1 Transforming Hawaii’s Grid: Integration Planning University of Hawaii, Seminar November 12, 2009
Jan 22, 2015
1
Transforming Hawaii’s Grid:Integration Planning
University of Hawaii, Seminar November 12, 2009
2
Overview
RPS and GHG Policy Drivers What are we working toward? What are our options? Why do we need planning studies? Why now?
Transformational Change Areas Tools – Data, Models & Equipment Application/Programs – H.U.I., BESS, DREEM,
Inter-island Wind Processes – Standards, CESP, Cost Recovery
Status & Summary Q&A
3
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$200
$220
Time Period (Month, Year)
Res
iden
tial
Bil
l @
600
kW
h C
on
sum
pti
on
Residential Bill @ 600 kWh Consumption
2007 2008 2009
What are we working toward?
Energy price stability Reasonable electricity
price today & tomorrow Long-term price
reduction opportunity
Secure local source of energy
Reduce Green House Gas emissions
Service reliability
$202 Residential Bill
4
HI Energy Mix
Primary resource is imported petroleum from foreign countries
Top 10 generation plants are petroleum, coal, and waste resources
No interconnections between islands; No high voltage or DC transmission
* Source: HECO website 2008
Hawaii
Oil76.5%
Wind2.3% Hydro
0.4%
Geothermal2.2%
Biomass (MSW)4.0%
Biofuel0.1%
Coal14.5%
5
What are our Options?
Approach ResultsStatus Quo Will not meet 2015 and
beyond RPS targets
DSM/Energy Efficiency Positive progress but not alone sufficient to meet 2015 and beyond RPS targets
Maximize Renewables on-island
Positive progress but unlikely to meet 2015 and beyond RPS targets
Inter-island cable integrating multi-island resources & load
Transformational progress toward achieving 2015 and future targets
6
Kauai
Oahu
Molokai
Lanai
Maui
Hawaii
Recognizing Hawaii’s Wealth of Renewable Potential
Solar
Wind Geothermal
Pumped Storage
MSW
Biomass/Biofuel
OTEC/Wave
DSM/Energy Efficiency
7
Renewable Energy Resource Options for Oahu
Solar Biomass DSM/Energy
Efficiency Geothermal OTEC Wind Wave Biofuel Refuse Hydrogen
are a commercially available technology?
are available within a 5-year horizon?
are available on a large-scale?
have no fuel cost?
There is NO silver-bullet.In the long-run, portfolio of resources will play a role in our energy future. However, which resources…
Timing, incentives and technology maturity matters
8
Renewable Energy Resource Opportunities for Oahu Today
Wind Solar
9
Renewable Game Plan for Hawaii
The load is on Oahu, but the renewable resource is limited. The neighbor islands have abundant renewable resources, but limited load.
Fundamental change in Planning Perspective• Clean Energy Scenario Planning (CESP) is the new
planning process driving change above the status quo
• Stimulus activities paving the way Ultimately, may need to explore
opportunities, such as cabling the islands together• Maximize benefits for all islands• Minimize impact of integrating wind (i.e. cost, risk)
10
Why Conduct Planning Studies?
Minimize risks by ensuring operational fit Investigate via detailed modeling studies the
means to integrate high-penetration wind and solar resources
Collect and assess renewable performance data to inform mitigation strategies
Determine technologies and new system architecture for enhancing accommodation of variable renewable resources
Stage 1A
Stage 1B
Stage 2
Possible PV Resources
Possible Wind ResourcesPossible Wind Resources
100 MW of on-island and400 MW of neighbor-island
wind resources via submarine cables and new infrastructure
“BIG Wind” is a vital component to achieving RPS
11
Impacts in Perspective
The HELCO and MECO grids already have some of the highest penetration of wind energy in the world.
**If the HECO system had 500 MW of wind power, the penetration level would be roughly 78% = (500 MW Wind /(635 MW load)
Power System Region
Max Wind Power/ Min Load + Export
Capacity (MW)
West Denmark 58%
Schleswig Holstein
(Germany) 44%
Gotland (Sweden) 40%
Ireland 38%
MECO 38%
HELCO 39%
(HECO**) 78%
* source of data for regions other than HECO, HELCO and MECO, from "Wind Power Integration in EirGrid
Operating Experience", Jody Dillon, Renewables Integration Group, presented at the UWIG conference in
Fort Worth, Texas April 2008.
12
Why Now?
Federal Support / Incentives DOE Stimulus funding &
technical resources TRC review & input Technology transfer Tax credits
State Energy Policy RPS & GHG Energy Security &
Independence Fossil Fuel Costs
Technology Advancements WTG Storage Cables Power Electronics Sensors/Controls
Incentives
Policy Technology
Momentum to achieve RPS &
Sustainability Goals
Motivation – What we NEED!!!
Reliably and sustainably accommodate and assess amount of renewable utilization
Tools to manage intermittent or variable resources (visibility, communication, controls)
Working knowledge-base of the performance characteristics of new system resources like wind & solar
Demonstrated integration tools such as more accurate and targeted modeling/forecasting for utility utilization
We are in an exciting era of change for the electric power industry, an industry that has remained relatively stable and unchanged for the past 30-40 years .
Activities
Transformational Changes New Tools – Data, Models & Equipment New Application/Programs – H.U.I., DREEM,
BESS, Inter-island Wind (“BIG Wind”) New Processes – Reliability Standards, CESP,
Cost Recovery Mechanisms
Collaborations Partnerships in education: sustainable pipeline
of informed workforce Partnerships with industry: build-up and apply
Hawaii-based technology and ingenuity
Communication/Education Internal & External, at all levels (even K-12)
14
Tools: New Hi-Res Data, Remote Sensing, 4-D Space Responds to needs to acquire
accurate, upper atmospheric wind data within the operating regime of current wind turbine technologies
Enables wind data to be remotely measured at integration elevations (50m to 1000m) and at strategic inflow/outflow locations
Reduces integration & development risk at new sites with wind data measurements
Provides much needed volume space of data (3-D DOF) correlated with time (1 DOF) or 4-D Space for development of utility responsive forecasts
Build on data collection campaigns to improve models & techniques
Ex. SODAR unit in the field
Similar Monitoring Efforts in CA
16
Ex: Wind & Solar Data & EquipmentUtility Efforts with Industry & Labs
Develop high resolution wind and solar time series data for Modeling & Scenario Analysis
Deployment of data monitoring equipment to improve current knowledge of system (wind, solar, distribution-level data)
Support analysis, quality assurance and validation of resources modeled with observed data
17
1. Meteorology – Seasonal Variations
2. Geographic location
3. Topology &
4. Data resolution
Account for New Development & Variability of Resources
Annual Averaged map
Some Applications/Programs
ARRA Stimulus Hawaii Utility Integration Initiatives
(H.U.I) - funded Hawaii Battery Energy Storage Strategy
for Renewables Demonstration Project (Hawaii BESS4Renewables) – applied
Hawaii Smart Distributed Resources and Efficient Energy Management Demonstration Project (Hawaii Smart DREEM) – applied
Inter-Island Wind
18
Hawaii Utility Integration (H.U.I.) Initiatives - $750k
Initiative 1: WindNET Sensor Development & Pilot Field Campaign – Objectives are to investigate, test and deploy pilot sensor (i.e. sodar, lidar, doppler) units to address in-the-field logistics of operating, tuning, integrating and maintaining a more permanent WindNET.
Initiative 2: “Smart-Grid Prep” Enhancements – Objectives focus on extracting additional real-time phasor data from existing electronic relays to improve system operator’s awareness of potential stability issues resulting from the system dynamics or wind-induced variability issues – HELCO focused
Initiative 3: Green Smart Grid (GSG) Framework – Objectives include identifying grid automation or enhancement options to resolve existing system challenges and developing a GSG framework to address anticipated system change impacts with increasing renewables and variable distributed generation.
H.U.I. Collaborations with WindSENSE in California and Oregon Efforts
Operationalize wind forecasting in the control room
Provide tools for visualization and decision making
Utilize modeling and in situ data to inform monitoring parameters
Enhance with observationally targeted monitoring locations
In situ weather monitoring locations
S – Secondary wind direction during Santa Anas
• Primary In-flow corridor to the Tehachapi Pass, CAPrimary In-flow corridor to the Tehachapi Pass, CA
• Observational Targeting- Evaluating sites for Observational Targeting- Evaluating sites for strategic sensor to monitor horizontal & vertical datastrategic sensor to monitor horizontal & vertical data
Complex inland & marine-layer Complex inland & marine-layer interaction require higher interaction require higher
resolution vertical profile dataresolution vertical profile data
Identifying new monitoring Identifying new monitoring locations for remote locations for remote
sensors in addition to sensors in addition to existing towersexisting towers
Monitor 2
Optimal distance between monitoring
locations
Must Link and be of Value to System Operations
Decisions are based on a set of conditions
Wind adds additional variability to the set of conditions used in informing decisions
Decision makers (i.e. operators) need “a read” on the system prevailing conditions and come to a clear and worthwhile picture for action
Need appropriate information & tools
Set of Conditions
ON
OFF
Decision Response M A Y B E
Goal: Wind SENSE Capability for Control Rooms & Operations
Nutshell: Early
Warning System vs a Crystal Ball
Provide information to increase User Confidence & Awareness for resource utilization
* Teaming with CA, OR, Canada
60mi
32mi
Show Me the Wind
24
Inter-island Wind Components & Issues
Inter-island Wind
Wind Plant Development &
Performance=
Required wind plant forecasting and performance characteristics
Resource intermittency mitigation and management (e.g. energy storage requirements)
Adequate capacity factor yielding commercially reasonable pricing
Community acceptance of large wind plants
Wind Plant Issues
Undersea Cable Intertie
+
Sizing and selection (AC, DC) Cable system reliability and
configuration (e.g. mono-pole, bi-pole, spare cable, etc.)
Landing sites and footprint for converter station and supporting equipment
Ocean permitting and environmental issues
O&M responsibilities and operating agreement
Cable Issues
Oahu Integration & Infrastructure
+
Oahu Issues Maintain 60Hz frequency and
system stability Maintain adequate operating
reserves in response to wind Improve generator response Enhance system controls and
automated features Maintain reliable operations via
PPA commitments Community acceptance of new
T&D infrastructure
25
Cable System is Technically Feasible
Capacity
Distance
Depth
330 MW 1320 MW
400 MW 800 MW
4 Miles 360 Miles
40 MilesMolokai
20 Feet 5,200 feet
2,500 feet6,400 feetBig Island
80 MilesLanai
160 MilesBig Island
26
HVDC Cable Analysis/Configuration
Investigate detailed cable configuration and cost options
Modeling technical transfer capability and losses Determine reliability and contingencies Conduct economic trade-off analysis Refine price quotes and cost options
70 mi
40 mi
50 mi70 mi
40 mi
50 mi
Note: Schematics & Graphics for Illustrative Purposes Only
27
Timeline for Planning Resources
Project Design & Development (Financing)
Transmission Development Environmental (EIS) permitting &
Community Interaction Planning now to meet 2015, 2020 and
2030 RPS requirements
Illustrative Timeline for a Utility-Scale Renewable Project (Wind or Solar)
Year 3
Complete
Year 4 Year 5Year 1 Year 2
28
Investigating Routing OptionsUSDOE/DBEDT/Univ of Hawaii – SOEST
28
29
OWITS – Oahu Wind Integration & Transmission Studies
TCRPS – Transmission/ Cable Routing & Permitting Studies
Stage 1A: Oahu System Studies to Understand Impacts & Determine Feasibility
30
Phase I – System Model Development Flowchart
Source: GE Phase I
GE Phase I
Model
31
Accounting for Output Profiles for Different Generators
1.5
1.7
1.9
2.1
2.3
2.5
2.7
2.9
3.1
3.3
3.5
15:5
6:01
15:5
7:25
15:5
8:50
16:0
0:19
16:0
3:17
16:0
4:49
16:0
7:40
16:0
9:13
16:1
0:35
16:1
2:00
16:1
3:33
16:1
4:58
16:1
6:30
16:1
7:51
16:1
9:16
16:2
0:48
16:2
2:17
16:2
3:46
16:2
5:07
16:2
6:31
16:2
7:54
Pow
er (
MW
)
Time
Peaker Base Generation Intermittent (Wind)
Typical Output Profile for Different Generators
32
New Intra-hour Modeling Tools for System Planning
Led to new Intra-hour modeling tools created to bridge traditional Production Simulation and Dynamic Simulation to account for impact of Variable Wind and Solar resources
33
Oahu Wind Integration Study - Phase II Scenario Development (2014) & Mitigation Analysis
LanaiWind
MolokaiWind
OahuWind
Solar PV
--400MW100MWScenario # 3
-200MW-100MWScenario # 2
200MW
-
-
Molokai
SolarWindScenario
100MW
-
100MW
Oahu
200MW
-
-
Lanai
100MWScenario # 5
100MWScenario # 4
-Scenario # 1
Oahu
--400MW100MWScenario # 3
-200MW-100MWScenario # 2
200MW
-
-
Molokai
SolarWindScenario
100MW
-
100MW
Oahu
200MW
-
-
Lanai
100MWScenario # 5
100MWScenario # 4
-Scenario # 1
Oahu
• The solar component consists of a 60MW centralized plant, 20MW centralized plant, 5MW, centralized plant, and 15MW aggregation of distributed PV to provided to GE by HECO.>5MW utility scale PV
<5MW industrial/residential PV
50MW each wind
>5MW utility scale PV
<5MW industrial/residential PV
50MW each wind
Model a 20 MW PV facility
Model a 60 MW PV facility
Model large5 MW PV facility
Model 1-2 MW distributed PV clusters totaling 15 MW
Prelimary Resource Assumptions for Intermittency Impact Analysis
100 MW of Wind Solar component consists of
60 MW centralized plant 20 MW centralized plant 5 MW centralized plant 15 MW of distributed PV
34
Consideration of Mitigation Options
35
OWITS – Oahu Wind Integration & Transmission Studies
TCRPS – Transmission/ Cable Routing & Permitting Studies
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
SFigure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
Transmission & System Integration
16%
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
SFigure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
Transmission & System Integration
16%
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
SFigure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
System Operations & Controls
3%
Transmission & System Integration
16%
Transmission & System Integration
16%
Stage 1A: System Studies to Understand Impacts & Determine Feasibility
36
Ages of Generating UnitsAges of Generating Units
Unit Capability TypeOperating
ModeService
Date Age
Honolulu 8 56 Steam, Non-Reheat Cycling 1954 55Honolulu 9 57 Steam, Non-Reheat Cycling 1957 52Waiau 3 49 Steam, Non-Reheat Cycling 1947 62Waiau 4 49 Steam, Non-Reheat Cycling 1950 59Waiau 5 57 Steam, Non-Reheat Cycling 1959 50Waiau 6 56 Steam, Non-Reheat Cycling 1961 48Waiau 7 92 Steam, Reheat Base 1966 43Waiau 8 94 Steam, Reheat Base 1968 41Waiau 9 53 Combustion Turbine Peaking 1973 36Waiau 10 54 Combustion Turbine Peaking 1973 36Kahe 1 92 Steam, Reheat Base 1963 46Kahe 2 89 Steam, Reheat Base 1964 45Kahe 3 92 Steam, Reheat Base 1970 39Kahe 4 93 Steam, Reheat Base 1972 37Kahe 5 142 Steam, Reheat Base 1974 35Kahe 6 142 Steam, Reheat Base 1981 28
HPOWER 46 Steam, Non-Reheat Base 1990 19Kalaeloa 208 Combined Cycle Base 1991 18AES 180 Steam, Reheat Base 1992 17
Major Independent Power Producers
HECO Generating Units
Average age of HECO Base Load Steam Units 39.3 Years
Average age of HECO Cycling Steam Units 54.3 Years
37
Dynamic Response Study
Improving the dynamic responses of generating units on the HECO grid will facilitate the interconnection of greater amounts of variable generation with reduced amounts of other technologies to mitigate adverse operational impacts.
PREMISE
System Load/Frequency Response to Trip
39
Goal is to Achieve Coordinated Control Response from all Units within Limit as a Team
40
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
S
Figure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
Transmission & System Integration
16%
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
S
Figure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
Transmission & System Integration
16%
Model Development
System Conditions & Performance Characterization Studies
Scenario AnalysisUsing Model
Transmission Routing & Permitting
27%
Transmission Routing & Permitting
27%
Follow-on Implementation Tasks
TC
RP
SO
WIT
S
Figure 1. BIG WIND STUDIES – STAGE 1A Oahu/Molokai/Lanai
Scenario Development & Analysis
8%
GE PHASE 2
Scenario Development & Analysis
8%
GE PHASE 2
Electrical System Model Development & Validation
GE PHASE 1
11%
Electrical System Model Development & Validation
GE PHASE 1
11%
Environmental & Fuel Resource
1.4%
Environmental & Fuel Resource
1.4%
Generator Unit Response Enhancements
19%
Generator Unit Response Enhancements
19%
Steam Unit Cycling Capability
14%
Steam Unit Cycling Capability
14%
System Operations & Controls
3%
System Operations & Controls
3%
Transmission & System Integration
16%
Transmission & System Integration
16%
Stage 1A: System Studies to Understand Impacts & Determine Feasibility
41
Purpose of TCRPS
Support conceptual transmission planning Provide information for decision-making in HVDC
cable system planning Provide information to identify critical path
permitting & environmental reporting processes In parallel with OWITS to meet RPS goals
Transmission Planning
requirements
General transmission
corridors identified
Identify Project
Boundaries
Select HVDC landing sites & corridors
for study
Conduct technical studies
Reconcile technical & permitting
requirements
Conduct Due Diligence Studies
Consult with Permitting Agencies
Permitting & EIS
ProcessesNot part of PUC Docket No. 2009-0162
42
Undersea Cable Federal Permits - NEPA
State Permits – Chap. 343
Oahu Infrastructure State/County Permits – Chap. 343
Wind Farms Permits – EIS Processes
Permit Strategy & Considerations
43
Extruded Dielectric Cable Systems
1 - Conductor1 - Conductor2 - Inner Semi-Conductive Shield2 - Inner Semi-Conductive Shield3 - Extruded Solid Dielectric Insulation3 - Extruded Solid Dielectric Insulation4 - Outer Semi-Conductive Shield4 - Outer Semi-Conductive Shield5 - Semi-Conductive Swelling/Bedding Tapes5 - Semi-Conductive Swelling/Bedding Tapes6 - Concentric Copper Wire Metallic Shield6 - Concentric Copper Wire Metallic Shield7 - Semi-Conductive Swelling/Bedding Tapes7 - Semi-Conductive Swelling/Bedding Tapes8 - Moisture Barrier/Sheath8 - Moisture Barrier/Sheath9 - Protective Jacket9 - Protective Jacket
Typical Extruded Typical Extruded Dielectric Cable Dielectric Cable Cross-SectionCross-Section
Source: Power EngineersSource: Power Engineers
44
Transmission Line Construction Methods
Typical trench Typical trench excavation & excavation & duct bank duct bank installationinstallation
Typical horizontalTypical horizontal directional drilling set updirectional drilling set up
Typical manhole Typical manhole installationinstallation
Typical cable Typical cable pulling set uppulling set up
Source: Power EngineersSource: Power Engineers
45
Viability of Projects – Cost Analysis
How much will all this renewables costs?
Is Smart Grid the future and what will Hawaii’s Smart Grid look like?
Will this ensure reliability? What are the risks?
46
Summary
Adopting new tools & processes Application
H.U.I. – Involved in site reviews and awaiting funds to be allocated by DOE
DREEM & BESS – Awaiting announcement of award
Inter-island Wind - Early Stages Leveraging Resources from all
funding sources Building Relationships at All levels
via Communication
Some References
Areas of Active Research Other Utility Wind Research and Wind Ramp Tool Development Activities
1. http://powwow.risoe.dk/publ/JPease_(BPA)-BPAWindRampEventTrackingSystem_BestPracticeSTP-3_2009.pdf
2. http://cwec.ucdavis.edu/forum2003/proceedings/HawkinsD_CWEC2003.pdf
Industry Presentations of Needs1. http://www.esrl.noaa.gov/research/events/seas/Jan2009/Bailey_NREL-NCAR-
NOAA-SeminaronWindMeasurements-Jan09.pdf2. http://www.uwig.org/PHXForecastingworkshopagenda.pdf
WindSENSE Efforts in California1. http://www.bpa.gov/corporate/business/innovation/docs/2008/BPA_California
%20ISO%20LLNL.pdf2. https://str.llnl.gov/Mar09/yennakafuji.html
National Focus & Programs1. http://www.er.doe.gov/ASCR/ProgramDocuments/Docs/
CRNAREWorkshopReport.pdf2. http://www1.eere.energy.gov/windandhydro/
47
48
Mahalo
Questions/Comments??
For More Information:
Dora Nakafuji
Director, Renewable Energy Planning
Hawaiian Electric Company