Integrated System For Building Survey And Evaluation Of Seismic Retrofit Possibilities M. Bostenaru Dan Institute for Technology and Management in Construction University of Karlsruhe, Germany
May 19, 2015
Integrated System For Building Survey And Evaluation Of
Seismic Retrofit Possibilities
M. Bostenaru Dan
Institute for Technology and Management in Construction
University of Karlsruhe, Germany
Outline
• Introduction
• Romanian building stock
• Building survey
• Retrofit elements for certain building types
• Scale of the study
• Conclusions
Romanian building stock
• Description of building types
• Available information
• Needed information
Structural systems Type of load bearing structure material Main type Subtype
wooden floor vaulted
horizontally laid
unreinforced
composite steel with bricks vaulted
Masonry brick
reinforced with vertical posts and concrete floor slabs beam – column associations moment resisting frame with URM infill with soft storey
light concrete with concrete infill unreinforced concrete
without soft storey
frame
frame with concrete shear walls – dual systems wall “ fagure” with soft storey precast wall panes cellular without soft storey
Structural concrete
shear wall
spatial elements (made in Craiova) [5] moment resisting frame Steel lightweight
Building survey
• 1st Case: seen retrofit elements
• 2nd Case: seen hints in other elements
• 3rd Case: no hints but architectural style
• else
Seen retrofit elements on brand walls
Figure 5: visible vaults
Figure 4: Visible RC frames with diagonal bracing
Figure 3: Visible RC frames
Unfinished structures
Figure 6: RC frame with reversed
beams
Figure 7: RC frame with light
concrete infill
Figure 8: RC frame with masonry infill
Building physics hints
Figure 9: Column, thermo-
isolated with masonry
Figure 10: Column not thermo-
isolated
Figure 11: Masonry wall
Retrofit elements for certain building types
• Retrofit elements in building survey
• Retrofit elements in project management
• Retrofit elements in costs calculation
• Economic efficiency
Units from which retrofit elements are derived
Type Subdivision level #1 #2: element #3 : unit
Load bearing direction
Soft story column linear column
punctual
Frame Normal storey frame
beam
3D net
Pier One side Lintel field
opening
Wall
Other side
Wall Element
Wall
Vertical elements
One floor Room
area
floor Other floor
Floor element (also out of composite materials) balconies
Horizontal elements
Dividing building
framecorner
punctualstructure
addbracing
disipationelement
simpleframes
frame bracing
frameswith bracing
frames
linear structure
addshearwall
frameswith infill
concrete steel
manteling
column
boundaryelements
beam
columns& beams
soft storey
combination:linear
flat
interior exterior
reinforcing
openings piers lintels fields
FRP carbonfibre
glasfibre
reinforcedconcrete
manteling
structural walls
slab vaults composite
floors
flat structures
constructive element
Tasks assessmentID Task Name Duration Predecessors
14 Building up and removing drop tub 4th floor4 hrs 6
15 Building up and removing drop tub 6th floor4 hrs 8
16 Building up and removing drop tub 5th floor4 hrs 7
17 Knocking off the masonry wall 33 hrs
18 Knocking off the masonry wall 1st floor23 hrs 11
19 Knocking off the masonry wall 2nd floor23 hrs 12
20 Knocking off the masonry wall 3rd floor23 hrs 13
21 Knocking off the masonry wall 4th floor23 hrs 14
22 Knocking off the masonry wall 5th floor23 hrs 16
23 Knocking off the masonry wall 6th floor23 hrs 15
24 Breaking through the slab 12,5 hrs
31 Cleaning up the masonry 8 hrs? 15
32 Anchoring the reinforcement 20 hrs
39 Formwork 13 hrs
46 Concrete casting 11,5 hrs
53 Removing formwork 12 hrs
60 Removing scaffolding 12 hrs
67 Side 2 70 hrs?
T W T F S S M21 Oct '02 28 Oct '02
: Integration of design tasks
Identifyelements
Assessstructural
type
Calculatecosts
Assessperformance
?Economicefficiency
Conclusions
• building divided into small, manageable entities, called „ retrofit elements“
• „ retrofit elements“ serve as units for– typological classification– modelling for numerical simulation– assignement of tasks for costs calculation
• units defined at the begin of design process = integrated system