WCCUSD Bond Program Construction Update Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014
11

Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Dec 14, 2015

Download

Documents

Nelson Hubbart
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

WCCUSD Bond Program

Construction UpdateHarding Elementary School

Exterior Repairs & Select Roofing Replacement08/12/2014

Page 2: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Harding Elementary SchoolExterior Repairs & Select Roofing

Replacement

Site Plan

Page 3: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

General Contractor Best Contracting Services,

Inc.

Architect of Record Grossman Design Group

Construction Manager Willie Robinson

Harding Elementary SchoolExterior Repairs & Select Roofing

Replacement

Project Team

Page 4: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Contract Amount $918,600

Notice of Award 06/17/14

Notice to Proceed 07/21/14

Duration 56 days

Completion Date 09/15/14

Harding Elementary SchoolExterior Repairs & Select Roofing

Replacement

Project Team

Page 5: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Contractor has mobilized & installed site

surveillance

Set up stairs & scaffolding to access roof

and walls for demolition

Demolition of exterior walls

Removal of windows on west side of

building A

Harding Elementary SchoolExterior Repairs & Select Roofing

Replacement

Project Status

Page 6: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Removal of Cement Plaster at Exterior Wall

Page 7: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Removal of Cement Plaster at Exterior Wall

Page 8: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Removal of Existing Window at Exterior Wall

Page 9: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Scaffold Installed at Rear Courtyard to Access Roof

Page 10: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Guardrail Installed at Lower Roof

Page 11: Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.

Play Yard Equipment Protection