIR
Existing facility: provides ion-beam source and injector for FAIR
New future facility: provides ion and anti-matterbeams of highest-intensity and up to high energies
New future facility: provides ion and anti-matterbeams of highest-intensity and up to high energies
The International Committee Structure(for XFEL & FAIR)
PAC QCD
PAC NUSTAR
PAC APPA
TAC
Observes:
FCIFull Cost Issues
AFI Working GroupAdministrative + Funding Issues
LFILegal Framework Issus
STI Working GroupScientific + Technical Issues
ISCInternational Steering Committee
Delegates from partner states
CORECost Review Groups
Reviews• Cryogenics• Warm magnets •Cold magnets• Power Supplies• Beam Instrumentation• p-Linac
Austria China Finland France Germany Greece India Italy Poland Spain Sweden Russia Great Britain Romania
• Baseline Technical Report - accelerator TR's - experiment proposals - civil construction plans (~ 3500 pages)
• PAC & TAC Review Reports
• Cost Book
• Cost Review Reports - accelerator & civil construction (CORE-A) - experiments (CORE-E)
• Convention
• Articles of Association
• By-Laws
• Final Act Document
• Legal Framework Report (LFI)
• Full Cost Structure Report (FCI)
FAIR Project
2000 2002 2004 2006
Wor
ksho
ps /
Whi
te P
aper
s: e
xplo
ratio
n of
sci
ence
opp
ortu
nitie
s
Wis
sens
chaf
tsra
t-E
valu
atio
n
BM
BF
Pre
ss
Rel
ease
CD
R S
ubm
issi
on
Preparation of CDR700 scientists
WR – ESAC – ETAC – EMAC -- EAC
Inte
rnat
iona
l S
teer
ing
Com
mitt
ee
ISC STI PAC's / TAC / miniTACs
CORE-A / CORE-E
AFI (LFI / FCI )
Inte
rnat
iona
l M
oU
Accelerator R & D
coordinated by GSI
Proto-Collaborations
international community
Civil Construction Planning / Regulatory Processes / UVS
Preparation of FBTR 2400 scientists
FB
TR
S
ubm
issi
on
Project Costs
Accelerator investment costs 533 M€Civil construction costs 289 M€Baseline experimental facilities( incl Super-FRS ) 180 M€Investment budget 1002 M€Manpower (2400 person-years) 185 M€
Total Construction Costs 1187 M€
Commissioning Costs 28 M€Operation Costs up to 2025 1485 M€Sum 2700 M€
Germany committed part of funding
25% of funds have to come from non-
German partners
Scrutinized by CORE, TAC, STI …
FAIR Work Packages94 WPs defined, following WBS, FBTR and Cost Book schematics
13 subprojects
15 te
chni
cal s
yste
ms
interest to take WP indicated
in-kind
Recent decision by German Minister Ms. Schavan:
Start of the International FAIR Project
on November 7, 2007
together with all partners that have expressed their commitment on FAIR.
• Stage A: ? ; Stage B: SIS 300 and 300 Tm beamline
• 11/2007: official end of R&D-phase
• project money acc. costbook, no R&D money
SIS100/300 Design Parameters
First Stage: Second Stage:
Acceleration + Acceleration +
Compression Stretching
Reference Ions U28+
p
U28+
U92+
Magnet. rigidity 100 Tm 300 Tm
Circumference 1083 m 1083 m
Number of Particles
5 · 1011
5 · 1013
3 · 1011 /s
1 · 1010 /s
Energy 2.7 GeV/u
29 GeV
2.7 GeV/u
34 GeV/u
Beam time structure
25 – 90ns
50 ns
d.c.
slow ext.
Dipole flux density
2 T 4.5 T
Ramp Rate 4 T/s 1 T/s
SIS300SIS100
SIS300SIS100
Straight mark I full scale dipole magnetunder fabrication at BNG / WürzburgCurved mark I full scale dipole magnetunder fabrication at BINP / NovosibirskR&D continued at JINP / Dubna incl.Quadrupole prototype
Progress in SIS Magnet R&D
GSI001, first 4 T prototype by BNL6 T protoype under construction at DubnaCurved 4.5 T dipole magnetunder fabrication at INFN
BINP Novosibirsk
SIS 100 Dipole under Construction
Layout of Super-FRS
Bmax =20 Tm
SuperferricMultiplet
SuperferricMultiplet
3 x 9.75° Dipole Unit
MF2
MF1
SuperferricMultipleton-going magnet
activities: • conceptual design multiplett (Toshiba)• superferric dipole (China)• radiation resistant magnets (BINP)
The assembly of die First lamination punched
IMP LanzhouIPP HefeiIEE Beijing
CAS
Super-FRS Dipole Prototype Development in China
Coil fabrication Magnet design
High Energy Storage Ring
• Momentum: 1.5 – 15 GeV/c• Straights: Cooler and target section • Ring circumference: 573 m.
for antiprotons
Estimated Total Manpower for constructionas scrutinized and approved by CORE-A and STI in 2005/2006
Scientists Engineers TechniciansSystems Design 9 7 1 8 17 136
Interface Accelerator - Civil Construction 2 2 0 6 4 24Interface Accelerator - Experiments 4 2 0 6 6 36
Civil Construction 3 11 4 5 18 90
p-Linac 4 5 3 4 12 48SIS100/SIS300 10 6 0 5 16 80HEBT/Super-FRS 4 4 0 4 8 32Storage Rings 7 6 0 4 13 52
Magnets 9 9 6 6 24 144Power Supplies 5 9 8 5 22 110rf-systems 7 9 7 5 23 115Inj-/Extraction 3 7 6 5 16 80Beam-Diagnosis Systems 4 6 5 6 15 90Vacuum System 4 6 5 5 15 75Beam Cooling 5 6 5 5 16 80Cryo-System 4 9 5 6 18 108Control system 11 13 10 6 34 204
Magnet Testing 4 9 17 5 30 150Installations 2 6 16 6 24 144Commissioning 10 10 8 5 28 140
SUM 111 142 106 107 359 1938
Manpower Duration [years]
total Man Yearstotal FTE
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10
Zeitlicher Personalbedarf SIS100 (Summe 126 FTE)
Reihe17
Reihe16
Reihe15
Reihe14
Reihe13
Reihe12
Reihe11
Reihe10
Reihe9
Reihe8
Reihe7
Reihe6
Reihe5
Reihe4
Reihe3
Reihe2
Reihe1
0
5
10
15
20
25
30
35
40
45
50
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Zeitlicher Personalbedarf CR (121 FTE)
Control System
Cryo System
Beam Cooling
Vacuum System
Beam Diagnostics
Inj./ Extraction
RF-Systems
Power Converters
Magnets
Postproduction
Commissioning/ Beam
System Test
Mounting
Fabrication
Inquiry
Specifi cation
-
specification QA, construction
SIS 100
CR
Manpower Verteilung
0
50
100
150
200
250
300
350
400
450
500
2007 2008 2009 2010 2011 2012 2013 2014 2015
Jahr
An
zah
l
Re-directed
Beschleuniger
FAIR&FCC
ZT/WTI
Management
Man Power Resources(dominantly provided by GSI)
1950 man-years during 8 years required on site incl. 205 m-y for controls
FAIR Div.
Acc. Div.