Top Banner
Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved. Development of Preliminary Scenarios for Rural Electrification with Cost Estimation of Micro-grid in Myanmar HAJIME SASAKI NOBUO HASHIMOTO Policy Alternatives Research Institute, The University of Tokyo. Workshop on the Future Direction of Rural Electrification in Myanmar At Department of Rural Development, The Ministry of Livestock, Fisheries and Rural Development, NayPyiTaw [Session 2: The UT‘s Research] Cost Estimation in Rural Areas in Myanmar by UT
18

HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Apr 20, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Development of Preliminary Scenarios for Rural Electrification with Cost Estimation of Micro-grid in Myanmar

HAJIME SASAKI NOBUO HASHIMOTO Policy Alternatives Research Institute, The University of Tokyo.

Workshop on the Future Direction of Rural Electrification in Myanmar At Department of Rural Development, The Ministry of Livestock, Fisheries and Rural Development, NayPyiTaw [Session 2: The UT‘s Research] Cost Estimation in Rural Areas in Myanmar by UT

Page 2: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Introduction n  According to our estimation based on JICA’s master plan, the target is to electrify 70% by 2030. ¨  434MW should be provided by micro-grid.

n  Not only grid extension but off-grid electrification.

High case Low case High case Low case High case Low case High case Low case

1,666 2,075 2,075 5,650 4,690 3,840 10,590 8,600 6,040 19,217 15,477 9,414

173 216 216 522 433 355 908 738 518 1,530 1,232 750

60 50 40 75 65 55 90 80 7069 67 65 91 87 82 100 95 90

18 56 43 29 68 56 43 86 74 61

Whole country 26Electrification ratio (%)

Urban area Rural area

45

PopulationkWh per capita

66,014,65850,495,377 56,882,668 61,278,788Demand (MW)

Demand in 2025

MOEPforecast

JICA forecastDemand in 2030

MOEPforecast

JICA forecastDemand in 2012

MOEPforecast

JICA forecastState/Region

Demand in 2020

MOEPforecast

JICA forecast

High case Low case High case Low case High case Low case High case Low case

1,666 2,075 2,075 5,650 4,690 3,840 10,590 8,600 6,040 19,217 15,477 9,414

173 216 216 522 433 355 908 738 518 1,530 1,232 750

60 50 40 75 65 55 90 80 7069 67 65 91 87 82 100 95 90

18 56 43 29 68 56 43 86 74 61

Whole country 26Electrification ratio (%)

Urban area Rural area

45

PopulationkWh per capita

66,014,65850,495,377 56,882,668 61,278,788Demand (MW)

Demand in 2025

MOEPforecast

JICA forecastDemand in 2030

MOEPforecast

JICA forecastDemand in 2012

MOEPforecast

JICA forecastState/Region

Demand in 2020

MOEPforecast

JICA forecast

2

Page 3: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Research Questions and Methodology

n  Research Questions ¨ How much does it cost to electrify rural area in whole country.

¨ Explore implications of the national electrification rate target of 70% by 2030

n  Methodology: ¨ Demand Projection (Mr. Seino has presented)

¨ Cost Estimation ¨ Development of Preliminary Scenarios

Source: http://www.asean.fta.govt.nz/myanmar-overview 3

Page 4: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Framework of this Research

4

(2)  Cost  Estimation  

(1)   Demand  Projection

(3)  Development  of  Preliminary  Scenarios

Simulate•  Optimal  system  design  for  representative  demand  casesEstimate•  Minimum  cost  for  Off-‐‑‒grid  electrification(using  “HOMER®“  for  calculations)

Estimate•  Setting  target  electrification  rate  (On-‐‑‒grid  +  Off-‐‑‒grid)  

•  Medium  voltage  distribution  line  area  →  Projection  of  electrification  area  (On-‐‑‒grid・Off-‐‑‒grid)

•  The  number  of  electrified  villages  and  demand  projection  (Off-‐‑‒grid)

Estimate•  Total  cost  to  meet  off-‐‑‒grid  demand

Renewable  energy  potential

Costs  of  power  generation  technologies,  etc.

Costs  of  fuel,  etc.

Population

Achievements  of  rural  electrification  in  

neighboring  countries

Power  supply  plan  High  voltage  transmission  lines  extension  plan  

Page 5: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Framework of this Research

5

(2)  Cost  Estimation  

(1)   Demand  Projection

(3)  Development  of  Preliminary  Scenarios

Simulate•  Optimal  system  design  for  representative  demand  casesEstimate•  Minimum  cost  for  Off-‐‑‒grid  electrification(using  “HOMER®“  for  calculations)

Estimate•  Setting  target  electrification  rate  (On-‐‑‒grid  +  Off-‐‑‒grid)  

•  Medium  voltage  distribution  line  area  →  Projection  of  electrification  area  (On-‐‑‒grid・Off-‐‑‒grid)

•  The  number  of  electrified  villages  and  demand  projection  (Off-‐‑‒grid)

Estimate•  Total  cost  to  meet  off-‐‑‒grid  demand

Renewable  energy  potential

Costs  of  power  generation  technologies,  etc.

Costs  of  fuel,  etc.

Population

Achievements  of  rural  electrification  in  

neighboring  countries

Power  supply  plan  High  voltage  transmission  lines  extension  plan  

Page 6: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Framework of this Research

6

(2)  Cost  Estimation  

(1)   Demand  Projection

(3)  Development  of  Preliminary  Scenarios

Simulate•  Optimal  system  design  for  representative  demand  casesEstimate•  Minimum  cost  for  Off-‐‑‒grid  electrification(using  “HOMER®“  for  calculations)

Estimate•  Setting  target  electrification  rate  (On-‐‑‒grid  +  Off-‐‑‒grid)  

•  Medium  voltage  distribution  line  area  →  Projection  of  electrification  area  (On-‐‑‒grid・Off-‐‑‒grid)

•  The  number  of  electrified  villages  and  demand  projection  (Off-‐‑‒grid)

Estimate•  Total  cost  to  meet  off-‐‑‒grid  demand

Renewable  energy  potential

Costs  of  power  generation  technologies,  etc.

Costs  of  fuel,  etc.

Population

Achievements  of  rural  electrification  in  

neighboring  countries

Power  supply  plan  High  voltage  transmission  lines  extension  plan  

Page 7: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Equation for calculating minimum NPC

Total Net Presented Cost(NPC) [USD] required for Rural Electrification by 2030

=N of Micro-grid|case1× Unit Cost/Micro-grid|case1 +N of Micro-grid|case2× Unit Cost/Micro-grid|case2 +N of Micro-grid|case3× Unit Cost/Micro-grid|case3 +N of Micro-grid|case4× Unit Cost/Micro-grid|case4 +N of Micro-grid|case5× Unit Cost/Micro-grid|case5 +N of Micro-grid|case6× Unit Cost/Micro-grid|case6

7

Low case 70%

Middle case 20%

High case 10%

Page 8: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

(2)Cost Estimation - Boundary Condition

3 Cases (Load Level) ・Low Case(Case 1 and 2) ・Middle Case(Case 3 and 4) ・High Case(Case 5 and 6)

(1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

2 Cases (Environment)

・Without Hydro potential (Case 1, 3 and 5)

・With Hydro potential (Case 2, 4 and 6)

× =

6 Cases

Village

Micro grid

River

0"

200"

400"

600"

800"

1000"

1200"

1400"

1" 2" 3" 4" 5" 6" 7" 8" 9" 10"11"12"13"14"15"16"17"18"19"20"21"22"23"24"

Daily&Loa

d&Cu

rve&pe

r&Unit&M

icro&grid

&[&K

wh&]&�

Middle"Case"(Case3"and"Case4)�

High"Case"(Case5"and"Case6)�

Time"�

Low"Case"(Case1"and"Case2)�

90% of whole Micro grids in Myanmar (No evidential data)

10% of whole Micro grids in Myanmar (No evidential data)

8

Page 9: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Components

• Photovoltaic(PV) • Diesel Generator • Biogas Generator • Battery • Converter • Hydro Generator

(2)Cost Estimation - Boundary Condition (1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

Only for Case 2, 4 and 6

For All Cases

→Seek for an optimal (minimum cost) configuration for each micro grid.

9

Page 10: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

(2)Cost Estimation - Boundary Condition (1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

Characteristics PV module Hydro turbine Diesel GeneratorModel Typical Mini hydro Typical

Power 1kWp 151kW 50 kWLife time 20 years 25 years 20 yearsPrice 2250 USD/kW 4000 USD/kW 15000 USD/50kWReplacement 1500 USD/kW 4000 USD/kW 8000 UDS/50kWMaintenance[/year] 2 USD/kW 80 USD/kw 0.7 USD/hr/50kWInstall Unit 10 kW 1 unit 10 kW

Adapted Source: Author edited refer from Lipu, et al., (2013).

Technical Specification of Composite Power Sources (1)

10

Page 11: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

(2)Cost Estimation - Boundary Condition (1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

CharacteristicsModel

PowerLife timePriceReplacementMaintenance[/year]Install Unit

Biogas Generator Battery ConverterRH-3 Trojan T-105 Typical

Nominal voltage 6VNominal capacity 225 Ah 1kWLietime throughput 845 kWh 20 years

2300 USD/6kW 225 USD/battery 400 USD/kW1700 USD/6kW 200 USD/battery 250 USD/kW0.01 USD/10kW 1 USD/battery 1 USD/kW10 kW 10 unit 10 kW

Reference Source: Author edited refer from Lipu, et al., (2013).

Technical Specification of Composite Power Sources (2)

11

Page 12: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Source: Tiet et al. (2008)

(1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

Amount of Sunlight

12

Page 13: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Boundary Condition - Hydro Power Potential

(1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

Source: The Institute of Electrical Engineers of Japan. (2001).

13

Page 14: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Biogas potential

Source: The Institute of Electrical Engineers of Japan (2001)

The daily production: 123 kg / day (Average)

14

State / Division

Population in 1997

Paddy Production Rice Husk Production

Potential Energy

Potential Power in 1996-1997 par capita

1,000 1000 ton kg 1,000 ton GWh kW

Ayeyarwady Division 6,436 5,894 916 1,179 94 43,060

Bago Division 4,848 2,930 604 586 47 21,420

Yangon Division 5,295 1,623 306 325 26 11,870

Shan State 4,629 942 203 188 15 6,890

Union Total 46,402 17,397 375 3,480 278 127,120

・・・

・・・

・・・

・・・

・・・

・・・

・・・

Page 15: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

(3) Scenario Preparation Total cost for micro-grid installation in off-grid electrification

(1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

Capital Cost: 2,004 M USD Operating Cost: 5,632 MUSD

Caveats: the results depend on: hydro availability, technology costs (e.g., PV), rather large demand, coarse data resolution

15

Component ofmicro-grid

Capital cost Operating cost Total1 PV+Dies+Biog+Bat+Con 638 1,482 2,1202 PV+Dies+Biog+Bat+Con 71 165 2363 PV+Dies+Biog+Bat+Con 458 1,729 2,1874 Hydro+Bat +Con 192 11 2035 PV+Dies+Biog+Bat+Con 544 2,229 2,7736 Hydro+Dies+ Biog+Bat+Con 101 16 117

126,387 355,197 481,5843,891 10,936 14,827

2,004 5,632 7,636

US$ per micro-gridUS$ per kW

Total

CaseElectrification cost (MUS$) by 2030

Page 16: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Summary

n  (1) Demand Projection of Rural Area ¨  To achieve 70% electrification, 434MW should be provided by micro-grid.

n  (2) Cost Estimation ¨  Unit micro grid cost is estimated at 0.2M USD - 2M USD depending on configurations.

n  (3) Development of Preliminary Scenarios ¨ We tentatively estimated total cost(inc. capital and operation costs ) at 7.6 Billion USD for rural electrification for approx.16,000 micro-grids.

(1)Demand Projection (2) Cost Estimation (3) Scenario Preparation

16

Page 17: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Future Work & Our Proposal

n  This result is tentative. n  Produce multiple scenarios that take priorities into account.

n  Need to Improve data. ¨ Potential data for Hydro Power ¨ Potential data for Biogas ¨ Specification data for Compositions. Such as

n Diesel Generations. n  Batteries and Converters.

17

Page 18: HAJIME SASAKI NOBUO HASHIMOTO - 東京大学

Copyright (C) 2014 Policy Alternatives Research Institute, All Rights Reserved.

Information to Improve Our study and to Contribute for Myanmar’s Electrification.(from Mr.Seino’s presentation)

18

•  Current national census data and •  Geospatial data of villages •  Current data of household and village

electrification rates and demand •  Geospatial data of current and future plan

of transmission line and sub-station •  Standard connection method of HV line and

MV line •  Data of existing and planned small hydro

power •  Data of existing diesel power