Hal Tompkins Photon Systems [email protected] d.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory Committee October 29, 2007 Hal Tompkins LCLS Photon Systems Deputy Manager
25

Hal Tompkins Photon [email protected] October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Dec 22, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 1

LCLS Photon Systems Installation and Commissioning

Presentation to Facility Advisory Committee October 29, 2007

Hal Tompkins

LCLS Photon Systems Deputy Manager

Page 2: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 2

Important Dates

Beam Dump Co-occupancy - 12/5/07

FEE and NEH Co-occupancy - 12/21/07

FEE and NEH Beneficial Occupancy - 3/21/08 (NEH elevator - 4/08?)

X-Ray Transport Tunnel Co-occupancy - 1/08/08

FEH Co-occupancy - 3/24/08

Tunnel/FEH Beneficial Occupancy - 6/23/08

Page 3: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 3

FEE Layout

Page 4: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 4

NEH Layout

Page 5: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 5

Page 6: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 6

Beam Dump Installation

Electron beam dump installations are critical.

Must install two electron-photon stopper systems, fast shutter, collimator, penetration tube, and backfill steel and concrete in Muon Wall 1.

Expect to certify PPS though electron beam dump in 10/09.

This allows electrons into BTH, UH, etc.

Page 7: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 7

Page 8: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 8

FEE Installation

Fixed Mask, Adjustable Slits, Gas Detectors, and Gas Attenuator make up phase 1 (June 11-July 1, 2008).

Calorimeter, K-spectrometer, Soft X-ray imager, and Direct imager make up phase 2 (July 2-23, 2008).

Soft x-ray Offset Mirror System (SOMS) is phase 3 (Jan. 16-Feb. 5, 2009).

Note the gap between phase 2 and phase 3. This is driven by deferring purchase of the FEE Mech/Vac (mainly collimators) and pop-in monitors to FY09 for budgetary reasons. It is not driven by delivery date of SOMS mirror substrates.

Hard x-ray Offset Mirror System (HOMS) is phase 4. This is close to being delivery-date dependent (Feb. 6-26, 2009).

PPS/BCS installed by 2/09.

Page 9: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 9

NEH Installation

Vacuum transport through hutches 1 and 2 will be installed.

Anticipate LUSI will handle vacuum transport in hutch 3.

XES laser installation begins with NEH B.O. and is expected to be complete in 5/09. Commissioning the laser diagnostics and controls follows immediately afterwards.

AMO experiment installation begins with NEH B.O. and is slated to be complete in 7/09.

Page 10: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 10

Page 11: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 11

Tunnel/FEH Installation

X-Ray Tunnel and Far Experimental Hall component purchases also delayed until FY09.

FEH hutch construction estimated at 8-9 months.

Page 12: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 12

Page 13: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 13

Page 14: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 14

FEL Commissioning Timeline

Page 15: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 15

Commissioning

Nominal first beam to FEE is 5/14/09

Commission the X-ray diagnostics simultaneously with commissioning the undulator.

Start with Direct Imager, then move on to Adjustable Slits, Gas Detectors, the Attenuators, and the Calorimeter.

Then do K-spectrometer and Soft X-ray Imager.

Align and characterize the spontaneous radiation beam

Measure photon flux per pulse

Find SASE and optimize gain (first at low energy)

Deliver beam through offset mirror systems to experiments in NEH hutches.

Page 16: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 16

Commissioning

Stabilize FEL for User Run

User Run

SLAC shutdown

Recommission upstream pieces of LCLS

If ready, transport x-rays into Tunnel and Far Hall

Detect x-rays in Far Hall - complete CD 4

Continue working on lasing at higher energies

Alternate machine work with experiments

Page 17: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 17

Summary

Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations.

Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations.

We think we have a good shot at lasing at 1.5 nm for the User Run - stability is a bigger question.

Operation at .15 nm for the User Run will likely be with spontaneous radiation.

Page 18: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 18

End of Presentation

Page 19: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 19

Detailed FEE Vacuum Installation Schedule

Install vacuum system 65d Thu 3/27/08 Wed 6/25/08

install fixed mask/valve 3d Thu 3/27/08 Mon 3/31/08

align fixed mask/valve 2d Tue 4/1/08 Wed 4/2/08

install slit system 4d Tue 4/1/08 Fri 4/4/08

align slit system 2d Mon 4/7/08 Tue 4/8/08

install attenuators/gas detectors 8d Mon 4/7/08 Wed 4/16/08

install K-spectrometer 2d Thu 4/17/08 Fri 4/18/08

align attenuators/gas detectors 4d Thu 4/17/08 Tue 4/22/08

install calorimeter 3d Mon 4/21/08 Wed 4/23/08

align K-spectrometer 1d Wed 4/23/08 Wed 4/23/08

align calorimeter 1d Thu 4/24/08 Thu 4/24/08

install direct imager 2d Thu 4/24/08 Fri 4/25/08

install isolation valve 0.5d Mon 4/28/08 Mon 4/28/08

align direct imager 1d Mon 4/28/08 Mon 4/28/08

install differential pumping section 1d Mon 4/28/08 Tue 4/29/08

install collimator C1 0.5d Tue 4/29/08 Tue 4/29/08

align diff. pump. section 1d Tue 4/29/08 Wed 4/30/08

install SOMS M1S 2d Wed 4/30/08 Thu 5/1/08

align collimator C1 0.5d Wed 4/30/08 Wed 4/30/08

Page 20: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 20

Detailed FEE Vacuum Installation Schedule (cont.)

align SOMS M1S 1d Fri 5/2/08 Fri 5/2/08install HOMS M1H 2d Fri 5/2/08 Mon 5/5/08install SOMS M2S 2d Fri 5/2/08 Mon 5/5/08align HOMS M1H 1d Tue 5/6/08 Tue 5/6/08install collimators C2S 1d Tue 5/6/08 Tue 5/6/08align collimators C2S 0.5d Wed 5/7/08 Wed 5/7/08install HOMS C2H 0.5d Wed 5/7/08 Wed 5/7/08align SOMS M2S 1d Wed 5/7/08 Wed 5/7/08install HOMS M2H 2d Wed 5/7/08 Fri 5/9/08align HOMS C2H & M2H 1d Fri 5/9/08 Mon 5/12/08

install FEE/NEH beam pipes (3) 2d Fri 5/9/08 Tue 5/13/08align FEE/NEH beam pipes (3) 1d Tue 5/13/08 Wed 5/14/08backfill wall 1 window 10d Wed 5/14/08 Wed 5/28/08

install C3H, C3S1, & C3S2 collimators 2d Wed 5/28/08 Fri 5/30/08align C3H, C3S1, & C3S2 collimators 1d Fri 5/30/08 Mon 6/2/08

Page 21: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 21

Detailed FEE Vacuum Installation Schedule (cont.)

fix collimator positions per RP 2d Mon 6/2/08 Wed 6/4/08

install HXR stoppers 3d Mon 6/2/08 Thu 6/5/08

Install SXR stoppers 3d Thu 6/5/08 Tue 6/10/08

install HXR diff. pump. Section 0.5d Tue 6/10/08 Tue 6/10/08

align HXR & SXR stoppers 1d Tue 6/10/08 Wed 6/11/08

install SOMS M3S & M4S 3d Wed 6/11/08 Fri 6/13/08

install isolation valves 3d Mon 6/16/08 Wed 6/18/08

align isolation valves 1d Thu 6/19/08 Thu 6/19/08

install vacuum piping 2d Thu 6/19/08 Fri 6/20/08

install shadow wall 3d Mon 6/23/08 Wed 6/25/08

install ion pumps 3d Mon 6/23/08 Wed 6/25/08

Page 22: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 22

Task duration start date end date predecessor

* Commission XES laser 105d Thu 5/8/08 Wed 10/1/08

laser installation complete 0d Thu 5/8/08 Thu 5/8/08

commission laser with vendor 45d Thu 5/8/08 Wed 7/9/08 2

commission laser diagnostics 60d Thu 7/10/08 Wed 10/1/08 3

commission laser controls-pointing stability 60d Thu 7/10/08 Wed 10/1/08 3

* Integrate with AMO experiment 212d Thu 10/2/08 Fri 7/24/09

commission compressor/hutch diagnostics 50d Thu 10/2/08 Wed 12/10/08 5

laser to high field chamber 50d Thu 12/11/08 Wed 2/18/09 7

laser to AMO experiment 50d Thu 2/19/09 Wed 4/29/09 8

LBNL timing system avail 0d Mon 6/1/09 Mon 6/1/09

integrate laser/fast timing system 40d Mon 6/1/09 Fri 7/24/09 10

1st beam to FEE 0d Fri 5/15/09 Fri 5/15/09

RP measurements in FEE, NEH 5d Fri 5/15/09 Thu 5/21/09 12

* Commission Direct Imager 13.3d Fri 5/22/09 Wed 6/10/09

insert imager into beam 1d Fri 5/22/09 Fri 5/22/09 13

RP measurements in NEH 0.5d Mon 5/25/09 Mon 5/25/09 15

calibrate image height 2.4d Mon 5/25/09 Wed 5/27/09 16

characterize camera 2.4d Wed 5/27/09 Mon 6/1/09 17

measure beam position 2d Mon 6/1/09 Wed 6/3/09 18

Characterize FEE slit operation 3d Wed 6/3/09 Mon 6/8/09 19

measure position jitter (spontaneous) 2d Mon 6/8/09 Wed 6/10/09 20

Commissioning Schedule

Page 23: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 23

* Commission Gas Detectors 10d Wed 6/10/09 Wed 6/24/09

insert/align differential pump apertures 4d Wed 6/10/09 Tue 6/16/09 21

Add gas to upstream chamber 1d Tue 6/16/09 Wed 6/17/09 23

Measure detector response time, noise 2d Wed 6/17/09 Fri 6/19/09 24

Add gas to downstream chamber 1d Fri 6/19/09 Mon 6/22/09 25

Measure detector response time, noise 2d Mon 6/22/09 Wed 6/24/09 26

* Commission Attenuators 4.5d Wed 6/24/09 Tue 6/30/09

Insert Be attenuators 1d Wed 6/24/09 Thu 6/25/09 27

Add gas to gas attenuator 1d Thu 6/25/09 Fri 6/26/09 29

RP measurements in NEH 0.5d Fri 6/26/09 Fri 6/26/09 30

Check absorption, reproducibility 2d Fri 6/26/09 Tue 6/30/09 31

* Commission Calorimeter 8.5d Tue 6/30/09 Mon 7/13/09

motion tests 1d Tue 6/30/09 Wed 7/1/09 32

cool detector, laser calibration 2d Wed 7/1/09 Fri 7/3/09 34

insert into beam 1d Fri 7/3/09 Mon 7/6/09 35

RP measurements in NEH 0.5d Mon 7/6/09 Tue 7/7/09 36

measure time constants 2d Tue 7/7/09 Thu 7/9/09 37

calibrate gas detectors/direct imager 2d Thu 7/9/09 Mon 7/13/09 38

* Commission Undulator K spectrometer 6.5d Mon 7/13/09 Tue 7/21/09

translate crystal into beam 1d Mon 7/13/09 Tue 7/14/09 39

RP measurements 0.5d Tue 7/14/09 Tue 7/14/09 41

measure spectrum from single undulator 5d Tue 7/14/09 Tue 7/21/09 42

* Commission Soft X-Ray Imager 5d Tue 7/21/09 Tue 7/28/09

translate multilayer into beam 1d Tue 7/21/09 Wed 7/22/09 43

characterize camera image 4d Wed 7/22/09 Tue 7/28/09 45

Commissioning Schedule (cont.)

Page 24: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 24

* Commission Soft X-Ray (SXR) Mirror 10d Tue 7/28/09 Tue 8/11/09

insert 1st mirror, verify beam on monitor 3d Tue 7/28/09 Fri 7/31/09 46

insert 2nd mirror, vertify beam on monitor 3d Fri 7/31/09 Wed 8/5/09 48

insert 3rd mirror, verify beam on monitor 3d Wed 8/5/09 Mon 8/10/09 49

RP measurements in NEH 1d Mon 8/10/09 Tue 8/11/09 50

* Commission AMO experiment 15d Tue 8/11/09 Tue 9/1/09

beam to high field chamber 5d Tue 8/11/09 Tue 8/18/09 51

beam to KB optics 5d Tue 8/18/09 Tue 8/25/09 53

commission diagnostics chamber 5d Tue 8/25/09 Tue 9/1/09 54

* User Run 22d Tue 9/1/09 Wed 9/30/09

FEE support during user run 22d Tue 9/1/09 Wed 9/30/09

* Commission Hard X-Ray (HXR) Mirror 7d Thu 10/1/09 Fri 10/9/09

insert 1st mirror, verify beam on monitor 3d Thu 10/1/09 Mon 10/5/09 56

insert 2nd mirror, verify beam on monitor 3d Tue 10/6/09 Thu 10/8/09 59

RP measurements 1d Fri 10/9/09 Fri 10/9/09 60

* Pump-probe experiment commissioning 30d Thu 10/1/09 Wed 11/11/09

coordinate laser with fast timing 30d Thu 10/1/09 Wed 11/11/09 56

* CXI experiment commissioning 30d Thu 10/1/09 Wed 11/11/09

commission array detector 30d Thu 10/1/09 Wed 11/11/09 56

* AMO experiment commissioning 90d Thu 10/1/09 Wed 2/3/10

continue timing characterization 30d Thu 10/1/09 Wed 11/11/09 56

continue detector characterization 30d Thu 11/12/09 Wed 12/23/09

continue particle injector characterization 30d Thu 12/24/09 Wed 2/3/10 68

* SLAC 2009 shutdown 45d Sun 11/1/09 Fri 1/1/10

Commissioning Schedule (cont.)

Page 25: Hal Tompkins Photon Systemstompkins@slac.stanford.edu October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Hal Tompkins

Photon Systems [email protected]

October 30, 2007 25

* Transport beam to Far Hall 27.5d Mon 1/4/10 Wed 2/10/10

first beam into tunnel 20d Mon 1/4/10 Fri 1/29/10 70

transport beam through tunnel 5d Mon 2/1/10 Fri 2/5/10 72

detect beam in CXI hutch 2d Mon 2/8/10 Tue 2/9/10 73

RP measurements 0.5d Wed 2/10/10 Wed 2/10/10 74

complete CD 4 requirements 0d Wed 2/10/10 Wed 2/10/10 75

* FEL optimization 82d Wed 2/10/10 Fri 6/4/10

characterize energy jitter 3d Wed 2/10/10 Mon 2/15/10 76

measure spectrum from each undulator 8d Mon 2/15/10 Thu 2/25/10 78

measure spectra pairwise, set K 10d Thu 2/25/10 Thu 3/11/10 79

RP measurements in FEE, NEH 1d Thu 3/11/10 Fri 3/12/10 80

search for 8 keV lasing 60d Fri 3/12/10 Fri 6/4/10 81