Hacienda Avenue Green Street Improvement Project City of Campbell
Project Funding
State Department of Water Resources (DWR), Integrated Regional
Water Management Grant Program (IRWMP)
$2,000,000
Federal Transportation Enhancement (TE) , VTA Community Design &
Transportation (CDT)
$544,000
Local Capital Improvement Program (CIPR)
$1,500,000
Other Partners SCVURPPP
San Francisco Estuary Partnership (SFEP)
Design
Design Elements Road Diet
Street Re-grading
Bio-Infiltration Areas
Bulb-Outs
Sidewalk Infill
Bicycle Lanes
LED Streetlights
Full Depth Rehabilitation
New Street Standard
New Developments are Required to Implement
Green Street Design on Hacienda Avenue
Storm Water Treatment
Treatment Details Sized Using SCVURPPP Methodology
Combination Flow and Volume Approach
Total Project Drainage Area = 18 acres
63 Individual Drainage Areas
Capturing 0.95 ac-ft of runoff
(Greater than 80% of the
average annual rainfall-
project wide)
Storm Water Treatment (cont’d)
Bio-Infiltration Areas
3 ft Deep Section
3:1 Side Slopes
Overflow Pipes
Perc. at 4 inch/hr
Water Monitoring
San Francisco
Estuary Institute
(SFEI)
Community Outreach
Community Meetings Preliminary Conceptual Design
Final Conceptual Design
Landscape Design
Mailers
Website Provide Updates
Submit Questions
Certifications
Bay Friendly Grant Requirement
Promotes Sustainable
Landscape Design
Greenroads Sustainability Rating System for Roads
Points Awarded for:
Treatment of Runoff
Reduction of Light Pollution
Material Recycling
Using Regional Materials…
Project Status
Plans and Specs are complete
Received Approval from City Council and
Caltrans
Utility Work has begun
Award Contract in June
Construction to begin in July/August
1 year to complete project