Top Banner
Corridor H Section 6 Mainline over South Branch Potomac River Abutment No. 1 Site Inspection State Project No. X316-H-100.40 04 Federal Project No. APD-0484(255)C Hardy County, West Virginia Cornerstone of the Past - Dedicated To the Future H. C. Nutting Company H. C. Nutting Company
21

H. C. Nutting Company - Marshall University

Jan 21, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: H. C. Nutting Company - Marshall University

Corridor H Section 6 Mainline over South Branch Potomac River

Abutment No. 1 Site Inspection

State Project No. X316-H-100.40 04

Federal Project No. APD-0484(255)C

Hardy County, West Virginia

Cornerstoneof the Past -

DedicatedTo the Future

H. C. Nutting CompanyH. C. Nutting Company

Page 2: H. C. Nutting Company - Marshall University

Purpose

H. C. Nutting Personnel conducted a field inspection of the site as per request by the WVDOH and the FHWA.

The Purpose of the inspection was to try to verify the orientation of the joint system, fractures and more closely examine the condition of the high wall slope rising above the river in the vicinity below the proposed location of abutment 1.

Page 3: H. C. Nutting Company - Marshall University

Home on the Range

Page 4: H. C. Nutting Company - Marshall University

Moorefield Geology Profile

Page 5: H. C. Nutting Company - Marshall University

Original Proposed Design

Alternate 1

Page 6: H. C. Nutting Company - Marshall University

Original Proposed Design

Alternate 2

Page 7: H. C. Nutting Company - Marshall University

Original Proposed Design

Alternate 3 Early on - Considered the Design of Choice

Page 8: H. C. Nutting Company - Marshall University

Upper Slope Joint/Discontinuity

The surface is subjected to freezing and thawing cycles, and wet and dry cycles resulting in significant shallow spalling of the surface as evidenced by the accumulation of talus at the base of the slope.

Page 9: H. C. Nutting Company - Marshall University

Lower Slope Joints/Discontinuities

At the base of the slope, two measured joint sets were observed in the siltstone, which vary from 80° to near vertical.

The measured orientations of the joints are:

Joint Set 1 - 85° dip and 50°to 60° dip direction

Joint Set 2 - 80° to 88° dip and 320° to 335° dip direction

Page 10: H. C. Nutting Company - Marshall University

Small Scale Folding in Lower Slope

The Rock strata, although interrupted by some isolated, small scale folding and discontinuities has an approximate dip of 5 to 10 degrees from the horizontal in a southeasterly direction, with a strike of approximately 20 to 30 degrees in a northeasterly direction.

Page 11: H. C. Nutting Company - Marshall University

Small Scale Wedge Failure in Lower Slope

The risk for planar or block failure on a large scale does not appear to be a significant issue based upon the geometry of the rock strata.

Page 12: H. C. Nutting Company - Marshall University

Weathered Shale Slope

This type of erosion creates a very irregular slope that is subject to frequent pop outs resulting in some overhanging and weathered shale bluffs that appear to be at high risk of failing with a minimum effort of disturbance.

Page 13: H. C. Nutting Company - Marshall University

Undercutting & Overhanging of Shale Bluff

Page 14: H. C. Nutting Company - Marshall University

Width of Bench in Front of Abutment 1

South Edge of Abutment 1 to Edge of Slope is Approx. 65 ft.North Edge of Abutment 1 to Edge of Slope is Approx. 18’

Approx. 65’

Approx. 18’

Page 15: H. C. Nutting Company - Marshall University

Alluvial Terrace Deposits North Side of Abutment No. 1

The North Corner of the abutment is located near the contact of the discontinuity of the siltstone and extremely soft, brown, silty, clayey shale and alluvial terrace soil deposits.

Page 16: H. C. Nutting Company - Marshall University

Sloping Bedrock Interface Along Abutment No. 1

The desired bedrock foundation at elevation 846.0 is not consistent for the full width of the abutment as observed by visual observation.

Page 17: H. C. Nutting Company - Marshall University

Summary of Field Investigation

•Recommendations by H. C. Nutting Company

•Review by the Prime Consultant

•Various Construction Alternatives

•Conclusion

Page 18: H. C. Nutting Company - Marshall University

Sloping Bedrock Interface Along Abutment No. 1

Page 19: H. C. Nutting Company - Marshall University

Proposed Plan ElevationFor Construction of Drilled Shafts

Page 20: H. C. Nutting Company - Marshall University

Wing Wall Details

Page 21: H. C. Nutting Company - Marshall University

Thank You

H. C. Nutting Company

H. C. Nutting CompanyH. C. Nutting Company

Questions