HAMPTON ROADS DISTRICT PROJECT UPDATE James W. Utterback, PMP District Administrator
15

HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Sep 09, 2018

Download

Documents

doananh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

HAMPTON ROADS DISTRICT

PROJECT UPDATE

James W. Utterback, PMP

District Administrator

Page 2: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

ResidenciesResidencies•Accomac•Franklin•Williamsburg

District District OverviewOverview

9 Counties/12 Cities/2 Islands

• Approximately 825 positions

• Approximately 10,000 Total Lane Miles

Tunnels/Facilities

• I-64 Hampton Roads Bridge-Tunnel

Interstate Management Interstate Management

Office (IMO) Office (IMO) •TAMS Contract•Urban Construction

• I-64 Hampton Roads Bridge-Tunnel (HRBT)

• I-664 Monitor-Merrimac Memorial Bridge-Tunnel (MMMBT)

• Jamestown Scotland Ferry

• Transportation Operations Center (TOC)

Major Bridges

• James River Bridge

• High Rise Bridge

• Berkley Bridge

• Coleman Bridge

• Chincoteague Bridge

Page 3: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement
Page 4: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Interstate DInterstate D--B Pavement Rehabilitation B Pavement Rehabilitation

Route Project Description Est. Cost Projected Ad

I-64 &

I-264

Pavement Rehabilitation Design Build

(DB) - Norfolk

asphalt overlay of concrete pavements; 48

lane miles on I-64 and 19 lane miles on I-

264

$50 M July 2013

4

264

I-64 Pavement Rehabilitation Design Build

(DB) - Norfolk

asphalt overlay of 19 lane miles of

concrete pavement

$16 M July 2013

I-264 Pavement Rehabilitation Design Build

(DB) – Virginia Beach

asphalt overlay of 76 lane miles of

concrete pavement

$54 M July 2013

Total $120 M

Page 5: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects In ConstructionTransportation Projects In Construction

Gilmerton Bridge Replacement - $134 million in City of Chesapeake

• Replace 70 year old movable bridge

• Increase navigable clearance for Intercoastal Waterway

• Completion early 2014

5

Page 6: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects In ConstructionTransportation Projects In Construction

Dominion Boulevard Widening - $345 million in City of Chesapeake

• First Virginia Infrastructure Improvement Bank (VTIB) project

• Local Administration with VDOT support

• Completion mid-2014

6

Page 7: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects In ConstructionTransportation Projects In Construction

Middle Ground Boulevard - $38 million in City of Newport News

• Expedited design-build contract

• Provides critical north-south connection to growing City Center

• Completion late 2014

7

Page 8: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects In ConstructionTransportation Projects In Construction

Princess Anne Road - $28 million in City of Virginia Beach

• Widen the existing highway to a four-lane roadway

• Construct short section of Nimmo Parkway, providing a connector between

Princess Anne Road and Holland Road

• Completion Summer 2014

Page 9: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects In Construction Transportation Projects In Construction

George Washington Memorial Highway (U.S. 17) - $25.2 million in York County

• Increases the capacity from 4 to 6 lanes

• Includes a shared-use path parallel to the northbound lane

• Replaces two bridges over the Poquoson River with one 6 lane bridge

• Completion Winter 2016

Page 10: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects in DesignTransportation Projects in Design

I-64 High Rise Bridge Widening Study - $5 million in City of Chesapeake

• Expedited environmental

documentation study

• Widens from I-464 to I-664

10

I-64 Peninsula Widening Design-

Build - $100 million in City of

Newport News, James City

County, and City of

Williamsburg

• 5 miles of interstate expansion to

6-lanes

• Fort Eustis (Exit 250) to

Jefferson Avenue (Exit 255)

Page 11: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects in DesignTransportation Projects in Design

I-564 Intermodal Connector Design-Build -$157 million in City of Norfolk

• Interstate connection to Navy and Virginia

Port Piers

• Halfway point in Navy Triangle

Improvement Plan supporting Patriot’s

CrossingCrossing

11

Lesner Bridge Replacement - $84 million

in City of Virginia Beach

• Replacement of deteriorating NHS bridge

w/signature structure

• Local Administration with VDOT

support

Page 12: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

Transportation Projects Transportation Projects in Designin Design

Route 35 Bridge Replacement Design-

Build– $12 million in Courtland• Replaces Nottoway River Bridge

• 12-month desired CN schedule

12

Route 13 Military Highway CFI

Design-Build – $59 million in

City of Norfolk

• Combines three projects

• Widens to 6- and 8- lanes

• Completes widening of Route 13 to

I-64

Page 13: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

PPTA:PPTA:Downtown/Midtown/MLK, Portsmouth/ NorfolkDowntown/Midtown/MLK, Portsmouth/ Norfolk

LENGTH: 0.8 mile (Added Midtown)

1.2 miles (MLK Extension)

Martin Luther King Extension

- London Blvd to I-264

PROJECT: 2 Lanes Parallel Tube at

New, parallel two-lane tunnel

Refurbishment and safety

improvements

Brambleton Ave / Hampton Blvd interchange modifications

13

PROJECT: 2 Lanes Parallel Tube at

Midtown

4 Lanes Limited Access MLK

Upgrade Existing Tunnels

Rehab of Existing Tunnels

CURRENT STATUS:

Under Construction

Construction Completion Date: April 2018

Refurbishment and safety

improvements

Extending MLK to I-264, High St interchange

Page 14: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

PPTA: PPTA:

Route 460 Corridor, Suffolk/Isle of WightRoute 460 Corridor, Suffolk/Isle of Wight

CONSTRUCTION COST: $1.46 billion for

development, design, construction and right

of way acquisitions

LENGTH: 55 miles—Route 58 Suffolk to I-

295 Petersburg

14

295 Petersburg

PROJECT: 4 Lanes/median limited-access

highway on new alignment

CURRENT STATUS:

Under Design

Construction start late 2014 /early 2015

Construction Completion: December 2017

Page 15: HAMPTON ROADS DISTRICT PROJECT UPDATE · HAMPTON ROADS DISTRICT PROJECT UPDATE ... • Halfway point in Navy Triangle ... Transportation Projects in Design Route 35 Bridge Replacement

QuestionsQuestions

15