Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer To: HDA-IN Ms. Heather Kennedy Deputy Commissioner Capital Program Management 100 North Senate Avenue Indianapolis, IN 46204 Dear Ms. Kennedy: We have completed our review of INDOT’s Amendment #20-01 to the FY 2020-2024 Indiana Statewide Transportation Improvement Program (STIP) dated July 25, 2019. INDOT has re- demonstrated fiscal constraint, air quality conformity, where applicable, and provided opportunity for public comment and involvement on Amendment #20-01. FHWA considers this amendment to be in substantial compliance with the applicable requirements as sufficient to support a consistency finding for inclusion into the STIP. Should you have any questions regarding this approval please contact Joyce Newland at 317- 226-5353 or e-mail at [email protected]. Sincerely, For: Mayela Sosa Division Administrator Enclosure cc: Michael McNeil, INDOT
67

HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

Aug 06, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer To: HDA-IN Ms. Heather Kennedy Deputy Commissioner Capital Program Management 100 North Senate Avenue Indianapolis, IN 46204 Dear Ms. Kennedy: We have completed our review of INDOT’s Amendment #20-01 to the FY 2020-2024 Indiana Statewide Transportation Improvement Program (STIP) dated July 25, 2019. INDOT has re-demonstrated fiscal constraint, air quality conformity, where applicable, and provided opportunity for public comment and involvement on Amendment #20-01. FHWA considers this amendment to be in substantial compliance with the applicable requirements as sufficient to support a consistency finding for inclusion into the STIP. Should you have any questions regarding this approval please contact Joyce Newland at 317-226-5353 or e-mail at [email protected].

Sincerely,

For: Mayela Sosa Division Administrator

Enclosure cc: Michael McNeil, INDOT

Page 2: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

www.in.gov/dot/ An Equal Opportunity Employer

100 North Senate Avenue Room N955 Indianapolis, Indiana 46204

PHONE: (317) 232-0223 FAX: (317) 232-1499 Eric Holcomb, Governor

Joe McGuinness, Commissioner

July 25, 2019 Ms. Mayela Sosa, Division Administrator FHWA Indiana Division 575 North Pennsylvania Street, Room 254 Indianapolis, Indiana 46204 Dear Ms. Sosa: The Indiana Department of Transportation requests the projects listed in STIP Amendment 20-01 to be incorporated into the 2020-2024 Statewide Transportation Improvement Program (STIP). The required Metropolitan Planning Organization (MPO) Transportation Improvement Program (TIP) documents have been included in this request and duly noted in the Amendment. We have determined that the proposed amendments are: 1) consistent with the transportation plan; 2) the TIP remains fiscally constrained in that federal funding resources are sufficient to support the new or modified projects; and 3) conform to state and national air quality standards. At the time USDOT approved the FY 2020-2024 STIP, INDOT had a balance of $258,808,206 in funds for “Cost yet to be identified from future needs for FY 2020.” The grand total of this amendment is $54,030,694. The new balance is $204,777,512. A draft of this amendment was posted on INDOT’s STIP website http://www.in.gov/indot/STIP for comments. No comments were given about any project listed. We request your review and approval of the subject amendment. Should you have any questions pertaining to this amendment, please contact Michael McNeil, STIP Specialist at (317) 232-0223 or at [email protected]. Sincerely,

Roy Nunnally, Director Asset Planning & Management Division

Page 3: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Adams County

Adams County IR 1005 Bike/Pedestrian

Facilities

Adams Co BP: from the

Wabash River to CR 850 S

Fort Wayne .32 STBG Local Funds CN $0.00 $461,823.00 $461,823.00 A 01 $3,107,855.0035191 /

1173218

Local

Transportation

Alternatives

CN $2,646,032.00 $0.00 $2,646,032.00

Comments:Add CN to STIP for CN FY 2020. No MPO

Indiana Department

of Transportation

US 27 Concrete Pavement

Restoration (CPR)

From 0.11 Miles North of US 33

(Borum Run Bridge) to 2.53

Miles North of US 224 North Jct

Fort Wayne 4.44 NHPP Road

Construction

CN $1,396,989.60 $349,247.40 $1,746,237.00 A 01 $1,848,237.0040486 /

1900624

Road Consulting PE $81,600.00 $20,400.00 $102,000.00

Comments:NO MPO. DES 1900624 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Adams County Total

Federal: $4,124,621.60 Match :$831,470.40 2020: $3,209,855.00 2021: 2022: $1,746,237.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 1 of 64 Report Created:7/25/2019 7:07:56AM

Page 4: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Benton County

Indiana Department

of Transportation

SR 55 Road Rehabilitation (3

R/4R Standards)

From 0.59 mi N of US 52 N jct to

US 24

Crawfordsville 8.992 STPBG Road ROW RW $450,400.00 $112,600.00 $563,000.00 A 01 $12,203,984.3040578 /

1700117

Comments:RW phase for $563,000 FY20, No MPO.

Indiana Department

of Transportation

SR 352 Br Repl, Comp.Cont.Pr

es.Conc. I-Beam

01.61 E US 41at Mud Pine

Creek

Crawfordsville 0 STBG Bridge ROW RW $31,200.00 $7,800.00 $39,000.00 A 01 $4,679,906.0040579 /

1601083

Comments:ROW phase for $39,000 FY20 No MPO.

Benton County Total

Federal: $481,600.00 Match :$120,400.00 2020: $602,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 2 of 64 Report Created:7/25/2019 7:07:56AM

Page 5: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Blackford County

Montpelier ST 1001 Sign Modernization (S

eries Of Units)

Sign replacement in the City of

Montpelier

Fort Wayne 14.2 Safety Local Funds CN $0.00 $22,380.00 $22,380.00 A 01 $257,000.0041149 /

1702855

Local Safety

Program

PE $29,790.00 $0.00 $29,790.00

Local Funds PE $0.00 $3,310.00 $3,310.00

Local Safety

Program

CN $201,420.00 $0.00 $201,420.00

Comments:Add new Project to STIP for PE

Indiana Department

of Transportation

SR 3 Bridge Deck Overlay Bridge over LITTLE LICK CREEK

, 00.67 South of SR 26.

Fort Wayne 0 STBG Bridge

Construction

CN $616,909.60 $154,227.40 $771,137.00 A 01 $856,137.0042468 /

1901488

Bridge Consulting PE $68,000.00 $17,000.00 $85,000.00

Comments:NO MPO. DES 1901488 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Blackford County Total

Federal: $916,119.60 Match :$196,917.40 2020: $118,100.00 2021: 2022: $994,937.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 3 of 64 Report Created:7/25/2019 7:07:56AM

Page 6: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Boone County

Indiana Department

of Transportation

SR 75 Bridge Replacement,

Other Construction

Bridge over Wells Ditch, 2.15 mi

N of I-74

Crawfordsville 0 STPBG Bridge ROW RW $8,000.00 $2,000.00 $10,000.00 A 01 $1,203,846.0038767 /

1400219

Comments:ROW Phase for $10,000 FY20, No MPO

Boone County IR 1033 Bridge Replacement On CR 500W, approximately

750' South of Middle

Jamestown Road

Crawfordsville .18 STPBG Local Funds CN $0.00 $204,412.50 $204,412.50A 01 $1,073,340.0040874 /

1800246

Local Bridge

Program

RW $58,400.00 $0.00 $58,400.00

Local Funds RW $0.00 $14,600.00 $14,600.00

Local Bridge

Program

CN $817,650.00 $0.00 $817,650.00

Comments:No MPO please add RW funds to FY 20 in the amount of 58,400 federal and 14,600 local. please add CN funds to FY 21 in the amount 817,650 federal and 204,412.50 local

Boone County Total

Federal: $884,050.00 Match :$221,012.50 2020: $83,000.00 2021: $1,022,062.50 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 4 of 64 Report Created:7/25/2019 7:07:56AM

Page 7: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Carroll County

Indiana Department

of Transportation

US 421 Bridge Replacement,

Steel

Over Wildcat Creek, 4.06mi N

of SR 26

LaPorte 0 NHPP Bridge Consulting PE $1,296,085.60 $324,021.40 $1,620,107.00 A 01 $4,977,139.0040607 /

1700101

Comments:Please amend FY20 PE phase into the STIP. No MPO.

Carroll County Total

Federal: $1,296,085.60 Match :$324,021.40 2020: $1,620,107.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 5 of 64 Report Created:7/25/2019 7:07:56AM

Page 8: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Cass County

Indiana Department

of Transportation

SR 218 Bridge Replacement,

Other Construction

Over Government Ditch, 2.00

mi W of US 31

LaPorte 0 STBG Bridge ROW RW $40,000.00 $10,000.00 $50,000.00 A 01 $663,173.0038755 /

1500087

Comments:Please amend RW phase into the STIP. No MPO.

Cass County Total

Federal: $40,000.00 Match :$10,000.00 2020: $50,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 6 of 64 Report Created:7/25/2019 7:07:56AM

Page 9: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Clay County

Indiana Department

of Transportation

SR 59 Bridge Deck

Replacement

over Connelley Ditch; 02.11 mi

N of SR 246

Crawfordsville 0 STBG Bridge

Construction

CN $2,418,316.80 $604,579.20 $3,022,896.00A 01 $3,382,896.0039762 /

1800504

Bridge Consulting PE $72,040.00 $18,010.00 $90,050.00

Comments:PE phase for $90,050 FY20

Indiana Department

of Transportation

SR 42 Small Structure Pipe

Lining

0.69 mi E of SR 59 Crawfordsville 0 STBG Bridge ROW RW $40,000.00 $10,000.00 $50,000.00 A 01 $694,344.0040537 /

1500118

Comments:RW phase for $50,000 FY20, No MPO

Indiana Department

of Transportation

I 70 Bridge Maintenance

And Repair

WB over Honey Creek, Priv Rd,

04.86 mi W of SR 59

Crawfordsville 0 NHPP Bridge Consulting PE $46,800.00 $5,200.00 $52,000.00 A 01 $659,363.0042090 /

1900768

Bridge

Construction

CN $546,626.70 $60,736.30 $607,363.00

Comments:PE phase for $52,000 FY20

Clay County Total

Federal: $3,123,783.50 Match :$698,525.50 2020: $192,050.00 2021: $3,630,259.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 7 of 64 Report Created:7/25/2019 7:07:56AM

Page 10: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Clinton County

Indiana Department

of Transportation

SR 28 Pavement

Replacement

From 1.64 mi W of SR 39 to SR

39 (Jackson St)

Crawfordsville 1.632 STBG Road ROW RW $628,000.00 $157,000.00 $785,000.00 A 01 $14,829,779.0038221 /

1005600

Comments:RW phase for $785,000 FY20, No MPO

Indiana Department

of Transportation

US 52 Small Structure

Replacement

1.12 mi E of SR 28 S Jct Crawfordsville 0 STPBG Bridge ROW RW $16,000.00 $4,000.00 $20,000.00 A 01 $2,484,762.0039956 /

1600874

Comments:RW phase for $20,000 FY20, No MPO

Indiana Department

of Transportation

SR 75 Small Structure

Replacement

0.80 mi S of SR 26 Crawfordsville 0 STPBG Bridge ROW RW $60,000.00 $15,000.00 $75,000.00 A 01 $887,979.0040536 /

1500107

Comments:RW phase for $75,000 FY20, No MPO

Indiana Department

of Transportation

SR 38 HMA Overlay Minor

Structural

From 0.31 mi W of US 421 E Jct

to 0.52 mi E of US 421 E Jct

Crawfordsville .835 STPBG Road Consulting PE $112,569.76 $28,142.44 $140,712.20 A 01 $971,773.2041609 /

1800271

Comments:PE phase for $140,712.20 FY20, No MPO

Clinton County Total

Federal: $816,569.76 Match :$204,142.44 2020: $1,020,712.20 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 8 of 64 Report Created:7/25/2019 7:07:56AM

Page 11: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Crawford County

Indiana Department

of Transportation

SR 66 Bridge Deck Overlay Over Branch Brandywine Fork,

01.32 mi W SR-64

Vincennes 0 STPBG Bridge Consulting PE $141,520.00 $35,380.00 $176,900.00 A 01 $922,112.0041125 /

1800951

Comments:Amend 2020-2024 STIP. Adding FY20 PE $176,900.00. No MPO.

Crawford County Total

Federal: $141,520.00 Match :$35,380.00 2020: $176,900.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 9 of 64 Report Created:7/25/2019 7:07:56AM

Page 12: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Daviess County

Indiana Department

of Transportation

US 231 Bridge Thin Deck

Overlay

Over First Creek, 01.52 mi S SR

-558

Vincennes 0 NHPP Bridge

Construction

CN $2,600,000.00 $650,000.00 $3,250,000.00 A 01 $3,697,500.0042143 /

1900784

Bridge Consulting PE $358,000.00 $89,500.00 $447,500.00

Comments:Amend 2020-2024 STIP. Adding FY20 PE $447,500.00, FY22 CN $3,250,000.00. No MPO.

Daviess County Total

Federal: $2,958,000.00 Match :$739,500.00 2020: $447,500.00 2021: 2022: $3,250,000.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 10 of 64 Report Created:7/25/2019 7:07:56AM

Page 13: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Dekalb County

Indiana Department

of Transportation

SR 101 HMA Overlay,

Preventive

Maintenance

From 2.60 Miles North of 37 (All

en/Dekalb CL) to SR 8

Fort Wayne 5.976 STPBG Toll Lease

Amendment

Proceeds

RW $80,000.00 $20,000.00 $100,000.00 A 01 $5,922,281.0041083 /

1800545

Comments:NO MPO. DES 1601022 adding RW to FY 2020 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 8 HMA Overlay,

Preventive

Maintenance

From I-69 to 3.12 Miles East of I

-69 (CR 35) (Auburn).

Fort Wayne 3.03 STPBG Road

Construction

CN $2,651,978.40 $662,994.60 $3,314,973.00 A 01 $3,850,599.0042152 /

1900623

Road Consulting PE $428,500.80 $107,125.20 $535,626.00

Comments:NO MPO. DES 1900623 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 327 HMA Overlay,

Structural

From US 6 to SR 4. Fort Wayne 6.17 STPBG Road

Construction

CN $7,631,989.60 $1,907,997.40 $9,539,987.00 A 01 $10,682,227.0042373 /

1601023

Toll Lease

Amendment

Proceeds

PE $793,792.00 $198,448.00 $992,240.00

Toll Lease

Amendment

Proceeds

CN $120,000.00 $30,000.00 $150,000.00

Comments:NO MPO. DES 1601023, and 1800144 adding PE to FY 2020 and CN to FY 2023

Indiana Department

of Transportation

I 69 Bridge Replacement,

Other Construction

Bridge carrying CR27, 1.74

Miles South of SR 6.

Fort Wayne 2 NHPP Bridge

Construction

CN $3,326,487.30 $369,609.70 $60,000.00 $3,636,097.00 A 01 $4,236,097.0042374 /

1900058

Bridge Consulting PE $486,000.00 $54,000.00 $540,000.00

Comments:NO MPO. DES 1900058

Indiana Department

of Transportation

SR 1 Box Culvert

Replacement

Over Wade Ditch, 3.4 miles

north of the Allen/ DeKalb

County Line

Fort Wayne .2 STPBG Bridge

Construction

CN $1,232,168.80 $308,042.20 $40,000.00 $1,500,211.00 A 01 $2,015,211.0042377 /

1900068

Bridge Consulting PE $328,000.00 $82,000.00 $410,000.00

Bridge ROW RW $52,000.00 $13,000.00 $65,000.00

Comments:NO MPO. DES 1900075

Indiana Department

of Transportation

US 6 Replace

Superstructure

Bridge over Matson Ditch, 1.19

miles Eof SR 427

Fort Wayne 0 NHPP Bridge

Construction

CN $749,468.80 $187,367.20 $936,836.00 A 01 $1,332,436.0042392 /

1701393

Bridge ROW RW $4,000.00 $1,000.00 $5,000.00

Comments:NO MPO. DES 1701393

Dekalb County Total

Federal: $17,884,385.70 Match :$3,941,584.30 2020: $2,582,866.00 2021: 2022: $4,416,809.00 2023: $150,000.00 2024: $14,676,295.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 11 of 64 Report Created:7/25/2019 7:07:56AM

Page 14: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Elkhart County

Goshen US 33 Auxiliary Lanes from Fairfield to Plymouth Ave Fort Wayne .26 STBG Local Funds PE $0.00 $41,260.00 $41,260.00 A 01 $1,031,450.0041587 /

1801613

Local Funds CN $0.00 $165,040.00 $165,040.00

Elkhart-Goshen

MPO

PE $165,040.00 $0.00 $165,040.00

Elkhart-Goshen

MPO

CN $660,160.00 $0.00 $660,160.00

Comments:Add project to STIP for PE

Goshen ST 1029 Auxiliary Lanes, Two-

way Left Turn Lanes

College Ave from US 33 to NS

Railroad Line (East Entrance of

parking lot)

Fort Wayne .84 STBG Local Funds PE $0.00 $75,000.00 $75,000.00 A 01 $5,107,000.0042000 /

1900739

Local Funds RW $0.00 $171,400.00 $96,400.00 $75,000.00

Elkhart-Goshen

MPO

PE $300,000.00 $0.00 $300,000.00

Elkhart-Goshen

MPO

RW $685,600.00 $0.00 $385,600.00 $300,000.00

Comments:Add project to STIP for PE

Elkhart County Total

Federal: $1,810,800.00 Match :$452,700.00 2020: $581,300.00 2021: $825,200.00 2022: $482,000.00 2023: $375,000.00 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 12 of 64 Report Created:7/25/2019 7:07:56AM

Page 15: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Fountain County

Indiana Department

of Transportation

US 136 Br Repl, Comp.Cont.Pr

es.Conc. I-Beam

Bridge over East Fork Coal

Creek, 1.97 mi W of SR 25

Crawfordsville 0 STPBG Bridge ROW RW $24,000.00 $6,000.00 $30,000.00 A 01 $3,013,043.0039957 /

1601095

Comments:RW Phase for $30,000 FY20, No MPO

Indiana Department

of Transportation

US 136 HMA Overlay Minor

Structural

From 1.53 mi W of US 41 N Jct

to US 41 W Jct

Crawfordsville 1.52 STPBG Road Consulting PE $267,953.04 $66,988.26 $334,941.30 A 01 $3,956,354.3041614 /

1800192

Comments:PE phase for $334,941 FY20, No MPO

Fountain County Total

Federal: $291,953.04 Match :$72,988.26 2020: $364,941.30 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 13 of 64 Report Created:7/25/2019 7:07:56AM

Page 16: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Franklin County

Indiana Department

of Transportation

US 52 HMA Overlay,

Preventive

Maintenance

0.7 miles E of SR 252 (Blue

Creek Rd) to E Jct of SR 1

Seymour 4.51 STPBG District Other

ROW

RW $20,000.00 $5,000.00 $25,000.00A 01 $1,911,928.0041868 /

1900690

District Other

Construction

CN $460,000.00 $115,000.00 $575,000.00

Road

Construction

CN $889,542.40 $222,385.60 $1,111,928.00

Road Consulting PE $160,000.00 $40,000.00 $200,000.00

Comments:Amend to the current STIP. No MPO.

Franklin County Total

Federal: $1,529,542.40 Match :$382,385.60 2020: $200,000.00 2021: $25,000.00 2022: $1,686,928.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 14 of 64 Report Created:7/25/2019 7:07:56AM

Page 17: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Fulton County

Indiana Department

of Transportation

SR 114 HMA Overlay,

Preventive

Maintenance

From SR 14 to SR 15 Fort Wayne 7.747 STBG Road

Construction

CN $1,512,966.40 $378,241.60 $1,891,208.00A 01 $2,091,208.0039890 /

1800541

Comments:NO MPO. Des. 1800541, Adding CN to FY 2021 into FY 2020 - 2024 STIP.

Fulton County Total

Federal: $1,512,966.40 Match :$378,241.60 2020: 2021: $1,891,208.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 15 of 64 Report Created:7/25/2019 7:07:56AM

Page 18: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Gibson County

Indiana Department

of Transportation

SR 64 Pavement

Replacement

From 1.79 mi W of I-69 to 1.33

mi W of I-69 (Francisco)

Vincennes .54 STPBG Bridge

Construction

CN $0.00 $0.00 A 01 $6,430,807.0039768 /

1593061

Bridge ROW RW $16,000.00 $4,000.00 $20,000.00

Road

Construction

CN $1,080,000.00 $270,000.00 $1,350,000.00

Road ROW RW $385,600.00 $96,400.00 $482,000.00

Comments:Amend 2020-2024 STIP. Adding FY20 RW Bridge $20,000.00, FY20 RW Road $482,000.00, FY20 CN Road $1,350,000.00. No MPO.

Indiana Department

of Transportation

SR 64 HMA Overlay,

Preventive

Maintenance

2.45 mi W I-69 (ECL of

Francisco) to SR-57

Vincennes 3.95 STPBG Road

Construction

CN $1,201,600.00 $300,400.00 $1,502,000.00 A 01 $1,682,240.0042121 /

1900560

Road Consulting PE $144,192.00 $36,048.00 $180,240.00

Comments:Amend 2020-2024 STIP. Adding FY20 PE $180,240.00, FY22 CN $1,502,000.00. No MPO.

Indiana Department

of Transportation

I 69 Retaining Wall Repair

or Replacement

Over CR-550 South, NB and SB

1.85 miles N of SR-168

Vincennes 0 NHPP Bridge

Construction

CN $98,640.00 $10,960.00 $109,600.00 A 01 $338,300.0042402 /

1901746

Bridge Consulting PE $72,000.00 $8,000.00 $80,000.00

Gainsharing CN $133,830.00 $14,870.00 $148,700.00

Comments:Amend 2020-2024 STIP. Adding FY20 PE $80,000.00, FY20 CN 148,700.00, FY20 CN $109,600.00. No MPO.

Gibson County Total

Federal: $3,131,862.00 Match :$740,678.00 2020: $2,370,540.00 2021: 2022: $1,502,000.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 16 of 64 Report Created:7/25/2019 7:07:56AM

Page 19: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Grant County

Indiana Department

of Transportation

SR 26 HMA Overlay Minor

Structural

From SR 13 to I-69 Greenfield 14.508 STBG Bridge Consulting PE $124,380.80 $31,095.20 $155,476.00 A 01 $11,706,687.0040496 /

1700031

Road Consulting PE $306,915.20 $76,728.80 $383,644.00

Comments:Added PE Phase

Sweetser ST 1019 Bike/Pedestrian

Facilities

SR 18 sidewalks: from Main St

to Allen Dr & Main St: SR 18 to

Peterson Dr

Fort Wayne .504 TA Local Funds PE $0.00 $10,860.00 $10,860.00 A 01 $323,000.0041152 /

1702856

Local Funds CN $0.00 $53,780.00 $53,780.00

Local

Transportation

Alternatives

PE $43,440.00 $0.00 $43,440.00

Local

Transportation

Alternatives

CN $215,120.00 $0.00 $215,120.00

Comments:Add new Project to STIP. All Phases and costs: No MPO

Grant County IR 1021 Bridge Rehabilitation

Or Repair

Bridge No. 254 on

Pennsylvania St over the

Mississinewa River

Fort Wayne .25 STBG Local Funds CN $0.00 $414,920.00 $414,920.00A 01 $2,075,000.0041951 /

1802916

Local Bridge

Program

CN $1,659,680.00 $0.00 $1,659,680.00

Comments:Add new Project to STIP. No MPO

Indiana Department

of Transportation

US 35 Bridge Replacement,

Other Construction

0.09 Miles East of SR 15, Over

The Mississinewa River

Fort Wayne .1 NHPP Bridge

Construction

CN $5,555,762.40 $1,388,940.60 $30,000.00 $6,914,703.00 A 01 $7,999,703.0042363 /

1900047

Bridge Consulting PE $796,000.00 $199,000.00 $995,000.00

Bridge ROW RW $48,000.00 $12,000.00 $60,000.00

Comments:NO MPO. DES 1900048

Indiana Department

of Transportation

I 69 Bridge Deck Overlay NB Bridge over MISSISSINEWA

RIVER, 01.78 South of US 35.

Fort Wayne 0 NHPP Bridge

Construction

CN $3,023,298.90 $335,922.10 $3,359,221.00 A 01 $3,669,221.0042466 /

1901490

Bridge Consulting PE $279,000.00 $31,000.00 $310,000.00

Comments:NO MPO. DES 1901490 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

I 69 Bridge Deck Overlay SB Bridge over MISSISSINEWA

RIVER, 01.78 South of US 35.

Fort Wayne 0 NHPP Bridge

Construction

CN $3,023,298.90 $335,922.10 $3,359,221.00 A 01 $3,614,221.0042466 /

1901491

Bridge Consulting PE $229,500.00 $25,500.00 $255,000.00

Comments:NO MPO. DES 1901491 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Grant County Total

Federal: $15,304,396.20 Match :$2,915,668.80 2020: $2,153,420.00 2021: $2,343,500.00 2022: $6,808,442.00 2023: 2024: $6,914,703.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 17 of 64 Report Created:7/25/2019 7:07:56AM

Page 20: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Hamilton County

Indiana Department

of Transportation

SR 47 Road Reconstruction

(3R/4R Standards)

From the Boone/Hamilton Co

Line to SR 38

Greenfield 1.622 STBG Road Consulting PE $19,280.00 $4,820.00 $24,100.00 A 01 $8,657,300.0039288 /

1601982

Comments:Adding PE Phase

Indiana Department

of Transportation

US 31 New Bridge, Other New Bridge over US 31 at 226t

h Street

Greenfield 0 NHPP Mobility Consulting PE $544,000.00 $136,000.00 $680,000.00 A 01 $7,480,000.0042397 /

1900096

Mobility

Construction

CN $5,440,000.00 $1,360,000.00 $6,800,000.00

Comments:IMPO, PE in 2020 for $680,000 and CN in 2023 for $6,800,000.

Hamilton County Total

Federal: $6,003,280.00 Match :$1,500,820.00 2020: $704,100.00 2021: 2022: 2023: $6,800,000.00 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 18 of 64 Report Created:7/25/2019 7:07:56AM

Page 21: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Hancock County

Indiana Department

of Transportation

SR 234 Small Structure

Replacement

, 5.191 MI E SR 9 Greenfield 0 STBG Bridge Consulting PE $120,000.00 $30,000.00 $150,000.00 A 01 $390,000.0042268 /

1900201

Bridge

Construction

CN $180,000.00 $45,000.00 $225,000.00

Bridge ROW RW $12,000.00 $3,000.00 $15,000.00

Comments:New Project

Hancock County Total

Federal: $312,000.00 Match :$78,000.00 2020: $150,000.00 2021: 2022: $15,000.00 2023: 2024: $225,000.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 19 of 64 Report Created:7/25/2019 7:07:56AM

Page 22: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Hendricks County

Indiana Department

of Transportation

SR 75 Slide Correction on SR 75, 1.20 miles south of

SR 234

Crawfordsville 0 STPBG Road Consulting PE $81,538.80 $20,384.70 $101,923.50 A 01 $439,791.5041619 /

1801720

Comments:PE phase for $101,923.50, No MPO

Indiana Department

of Transportation

SR 39 ADA Sidewalk Ramp

Construction

From 1.70 mi N of US 40 to 2.73

mi N of US 40 (Clayton)

Crawfordsville 1.04 Safety Safety

Construction

CN $332,800.00 $83,200.00 $416,000.00 A 01 $416,000.0041932 /

1900487

Comments:CN phase for $416,000 FY20 via IMPO TIP Amend 20-00

Indiana Department

of Transportation

I 70 Erosion Control 1.08 mi W of SR 267, over

White Lick Creek EB & WB

Crawfordsville 0 NHPP Mobility ROW RW $22,500.00 $2,500.00 $25,000.00 A 01 $3,771,434.0042172 /

1600396

Bridge

Construction

CN $3,371,790.60 $374,643.40 $25,000.00 $3,721,434.00

Comments:CN phase for $3,746,434 FY20

Hendricks County Total

Federal: $3,808,629.40 Match :$480,728.10 2020: $567,923.50 2021: $3,721,434.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 20 of 64 Report Created:7/25/2019 7:07:56AM

Page 23: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Henry County

Indiana Department

of Transportation

US 40 Bridge Replacement,

Other Construction

Over Big Blue River, 0.36 mi E

of SR 140

Greenfield 0 STBG Bridge Consulting PE $286,634.40 $71,658.60 $358,293.00 A 01 $18,824,728.0039294 /

1701338

Road Consulting PE $372,342.40 $93,085.60 $465,428.00

Comments:Added PE Phase

Indiana Department

of Transportation

SR 38 Bridge Replacement,

Concrete

Over Big Blue River, .16 miles

W. of SR 3

Greenfield .01 STBG Bridge Consulting PE $309,360.00 $77,340.00 $386,700.00 A 01 $1,909,874.0040502 /

1593238

Comments:Added PE Phase

Indiana Department

of Transportation

SR 103 HMA Overlay,

Preventive

Maintenance

from 2.21 miles S. of SR 38(SC

L New Castle) to SR 38

Greenfield 2.213 STBG Road Consulting PE $146,640.00 $36,660.00 $183,300.00 A 01 $1,109,281.0041096 /

1800744

Comments:Added PE Phase

Henry County IR 1001 Signing Various Roads in Henry County Greenfield 223 Safety Local Funds PE $0.00 $4,120.00 $4,120.00 A 01 $751,200.0041304 /

1702758

Local Safety

Program

PE $37,080.00 $0.00 $37,080.00

Comments:No MPO - Add PE FY 20 Federal 37,080 and Local 4,120.

Indiana Department

of Transportation

SR 103 HMA Overlay,

Preventive

Maintenance

3.08 mi S of SR 38 (CR 300 S)

to 2.21 mi S of SR 38 (SCL

New Castle)

Greenfield .86 STBG Road

Construction

CN $324,000.00 $81,000.00 $405,000.00 A 01 $405,000.0042259 /

1901504

Comments:Added CN

Indiana Department

of Transportation

US 36 Small Structure Pipe

Lining

9.73 miles E of MADISON/HEN

RY Line

Greenfield 0 STBG Bridge

Construction

CN $101,600.00 $25,400.00 $127,000.00 A 01 $292,000.0042265 /

1702918

Bridge Consulting PE $120,000.00 $30,000.00 $150,000.00

Bridge ROW RW $12,000.00 $3,000.00 $15,000.00

Comments:New Project

Indiana Department

of Transportation

SR 103 Replace

Superstructure

SR over I-70 EB/WB, 03.16 N

US 40

Greenfield 0 STBG Bridge

Construction

CN $1,672,800.00 $418,200.00 $2,091,000.00 A 01 $2,526,000.0042266 /

1900124

Bridge Consulting PE $320,000.00 $80,000.00 $400,000.00

Bridge ROW RW $28,000.00 $7,000.00 $35,000.00

Comments:New Project

Henry County Total

Federal: $3,730,456.80 Match :$927,464.20 2020: $1,984,921.00 2021: $15,000.00 2022: $440,000.00 2023: 2024: $2,218,000.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 21 of 64 Report Created:7/25/2019 7:07:56AM

Page 24: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Howard County

Indiana Department

of Transportation

US 31 Bridge Maintenance

And Repair

US 31 -NB @ Wildcat Creek -19

01366

Greenfield 0 NHPP District Other

Construction

CN $580,735.20 $145,183.80 $725,919.00A 01 $725,919.0042059 /

1901366

Comments:Added CN

Indiana Department

of Transportation

SR 931 Bridge Thin Deck

Overlay

over US 31 SB/NB, 00.48 S SR

931-(1901523 L)

Greenfield 0 NHPP Bridge

Construction

CN $690,400.00 $172,600.00 $863,000.00 A 01 $863,000.0042208 /

1901523

Comments:Added CN

Howard County Total

Federal: $1,271,135.20 Match :$317,783.80 2020: 2021: $725,919.00 2022: $863,000.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 22 of 64 Report Created:7/25/2019 7:07:56AM

Page 25: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Huntington County

Indiana Department

of Transportation

I 69 HMA Overlay,

Preventive

Maintenance

From 5.64 Miles North of SR 18

to 0.37 Miles South of SR 5.

Fort Wayne 7.77 NHPP Road

Construction

CN $5,502,849.30 $611,427.70 $6,114,277.00 A 01 $7,111,585.001900618

Road Consulting PE $897,577.20 $99,730.80 $997,308.00

Comments:NO MPO. DES 1900618 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 124 Small Structure

Replacement

Carries UNT Salamonie River,

0.38 Miles East of SR 9

Fort Wayne .18 STPBG Bridge

Construction

CN $2,754,518.40 $688,629.60 $90,000.00 $3,353,148.00 A 01 $4,228,148.0042385 /

1900242

Bridge Consulting PE $528,000.00 $132,000.00 $660,000.00

Bridge ROW RW $100,000.00 $25,000.00 $125,000.00

Comments:NO MPO. DES 1900084, 1900238, 1900241, 1900242 adding PE to FY 2020, ROW to FY22 and CN to FY 2022 into FY 2020 - 2024 STIP.

Huntington County Total

Federal: $9,782,944.90 Match :$1,556,788.10 2020: $1,657,308.00 2021: 2022: $6,329,277.00 2023: 2024: $3,353,148.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 23 of 64 Report Created:7/25/2019 7:07:56AM

Page 26: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Jackson County

Jackson County IR 1001 Replace

Superstructure

Bridge #154 on CR 300 S over

Rider Ditch

Seymour .02 STPBG Local Funds PE $0.00 $48,922.60 $48,922.60 A 01 $1,238,613.0040895 /

1703020

Local Bridge

Program

PE $195,690.40 $0.00 $195,690.40

Comments:Amending FY 2020 PE funds in the total amount of $244,613. No MPO

Jackson County Total

Federal: $195,690.40 Match :$48,922.60 2020: $244,613.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 24 of 64 Report Created:7/25/2019 7:07:56AM

Page 27: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Jay County

Portland MS 7 ADA Sidewalk Ramp

Construction

Local-State Road 67 / Votaw

Street in Portland, Indiana -170

2762

Greenfield .617 TA Local Funds PE $0.00 $12,228.00 $12,228.00 A 01 $722,695.0041308 /

1702762

Local

Transportation

Alternatives

PE $48,912.00 $0.00 $48,912.00

Comments:NO MPO - Add PE FY 20 Federal 48,912 and Local 12,228.

Dunkirk MS 5301 Bike/Pedestrian

Facilities

Multi-use path in the Dunkirk

City Park Along Speedcat Alley

Greenfield .284 TA Local Funds PE $0.00 $14,000.00 $14,000.00 A 01 $300,000.0042075 /

1802925

Local

Transportation

Alternatives

PE $56,000.00 $0.00 $56,000.00

Comments:No MPO - Add PE FY 20 Federal 56,000 and Local 14,000

Indiana Department

of Transportation

SR 67 Bridge Thin Deck

Overlay

Bridge over LIMBERLOST

CREEK, 02.37 North of US 27.

Fort Wayne 0 STPBG Bridge

Construction

CN $257,617.60 $64,404.40 $322,022.00 A 01 $372,022.0042156 /

1901489

Bridge Consulting PE $40,000.00 $10,000.00 $50,000.00

Comments:NO MPO. DES 1901489 adding PE to FY 2020, and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 67 Bridge Deck Overlay over NORFOLK SOUTHERN RR,

00.63 S SR 1

Greenfield 0 STBG Bridge

Construction

CN $520,000.00 $130,000.00 $650,000.00 A 01 $650,000.0042207 /

1901542

Comments:Added CN

Jay County Total

Federal: $922,529.60 Match :$230,632.40 2020: $181,140.00 2021: 2022: $972,022.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 25 of 64 Report Created:7/25/2019 7:07:56AM

Page 28: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Jefferson County

Indiana Department

of Transportation

SR 250 Bridge Deck Overlay 0.05 mile E of SR 62 over

Wilson Fork Creek

Seymour 0 STPBG Bridge Consulting PE $105,120.00 $26,280.00 $131,400.00 A 01 $644,871.0040994 /

1600307

Bridge

Construction

CN $410,776.80 $102,694.20 $513,471.00

Comments:Amend to the current STIP. No MPO.

Jefferson County Total

Federal: $515,896.80 Match :$128,974.20 2020: $131,400.00 2021: $513,471.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 26 of 64 Report Created:7/25/2019 7:07:56AM

Page 29: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Knox County

Indiana Department

of Transportation

US 50 Bridge Thin Deck

Overlay

Bridge over Wabash River and

ILL 33 WBL, 01.85 mile W of US

41

Vincennes 0 NHPP Bridge

Construction

CN $160,000.00 $40,000.00 $200,000.00 A 01 $230,000.001901942

Bridge Consulting PE $24,000.00 $6,000.00 $30,000.00

Comments:No MPO- Amend 20-24 STIP for this project for FY 2020 PE and FY 2022 CN.

Indiana Department

of Transportation

US 50 Bridge Thin Deck

Overlay

Bridge over Wabash River and

ILL 33 WBL, 01.85 mile W of US

41

Vincennes 0 NHPP Bridge

Construction

CN $160,000.00 $40,000.00 $200,000.00 A 01 $230,000.001901943

Bridge Consulting PE $24,000.00 $6,000.00 $30,000.00

Comments:New Des Number for US Thin Deck Overlay. CN $200,000 FY 21 PE $30,000 FY20

Indiana Department

of Transportation

US 50 Bridge Painting Bridge over Wabash River and

ILL 33 WBL, 01.85 mile W of US

41

Vincennes 0 NHPP Bridge

Construction

CN $1,520,000.00 $380,000.00 $1,900,000.00 A 01 $1,995,000.001901987

Bridge Consulting PE $76,000.00 $19,000.00 $95,000.00

Comments:New Des US 50 PE $95K FY 21 CN $1.9M FY 23 Painting

Indiana Department

of Transportation

US 50 Bridge Painting Bridge over Wabash River and

ILL 33 EBL, 01.85 mile W of US

41

Vincennes 0 NHPP Bridge

Construction

CN $1,520,000.00 $380,000.00 $1,900,000.00 A 01 $1,995,000.001901988

Bridge Consulting PE $76,000.00 $19,000.00 $95,000.00

Comments:No MPO

Indiana Department

of Transportation

US 50 HMA Overlay,

Preventive

Maintenance

From Illinois State Line to W Jct

US 41

Vincennes 1.63 NHPP Road

Construction

CN $4,412,800.00 $1,103,200.00 $5,516,000.00 A 01 $6,178,000.0042136 /

1900567

Road Consulting PE $529,600.00 $132,400.00 $662,000.00

Comments:Amend 2020-2024 STIP. Adding FY20 PE $662,000.00, FY22 CN $5,516,000.00. No MPO.

Knox County Total

Federal: $8,502,400.00 Match :$2,125,600.00 2020: $722,000.00 2021: $190,000.00 2022: $5,916,000.00 2023: $3,800,000.00 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 27 of 64 Report Created:7/25/2019 7:07:56AM

Page 30: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Kosciusko County

Indiana Department

of Transportation

SR 14 Small Structure

Replacement

Carrying Joseph Metzger Ditch,

4.00 miles E of SR 15

Fort Wayne 0 STBG Bridge

Construction

CN $613,502.40 $153,375.60 $758,878.00 $8,000.00A 01 $1,202,363.0040476 /

1701383

Bridge ROW RW $54,000.00 $13,500.00 $15,000.00 $52,500.00

Comments:MACOG MPO Initial TIP 2020-2024 for DES 1701383 & 1383626. Adding RW to 2020 for $67,500 and CN to 2021 for $766,878.

Kosciusko County Total

Federal: $667,502.40 Match :$166,875.60 2020: $15,000.00 2021: $60,500.00 2022: $758,878.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 28 of 64 Report Created:7/25/2019 7:07:56AM

Page 31: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

LaGrange County

Lagrange ST 1010 Pavement

Replacement

Hawpatch St: from S Townline

Road to W Central Avenue

Fort Wayne .663 STBG Group IV Program PE $523,728.00 $0.00 $523,728.00 A 01 $4,240,000.0041148 /

1702844

Local Funds PE $0.00 $130,932.00 $130,932.00

Comments:add new project to STIP for PE. NO-MPO

Indiana Department

of Transportation

US 20 Box Culvert

Replacement

4.07 Miles East of SR 9, Carries

East Fly Creek

Fort Wayne 1.02 NHPP Bridge

Construction

CN $707,390.40 $176,847.60 $884,238.00 A 01 $1,179,238.0042371 /

1900076

Toll Lease

Amendment

Proceeds

PE $188,000.00 $47,000.00 $235,000.00

Toll Lease

Amendment

Proceeds

RW $32,000.00 $8,000.00 $40,000.00

Toll Lease

Amendment

Proceeds

CN $16,000.00 $4,000.00 $20,000.00

Comments:NO MPO. DES 1900076 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

LaGrange County Total

Federal: $1,467,118.40 Match :$366,779.60 2020: $889,660.00 2021: 2022: $60,000.00 2023: 2024: $884,238.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 29 of 64 Report Created:7/25/2019 7:07:56AM

Page 32: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Lake County

Indiana Department

of Transportation

US 41 Traffic Signals, New

Or Modernized

101st Place at US 41, 0.95mi N

of US 231

LaPorte 0 NHPP District Other

Construction

CN $104,000.00 $26,000.00 $130,000.00 A 01 $150,000.001901898

District Other

Consulting

PE $16,000.00 $4,000.00 $20,000.00

Comments:Please amend all phases into the STIP. NIRPC amendment 19-22.

Gary ST 1047 Road Reconstruction

(3R/4R Standards)

Industrial Highway Phase III.

Cline Ave to EJ&E RR Bridge

LaPorte 1.32 STBG Local Funds RW $0.00 -$40,000.00 ($40,000.00) A 01 $3,292,600.0040733 /

1600418

Northwest Indiana

MPO

RW -$160,000.00 $0.00 ($160,000.00)

Comments:MPO Funds June 2019 NIRPC amendment Removing RW funds and adding in CN funds for FY20

Gary US 20 Enhancement Complete Streets

Enhancements

LaPorte .05 STPBG Northwest Indiana

MPO

CN $2,060,000.00 $0.00 $2,060,000.00A 01 $2,775,544.0041770 /

1801738

Local Funds CN $0.00 $515,000.00 $515,000.00

Comments:NIRPC amendment #22 adding CN phase FY21 MPO funds 80/20

Lowell ST 2375 Bike/Pedestrian

Facilities

State Road 2 from Harding

Street west to 920 feet west

of Willow Street

LaPorte .86 STPBG Local Funds PE $0.00 $147,082.10 $147,082.10 A 01 $2,902,298.8042064 /

1802924

Local

Transportation

Alternatives

PE $588,328.40 $0.00 $588,328.40

Comments:19-15 Amendment April 21 New project adding PE funds for FY20 Local transportation funds 80/20

Lake County Total

Federal: $2,608,328.40 Match :$652,082.10 2020: $685,410.50 2021: $2,575,000.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 30 of 64 Report Created:7/25/2019 7:07:56AM

Page 33: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Madison County

Indiana Department

of Transportation

SR 28 Pavement

Replacement

from WCL of Elwood to SR 37 Greenfield 2.78 STBG Road

Construction

CN $6,178,380.00 $1,544,595.00 $7,722,975.00 A 01 $8,422,975.0042307 /

1900254

Road Consulting PE $560,000.00 $140,000.00 $700,000.00

Comments:New Project MCCOG Resolution

Madison County Total

Federal: $6,738,380.00 Match :$1,684,595.00 2020: $700,000.00 2021: 2022: 2023: 2024: $7,722,975.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 31 of 64 Report Created:7/25/2019 7:07:56AM

Page 34: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Marion County

Indiana Department

of Transportation

US 36 Added Travel Lanes From 3 miles west of I-465 to 1.

65 miles west of I-465.

Greenfield 1.403 NHPP Mobility Consulting PE $1,577,600.00 $394,400.00 $1,972,000.00 A 01 $32,394,813.0041781 /

1800035

Comments:Adding PE Phase. IMPO 20-00

Marion County Total

Federal: $1,577,600.00 Match :$394,400.00 2020: $1,972,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 32 of 64 Report Created:7/25/2019 7:07:56AM

Page 35: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Marshall County

Indiana Department

of Transportation

US 31 New Interchange

Construction

At SR 10 LaPorte 0 NHPP Safety

Construction

CN $23,580,536.00 $5,895,134.00 $500,000.00 $28,975,670.00 A 01 $32,975,670.0041777 /

1802051

Safety Consulting PE $2,400,000.00 $600,000.00 $3,000,000.00

Safety ROW RW $400,000.00 $100,000.00 $500,000.00

Comments:Please amend all phases into the current STIP. MACOG approval Resolution 27-19 uploaded.

Marshall County Total

Federal: $26,380,536.00 Match :$6,595,134.00 2020: $3,000,000.00 2021: 2022: $1,000,000.00 2023: $28,975,670.00 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 33 of 64 Report Created:7/25/2019 7:07:56AM

Page 36: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Miami County

Indiana Department

of Transportation

SR 16 Pavement

Replacement

2.90 miles E of US 31 to 3.71

miles E of US 31 (Denver Small

Towns)

Fort Wayne .045 STBG Road ROW RW $80,000.00 $20,000.00 $100,000.00 A 01 $4,361,891.001600294

Road

Construction

CN $2,946,272.80 $736,568.20 $3,682,841.00

Comments:NO MPO. DES 1600294 adding ROW to FY 2020 into FY 2020 - 2024 STIP.

Miami County IR 1005 Replace

Superstructure

Bridge #501 on Wayne Street

over Wabash River

Fort Wayne .14 STBG Local Funds CN $0.00 $737,500.00 $737,500.00A 01 $3,687,500.0041950 /

1802959

Local Bridge

Program

CN $2,950,000.00 $0.00 $2,950,000.00

Comments:Add new project to STIP. No MPO

Indiana Department

of Transportation

SR 19 HMA Overlay Minor

Structural

From SR 18 to 1.39 Miles South

of SR 124 (South Limit Peru, CR

150)

Fort Wayne 13.938 STPBG Road

Construction

CN $5,751,008.80 $1,437,752.20 $7,188,761.00 A 01 $7,907,641.0042364 /

1601006

Road Consulting PE $575,104.00 $143,776.00 $718,880.00

Comments:NO MPO. DES 1601006 adding PE to FY 2020 and CN to FY 2024 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

US 24 Small Structure

Replacement

2.53 Miles East of SR 19,

Carries UNT of Schrock Creek

Fort Wayne .2 NHPP Bridge

Construction

CN $4,156,868.80 $1,039,217.20 $70,000.00 $5,126,086.00 A 01 $6,203,586.0042367 /

1900079

Bridge Consulting PE $706,000.00 $176,500.00 $882,500.00

Bridge ROW RW $100,000.00 $25,000.00 $125,000.00

Comments:NO MPO. DES 1900079, 1900087, 1900086, 1900234 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

US 24 Small Structure

Replacement

2.83 Miles East of US 31,

Carries UNT of Prairie Creek

Fort Wayne .2 NHPP Bridge

Construction

CN $1,948,635.20 $487,158.80 $45,000.00 $2,390,794.00 A 01 $3,090,794.0042368 /

1900078

Bridge Consulting PE $304,000.00 $76,000.00 $380,000.00

Bridge ROW RW $64,000.00 $16,000.00 $80,000.00

Comments:NO MPO. DES 1900077, 1900078, 1900230 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 16 Small Structure

Replacement

Carries UNT of Eel River, 3.36

Miles East of SR 19, North

Junction.

Fort Wayne .1 STPBG Bridge

Construction

CN $318,995.20 $79,748.80 $20,000.00 $378,744.00 A 01 $588,744.0042369 /

1800016

Bridge Consulting PE $128,000.00 $32,000.00 $160,000.00

Bridge ROW RW $24,000.00 $6,000.00 $30,000.00

Comments:NO MPO. DES 1800016 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Miami County Total

Federal: $20,052,884.80 Match :$5,013,221.20 2020: $2,241,380.00 2021: $7,370,341.00 2022: $370,000.00 2023: 2024: $15,084,385.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 34 of 64 Report Created:7/25/2019 7:07:56AM

Page 37: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Montgomery County

Indiana Department

of Transportation

SR 59 Br Repl, Pipe Arch Bridge over Little Raccoon

Creek, 1.02 mi S of SR 47

Crawfordsville 0 STPBG Bridge ROW RW $40,000.00 $10,000.00 $50,000.00 A 01 $1,965,304.0039958 /

1601080

Comments:RW phase for $50,000 FY20, No MPO

Indiana Department

of Transportation

SR 32 Bridge Replacement,

Other Construction

over Mill Creek; 3.70 mi W of

SR 47

Crawfordsville 0 STPBG Bridge Consulting PE $184,806.96 $46,201.74 $231,008.70 A 01 $6,091,306.7041590 /

1800075

Comments:PE phase for $231,008.70 FY20, No MPO

Montgomery County Total

Federal: $224,806.96 Match :$56,201.74 2020: $281,008.70 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 35 of 64 Report Created:7/25/2019 7:07:56AM

Page 38: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Morgan County

Indiana Department

of Transportation

SR 135 Bridge Rehabilitation

Or Repair

0.33 miles S of SR 252 on SR

135 at Indian Creek

Seymour 0 STPBG Bridge ROW RW $14,400.00 $3,600.00 $18,000.00 A 01 $2,434,849.0030773 /

1600025

Comments:Amend RW phase to current STIP. No MPO.

Indiana Department

of Transportation

SR 142 Erosion Control over BR Mill Hollow Branch; 00.

09 mi W of SR 39

Crawfordsville 0 STPBG Bridge

Construction

CN $41,859.20 $10,464.80 $52,324.00 A 01 $52,324.0041973 /

1801307

Comments:CN phase for $52,324 FY20, No MPO

Morgan County Total

Federal: $56,259.20 Match :$14,064.80 2020: $70,324.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 36 of 64 Report Created:7/25/2019 7:07:56AM

Page 39: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Newton County

Indiana Department

of Transportation

US 41 HMA Overlay,

Preventive

Maintenance

SR 14 to SR 10 LaPorte 9.14 NHPP Road

Construction

CN $5,274,476.80 $1,318,619.20 $6,518,096.00 $75,000.00A 01 $7,934,196.0042221 /

1901363

Bridge

Construction

CN $246,940.80 $61,735.20 $308,676.00

Road Consulting PE $1,072,880.00 $268,220.00 $991,100.00 $350,000.00

Comments:Please amend all phases into the STIP. No MPO.

Newton County Total

Federal: $6,594,297.60 Match :$1,648,574.40 2020: $991,100.00 2021: $75,000.00 2022: $7,176,772.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 37 of 64 Report Created:7/25/2019 7:07:56AM

Page 40: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Noble County

Indiana Department

of Transportation

SR 3 Other Intersection

Improvement

SR 3 at Waits Road, 2.22 miles

S of US 6

Fort Wayne .37 STPBG Safety

Construction

CN $1,101,393.60 $275,348.40 $1,376,742.00 A 01 $1,476,742.0042375 /

1900138

Safety Consulting PE $80,000.00 $20,000.00 $100,000.00

Comments:NO MPO. DES 1900138 adding PE to FY 2020 and CN to FY 2024 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 205 Bridge Replacement,

Other Construction

0.65 Miles South of SR 3 Over

Black Creek

Fort Wayne .1 STPBG Bridge

Construction

CN $754,487.20 $188,621.80 $20,000.00 $923,109.00 A 01 $1,198,109.0042376 /

1900052

Bridge Consulting PE $172,000.00 $43,000.00 $215,000.00

Bridge ROW RW $32,000.00 $8,000.00 $40,000.00

Comments:NO MPO. DES 1900052 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Noble County Total

Federal: $2,139,880.80 Match :$534,970.20 2020: $315,000.00 2021: 2022: $60,000.00 2023: 2024: $2,299,851.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 38 of 64 Report Created:7/25/2019 7:07:56AM

Page 41: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Owen County

Indiana Department

of Transportation

SR 42 Small Structure

Replacement

5.82 mi W of SR 243 Crawfordsville 0 STPBG Bridge ROW RW $20,000.00 $5,000.00 $25,000.00 A 01 $811,327.0039965 /

1601019

Comments:RW phase for $25,000 FY20, No MPO

Owen County Total

Federal: $20,000.00 Match :$5,000.00 2020: $25,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 39 of 64 Report Created:7/25/2019 7:07:56AM

Page 42: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Posey County

Indiana Department

of Transportation

I 64 Bridge Deck Patching I 64 EB over the Wabash Vincennes 0 NHPP Bridge

Construction

CN $540,000.00 $60,000.00 $600,000.00 A 01 $300,000.0040782 /

1702645

Comments:New Des, Deck Patching, I64. CN $150,000 FY 2020

Posey County Total

Federal: $540,000.00 Match :$60,000.00 2020: $600,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 40 of 64 Report Created:7/25/2019 7:07:56AM

Page 43: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Pulaski County

Indiana Department

of Transportation

SR 114 Bridge Deck Patching Over MP Hill Ditch, 0.89mi W of

US 421

LaPorte 0 STBG Bridge

Construction

CN $115,290.40 $28,822.60 $144,113.00A 01 $196,113.0042212 /

1900817

Bridge Consulting PE $41,600.00 $10,400.00 $40,000.00 $12,000.00

Comments:No MPO. Please amend all phases into the STIP.

Pulaski County Total

Federal: $156,890.40 Match :$39,222.60 2020: $40,000.00 2021: $156,113.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 41 of 64 Report Created:7/25/2019 7:07:56AM

Page 44: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Putnam County

Indiana Department

of Transportation

US 40 HMA Overlay,

Preventive

Maintenance

From 0.07 mi W of US 231 to

SR 75

Crawfordsville 8.593 STPBG Bridge ROW RW $20,000.00 $5,000.00 $25,000.00 A 01 $10,220,854.0039259 /

1592687

Comments:ROW phase for $25,000 FY20, No MPO

Indiana Department

of Transportation

US 231 Road Rehabilitation (3

R/4R Standards)

From 0.03 mi S of SR 240 to 1.6

1 mi N of SR 240 (Greencastle)

Crawfordsville 1.63 STPBG Road ROW RW $360,000.00 $90,000.00 $450,000.00 A 01 $8,091,587.0040573 /

1700121

Comments:ROW phase for $450,000 FY20, No MPO

Indiana Department

of Transportation

US 40 Slide Correction 3.55 mile E of US 231, Mt.

Meridian

Crawfordsville 0 STBG Road Consulting PE $40,769.28 $10,192.32 $50,961.60 A 01 $220,833.6041618 /

1801719

Comments:PE phase for $50,961.60 FY20, No MPO

Indiana Department

of Transportation

I 70 Bridge Maintenance

And Repair

7.10 mi W of SR 243 (EB) Crawfordsville 0 NHPP Bridge

Construction

CN $297,963.00 $33,107.00 $331,070.00 A 01 $371,070.0042093 /

1901581

Bridge Consulting PE $36,000.00 $4,000.00 $40,000.00

Comments:PE phase for $40,000 FY20 & CN phase for $331,070 FY20, No MPO

Putnam County Total

Federal: $754,732.28 Match :$142,299.32 2020: $897,031.60 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 42 of 64 Report Created:7/25/2019 7:07:56AM

Page 45: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Randolph County

Indiana Department

of Transportation

SR 28 HMA Overlay,

Preventive

Maintenance

from SR 1 to WCL of Ridgeville Greenfield 6.178 STBG Road Consulting PE $160,000.00 $40,000.00 $200,000.00 A 01 $3,668,502.0040612 /

1700900

Comments:Added PE Phase

Indiana Department

of Transportation

SR 1 HMA Overlay,

Preventive

Maintenance

SR 1 from SR 32 N. Jct. To SR

28

Greenfield 7.928 STBG Road Consulting PE $160,000.00 $40,000.00 $200,000.00 A 01 $1,994,459.0041102 /

1800743

Comments:Added PE Phase

Union City IR 1889 Road Reconstruction

(3R/4R Standards)

The project is located approx.

350' north of the Intersection of

W. Chestnut St. and Jackson

Greenfield .109 STPBG Group III Program PE $108,000.00 $0.00 $108,000.00 A 01 $1,184,575.0042071 /

1802944

Group III Program RW $36,000.00 $0.00 $36,000.00

Group III Program CN $803,660.00 $0.00 $799,660.00$4,000.00

Local Funds PE $0.00 $27,000.00 $27,000.00

Local Funds RW $0.00 $9,000.00 $9,000.00

Local Funds CN $0.00 $200,915.00 $199,915.00$1,000.00

Comments:No MPO - Add PE FY 20 Federal 108,000 and Local 27,000, Add CN FY 21 Federal 4,000 and Local 1,000, Add RW FY 22 Federal 36,000 and Local 9,000, Add CN FY 24 Federal 799,660 and Local 199,915.

Randolph County Total

Federal: $1,267,660.00 Match :$316,915.00 2020: $535,000.00 2021: $5,000.00 2022: $45,000.00 2023: 2024: $999,575.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 43 of 64 Report Created:7/25/2019 7:07:56AM

Page 46: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Ripley County

Indiana Department

of Transportation

SR 229 HMA Overlay Minor

Structural

1.07 mile S of SR 46 to SR 46 Seymour 1.162 STBG Road Consulting PE $160,000.00 $40,000.00 $200,000.00 A 01 $1,986,469.0040429 /

1700054

Comments:Amend PE to current STIP. No MPO.

Ripley County Total

Federal: $160,000.00 Match :$40,000.00 2020: $200,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 44 of 64 Report Created:7/25/2019 7:07:56AM

Page 47: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Rush County

Indiana Department

of Transportation

SR 44 HMA Overlay,

Preventive

Maintenance

SR 44 from 0.31 mi E of SR 3 to

7.40 mi E of SR 3 (WCL)-Rush

Co.

Greenfield 7.087 STBG Road Consulting PE $148,000.00 $37,000.00 $185,000.00 A 01 $2,033,263.0041105 /

1800763

Comments:Added PE

Glenwood IR 1014 ADA Sidewalk Ramp

Construction

Various locations on North and

South Main Street and State

Street (SR 44)

Greenfield .48 TA Local Funds PE $0.00 $28,192.60 $28,192.60 A 01 $461,819.0041311 /

1702774

Local

Transportation

Alternatives

PE $112,770.40 $0.00 $112,770.40

Comments:No MPO - Add PE FY 20 Federal 112,770.40 and Local 28,192.60.

Indiana Department

of Transportation

SR 244 Slide Correction At North Branch Clifty Creek, S

Side Roadway, 4.79 mi East SR

3

Greenfield 0 STBG District Other

Construction

CN $88,491.20 $22,122.80 $10,000.00 $100,614.00A 01 $215,614.0042031 /

1901370

District Other

Consulting

PE $80,000.00 $20,000.00 $100,000.00

District Other

ROW

RW $4,000.00 $1,000.00 $5,000.00

Comments:New Project

Rush County IR 4940 Bridge Replacement Rush County Bridge No. 1 on

CR 1100 N over Six Mile Creek

Greenfield .16 STPBG Local Funds PE $0.00 $41,272.00 $41,272.00 A 01 $2,196,360.0042073 /

1802929

Local Funds RW $0.00 $20,000.00 $20,000.00

Local Funds CN $0.00 $378,000.00 $378,000.00

Local Bridge

Program

PE $165,088.00 $0.00 $165,088.00

Local Bridge

Program

RW $80,000.00 $0.00 $80,000.00

Local Bridge

Program

CN $1,512,000.00 $0.00 $1,512,000.00

Comments:NO MPO - Add PE FY 20 Federal 165,088 and Local 41,272, Add RW FY 22 Federal 80,000 and Local 20,000, Add CN FY 24 Federal 1,512,000 and Local 378,000.

Rush County IR 5000 Bridge Replacement Rush County Bridge 155 on CR

450 South over Branch of Little

Flatrock River

Greenfield .22 STPBG Local Funds PE $0.00 $34,738.00 $34,738.00 A 01 $1,778,690.0042074 /

1802927

Local Funds RW $0.00 $12,000.00 $12,000.00

Local Funds CN $0.00 $309,000.00 $309,000.00

Local Bridge

Program

PE $138,952.00 $0.00 $138,952.00

Local Bridge

Program

RW $48,000.00 $0.00 $48,000.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 45 of 64 Report Created:7/25/2019 7:07:56AM

Page 48: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Rush County IR 5000 Bridge Replacement Rush County Bridge 155 on CR

450 South over Branch of Little

Flatrock River

Greenfield .22 STPBG Local Bridge

Program

CN $1,236,000.00 $0.00 $1,236,000.00 A 01 $1,778,690.0042074 /

1802927

Comments:No MPO - Add PE FY 20 Federal 138,952 and Local 34,738, Add RW FY 22 Federal 48,000 and Local 12,000, Add CN FY 24 Federal 1,236,000 and Local 309,000.

Rush County Total

Federal: $3,613,301.60 Match :$903,325.40 2020: $821,013.00 2021: $100,614.00 2022: $160,000.00 2023: 2024: $3,435,000.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 46 of 64 Report Created:7/25/2019 7:07:56AM

Page 49: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Shelby County

Indiana Department

of Transportation

US 52 Intersection

Improvement,

Roundabout

At SR 9 Greenfield 0 STBG Bridge ROW RW $40,000.00 $10,000.00 $50,000.00 A 01 $6,501,000.0039730 /

1600625

Mobility ROW RW $40,000.00 $10,000.00 $50,000.00

Comments:RW $100,00 in FY 2020. No MPO.

Indiana Department

of Transportation

I 74 Road Reconstruction

(3R/4R Standards)

From 0.11 mi W of SR 244 to 0.

11 mi E of SR 244

Greenfield .22 STBG Road Consulting PE $33,210.00 $3,690.00 $36,900.00 A 01 $5,712,129.0040506 /

1601973

Comments:Added PE Phase

Indiana Department

of Transportation

SR 9 Bridge Thin Deck

Overlay

over N BRANCH LEWIS CREEK,

04.54 S SR 44

Greenfield 0 STBG Bridge

Construction

CN $278,400.00 $69,600.00 $348,000.00 A 01 $348,000.0042211 /

1901538

Comments:Added CN

Indiana Department

of Transportation

SR 9 HMA Overlay,

Preventive

Maintenance

1.56 mi S of I-74 to 0.29 mi N of

I-74

Greenfield 1.85 STBG Road

Construction

CN $1,024,000.00 $256,000.00 $1,280,000.00 A 01 $1,280,000.0042260 /

1901508

Comments:Added CN

Indiana Department

of Transportation

SR 244 Road Rehabilitation (3

R/4R Standards)

from 0.06 mi E of I-74 (E ramps

I-74) to 5.18 mi E of I-74 at Deer

Creek

Greenfield 5.098 STBG Bridge

Construction

CN $323,200.00 $80,800.00 $404,000.00 A 01 $6,957,451.0042264 /

1600801

Bridge Consulting PE $32,800.00 $8,200.00 $41,000.00

Road

Construction

CN $3,449,960.80 $862,490.20 $4,312,451.00

Road Consulting PE $560,000.00 $140,000.00 $700,000.00

Road ROW RW $1,200,000.00 $300,000.00 $500,000.00 $1,000,000.00

Comments:New Project

Shelby County Total

Federal: $6,981,570.80 Match :$1,740,780.20 2020: $877,900.00 2021: 2022: $2,128,000.00 2023: $1,000,000.00 2024: $4,716,451.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 47 of 64 Report Created:7/25/2019 7:07:56AM

Page 50: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Steuben County

Indiana Department

of Transportation

SR 427 Small Structure

Replacement

Carries Baker Ditch, 2.39 Miles

East of SR 1, RP 12+39

Fort Wayne .2 STPBG Bridge

Construction

CN $420,603.20 $105,150.80 $525,754.00 A 01 $760,754.0042372 /

1900243

Toll Lease

Amendment

Proceeds

PE $132,000.00 $33,000.00 $165,000.00

Toll Lease

Amendment

Proceeds

RW $36,000.00 $9,000.00 $45,000.00

Toll Lease

Amendment

Proceeds

CN $20,000.00 $5,000.00 $25,000.00

Comments:NO MPO. DES 1900243 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Steuben County Total

Federal: $608,603.20 Match :$152,150.80 2020: $165,000.00 2021: 2022: $70,000.00 2023: 2024: $525,754.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 48 of 64 Report Created:7/25/2019 7:07:56AM

Page 51: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Switzerland County

Indiana Department

of Transportation

SR 156 Slide Correction 4.7 miles west of the junction

with SR 56

Seymour .05 STPBG Road Consulting PE $160,000.00 $40,000.00 $200,000.00 A 01 $3,954,281.0042288 /

1900351

Comments:Amend PE to current STIP. No MPO.

Indiana Department

of Transportation

SR 156 Slide Correction 2.0 miles west of the junction

with SR 101

Seymour .14 STPBG Road Consulting PE $400,000.00 $100,000.00 $500,000.00 A 01 $8,543,535.0042290 /

1900349

Comments:Amend PE phase to current STIP. NO MPO.

Switzerland County Total

Federal: $560,000.00 Match :$140,000.00 2020: $700,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 49 of 64 Report Created:7/25/2019 7:07:56AM

Page 52: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Tippecanoe County

Indiana Department

of Transportation

US 231 Auxiliary Lanes,

Passing

From 4.19 mi N of I-74 to 2.53

mi N of SR 28

Crawfordsville 10.856 STBG Mobility Consulting PE $157,420.00 $39,355.00 $196,775.00 A 01 $9,566,690.0041623 /

1700190

Comments:PE Phase for $196,775 FY20 via TCAPC MPO 2020-2024 TIP

Indiana Department

of Transportation

SR 25 Small Structure

Replacement

SR 25, 1.51 mi S of SR 28, W

Jct, Over Wallace Ditch

Crawfordsville 0 STPBG Bridge ROW RW $40,000.00 $10,000.00 $50,000.00 A 01 $760,995.0041880 /

1500120

Comments:ROW phase for $50,000 FY20 via TCAPC 2020-2024 TIP

Indiana Department

of Transportation

I 65 Bridge Maintenance

And Repair

0.23 mi S of SR 43 (NB) Crawfordsville 0 NHPP Bridge

Construction

CN $297,963.00 $33,107.00 $331,070.00 A 01 $351,070.0042092 /

1901578

Bridge Consulting PE $18,000.00 $2,000.00 $20,000.00

Comments:PE phase for $20,000.00 FY20 & CN phase for $331,070.00 FY20 via TCAPC 2020-2024 TIP (CN) & Mod (PE) dated 7/11/2019

Indiana Department

of Transportation

I 65 Bridge Deck Patching 0.58 mi S of SR 43 Crawfordsville 0 NHPP Bridge

Construction

CN $111,906.00 $12,434.00 $124,340.00 A 01 $134,340.0042095 /

1901585

Bridge Consulting PE $9,000.00 $1,000.00 $10,000.00

Comments:PE phase for $10,000 FY20 & CN phase for $124,340 FY20 via TCAPC 2020-2024 TIP and mod dated 7/11/2019

Indiana Department

of Transportation

SR 38 Bridge Deck Overlay WB over Elliott Ditch Crawfordsville 0 STBG Bridge

Construction

CN $569,451.20 $142,362.80 $711,814.00 A 01 $711,814.0042148 /

1701561

Comments:CN phase for $711,814.00 via TCAPC 2020-2024 TIP

Tippecanoe County Total

Federal: $1,203,740.20 Match :$240,258.80 2020: $732,185.00 2021: 2022: 2023: 2024: $711,814.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 50 of 64 Report Created:7/25/2019 7:07:56AM

Page 53: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Tipton County

Indiana Department

of Transportation

US 31 New Bridge, Other .97 miles N of SR 28 over the N

/S Railroad

Greenfield .778 NHPP Safety ROW RW $1,840,000.00 $460,000.00 $2,300,000.00 A 01 $23,880,465.0039052 /

1592421

Comments:Adding ROW Phase.

Indiana Department

of Transportation

SR 19 HMA Overlay,

Preventive

Maintenance

from 1.05 mi. S. of SR 28(SCL

Tipton) to .41 mi. S. of SR 28 (C

icero Ck.)

Greenfield .643 STBG District Other

Consulting

PE $49,200.00 $12,300.00 $61,500.00 A 01 $1,058,548.0041043 /

1800752

Comments:Added PE Phase

Indiana Department

of Transportation

SR 28 Pavement

Replacement

from WCL of Tipton to SR 19 W

junct

Greenfield .86 STBG Road

Construction

CN $7,819,320.80 $1,954,830.20 $9,774,151.00 A 01 $10,648,176.0042230 /

1900253

Road Consulting PE $619,220.00 $154,805.00 $774,025.00

Road ROW RW $80,000.00 $20,000.00 $100,000.00

Comments:New Project

Tipton County Total

Federal: $10,407,740.80 Match :$2,601,935.20 2020: $3,135,525.00 2021: 2022: $100,000.00 2023: 2024: $9,774,151.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 51 of 64 Report Created:7/25/2019 7:07:56AM

Page 54: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Union County

Indiana Department

of Transportation

US 27 HMA Overlay,

Preventive

Maintenance

0.31 mi S of SR 44 S junct (SE

City Limits of Liberty) to 0.33 mi

N of SR 44 N junct (NCL of

Greenfield 1.13 NHPP Road Consulting PE $60,000.00 $15,000.00 $75,000.00 A 01 $513,260.0042261 /

1901509

Safety

Construction

CN $36,000.00 $9,000.00 $45,000.00

Comments:New Project

Union County Total

Federal: $96,000.00 Match :$24,000.00 2020: $75,000.00 2021: 2022: $45,000.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 52 of 64 Report Created:7/25/2019 7:07:56AM

Page 55: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Vanderburgh County

Evansville ST 1 Road Reconstruction

(3R/4R Standards)

Walnut Street from US 41 to

Weinbach Ave. - Phase 1

Vincennes 2.07 STBG Local Funds RW $0.00 $10,000.00 $10,000.00 A 01 $2,940,000.0040124 /

1700400

Evansville MPO RW $28,000.00 $0.00 $28,000.00

Evansville MPO -

PYB

RW $12,000.00 $0.00 $12,000.00

Comments:Adding FY20 RW Federal $40,000.00, FY20 RW Local $10,000.00. Per EMPO TIP Letter dated 7/22/2019

Vanderburgh County Total

Federal: $40,000.00 Match :$10,000.00 2020: $50,000.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 53 of 64 Report Created:7/25/2019 7:07:56AM

Page 56: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Various County

Indiana Department

of Transportation

VA VARI Traffic Signals, New

Or Modernized

Traffic Mods in Various

locations in Seymour District

2020

Seymour 0 STPBG Safety

Construction

CN $16,000.00 $4,000.00 $20,000.00 A 01 $783,630.0040185 /

1700314

Comments:Amend RR/PE (CN phase) to current STIP. Amended to KIPDA's TIP per Administrative Modification 31 dated 5/23/19.

Indiana Department

of Transportation

VA VARI ITS Traffic

Management Systems

DMS Box Truss Structure

Upgrade in Indianapolis,

Northwest IN, Southern IN, &

Greenfield 0 NHPP Statewide

Construction

CN $1,161,951.30 $129,105.70 $1,291,057.00 A 01 $1,291,057.0041220 /

1800723

Comments:Federal Funds were De-obligated. DES 1800723 Adding CN to FY 2020 into FY 2020-2024 STIP.

Indiana Department

of Transportation

VA VARI Guardrail Attenuators,

New Or Modernize

Various Locations Within the

Vincennes District

Vincennes 0 STPBG Safety Consulting PE $204,800.00 $51,200.00 $256,000.00 A 01 $1,546,422.0041250 /

1801397

Comments:Amend 2020-2024 STIP. Adding FY20 PE $256,000.00. No MPO.

Indiana Department

of Transportation

VA VARI Asphalt Patching Various Locations Throughout

the LaPorte District - Northern

Counties / Winter Damage

LaPorte 0 Multiple Toll Lease

Amendment

Proceeds

PE $0.00 $247,000.00 $247,000.00 A 01 $4,097,305.0041963 /

1900542

Comments:Please amend PE/CE phase into the STIP.

Indiana Department

of Transportation

VA VARI Asphalt Patching Various Locations Throughout

the LaPorte District - Southern

Counties / Winter Damage

LaPorte 0 Multiple Road Consulting PE $80,000.00 $20,000.00 $100,000.00 A 01 $1,949,198.0041964 /

1900543

Comments:No MPO. Please amend PE/CE phase into the STIP.

Indiana Department

of Transportation

VA 1019 Roadside

Maintenance, Tree

Removal/Trimming

Various Tree Locations

Throughout the LaPorte District

LaPorte 0 Multiple Road

Construction

CN $200,000.00 $50,000.00 $250,000.00 A 01 $250,000.0041970 /

1900518

Comments:Please amend CN phase into the STIP. MACOG TIP Resolution 13-19 approved 3/13/19.

Indiana Department

of Transportation

VA 1019 Repair Or Replace

Barrier Wall

Various Roads in the

Greenfield District.

Greenfield 0 STBG District

Maintenance

Work Program -

CN $147,200.00 $36,800.00 $184,000.00 A 01 $184,000.0042021 /

1901334

Comments:Added CN

Indiana Department

of Transportation

VA 1019 Raised Pavement

Markings,

Refurbished

RPM Refurbishment project

Various locations in the

Greenfield District.

Greenfield 0 Multiple Safety

Construction

CN $480,000.00 $120,000.00 $600,000.00 A 01 $600,000.0042082 /

1901564

Comments:Added CN

Indiana Department

of Transportation

SP VARI Demolition, Remove

Buildings,

Foundations

clearing of state-owned

parcels along US 31 in Hamilton

and Tipton County

Greenfield 0 STBG Statewide

Construction

CN $800,000.00 $200,000.00 $1,000,000.00 A 01 $1,000,000.0042098 /

1901630

Comments:IMPO CN in 2020 for $1,000,000

Indiana Department

of Transportation

VA VARI Asphalt Patching Various terminal joints

throughout the Seymour District

Seymour 0 Multiple Bridge

Construction

CN $3,694,292.00 $923,573.00 $4,617,865.00 A 01 $4,617,865.0042099 /

1901448

Comments:Amend CN to current STIP. Amended to KIPDA's TIP per Administrative Modification 31 dated 5/23/19.

Indiana Department

of Transportation

VA 1019 Asphalt Patching Various Terminal Joints

throughout the Crawfordsville

District (TCAPC)

Crawfordsville 0 STBG Statewide

Construction

CN $926,129.16 $231,532.29 $1,157,661.45 A 01 $1,157,661.4542126 /

1901663

Comments:CN phase for $1,157,661.45 FY20 via TCAPC 2024 TIP (1901434)

Indiana Department

of Transportation

VA VARI Patch And Rehab

Pavement

Various Locations throughout

the Vincennes District

Vincennes 0 STPBG Road

Construction

CN $1,254,085.76 $313,521.44 $1,567,607.21 A 01 $1,567,607.2142146 /

1901677

Comments:Amend 2020-2024 STIP. Adding FY20 CN $1,567,607.21. No MPO.

Indiana Department

of Transportation

VA 1019 Asphalt Patching Various Terminal Joints

throughout the Crawfordsville

District (WCIEDD)

Crawfordsville 0 STBG Statewide

Construction

CN $455,428.91 $113,857.22 $569,286.14 A 01 $569,286.1442178 /

1901786

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 54 of 64 Report Created:7/25/2019 7:07:56AM

Page 57: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Comments:CN phase for $569,286.14 FY20, WCIEDD 2020-2024 TIP

Indiana Department

of Transportation

VA 1019 Asphalt Patching Various Terminal Joints

throughout the Crawfordsville

District

Crawfordsville 0 STBG Statewide

Construction

CN $335,833.64 $83,958.41 $419,792.05 A 01 $419,792.0542180 /

1901787

Comments:CN phase for $419,792.05 FY20, No MPO

Indiana Department

of Transportation

VA 1019 Patch And Rehab

Pavement

Slap Jacking Various Locations

in the Greenfield District

Greenfield 0 Multiple District

Maintenance

Work Program -

CN $80,000.00 $20,000.00 $100,000.00 A 01 $100,000.0042220 /

1901804

Comments:Added CN

Indiana Department

of Transportation

VA 1019 Guardrail,

Maintenance

Various Locations in Marion

County

Greenfield 0 STBG District

Maintenance

Work Program -

CN $800,000.00 $200,000.00 $1,000,000.00 A 01 $1,000,000.0042224 /

1901867

Comments:Added CN

Various County Total

Federal: $10,635,720.77 Match :$2,744,548.06 2020: $13,380,268.85 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 55 of 64 Report Created:7/25/2019 7:07:56AM

Page 58: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Vermillion County

Indiana Department

of Transportation

SR 71 Small Structure

Replacement

0.20 mi N of SR 163 Crawfordsville 0 STPBG Bridge ROW RW $16,880.00 $4,220.00 $21,100.00 A 01 $694,138.0038771 /

1500138

Comments:RW Phase for $21,100 FY20, No MPO

Indiana Department

of Transportation

SR 163 Bridge Replacement,

Other Construction

Over Brouiletts Creek Crawfordsville 0 STPBG Bridge ROW RW $20,000.00 $5,000.00 $25,000.00 A 01 $5,844,683.0040580 /

1701589

Comments:ROW phase for $25,000 FY20, No MPO

Indiana Department

of Transportation

SR 32 Bridge Maintenance

And Repair

over Wabash River, 01.19 mi E

of SR 63

Crawfordsville 0 STBG Bridge

Construction

CN $1,504,312.00 $376,078.00 $8,000.00 $1,872,390.00A 01 $1,989,390.0040956 /

1900759

Bridge Consulting PE $87,200.00 $21,800.00 $109,000.00

Comments:PE phase for $109,000 FY20

Indiana Department

of Transportation

SR 63 Bridge Maintenance

And Repair

0.24 mi S of SR 234 (NB) Crawfordsville 0 NHPP Bridge

Construction

CN $248,302.40 $62,075.60 $310,378.00 A 01 $351,070.0042091 /

1901576

Bridge Consulting PE $16,000.00 $4,000.00 $20,000.00

Comments:PE Phase for $20,000 FY20

Vermillion County Total

Federal: $1,892,694.40 Match :$473,173.60 2020: $493,478.00 2021: $1,872,390.00 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 56 of 64 Report Created:7/25/2019 7:07:56AM

Page 59: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Wabash County

Indiana Department

of Transportation

SR 218 Small Structure

Replacement

SR 218 over Metocinah Creek,

2.83 miles E of SR 15

Fort Wayne .1 STPBG Bridge ROW RW $25,280.00 $6,320.00 $31,600.00 A 01 $4,309,751.0038563 /

1600691

Comments:NO MPO. DES 1401737 Adding additional RW to FY 2020 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 13 Bridge Maintenance

And Repair

Bridge over MISSISSINEWA

RIVER, 04.19 Miles South of SR

124.

Fort Wayne 0 STPBG Bridge

Construction

CN $423,195.20 $105,798.80 $528,994.00A 01 $778,994.0042034 /

1901313

Bridge Consulting PE $200,000.00 $50,000.00 $250,000.00

Comments:NO MPO. DES 1901311, 1901318, 1901321, 1901323, 1901325 adding PE to FY 2020, and CN to FY 2021 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 124 Box Culvert

Replacement

2.46 Miles west of SR 13,

Carries Mill Creek

Fort Wayne .1 STPBG Bridge

Construction

CN $1,186,491.20 $296,622.80 $40,000.00 $1,443,114.00 A 01 $1,948,114.0042365 /

1900069

Bridge Consulting PE $324,000.00 $81,000.00 $405,000.00

Bridge ROW RW $48,000.00 $12,000.00 $60,000.00

Comments:NO MPO. DES 1900069

Indiana Department

of Transportation

US 24 Small Structure

Replacement

UNT of Helms Creek, 00.55 E

SR 115

Fort Wayne .2 NHPP Bridge

Construction

CN $6,437,242.40 $1,609,310.60 $90,000.00 $7,956,553.00 A 01 $9,454,053.0042366 /

1900240

Bridge Consulting PE $982,000.00 $245,500.00 $1,227,500.00

Bridge ROW RW $144,000.00 $36,000.00 $180,000.00

Comments:NO MPO. DES 1900072, 1900080, 1900081, 1900236, 1900071, 1900240 adding PE to FY 2020, RW to FY 2022 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 114 Bridge Replacement,

Other Construction

1.66 Miles East of SR 13, Over

the Eel River

Fort Wayne .1 STPBG Bridge

Construction

CN $4,631,139.20 $1,157,784.80 $50,000.00 $5,738,924.00 A 01 $6,455,174.0042370 /

1900051

Bridge Consulting PE $533,000.00 $133,250.00 $666,250.00

Comments:NO MPO. DES 1900051 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Wabash County Total

Federal: $14,934,348.00 Match :$3,733,587.00 2020: $2,580,350.00 2021: $528,994.00 2022: $420,000.00 2023: 2024: $15,138,591.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 57 of 64 Report Created:7/25/2019 7:07:56AM

Page 60: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Warren County

Warren County IR 1004 Bridge Rehabilitation

Or Repair

Bridge #36 over Wabash River

on Warren County Road 100 E

Crawfordsville .153 STBG Local Funds CN $0.00 $495,208.73 $495,208.73 A 01 $1,500,000.0037638 /

1400805

Local Bridge

Program

CN $1,172,084.27 $0.00 $1,172,084.27

Comments:NO MPO, please add CN funds to FY 20 in the amount of 1,172,084.27 federal and 495,208.73 local

Indiana Department

of Transportation

SR 26 Road Rehabilitation (3

R/4R Standards)

From US 41 (E jct) to SR 55 (W

jct)

Crawfordsville 6.195 STPBG Road ROW RW $88,000.00 $22,000.00 $110,000.00 A 01 $15,553,842.5040577 /

1400249

Comments:ROW phase for $110,000 FY20, No MPO

Warren County Total

Federal: $1,260,084.27 Match :$517,208.73 2020: $1,777,293.00 2021: 2022: 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 58 of 64 Report Created:7/25/2019 7:07:56AM

Page 61: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Wayne County

Indiana Department

of Transportation

SR 38 Bridge Replacement,

Steel

Over Nettle Creek, 1.47 miles W

of SR 1

Greenfield .01 STBG Bridge ROW RW $4,800.00 $1,200.00 $6,000.00 A 01 $3,664,610.0038527 /

1593239

Comments:Adding ROW Phase

Wayne County ST 4780 Bridge Rehabilitation

Or Repair

Bridge #701 carrying South "G"

Street over E Fork Whitewater

River

Greenfield .18 STPBG Local Funds PE $0.00 $90,000.00 $90,000.00 A 01 $3,137,500.0042068 /

1802930

Local Funds RW $0.00 $10,000.00 $10,000.00

Local Funds CN $0.00 $527,500.00 $527,500.00

Local Bridge

Program

PE $360,000.00 $0.00 $360,000.00

Local Bridge

Program

RW $40,000.00 $0.00 $40,000.00

Local Bridge

Program

CN $2,110,000.00 $0.00 $2,110,000.00

Comments:No MPO - Add PE FY 20 Federal 360,000 and Local 90,000, Add RW FY 22 Federal 40,000 and Local 10,000, Add CN FY 24 Federal 2,110,000 and Local 527,500.

Wayne County IR 2225 Bridge Replacement Bridge #149 carrying Fountain

City Pike over Nolands Fork

Greenfield .07 STPBG Local Funds PE $0.00 $48,000.00 $48,000.00 A 01 $1,720,000.0042069 /

1802936

Local Funds RW $0.00 $10,000.00 $10,000.00

Local Funds CN $0.00 $286,000.00 $286,000.00

Local Bridge

Program

PE $192,000.00 $0.00 $192,000.00

Local Bridge

Program

RW $40,000.00 $0.00 $40,000.00

Local Bridge

Program

CN $1,144,000.00 $0.00 $1,144,000.00

Comments:NO MPO - Add PE FY 20 Federal 192,000 and Local 48,000, Add RW FY 22 Federal 40,000 and Local 10,000, Add CN FY 24 Federal 1,144,000 and Local 286,000.

Wayne County ST 3154 Bridge Replacement Bridge #720 carrying Bridge

Avenue over W Fork of

Whitewater River

Greenfield .07 STPBG Local Funds PE $0.00 $52,000.00 $52,000.00 A 01 $1,850,000.0042072 /

1802934

Local Funds RW $0.00 $10,000.00 $10,000.00

Local Funds CN $0.00 $308,000.00 $308,000.00

Local Bridge

Program

PE $208,000.00 $0.00 $208,000.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 59 of 64 Report Created:7/25/2019 7:07:56AM

Page 62: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Wayne County ST 3154 Bridge Replacement Bridge #720 carrying Bridge

Avenue over W Fork of

Whitewater River

Greenfield .07 STPBG Local Bridge

Program

RW $40,000.00 $0.00 $40,000.00 A 01 $1,850,000.0042072 /

1802934

Local Bridge

Program

CN $1,232,000.00 $0.00 $1,232,000.00

Comments:No MPO - Add PE FY 20 Federal 208,000 and Local 52,000, Add RW FY 22 Federal 40,000 and Local 10,000, Add CN FY 24 Federal 1,232,000 and Local 308,000.

Indiana Department

of Transportation

SR 227 Small Structure

Replacement

5.676 mile I-70 (SS-227-89-20.

79)

Greenfield 0 STBG Bridge

Construction

CN $198,047.20 $49,511.80 $247,559.00 A 01 $285,559.0042088 /

1296532

Comments:Added CN

Indiana Department

of Transportation

US 27 HMA Overlay,

Preventive

Maintenance

1.46 mi N of I-70 to 5.72 mi N of

I-70 (SCL Fountain City)

Greenfield 4.26 NHPP Bridge

Construction

CN $271,200.00 $67,800.00 $339,000.00 A 01 $1,850,000.0042262 /

1901510

Road

Construction

CN $1,208,800.00 $302,200.00 $1,511,000.00

Comments:Added CN

Indiana Department

of Transportation

I 70 Replace

Superstructure

over PLUM CREEK, 02.44 E SR

1

Greenfield 0 NHPP Bridge

Construction

CN $4,952,700.00 $550,300.00 $5,503,000.00 A 01 $6,218,000.0042267 /

1900184

Bridge Consulting PE $630,000.00 $70,000.00 $700,000.00

Bridge ROW RW $13,500.00 $1,500.00 $15,000.00

Comments:New Project

Indiana Department

of Transportation

US 40 Scour Protection (Ero

sion)

US 40 over Greens Fork Greenfield 0 STBG Bridge

Construction

CN $477,960.00 $119,490.00 $597,450.00 A 01 $762,450.0042270 /

1900228

Bridge Consulting PE $120,000.00 $30,000.00 $150,000.00

Bridge ROW RW $12,000.00 $3,000.00 $15,000.00

Comments:New Project

Indiana Department

of Transportation

US 35 Scour Protection (Ero

sion)

US 35 OVER GREENS FORK,

06.46 N SR 38

Greenfield 0 STBG Bridge

Construction

CN $86,540.00 $21,635.00 $108,175.00 A 01 $108,175.0042271 /

1900257

Comments:Added CN

Wayne County Total

Federal: $13,341,547.20 Match :$2,558,136.80 2020: $2,053,559.00 2021: 2022: $2,030,000.00 2023: 2024: $11,816,125.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 60 of 64 Report Created:7/25/2019 7:07:56AM

Page 63: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Wells County

Indiana Department

of Transportation

SR 301 Small Structure

Replacement

Carried Eight Mile Creek, 1.85

Miles North of SR 124.

Fort Wayne .1 STPBG Bridge

Construction

CN -$340,473.60 -$85,118.40 ($425,592.00) A 01 $0.0041569 /

1800049

Bridge ROW RW -$16,000.00 -$4,000.00 ($20,000.00)

Comments:No MPO. Removing CN

Indiana Department

of Transportation

SR 1 HMA Overlay,

Preventive

Maintenance

From SR 124 S. Jct. (Wabash

River Bridge) to SR 116 N. Jct. (

Dustman Rd.)

Fort Wayne 1.02 STPBG Road

Construction

CN $2,135,642.40 $533,910.60 $2,669,553.00 A 01 $3,101,553.0041874 /

1900621

Road Consulting PE $345,600.00 $86,400.00 $432,000.00

Comments:NO MPO. DES 1900621 adding PE to FY 2020 and CN to FY 2022 into FY 2020 - 2024 STIP.

Indiana Department

of Transportation

SR 218 Bridge Maintenance

And Repair

Bridge over ELM CREEK, 04.15

West of SR 1.

Fort Wayne 0 STPBG Bridge

Construction

CN $736,151.20 $184,037.80 $920,189.00A 01 $1,570,189.0042033 /

1901340

Bridge Consulting PE $520,000.00 $130,000.00 $600,000.00 $50,000.00

Comments:NO MPO. DES 1900827, 1901326 thru 1901331, 1901339 thru 1901341, 1901343, 1901350 1901351 adding PE to FY 2020

Indiana Department

of Transportation

SR 1 Replace

Superstructure

Over Eight Mile Creek, 2.95

Miles North of US 224

Fort Wayne .11 STPBG Bridge

Construction

CN $938,228.00 $234,557.00 $25,000.00 $1,147,785.00 A 01 $1,477,785.0042383 /

1900035

Bridge Consulting PE $212,000.00 $53,000.00 $265,000.00

Bridge ROW RW $32,000.00 $8,000.00 $40,000.00

Comments:NO MPO. DES 1900035 adding PE to FY 2020

Indiana Department

of Transportation

SR 124 HMA Overlay Minor

Structural

From SR 3 to SR 116 North Jct. Fort Wayne 11.249 STPBG Bridge

Construction

CN $786,231.20 $196,557.80 $35,000.00 $947,789.00 A 01 $7,723,879.0042384 /

1800161

Bridge Consulting PE $216,000.00 $54,000.00 $270,000.00

Bridge ROW RW $56,000.00 $14,000.00 $70,000.00

Road

Construction

CN $4,620,216.00 $1,155,054.00 $5,775,270.00

Road Consulting PE $500,656.00 $125,164.00 $625,820.00

Comments:NO MPO. DES 1800161, 1900085,

Indiana Department

of Transportation

SR 218 Bridge Replacement,

Other Construction

0.68 Miles East of SR 1, Carries

St. John Ditch

Fort Wayne .1 STPBG Bridge

Construction

CN $918,228.00 $229,557.00 $1,147,785.00 A 01 $1,297,785.0042386 /

1900053

Bridge Consulting PE $120,000.00 $30,000.00 $150,000.00

Comments:NO MPO. DES 1900053 adding PE to FY 2020 and CN to FY 2024 into FY 2020 - 2024 STIP.

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 61 of 64 Report Created:7/25/2019 7:07:56AM

Page 64: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Indiana Department

of Transportation

SR 3 Bridge Replacement,

Other Construction

1.32 Miles South of SR 218 Fort Wayne .1 STPBG Bridge

Construction

CN $2,617,912.80 $654,478.20 $25,000.00 $3,247,391.00 A 01 $3,757,391.0042387 /

1900038

Bridge Consulting PE $356,000.00 $89,000.00 $445,000.00

Bridge ROW RW $32,000.00 $8,000.00 $40,000.00

Comments:NO MPO. DES 1900038 adding PE to FY 2020, ROW to FY22 and CN to FY 2022 into FY 2020 - 2024 STIP.

Wells County Total

Federal: $14,786,392.00 Match :$3,696,598.00 2020: $2,787,820.00 2021: $970,189.00 2022: $2,884,553.00 2023: -$425,592.00 2024: $12,266,020.00

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 62 of 64 Report Created:7/25/2019 7:07:56AM

Page 65: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

White County

Indiana Department

of Transportation

US 24 HMA Overlay,

Preventive

Maintenance

0.68mi E of US 421/SR 43 to 2.

65mi W of SR 39 (CR 300E)

LaPorte 2.61 NHPP Bridge

Construction

CN $140,546.40 $35,136.60 $175,683.00 A 01 $1,470,894.0042222 /

1901360

Bridge Consulting PE $105,700.00 $26,425.00 $132,125.00

Road

Construction

CN $968,971.20 $242,242.80 $1,201,214.00 $10,000.00

Road Consulting PE $207,744.00 $51,936.00 $183,940.00 $75,740.00

Comments:Please amend all phases into the STIP. No MPO

Indiana Department

of Transportation

US 421 Bridge Replacement,

Concrete

Over Hoagland Ditch, 3.50mi S

of SR 16

LaPorte 0 NHPP Bridge

Construction

CN $1,911,953.60 $477,988.40 $2,294,942.00 $95,000.00A 01 $1,261,110.0042245 /

1700103

Bridge ROW RW $200,000.00 $50,000.00 $250,000.00

Comments:Please amend all phases into the STIP. No MPO.

White County Total

Federal: $3,534,915.20 Match :$883,728.80 2020: $316,065.00 2021: $355,000.00 2022: $3,747,579.00 2023: 2024:

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 63 of 64 Report Created:7/25/2019 7:07:56AM

Page 66: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

State Preservation and Local Initiated Projects FY 2020 - 2024

Indiana Department of Transportation (INDOT)

SPONSOR CONTR

ACT # /

LEAD

DES

ROUTE WORK TYPE LOCATION DISTRICT MILES FEDERAL

CATEGORY

PROGRAM PHASE FEDERAL MATCHEstimated

Cost left to

Complete

Project*

2020 2021 2022 2023 2024STIP

NAME

Whitley County

Indiana Department

of Transportation

SR 5 HMA Overlay Minor

Structural

From SR 114 to SR 14 North Jct

. (Eel River Bridge).

Fort Wayne 6.239 STPBG Road

Construction

CN $2,509,904.80 $627,476.20 $3,137,381.00 A 01 $3,451,131.0042382 /

1600944

Road Consulting PE $251,000.00 $62,750.00 $313,750.00

Comments:NO MPO. DES 1600944 adding PE to FY 2020 and CN to FY 2024 into FY 2020 - 2024 STIP.

Whitley County Total

Federal: $2,760,904.80 Match :$690,226.20 2020: $313,750.00 2021: 2022: 2023: 2024: $3,137,381.00

Grand Total

Federal: $249,357,659.38 2021: $28,972,194.502020: $65,833,818.65 2023: $40,675,078.002022: $56,478,434.00 2024: $115,899,457.00Match : $58,501,322.75

*Estimated Costs left to Complete Project column is for costs that may extend beyond the four years of a STIP. This column is not fiscally constrained and is for information purposes.

Page 64 of 64 Report Created:7/25/2019 7:07:56AM

Page 67: HDA-IN Deputy Commissioner Capital Program Management …Indiana Division 575 N. Pennsylvania St, Room 254 Indianapolis, IN 46204 July 25, 2019 317-226-7475 317-226-7341 In Reply Refer

www.in.gov/dot/ An Equal Opportunity Employer

100 North Senate Avenue Room N955 Indianapolis, Indiana 46204

PHONE: (317) 232-0223 FAX: (317) 232-1499 Eric Holcomb, Governor

Joe McGuinness, Commissioner