Top Banner
HAZARD MITIGATION ASSISTANCE Region X Mitigation Summit 2014
18

Hazard mitigation assistance

Mar 22, 2016

Download

Documents

cahil

Hazard mitigation assistance . Region X Mitigation Summit 2014. HMA Unified Guidance and SRIA Updates. Streamlining HMGP Advance Assistance Obligation Timeline Requirements Program Administration by States BCA Enhancements Ecosystem Services Benefits Pre-calculated benefits - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hazard mitigation assistance

HAZARD MITIGATIONASSISTANCE

Region X Mitigation Summit 2014

Page 2: Hazard mitigation assistance

HMA Unified Guidance and SRIA Updates

o Streamlining HMGPo Advance Assistanceo Obligation Timeline Requirementso Program Administration by States BCA Enhancements

Ecosystem Services Benefits Pre-calculated benefits Incorporating Sea Level Rise BCA v5.0 Release

Stakeholder engagement November 2013 FEMA HQ reached out to SHMOs for input

on HMA FEMA will use survey results to improve communication and

program delivery FEMA will use initial survey results as a base-line FEMA may reach out to SHMOs again to see how we’re

doing

Continued improvement of the HMA web page

2

Page 3: Hazard mitigation assistance

3

SRIA: Streamlining HMGP

Minimum criteria for complete applications Timeframes for review actions and decisions Phasing projects Industry cost guides for estimates Industry design and construction standards Pre-calculated benefits

Page 4: Hazard mitigation assistance

4

SRIA: Advance Assistance

Up to 25% of estimated ceiling, limit of $10 million

Leverage resources across complex programs with (in)compatible requirements

Evaluate multiple areas / facilities to determine effective mitigation Incorporate NEPA into decision-making Obtain technical resources to gather data, perform BCA and initiate

EHP and program data collection Develop complete applications that equal or exceed available ceiling Incorporate strategic fund management into budget and work schedule Incorporate Grantee level consistency review

Page 5: Hazard mitigation assistance

Sandy Supplemental: Obligation Timeframe Requirement

Title IX, Section 904 (c)-Obligated funds shall be expended within 24 months or returned to the Agency • Does not require each project to have a 24 month

performance period

• Requires increased oversight and monitoring by Grantee and FEMA

• Strategic Fund Management provides process to meet this requirement

Page 6: Hazard mitigation assistance

SRIA/Supplemental: All together

Title IX, Section 904 (c)-Obligated funds shall be expended within 24 months or returned to the Agency

• Does not require each project to have a 24 month performance period

• Requires increased oversight and monitoring by Grantee and FEMA

• Strategic Fund Management provides process to meet this requirement

Page 7: Hazard mitigation assistance

SRIA/Supplemental: All together

Page 8: Hazard mitigation assistance

Program Administration by States

Florida’s Disasters Under PAS DR-4068 awarded $14.9M out of $20M DR-4084 awarded $2.8M out of $5.3M DR-4138 activity underway

Benefits Scalable program is attractive Small disaster to start out Process reduced time between disaster and funding recovery Projects started more quickly Entered contracting phase earlier than they usually do Had to be more efficient to spend money right away Does not preclude FEMA assistance with applications

Page 9: Hazard mitigation assistance

BCA Enhancements

Pre-calculated benefits for residential safe rooms Use of one frequency/event in the damage frequency

assessment (DFA) module in the benefit cost toolkit Generator policy and how to analyze for cost effectiveness Incorporation of Ecosystem Service benefits for acquisitions Determination of cost effectiveness for acquisitions and

elevations in the 100 year special flood hazard area Incorporation of sea level rise estimates into mitigation

project design and benefit cost analysis Benefit Cost Analysis toolkit version 5.0 (released April 2014)

Page 10: Hazard mitigation assistance

Ecosystem Services Benefits

14 land use types, including types we perform acquisitions in. 25 ecosystem services for each land. FIMA released a policy for the Consideration of Environmental Benefits in

the Evaluation of Acquisition Projects under the Hazard Mitigation Programs

These additional benefits are calculated based on the square feet of land being deed restricted.

Policy restricts inclusion of the ecosystem service benefits

100 Year Benefits at 7% Discount Rate

Land Use Yearly Benefits 1 Acre ½ Acre 27,363 SqFt 16,585 SqFt

Wetlands $ 42,018.70 $ 599,843.85 $ 299,921.93 $ 376,802.74 $ 228,384.07

Green Open $ 11,949.16 $ 170,581.91 $ 85,290.96 $ 107,154.11 $ 64,947.22

Riparian $ 38,625.51 $ 551,403.89 $ 275,701.95 $ 346,374.30 $ 209,941.08

Page 11: Hazard mitigation assistance

Approved pre-determined cost-effectiveness for acquisition and elevation projects in the 100 year floodplain.

Applies to riverine and coastal areas

Pre-Calculated Benefits

$175,000 for elevations $276,000 for acquisitions

11

Page 12: Hazard mitigation assistance

Incorporating Sea Level Rise

Memo released on December 23, 2013 . The memo and frequently asked

questions (FAQs) include sources of information for sea level rise NOAA USACE Locally generated studies that have been

accepted and adopted by the state or jurisdiction.

Including sea level rise estimates can substantially increase a projects benefit cost ratio and level of protection, especially for acquisition projects and projects with a useful life of 30 or more years.

12

Page 13: Hazard mitigation assistance

13

FY 2013 PDM and HMA Grant Cycle

Lessons learned from 2013 cycle: Hot wash with Regions on 2/12/2014

A short application cycle (90-Days) still yields sufficient number of applications

Limiting sub-applications under the PDM program reduced review time Regions may need more technical assistance during reviews Regional review time (4 weeks) was adequate for most regions 24-Month and 36-Month POP from Notification letter

FY14 FMA & PDM application period opened April 21. PDM $23 M. FMA $89 M.

Page 14: Hazard mitigation assistance

14

FY 2014 PDM and HMA Grant Cycle

Key Dates: Application Start Date: 4/21/2014 – Due Date 7/25/2014 (11:59pm) Anticipated Funding Selection Date: 9/30/2014 (Anticipated) Award Date: 12/30/2014

PDM Priorities: All 50 States, D.C., federally recognized tribal governments, and territories will receive a base

amount of 1 percent of the total appropriated PDM funding, or $250,000. $5 million will be set aside for federally recognized tribal governments to receive up to $250,000

per tribe. The balance of PDM program funds will be distributed on a competitive basis.

FMA Priorities: $50,000 for state plans $25,000 for local plans Maximum 10 percent by the state EMA for management costs, and a maximum of 5 percent by

the local EMA for management costs.

Page 15: Hazard mitigation assistance

How Program Dollars Are Set

Page 16: Hazard mitigation assistance

16

e-Grants Deployments

Last Release - January 30, 2014 – Major changes: Added the ability to share the grant application between applicant staff of

the same grantee. Added certain closeout functionalities

Next Release - November 14, 2014 – Major Changes: Implement the ability to indicate that properties have been mitigated and

identify the mitigation action Remove old forms from the system and allow the applicants to upload new

soon to be approved OMB forms into the system. Identify how cost effectiveness was determined for properties (allowing the

use of pre-calculated benefits) Allow SOW sub-grant section revision requests post-award Add questions to property sub-grant section on NFIP participation

Page 17: Hazard mitigation assistance

Grants Policy – What’s on the Drawing Board

Outreach Program Digest HMGP Appeals Database

The Future Supporting and coordinating 404 and 406 mitigation Exploring mitigation value of green infrastructure

Policy Development Minimum Design Standards for HMA Projects in Flood Hazard Areas – “ASCE

24” Minor Flood Risk Reduction measures Duplication of Programs Subsurface Rights and Property Acquisition projects PEA for Eligible Wildfire Hazard Mitigation projects

Page 18: Hazard mitigation assistance

THANK-YOU!Region X Mitigation Summit 2014