Presented By: El Dorado County Community Development Agency, Transportation Division John Kahling, P.E. Deputy Director of Engineering Dwight Anderson, P.E. Associate Civil Engineer David Friestad Assistant in Civil Engineering Hank's Exchange Road Bridge Replacement Project Public Information Meeting, Wednesday, May 12, 2014 Gold Oak School 1
20
Embed
Hank's Exchange Road Bridge Replacement Project Projects... · 12/05/2014 · •Welcome and Introduction – John Kahling • County Bridge Program / Funding – John Kahling •
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Presented By:El Dorado CountyCommunity Development Agency, Transportation Division
John Kahling, P.E.Deputy Director of Engineering
Dwight Anderson, P.E.Associate Civil Engineer
David FriestadAssistant in Civil Engineering
Hank's Exchange Road Bridge Replacement Project
Public Information Meeting, Wednesday, May 12, 2014Gold Oak School
1
• Welcome and Introduction – John Kahling
• County Bridge Program / Funding – John Kahling
• Hank’s Exchange Bridge - Facts / Conditions –Dwight Anderson
• Project Overview – Dwight Anderson
• Open Question & Discussion Period
• County Staff Available to Answer Questions and Receive Public Input
Public Meeting Agenda
Hank's Exchange Bridge - Public Information Meeting, May 12, 2014 2
• 79 Bridges in County Bridge Inventory
• 21 are in 2013-14 Capital Improvement Program adopted February 11, 2014 http://www.edcgov.us/Government/DOT/CIP.aspx(see Section VIII: West Slope Projects)
• Included in the CIP – Hank’s Exchange Road at Squaw Hollow Creek – Bridge Replacement (CIP# 77135)
• Project is eligible for 100% reimbursement from the federal funding Highway Bridge Program (HBP)
County Bridge Inventory
Hank's Exchange Bridge - Public Information Meeting, May 12, 2014 3
Highway Bridge Program (HBP)
4
• Federal funding program for bridge safety projects -maintenance, rehabilitation and replacement
• Program authorized by Federal Highway Administration (FHWA) & administered by State DOT’s (CA – Caltrans)
• Requires Planning, Environmental, and Preliminary Engineering (PE) completed within 10 years of PE authorization date
• April 2012 – County received FHWA authorization to proceed with PE for Hank's Exchange at Squaw Hollow Creek – Bridge Replacement Project
• 100% Federal Participating Share - No Local Match(County General Fund will NOT be used)
Hank's Exchange Bridge - Public Information Meeting, May 12, 2014
Bridge Inspections / Sufficiency Ratings
5Hank's Exchange Bridge - Public Information Meeting, May 12, 2014
• Each bridge is thoroughly inspected by Caltrans every 2 years and rated on 140 elements
• Given a Sufficiency Rating (SR) score of 0 to 100
• Rating is overall measure of the bridge condition and sufficiency to remain in service
• Used to determine eligibility for federal funds and prioritization
• Rehab projects – cannot use any additional federal aid for 10 years.
• Replacement projects - bridge must be either functionally obsolete or structurally deficient.
Hank's Exchange Bridge - Public Information Meeting, May 12, 2014
Bridge Sufficiency Terminology
7Hank's Exchange Bridge - Public Information Meeting, May 12, 2014
Structurally Deficient:Limitations of the structural condition of the bridge, such as weight limits or load capacity.
Functionally Obsolete:Built to standards that are not used today, such as inadequate lane widths, shoulder widths, or vertical clearances to serve current traffic demand.
This status of this bridge is Functionally Obsolete.
Hank's Exchange Bridge Location
8Hank's Exchange Bridge - Public Information Meeting, May 12, 2014
• Year Built: 1930 (84 years old)• Expected life: 75 years• One-lane,13.5-foot wide x 22-foot span• Reinforced Concrete Slab • Avg. Daily Traffic: 1,245