After 50 years, Madison Square Garden’s (MSG) special arena permit has expired, presenting NYC with an opportunity to rethink Midtown. Under the NYC Planning Commission’s standard practice, a new permit would allow MSG to operate on top of Penn Station in perpetuity. This could permanently preclude any significant improvement to the transit hub, saddling future generations with a failed Penn Station. MAS invited some of New York’s most well-known and respected design firms to re-envision New York’s Penn Station – the busiest train station in North America – and Madison Square Garden.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: H3 Design Challenge Presentation

The time is now.

Page 2: H3 Design Challenge Presentation

How do we improve the lives of a million

people each day?

Page 3: H3 Design Challenge Presentation
Page 4: H3 Design Challenge Presentation
Page 5: H3 Design Challenge Presentation
Page 6: H3 Design Challenge Presentation
Page 7: H3 Design Challenge Presentation
Page 8: H3 Design Challenge Presentation
Page 9: H3 Design Challenge Presentation

These people and a million more use, live and work near Penn Station every day. How can we make something so central to so many people’s lives a better place?

Page 10: H3 Design Challenge Presentation

Perhaps a better question is, “Where would MSG want to be?”

Page 11: H3 Design Challenge Presentation

A place that is close to transit, connected to existing tourist, hospitality and entertainment attractions; A place that provides an enhanced patron experience, better service and functional access; and a place that creates a singular new identity for the Garden.

Page 12: H3 Design Challenge Presentation

Of all the locations that have been considered, we believe one site at the western end of 34th St meets these criteria.

Page 13: H3 Design Challenge Presentation

Partnering with appropriate government agencies, Pier 76, now the Tow Pound, could be extended south to 33rd Street, creating a 16 acre site on the Hudson where MSG could be located.

Page 14: H3 Design Challenge Presentation
Page 15: H3 Design Challenge Presentation

But how would you get there?

Page 16: H3 Design Challenge Presentation

The new 7 Flushing line subway will stop at 11th Ave and 34th Street and a park promenade would bring people up and over 12th Ave to the Arena’s front door.

Page 17: H3 Design Challenge Presentation

A LIRR station could be created in the northern part of the LIRR yard.

Page 18: H3 Design Challenge Presentation

A Metro-North station could be built underground here.

Page 19: H3 Design Challenge Presentation

NY Waterway’s 39th Street ferry terminal is next door, with service to New Jersey.

Page 20: H3 Design Challenge Presentation

There could even be a new bikeway and elevated pedestrian walk, call it the Water Line, connecting Hudson River Park, 42nd Street, the West Side and back to Penn.

Page 21: H3 Design Challenge Presentation

Finally, if you extend the 7 Line back to Penn Station, loop it under Park Avenue to Grand Central – you could create a “7 Circle Line” connecting east and west midtown with all major subway and regional train lines.

Page 22: H3 Design Challenge Presentation

This site puts MSG near all the attractions, hotels and restaurants that feed the city’s $55B tourist, entertainment and media industries.

Page 23: H3 Design Challenge Presentation

Most importantly, locating MSG next to the Javits Convention Center would stimulate new thinking about hosting large scale conventions, trade shows and special events in the city.

Page 24: H3 Design Challenge Presentation

With MSG as an anchor to the west, we can re-imagine Penn Station.

Page 25: H3 Design Challenge Presentation

By far the busiest on the Northeast Corridor, the current facility is way beyond capacity.

Page 26: H3 Design Challenge Presentation

Amtrak and NJ Transit have a plan, called Gateway, that builds two new tunnels under the Hudson, feeding into Penn Station. NJ Transit could run more trains thru and we can connect to our new 7 Circle line right next door.

Page 27: H3 Design Challenge Presentation

Amtrak’s high speed rail trains would use these tunnels and continue north to Boston.

Page 28: H3 Design Challenge Presentation

To the north, we can provide space for the growing number of commuter bus services, increasing mobility for everyone in the region.

Page 29: H3 Design Challenge Presentation

These new connections will transform the way we think of the Northeast Corridor. While the Acela takes three hours to get to DC now, and three and a half to get to Boston.

Page 30: H3 Design Challenge Presentation

Future high speed trains will cut that down to 90 minutes each way.

Page 31: H3 Design Challenge Presentation

If Penn Station can be reconfigured to provide better access to the region, it would allow the Farley Post Office building, also known as Moynihan Station, to be used differently.

Page 32: H3 Design Challenge Presentation

The Farley Building could be converted into a Center for Education. Drawing students from throughout the Tri-state region, it will help train employees for high-value high-demand industries.

Page 33: H3 Design Challenge Presentation

SECTION LOOKING NORTH

Without compromising access to the trains below, Amtrak’s West Concourse will be an entrance to the train platforms from 8th Ave, and the Post Office windows remain in the original lobby. The rest of the building would be academic classrooms, support spaces and labs.

Page 34: H3 Design Challenge Presentation

These are grand plans, but how do we pay for them?

Page 35: H3 Design Challenge Presentation

To add to the required contribution of public funding, one method is to allocate large footprint development sites at the four corners of the station.

Page 36: H3 Design Challenge Presentation

These buildings would be designed, not strictly as commercial office towers, but as hybrid buildings, offering diverse activities which are essential to sustainable growth and urban cultural vitality.

Page 37: H3 Design Challenge Presentation

6 acres of active public space provides increased value on the ground as well.

Page 38: H3 Design Challenge Presentation

In addition, several sites along 7th Avenue could be upzoned to convert these sites into mixed use developments, extending the renewal of Times Square and 42nd Street south to 34th.

Page 39: H3 Design Challenge Presentation
Page 40: H3 Design Challenge Presentation
Page 41: H3 Design Challenge Presentation

In Manhattan, there are few sites big enough that could accommodate the Arena. And even fewer that aren’t held by private interests. 12 Ave next to Javits has always felt like the West Side’s backyard.

Page 42: H3 Design Challenge Presentation

How can we flip this to make the area more accessible? Extend the existing pier south, and service the Arena at grade. The park promenade rises up and crosses over 12 Ave. Patrons will enter the Arena at this level. The Water Line would provide two other means of access.  

Page 43: H3 Design Challenge Presentation

Below, Hudson River Park’s shoreline will be restored to encourage marine life. Javits could pursue the expansion plan it shelved 5 years ago, expanding its capacity to be one of the top 10 centers in the country.

Page 44: H3 Design Challenge Presentation

With MSG relocated, Penn Station could become a true multimodal transportation center.

Page 45: H3 Design Challenge Presentation

With the ACE and 123 trains adjacent, and the 6TH Ave, Broadway and PATH trains nearby, the key is getting passengers distributed as quickly as possible.

Page 46: H3 Design Challenge Presentation

That means straightening and expanding the Exit Concourses where passengers first arrive. Extending those Concourses to accommodate the new Penn South platforms and the West Concourse under the Farley Building steps would be completed.

Page 47: H3 Design Challenge Presentation

The number 7 Circle line would anchor the south end of the new station complex.

Page 48: H3 Design Challenge Presentation

Gimbel’s passageway would be expanded to connect to subways and PATH trains at Herald Square.

Page 49: H3 Design Challenge Presentation

The station itself would have a central departure and waiting room concourse.

Page 50: H3 Design Challenge Presentation

All the train services would be clearly marked and accessed from.

Page 51: H3 Design Challenge Presentation

The Train Hall above ground would span above, extending from 34th to 30th St. A retail concourse extends towards 8th Ave and on 7th Ave, a three acre park. On the roof, another 3 acre roof garden.

Page 52: H3 Design Challenge Presentation

This bottom to top transformation of Penn Station will make connections easier and clearer. There will be enough space to accommodate the crowds and the station will have the architectural distinction to match Grand Central.

Page 53: H3 Design Challenge Presentation

Across 8th Ave, the Farley Building will be converted into the Center for Education at Moynihan Station.

Page 54: H3 Design Challenge Presentation

The Water Line would provide a bicycle and pedestrian connection and we would restore the building’s interior spaces and provide expansion space.

Page 55: H3 Design Challenge Presentation
Page 56: H3 Design Challenge Presentation

Rezoning the four sites will allow a significant new tower at 34th and 7th , a supertall skyscraper, 180 stories tall. Altogether, these sites would total 14M sf.

Page 57: H3 Design Challenge Presentation

Eight additional sites along 7th Ave would provide 10M sf more.

Page 58: H3 Design Challenge Presentation

On 7th Ave, a park spanning 3 blocks in front of the station, an incredible open space in an area of Midtown that is lacking in them.

Page 59: H3 Design Challenge Presentation

In the Train Hall, 120’ high, large skylights capture daylight from above.

Page 60: H3 Design Challenge Presentation

The west Exit Concourse. This open space reaches up to daylight and air.

Page 61: H3 Design Challenge Presentation

The retail concourse above has three levels of shops, restaurants and amenities to service both the station and the district.

Page 62: H3 Design Challenge Presentation

Above the retail, a three acre stepped garden and a rooftop gallery space is accessible directly from 8th Ave. It’s a sunlit horticultural garden, fragrant, colorful, and green, overlooking the west side with views of the river beyond. The Water Line extends west from the terrace connecting to the MSG promenade.

Page 63: H3 Design Challenge Presentation

Here’s MSG’s spectacular new home, it remains the center of sports, entertainment, media and pop culture in the city – with concerts, dog shows, the circus, and the Rangers, Liberty and Knicks.

Page 64: H3 Design Challenge Presentation

These new buildings will define the new skyline of New York. Located in the center of the city, Penn Station will be the heart of a 50 million person metropolis.

Page 65: H3 Design Challenge Presentation

This group of people, just a few of the million who use Penn Station each day, will have better lives if we make the changes in this plan. A new Penn Station can make life better for the people who use it, and the rest of the city.

Page 66: H3 Design Challenge Presentation

The time is now.

Page 67: H3 Design Challenge Presentation

Pascale BaladiAbby CarlenAriel FaustoJohn FontillasEric GalipoHugh HardyGeoff LynchBrennan PlunkettJames Willeford