Top Banner
GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email: [email protected]
31

Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

May 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

GUNN’S HILL WIND FARM

EXECUTIVE SUMMARY

FINAL

June 2013

Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email: [email protected]

Page 2: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

January 8, 2014

Reference: Notice of Project Design Change – Gunn’s Hill Wind Farm

PLEASE NOTE: The Renewable Energy Approval (REA) Application for the Gunn’s Hill wind Farm was submitted to the Ontario Ministry of the Environment (MOE) in June, 2013.

The tap line connecting the project substation to Woodstock Transformer Station will no longer be required, as connection will be at or near the substation itself.

The tapline has been removed from Project mapping, but there are no changes to the Draft REA Reports provided to the MOE for review.

Please note there are no new environmental effects due to removal of the tap line from the Project description.

Page 3: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

i

TABLE OF CONTENTS

1. PROJECT DESCRIPTION SUMMARY .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

1.1. Project Components ................................................................................................................ 1

1.2. Project Timing .......................................................................................................................... 2

1.3. Project Activities....................................................................................................................... 3

1.4. Construction Activities ............................................................................................................. 3

1.4.1. Surveying and Geotechnical Studies .......................................................................... 3

1.4.2. LAND CLEARING ........................................................................................................... 4

1.4.3. ACCESS ROAD AND CRANE PAD CONSTRUCTION...................................................... 4

1.4.4. TRANSPORT OF EQUIPMENT........................................................................................ 4

1.4.5. CONSTRUCTION OF TURBINE FOUNDATIONS............................................................. 4

1.4.6. WIND TURBINE ASSEMBLY AND INSTALLATION ........................................................ 4

1.4.7. ELECTRICAL NETWORK INSTALLATION....................................................................... 4

1.4.8. CONSTRUCTION OF SUBSTATION................................................................................ 4

1.4.9. CONSTRUCTION OF OPERATION AND MAINTENANCE BUILDING.............................. 5

1.4.10. CLEAN UP AND SITE RECLAMATION............................................................................ 5

1.5. OPERATION AND MAINTENANCE ............................................................................................ 5

1.5.1. WIND TURBINE OPERATION......................................................................................... 5

1.5.2. MAINTENANCE .............................................................................................................. 5

1.5.3. WASTE MANAGEMENT ................................................................................................. 6

1.6. DECOMMISSIONING ................................................................................................................ 6

1.7. POTENTIAL ENVIRONMENTAL EFFECTS ................................................................................. 6

1.7.1. CULTURAL HERITAGE And Archaeological Resources................................................ 6

1.7.2. NATURAL HERITAGE RESOURCES (SUCH AS WETLANDS AND WOODLANDS) ............ 7

1.7.3. SURFACE WATER AND GROUNDWATER...................................................................... 7

1.7.4. EMISSIONS TO AIR........................................................................................................ 8

1.7.5. NOISE ................................................................................................................ 8

1.7.6. LOCAL INTERESTS, LAND USE AND INFRASTRUCTURE ............................................. 8

1.7.7. PUBLIC HEALTH AND SAFETY ...................................................................................... 8

2. DESIGN AND OPERATIONS REPORT .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

2.1. FACILITY DESIGN PLAN..........................................................................................................10

2.1.1. WIND TURBINES .........................................................................................................10

2.1.2. ACCESS ROADS...........................................................................................................10

2.1.3. ELECTRICAL SYSTEM..................................................................................................11

2.1.4. SUBSTATION 11

Page 4: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

ii

2.1.5. TURBINE LAYDOWN AREAS AND CRANE PADS ........................................................12

2.1.6. OPERATIONS AND MAINTENANCE BUILDING ...........................................................12

2.2. FACILITY OPERATION PLAN ...................................................................................................12

2.2.1. WIND TURBINE OPERATION AND MAINTENANCE ....................................................12

2.2.2. MAINTENANCE ............................................................................................................12

2.2.3. WASTE MANAGEMENT ...............................................................................................13

2.3. EMERGENCY RESPONSE AND COMMUNICATION PLAN......................................................13

2.4. ENVIRONMENTAL EFFECTS MONITORING PLAN - SECTION 6 ............................................13

2.4.1. CULTURAL HERITAGE .................................................................................................13

2.4.2. ARCHAEOLOGICAL ASSESSMENT..............................................................................14

2.4.3. Natural Heritage Resources (such as wetlands and forests) ..................................14

2.4.4. WATER BODIES AND AQUTIC RESOURCES ...............................................................17

2.4.5. Emissions to Air ..........................................................................................................18

2.4.6. Noise ..............................................................................................................18

2.4.7. Local Interests, Land Use and Infrastructure ...........................................................18

2.4.8. Surveying and Geotechnical Studies ........................................................................18

3. CONSTRUCTION PLAN .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

3.1. Construction Activities ...........................................................................................................19

3.1.1. Surveying and Geotechnical Studies ........................................................................19

3.1.2. Land Clearing And Construction Of Access Roads ...................................................19

3.1.3. Construction Of Crane Pad and Laydown Areas.......................................................20

3.1.4. Transport Of Turbine Components ............................................................................21

3.1.5. Construction Of Turbine Foundations .......................................................................21

3.1.6. Wind Turbine Assembly And Installation...................................................................21

3.1.7. Construction Of Electrical Network ...........................................................................21

3.1.8. Construction Of Substation........................................................................................22

3.1.9. Construction Of Operation And Maintenance Building ............................................23

3.1.10. Clean Up And Site Reclamation.................................................................................23

3.2. Construction and Installation Schedule ...............................................................................23

3.2.1. Schedule ..............................................................................................................23

3.2.2. Timeline ..............................................................................................................24

4. DECOMMISSIONING .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

4.1. Restoration of Land and Water.............................................................................................25

LIST OF APPENDICES

Appendix A – Project Layout Map

Page 5: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

1

 

1. PROJECT DESCRIPTION SUMMARY

Prowind   Inc.   (Prowind)   is   a  Canadian  wind  energy  developer  based   in  Hamilton,  Ontario.  Prowind   is   affiliated   with   its   parent   company,   Prowind   GmbH,   based   in   Osnabrück,  Germany.    Prowind’s  mandate  is  to  create  small-­‐scale,  renewable  and  zero-­‐emission  power  generation.  Prowind  believes   in  distributed  generation  that  has  a  minimum  impact  on  the  surrounding  environment  and  landscape.    

Prowind  is  proposing  the  Gunn’s  Hill  Wind  Farm  (The  Project)  that  is  categorized  as  a  Class  4   facility,   which   will   consist   of   up   to   ten   (10)   turbines   from   the   Siemens   SWT   3.0-­‐113  family.  The  turbines  will  have  a  maximum  nameplate  rating  of  2.5  MW  each  and  the  project  will   have   a  maximum   total   installed   nameplate   capacity   of   25  MW.     These  wind   turbines  have  a  hub  height  of  99.5  m  and  a  rotor  diameter  of  113  m  for  a  total  height  of  156  m.    

Other  basic  components  include  step-­‐up  transformers  located  adjacent  to  the  base  of  each  turbine   (step  up  voltage   from  approximately  0.69  kV   to  27.6  kV),   a  27.6  kV  underground  collector   system,   fibre   optic   data   lines,   a   non-­‐Transformer   substation,   operation   and  maintenance   building   and/or   storage   shed   (if   required),   and   turbine   access   roads.          Temporary  components  during  construction  include  laydown  areas  at  the  turbine  locations,  crane  pads,  temporary  parking,  concrete  wash  ponds  and  construction  trailers  

The  27.6  kV  underground  collector  lines  will  transport  the  electricity  generated  from  each  turbine   to   the   substation   located   along   Firehall   Road,   just   east   of   the   buried   cable   to  Turbine  1.    As  this  is  a  distribution  connected  project,  a  27.6  kV  feeder  line  will  be  required  to   connect   into   the   local   distribution   system.   The   overhead   lines   will   be   owned   and  maintained  by  the  proponent  and  installed  on  rented  space  on  poles  owned  by  Hydro  One  and  Woodstock  Hydro.  

The  purpose  of  Executive  Summary  is  to  summarize  the  content  of  the  REA  reports;  it   is  a  key  document  for  consultation.    The  Executive  Summary  was  prepared  in  accordance  with  the   requirements   outlined   in   Ontario   Regulation   359/09,   the   regulation   governing  renewable  energy  projects  in  Ontario.  

1.1. PROJECT COMPONENTS

The  proposed  project  layout  includes  the  major  components  of  the  Project  listed  below:  

• Up  to  10  Siemens  SWT  3.0-­‐113  wind  turbines  (2.5  MW  maximum  power);  

• Step  up  transformers  located  at  or  within  the  base  of  each  turbine  (step  up  voltage  approximately  0.69  kV  to  27.6  kV);  

• Turbine  laydown  and  storage  areas  (including  temporary  staging  areas,  crane  pads  and  turnaround  areas  surrounding  each  wind  turbine);  

• Temporary   construction   infrastructure   (including   laydown   areas   for   construction  materials,  construction  trailers,  storage  sheds,  parking  areas,  concrete  wash  ponds);  

• Underground  fibre  optic  cables  and  electrical  collection  lines  (27.6  kV)  and  ancillary  equipment  (e.g.,  above  ground  electrical   junction  boxes)  to  connect  the  turbines  to  the  proposed  substation;  

Page 6: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

2

• Substation  which   switches   the  underground  electrical   collection   lines   to   overhead  lines   and   contains   the   necessary   protection   and   control,   switchgear,   and  communication  equipment  to  safely  operate  the  project;  

• An   approximately   6.5   km   underground   and   overhead   dedicated   feeder   line   (27.6  kV)   on   Hydro   One   and   Woodstock   Hydro   poles   to   connect   to   the   provincially  controlled  electrical  grid  (through  the  Woodstock  Transformer  Station);  

• Turbine  access  roads;  and  

• Optional  Operations  and  Maintenance  building,  with  permanent  parking  and/or  storage  shed.  

 

 

 

1.2. PROJECT TIMING

Construction   for   the   Gunn’s   Hill   Wind   Farm   is   expected   to   begin   in   January   2014  (dependent  on  receiving  the  required  approvals),  and  last  for  approximately  6  months.  The  operations   phase   is   anticipated   to   start   in   July   2014,   and   the   Project   will   operate   for  approximately   20   years,   after   which   point   the   Project   may   be   decommissioned   or  repowered.  

Page 7: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

3

1.3. PROJECT ACTIVITIES

The  lifecycle  of  a  wind  farm  progresses  through  three  stages:  

1. Construction   and   Installation   -­‐   This   stage   is   expected   to   take   6  months.   It  will   be  comprised  of  surveying,  road  construction,  foundation  construction,  electrical  cable  installation,  turbine  installation,  testing  and  commissioning.    

2. Operation   and   Maintenance   –   This   stage   is   expected   to   last   twenty   years   at   the  Gunn’s  Hill  Wind  Farm.  Maintenance  includes  regularly  scheduled  service  as  well  as  emergency  response.  

3. Decommissioning   -­‐   This   stage   is   similar   to   construction,   but   includes   the  dismantling   of   the   wind   turbines   and   other   infrastructure   and   restoration   of   the  land  to  its  original  state.  

Construction  will   occur  as   soon  as  permits  have  been   secured  and   the   site   conditions  are  suitable   for   planned   activities.     Certain   construction   activities   will   not   occur   during  restricted   seasonal   periods.     Local   roads   and   highways   are   not   available   for   heavy   loads  transport  during  March  and  April,  nor  is  the  ground  suitable  at  this  time  for  construction  of  the   crane   pad   areas.   Any   activity   within   30   m   of   surface   water   crossings   (hydro   pole  replacement)  will  not  be  done  during  the  fish  spawning  and  rearing  period  of  March  15  to  June  30.  

Once  started,  construction  is  expected  to  take  6  months,  not  including  the  exception  periods  stated  above.  

The  Operational  phase  of  the  project  will  begin  as  soon  as  commissioning  has  occurred  and  is   expected   to   last   for   20   years.     Routine   maintenance   will   be   ongoing   during   this   time.    Roadways   will   be   maintained   and   snow  will   be   cleared   throughout   the   operation   of   the  project.    It  is  expected  that  a  major  component  will  need  to  be  replaced  in  an  approximately  7-­‐year  cycle,  which  may  require  heavy   load   transportation  and  rehabilitation  of   the  crane  pad  areas  and  turning  radii.  

The  Decommissioning  phase  will  begin  after  the  end  of  operation  of   the  wind  farm  and  in  any  event,  no  later  than  12  months  beyond  the  official  decommissioning  date.    This  phase  is  expected  to   take   less   than  6  months  to  complete  and  will  occur  outside  any  period  where  road   limits   apply,  or   the  ground   is  not   suitable   for   crane  pad   reconstruction   (i.e.  March  –  April),  or  sensitive  time  periods  for  local  habitat.  

1.4. CONSTRUCTION ACTIVITIES

1.4.1. Surveying and Geotechnical Studies

Surveys  are  required  to  identify  locations  of  major  Project  components;  this  involves  surveyors  walking  around  the  sites  and  marking  locations  using  stakes.    

Geotechnical   sampling   is   required   to   locate   turbine   foundations;   this   involves   drilling  boreholes  and  sampling  within  the  turbine  foundation  area.  Turbine  manufacturers  require  knowledge  of  the  subsurface  soil  conditions  in  order  to  design  the  appropriate  foundation.    A  wide  variety  of  soil  properties  are  determined  and  groundwater   levels  are  measured  to  enable  an  engineer  to  design  a  safe  foundation.  

Page 8: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

4

1.4.2. LAND CLEARING

The  turbines  will  be  located  within  existing  agricultural  fields.    Land  clearing  will  be  limited  to  the  excavation  and  on-­‐site  stockpiling  of  topsoil.    No  topsoil  will  be  removed  from  the  site  at  any  time.    Land  clearing  will  occur  for  the  construction  of  the  access  roads,  crane  pad  and  tower  foundation.      

1.4.3. ACCESS ROAD AND CRANE PAD CONSTRUCTION

Access  roads  will  be  11  m  wide  during  the  construction  phase  and  are  required  to  transport  equipment   to   the   turbine   location   construction   sites.     Access   roads  will   be   built   to   a   5  m  width  and  maintained  throughout  the  life  of  the  project  for  maintenance  activities.  

Construction   laydown  areas  are  approximately  1  hectare  (ha)   in  size  around  each   turbine  during  construction  and  decommissioning  phases.    The  crane  pad  (approximately  20  m  x  40  m)  will  also  be  located  within  this  area.    

1.4.4. TRANSPORT OF EQUIPMENT

The  wind  turbine  and  related  hardware  will  be  transported  to  the  site  via  transport  truck.    Five   tower  sections  will  be  delivered  separately  and  be  stored  on   the   lay-­‐down  area  until  installation.    The  nacelle  and  each  of  the  blades  will  be  delivered  to  the  site  separately.    Due  to  the  size  of  the  wind  turbine  components,  oversized  transport  trucks  will  be  necessary  to  transport  equipment.  

1.4.5. CONSTRUCTION OF TURBINE FOUNDATIONS

Foundation  construction  begins  with  the  removal  and  stockpiling  of  topsoil.      • First   an   area   approximately   3   m   deep   x   20  m   in   diameter   is   dug   and   the   earth   is  stored  for  later  use.    

• The   foundations  are   the   shaped  of   an   inverted  bowl  and  made  of   a   reinforced   steel  frame  and  then  filled  with  concrete.    

After  construction,  the  subsoil  and  topsoil  will  be  returned  and  the  area  can  be  farmed  to  within  a  few  metres  of  the  turbine.    

1.4.6. WIND TURBINE ASSEMBLY AND INSTALLATION

Once   turbine   foundations   are   complete   and   the   concrete   has   set,   the   turbines   will   be  constructed,  usually  in  five  lifts  (three  for  the  towers,  one  for  the  nacelle  -­‐  which  houses  the  main  components  of  the  wind  turbine  such  as  the  rotor  shaft,  control  panel,  generator,  etc.  -­‐  and  one  for  the  rotor  with  the  blades  already  mounted).    

 

1.4.7. ELECTRICAL NETWORK INSTALLATION

The  electrical  collection  system  is  used  to  collect  and  deliver  the  power  generated  from  the  turbines   to   a   common   point   and   subsequently   the   provincial   distribution   grid.     A  combination  of  underground  and  overhead  wires  will  be  installed.      

The  collection  system  consists  of  three  electrical  cables  running  at  a  system  voltage  of  27.6  kV,  a  neutral  ground,  and  a  fibre  optic  cable.  The  fibre  optic  cable  is  used  for  communication  between  turbines.  

Page 9: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

5

The   collection   system   cables   connect   to   the   transformer   at   the   base   of   each   turbine   and  subsequently  connect  to  the  other  turbines  along  the  collection  system  route.    A  T-­‐Junction  box  will  be  used   to   join   radial  arms  of   the  collection  system  and   to   splice   cables   together  where  required.    

1.4.8. CONSTRUCTION OF SUBSTATION

The  substation  will  be  located  on  the  south  side  of  Firehall  Road  just  east  of  the  buried  cable  to  Turbine  1.    Construction  will  involve  the  removal  and  storage  of  topsoil  from  a  40  m  x  80  m  area.  A  concrete  foundation  will  be  poured  on  top  of  engineered  gravel.  

Substation   electrical   components   typically   consist   of   switchgear,   SCADA,   fuses,  communication   hardware   and   antenna,   and   other   protection   and   control   systems.     This  equipment   is   housed   in   grey   electrical   cabinets   bolted   to   a   concrete   foundation.     The  substation  area  will  be  fenced  to  ensure  safety  and  security.  

1.4.9. CONSTRUCTION OF OPERATION AND MAINTENANCE BUILDING

An   Operations   and  Maintenance   building  may   be   constructed   to   support   the   operational  phase   of   the   project.     The   building   will   have  maximum   dimensions   of   16  m   x   32  m   and  would   host   office   space,   parking   for   approximately   4   vehicles,   tools,   spare   parts,   and  equipment  for  the  wind  farm.  Both  new  and  waste  fluids  would  also  be  temporarily  stored  at   the   facility   before   and   after   use   respectively.   Waste   fluids   would   be   stored   until   a  qualified   service   provider   can   remove   them.   A   physical   spill   containment   area   would   be  constructed  within  the  building  for  the  fluids.  

1.4.10. CLEAN UP AND SITE RECLAMATION

Site  clean-­‐up  will  occur  throughout  the  construction  phase  and  site  reclamation  will  occur  after  construction  has  been  completed.      Materials  will  be  recycled  as  much  as  possible  and  waste   will   be   removed   from   the   site   and   disposed   of   at   an   appropriate   facility.       All  disturbed  areas  will  be  restored  with  the  stockpiled  soil  and  reseeded,  as  appropriate.  

1.5. OPERATION AND MAINTENANCE

1.5.1. WIND TURBINE OPERATION

Turbine  operation  and  maintenance  (O&M)  will  be  either  contracted  to  a  specialized  third  party   service   provider   or   handled   by   a   project   owner   possessing   infrastructure   and  capabilities   for   this   activity.     The  O&M   service   provider  will   have   a   staff   of   trained  Wind  Turbine   Technicians,   Site   Supervisors,   and   a   data   monitoring   centre   located   in   the   O&M  building  (if  constructed)  and/or  off-­‐site  to  monitor  the  status  of  each  turbine  24  hours  per  day,  365  days  per  year.  

The  scope  of  the  activities  will  include  day-­‐to-­‐day  monitoring  and  operation  of  the  turbines  via  SCADA  hardware  and  fibre  optic  communication  linkage  as  well  as  on-­‐going  

1.5.2. MAINTENANCE

Approximately  every  6  months,  routine  maintenance  will  be  carried  out  by  2-­‐3  workers  over  a  full  day  at  each  turbine.    

The  substation  will  receive  periodic  protective  relay  maintenance  and  the  collection  lines  will  receive  periodic  assessments  of  their  condition.  

Page 10: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

6

Unplanned  maintenance  can  include  failure  of  small  components  and  may  be  addressed  by  a  technician  over  several  hours.    

Events  involving  the  replacement  of  major  components  such  as  gearboxes  are  not  typical;  however,  this  could  require  the  use  of  large  equipment.      

1.5.3. WASTE MANAGEMENT

Waste  generated  during  operations  will  be  removed  from  the  operations  and  maintenance  building  by  a   licensed  operator  and  disposed  of  at  an  approved  facility.  Recycling  services  will  be  used  to  the  extent  available.    

 

1.6. DECOMMISSIONING

At   the   end   of   the   Project   life,   the   wind   turbines   may   be   ‘re-­‐powered’,   meaning   turbine  components   could   be   replaced   to   extend   the   life   of   the   Project   and   delay   any  decommissioning   activities.   Alternatively,   the   wind   turbines   may   be   decommissioned.  Project  decommissioning  will   follow  the  Ontario  Occupational  Health  and  Safety  Act  along  with  any  applicable  municipal,  provincial  and  federal  regulations  and  standards.  

The  following  components  will  be  removed  during  dismantling:  

1.  Turbines;  2.  Overhead  lines  and  poles;  and,  3.  Transformer  substation.  

1.7. POTENTIAL ENVIRONMENTAL EFFECTS

An  assessment   for  the  construction,  operation  and  decommissioning  phases  of   the  Project  was   completed   to   identify   potential   effects.   This   is   done   so   that   mitigation   or   corrective  actions  can  be  proposed  to  eliminate  or  minimize  potential  effects.  

This  section  provides  examples  of   some  potential  effects  and  mitigation  measures  of  each  phase   for   specific   environmental   components.   For   further   details   on  mitigation  measures  and   monitoring   plans,   please   refer   to   the   Construction   Plan   Report   and   the   Design   and  Operations  Report.  Note  that  effects  from  construction  are  anticipated  to  be  similar  to  those  from  decommissioning,  as  such,  they  are  shown  together  below.  

1.7.1. CULTURAL HERITAGE and ARCHAEOLOGICAL RESOURCES

There  is  a  potential  to  disrupt  existing  unknown  European  and  First  Nations  archaeological  sites  during  construction.  For  this  reason  Stage  1  and  Stage  2  archaeological  surveys  have  been   conducted   on   any   lands   likely   to   be   disrupted   during   construction.   These   surveys  included  both  desktop   and   field   surveys   (pedestrian   surveys   and   test   pitting)   throughout  the  project  area,   targeted  on  any  area  that  would  be  directly  affected  by  project  activities,  including   turbine   or   lay-­‐down   areas,   roadways,   underground   and   overhead   cabling  positions.   Results   are   presented   in   their   entirety   in   the   Archaeological   Assessment   and  Cultural  Heritage  Resources  Reports.    

Stage   2   Archaeological   Assessment   encountered   a   single   First   Nations   findspot.     The  findspot   is   an   isolated   individual   artefact   that   does   not   represent   a   significant   planning  

Page 11: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

7

concern.     No   further   work   is   recommended   at   the   location.     No   other   archaeological  resources  were  encountered  during  the  Stage  2  work.  

It  is  unlikely  that  unknown  archaeological  sites  exist  within  the  project  location  due  to  the  ongoing  and  extensive  soil  disruption  from  present  and  historic  agricultural  activities  in  the  project  area.  

A   Heritage   Impact   Assessment  was   conducted   for   Gunn’s   Hill  Wind   Farm   to   identify   any  Built  Heritage  features  or  Cultural  Heritage  Landscapes  in  the  project  area.    This  assessment  involved   desktop   historical   land-­‐use   studies   and   windshield   surveys   of   the   area   for  identification   of   culturally   significant   heritage   features.   The   assessment   concluded   that  there   will   be   no   impacts   from   the   wind   farm   on   heritage   features   or   landscapes   in   the  project  area.    An  additional  Heritage   Impact  Assessment  was  conducted  and  completed   in  Nov  2012  to  address  the  additional  overhead  lines  to  the  Woodstock  Transformer  Station.    The  assessment  determined  that  the  properties,  roads,  railway  and  other  heritage  resources  in  the  area  would  not  be  negatively  impacted  by  the  project.    Ministry  of  Tourism,  Culture  and   Sport   has   reviewed   and   provided   comment   on   both   Heritage   Impact   Assessment  Reports  and  has  released  the  Gunn’s  Hill  Wind  Farm  from  any  further  concerns.      

1.7.2. NATURAL HERITAGE RESOURCES (SUCH AS WETLANDS AND WOODLANDS)

Construction  and  decommissioning:  Vegetation  removal  could  disturb  wildlife  and  affect  wildlife  movement  in  the  area.    No  direct  impacts  to  wetlands  present  in  the  project  area.  

Mitigation  measures:    Designed  in  a  way  that  avoids  vegetation  removal  so  that  minimal  habitat  is  lost  during  construction  of  the  wind  farm.    

Operation:  Disturbance  or  mortality  to  wildlife  (e.g.  birds  and  bats)  may  occur  due  to  collisions  with  turbines.    

Mitigation   measures:   Operational   mitigation   techniques   may   be   implemented,   such   as   a  periodic  shut-­‐down  of  turbines  during  times  when  there  is  a  greater  change  for  bird  and  bat  collisions.  Monitoring  will  consist  of  post-­‐construction  mortality  surveys  for  birds  and  bats  which  will  be  submitted  to  the  Ministry  of  Natural  Resources.    

 

1.7.3. SURFACE WATER AND GROUNDWATER

Construction  and  decommissioning:  Construction  activities  close  to  streams  could  increased  surface  water  sedimentation,  increased  surface  water  contamination  and  fish  and  fish  habitat  disturbance.    

Mitigation  measures:  to  address  increased  surface  water  sedimentation  and  contamination  include   placing   sedimentation   control   measures   between   construction   activities   and   the  Water  Body.  Where  Water  Bodies  contained  fish  habitat,  timing  of  near  water  works  will  be  conducted  outside  of  the  fish  spawning  and  rearing  period  of  March  15  to  June  30  as  much  as  possible.    

Operation:  Water  contamination  is  possible,  although  unlikely,  due  to  accidental  spills  associated  with  maintenance  activities.    

Mitigation  measures:  A  spill  response  plan  will  be  developed  and  an  emergency  spill  kit  will  

Page 12: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

8

be  kept  on  site.  In  addition,  the  Ministry  of  the  Environment  and  the  local  municipalities  will  be  notified  of  any  spills.      

1.7.4. EMISSIONS TO AIR

Construction   and   decommissioning:   The   increase   of   heavy   truck   traffic   on   local   roads  during  construction  could  create  dust  and  increase  emissions  to  air.    

Mitigation   measures:   Road   surfaces   will   be   sprayed   with   water   or   an   environmentally  friendly  dust  suppressant  to  reduce  the  amount  of  dust  created.    

Operation:  Maintenance  vehicles  may  create  dust  and  increase  emissions  to  air.      Mitigation  measures:   To   reduce   the   amount   of   dust   generated,   the   speed   of  maintenance  vehicles  will  be  limited.  All  construction  vehicles  will  meet  provincial  emissions  regulations.  

1.7.5. NOISE

Construction  and  decommissioning:  Construction  activities  will  increase  noise  levels  in  the  Project  area.  

Mitigation  measures:  All  construction  equipment  will  be  maintained  in  good  working  condition  and  construction  activities  will  abide  by  local  by-­‐laws  regarding  hours  of  operation.  

Operation:  The  operating  turbines  and  substation  may  increase  noise  levels  experienced  by  some  residents.  

Mitigation  measures:  Turbines  will  be  set  back  at  least  550  m  from  all  residents  who  are  not  leasing   their   land   for   the   Project   to   avoid   or   lessen   the   effects.   Noise  modelling  was   also  conducted   to   predict   and   ensure   that   noise   levels   from   the   operating   turbines   and  substation  will   not   be   greater   than   limits   set   by   the  Ministry   of   Environment.   Any   noise-­‐related  complaints  will  be  tracked  and  follow-­‐up  monitoring  will  occur  as  required.    

 

1.7.6. LOCAL INTERESTS, LAND USE AND INFRASTRUCTURE

Construction  and  decommissioning:  The  increase  in  construction  traffic  could  cause  damage  to  local  roads.  

Mitigation   measures:   A   Traffic   Management   Plan   will   be   prepared   prior   to   beginning  construction   activities.   Finally,   any  damage   to   local   infrastructure   caused  by   construction  activities  will  be  repaired  to  original  (or  better)  condition.  

Operation:  Turbines,  access  roads,  and  the  substation  will  result  in  a  minor  reduction  in  usable  agricultural  land.  

Mitigation  measures:  The  length  of  access  roads  will  be  minimized  where  possible.      

1.7.7. PUBLIC HEALTH AND SAFETY

Construction  and  decommissioning:  Similar  effects  to  those  identified  under  Emissions  to  Air,  Noise  and  Local  Interest,  Land  Use  and  Infrastructure.    

Page 13: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

9

Operation:  Effects  on  human  health  and  safety  could  occur  from  ice  shed  and/or  shadow  flicker.    

Mitigation  measures:  All  setback  distances  will  be  adhered  to.  Any  safety  complaints  will  be  tracked  and  follow-­‐up  monitoring  will  occur  as  required.    

After  applying  the  mitigation  measures  presented  in  the  Construction  Plan  and  Design  and  Operations  Reports,  the  overall  conclusion  is  that  this  Project  can  be  constructed,  installed  and   operated   without   any   remaining   effects   that   could   harm   the   environment.   Post-­‐construction   monitoring   related   to   effects   on   wildlife,   including   birds   and   bats,   will   be  undertaken  to  confirm  this  conclusion.  

 

Page 14: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

10

2. DESIGN AND OPERATIONS REPORT

The  purpose  of  the  Design  and  Operations  Report  is  to  provide  specific  details  on  how  the  Project   is   designed,   the   equipment   used,   operated   and   how   emergencies   and   ongoing  communication  will  be  managed.  The  report  also  presents  mitigation  measures,  monitoring  commitments   and   residual   effects,   if   any.   Residual   effects   are   “left   over”   effects   once  mitigation  measures  have  been  applied.  

 The   Design   and   Operation   Reports   was   prepared   in   accordance   with   the   requirements  outlined  in  Ontario  Regulation  359/09,  the  regulation  governing  renewable  energy  projects  in  Ontario.    

The  Site  Plan  was  designed  to  meet  Provincial  “setback  distances”  outlined  in  the  following  table.    

Setback   Distance  (metres  (m))  

Details  

Noise  Receptors   550*   To  be  measured  from  the  centre  of  a  turbine’s  base  to  a  noise  receptor.  Property  Line   Hub  height    

(80)  Setback  can  be  reduced  to  blade  length  plus  10  m  (60  m  total)  measured  from  the  centre  of  the  turbine’s  base  to  the  nearest  property  boundary  if  a  Property  Line  Setback  Assessment  Report  demonstrates  that  siting  turbines  closer  will  not  cause  adverse  effects.  

Roads  and  Railway  

Blade  length    plus  10  m  

Blade  length  plus  10  m  (60  m  total)  measured  from  the  centre  of  the  turbine’s  base  to  the  boundary  of  the  right-­‐of-­‐way.  

Significant  Natural  Heritage  Features  

120   Measured  from  the  project  location  boundary  to  the  nearest  point  of  the  natural  features.  Project  components  may  be  sited  closer  than  the  prescribed  setback  if  an  Environmental  Impact  Study  is  prepared.  

Water  Bodies   120   Measured  from  the  average  annual  high  water  mark  of  a  lake,  or  permanent  /  intermittent  stream  (Project  components  may  be  sited  closer  than  120  m  if  a  Water  Body  Report  is  prepared  -­‐    note  that  turbines  and  transformers  may  not  be  sited  closer  than  30  m  to  these  features).  

Petroleum  Resources  

75   Setback  may  be  reduced  with  the  submission  of  a  Petroleum  Engineer’s  Report  to  the  MNR.    

Note:    *  Setback  does  not  apply  to  noise  receptors  on  land  owned  by  a  proponent  of  a  wind  energy  facility  or  by  a  person  who  has  entered  into  an  agreement  to  permit  all  or  part  of  the  facility  on  their  lands.  

 

2.1. FACILITY DESIGN PLAN

2.1.1. WIND TURBINES

Up  to  ten  (10)  turbines  from  the  Siemens  SWT  3.0-­‐113  family  will  be  used  for  this  Project.  The  turbines  will  have  a  maximum  nameplate  rating  of  2.5  MW.  These  wind  turbines  have  a  hub  heights  of  99.5  m  and  a  rotor  diameter  of  113  m  for  a  total  height  of  156.5  m.    

2.1.2. ACCESS ROADS

Access   roads   to   project   turbines  will   be   5  m  wide   during   the   operational   phase   and  will  have  a  foundation  of  ‘grade  B’  gravel  and  a  finished  surface  of  ‘grade  A’  gravel.    The  access  

Page 15: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

11

roads  provide  access  to  properties  for  equipment  during  construction  and  for  maintenance  during  operations.  

2.1.3. ELECTRICAL SYSTEM

Turbines   will   be   electrically   connected   to   one   another   and   to   the   substation   by   buried    cables   referred   to   as   the   collection   system.   The   collection   system   brings   electricity   and  operational   data   from   each   turbine   to   the   control   and   switchgear   hardware   in   the  substation.  The  electricity  is  then  fed  to  the  point  of  common  coupling  (PCC)  with  the  Hydro  One  controlled  grid  via  the  tap  line.  

The  collection  system  will  consist  of   three  electrical  cables  running  at  a  system  voltage  of  27.6  kV,  a  neutral  ground,  and  a  fibre  optic  cable  for  communication  and  control  purposes.    The  grounding  wire  will  be  the  same  diameter  as  the  Hydro  One  system  grounding  wire  to  minimize  any  risk  of  “stray  voltage”.      

A   tap   line   will   be   used   to   connect   the   project   substation   to   the   existing   provincially  controlled  grid.  The  routing  of  the  tap  line  was  selected  to  follow  the  most  direct  path  that  has  existing  hydro  poles  back  to  the  point  of  common  coupling  with  the  provincial  electrical  grid.   The   selected   route   follows   Hydro   One’s   M4   feeder   to   the   low   voltage   bus   of   the  Woodstock  TS.  Where  the  M4  feeder  traverses  the  Cedar  Creek  Golf  Club,  alternate  routes  were  considered  along  Juliana  Dr,  Norwich  Ave,  and  Parkinson  Rd,  as  well  as  through  other  nearby   residential   streets.   However,   the   route   through   the   golf   course   was   deemed  preferable.  

The  tap  line  will  be  buried  for  a  length  of  approximately  350  m  from  the  substation  west  to  the  existing  overhead  Hydro  One  poles.  The  line  will  share  the  Hydro  One  and  Woodstock  Hydro  poles  up  to  the  point  of  common  coupling  at  or  adjacent  to  the  Woodstock  TS.    The  overhead   wires   will   have   a   rated   voltage   of   27.6   kV,   which   is   common   on   Hydro   One’s  distribution  network  in  the  area.  Hydro  One  and  Woodstock  Hydro  will  determine  whether  upgrades  are  needed  to  the  existing  poles  to  support  the  additional  cables  and  perform  the  upgrades  at  the  cost  of  the  proponent.    

The   portion   of   the   tap   line   that   will   traverse   the   Cedar   Creek   Golf   Club   lands   may   be  overhead   or   underground   depending   on   the   needs   of   the   golf   course   owners   and   Hydro  One.  

2.1.4. SUBSTATION

The   substation  will   consist   of   an   entrance   from   Firehall   Rd,   an   internal   access   road,   and  fenced-­‐in   metal   enclosures   housing   switchgear   and   communication   hardware   for   the  project.  Substation  electrical  components  typically  consist  of  switchgear,  SCADA,  fuses,  and  other  protection  and  control  systems.    This  equipment  will  be  housed  in  electrical  cabinets  bolted  to  the  concrete  slab  and/or  a  small  e-­‐house  approximately  2.5  m  x  6  m  that  can  be  accessed  by  a  human.    There  is  also  potential  for  a  grounding  transformer  to  be  installed  at  the  substation.  

Page 16: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

12

2.1.5. TURBINE LAYDOWN AREAS AND CRANE PADS

A  turbine  component  “lay-­‐down”  area  covering  approximately  1  hectare  (100  m  x  100  m)  will  be  required  around  each  turbine  during  the  construction  phase.  This  area  is  required  to  store  tower  sections,  blades,  the  nacelle  and  the  rotor  hub  during  the  construction  process  and  decommissioning  processes.  The  crane  pad  will  also  be  located  within  this  area.  

2.1.6. OPERATIONS AND MAINTENANCE BUILDING

An   Operations   and  Maintenance   building  may   be   constructed   to   support   the   operational  phase  of   the  project.    The  building  would  have  dimensions  up   to  16  m  x  32  m  and  would  host  office  space,  parking  for  4  vehicles,  tools,  equipment,  and  spare  parts  for  the  wind  farm.    New  and  waste  lubricants  and  fluids  would  be  stored  within  the  facility.  An  area  within  the  building  would  be  built  to  a  standard  suitable  for  hazardous  waste  storage  so  that  any  leaks  or  spills  of  waste  lubricants  from  the  site  are  contained  and  prevented  from  contacting  the  ground  or  surface  water.  

2.2. FACILITY OPERATION PLAN

2.2.1. WIND TURBINE OPERATION AND MAINTENANCE

Turbine  operation  and  maintenance  (O&M)  will  be  either  contracted  to  a  specialized  third  party   service   provider   or   handled   by   a   project   owner   possessing   infrastructure   and  capabilities   for   this   activity.     The  O&M   service   provider  will   have   a   staff   of   trained  Wind  Turbine   Technicians,   Site   Supervisors,   and   a   data   monitoring   centre   located   in   the   O&M  building  (if  constructed)  and/or  off-­‐site  to  monitor  the  status  of  each  turbine  24  hours  per  day,  365  days  per  year.  

The  scope  of  the  activities  will  include  day-­‐to-­‐day  monitoring  and  operation  of  the  turbines  via  SCADA  hardware  and  fibre  optic  communication  linkage  as  well  as  on-­‐going.  maintenance  required  on-­‐site.  

2.2.2. MAINTENANCE

The  wind  turbines  will  be  subject  to  periodic  inspection  and  maintenance,  including  routine  motor   maintenance,   and   lubricant   and   fluid   replacement.     To   ensure   proper   operational  output  and  safety,   the  wind  turbines  will  be  maintained  by  certified  technicians  according  to  the  schedules  recommended  by  equipment  manufacturers.  

Regular  maintenance  activities  will  be  performed  by  a  small  crew  (2-­‐4  people)  accessing  the  site   using   a   pick-­‐up   truck.     Periodically,  major   components   of   the  wind   turbines   such   as  blades   or   generators   may   require   replacement.     Major   component   replacement   will   be  performed  with   similar   equipment   and  methods   to   those   used   in   the   construction   phase,  including   cranes   and   oversized   vehicles   for   transportation.     Crane   pads   will   be  reconstructed  as  necessary  for  this  activity.    

Scheduled  maintenance  will  include  the  following:  

• Visual  inspection;  

• Inspection  of  mechanical  components;  

• Inspection  of  electrical  components;  and,  

Page 17: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

13

• Greasing  and  general  maintenance.  

Initial  visits  for  planned  maintenance  are  more  frequent,  slowing  to  once  every  six  months  or  more  as  the  Project  matures.    Maintenance  of  each  wind  turbine  usually  takes  one  day  to  complete.  

The  proponent  will  also  provide  unscheduled  maintenance   for   the   turbine  units  when  required.  Maintenance  and   inspection  related   to   the  electrical  collector  system  will  be  sub-­‐contracted.    

2.2.3. WASTE MANAGEMENT

Waste  generated  during  operations  will  be  removed  by  a  licensed  operator  and  disposed  of  at  an  approved  facility.  Recycling  services  will  be  used  to  the  extent  available.  

2.3. EMERGENCY RESPONSE AND COMMUNICATION PLAN

The  Emergency  Response  and  Communication  Plan,  which  will  be  filed  with  the  Ministry  of  the  Environment  and  the  municipalities,  will  include  details  on:    

• Emergency   Action   Plans   for   outlining   steps   to   be   taken   in   the   event   of   an   on-­‐site  emergency;    

• Ongoing  Communication  to  update  the  community  throughout  the  construction  and  operations  phase;  and  

 • Complaints  Resolution  Process  for  dealing  with  any  questions  or  concerns.  

 

2.4. ENVIRONMENTAL EFFECTS MONITORING PLAN - SECTION 6

This  section  provides  a  summary  of  some  of  the  potential  effects,  mitigation  measures  and  monitoring  commitments  from  the  effects  assessment.  For  the  full  effects  assessment,  refer  to  the  Design  and  Operations  Report.    

2.4.1. CULTURAL HERITAGE

In  accordance  with  O.  Reg.  359/09,  a  Heritage  Impact  Assessment  (HIA)  was  undertaken  for  the   Project,   and   is   included   within   the   Archaeological   Assessment   and   Cultural   Heritage  Resources  Report.  

Two  HIAs  were  completed  for  this  project  –  1-­‐  wind  farm  area  excluding  the  overhead  cable  route,   2   -­‐   overhead   cable   route.     The   results   of   both   reports   have   been   merged   for   the  following  summary.  The  Heritage  Impact  Assessments  determined  that:    

• There  are  no  protected  properties  within  the  Project  Study  Area;    

• 32  properties  with  potential  built  heritage  resources  are  within  the  Study  Area  (  32   of   which   are   of   cultural   heritage   value   or   interest);   these   will   not   be  negatively  impacted  by  the  Project;  and,  

Page 18: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

14

• 3  potential  cultural  heritage  landscapes  are  within  the  Study  Area;  these  will  not  be  negatively  impacted  by  the  Project.    

Potential Effects

As  operational   and  maintenance  activities  will  not  occur  on   the  properties   containing   the  built   heritage   resources   and   cultural   heritage   landscapes,   no   adverse   effects   on   heritage  resources  are  anticipated  during  operations.      

The   Heritage   Impact   Assessment   Reports   determined   that   the   proposed   Project  infrastructure  will  not  result  in  the  direct  or  indirect  obstruction  of  any  significant  views  or  vistas   within,   from,   or   of   built   or   natural   features   associated   with   the   built   heritage  resources   or   cultural   heritage   landscapes.     Significant   views   and   vistas   are   not   heritage  attributes  of  any  of  the  properties  with  identified  heritage  resources.  .      

Mitigation Measures

As  no  potential  effects  are  likely  to  occur  as  a  result  of  the  Project  on  heritage  resources,  no  mitigation  measures  are  necessary.    The  Heritage  Impact  Assessment  Reports  recommended  that  “the  Gunn’s  Hill  Wind  Farm  be  released  from  further  heritage  concerns”.    

Net Effects

No  net  effects  are  anticipated.  

2.4.2. ARCHAEOLOGICAL ASSESSMENT

In   accordance   with   O.   Reg.   359/09,   a   Stage   1   Archaeological   Assessment   and   Stage   2  Archaeological  Assessments  were  completed  for  the  Project.      

A   Stage   2   Archaeological   Assessment   was   recommended   for   all   areas   of   archaeological  potential  within  the  Project  Location  including  the  areas  proposed  for  access  roads,  parking  lot,  optional  O&M  Building,  collector  lines,  turbines  and  the  distribution  substation.  

The  Stage  2  assessment   indicated   that   “…a  single  First  Nations   findspot  was  encountered.  The  First  Nations   findspot,   an   isolated   individual   artifact,  does  not   represent  a   significant  planning  concern.  No  further  work  is  recommended  at  this  location.”  

Potential Effects

There  are  no  areas  that  will  be  excavated  during  the  operation  phase  that  will  not  have  been  assessed   by   a   Stage   2   Archaeology   Assessment;   therefore   no   potential   effects   are  anticipated  to  archaeological  resources.      

Mitigation Measures

No  potential  effects  are  anticipated  during  operation  and  therefore  no  mitigation  measures  are  necessary.  

Net Effects

No  net  effects  are  anticipated.    

2.4.3. Natural Heritage Resources (such as wetlands and forests)

Wetlands  

Page 19: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

15

There   were   five   (5)   wetlands   identified   within   the   Zone   of   Investigation.   None   of   the  wetlands  will  be  directly  impacted  by  the  Project  and  therefore  assumed  to  all  be  significant  features.    There  will  be  no  impacts  to  wetlands  from  Operation  of  the  wind  farm,  so  there  were  no  mitigation  measures  suggested  for  this  period  of  the  wind  farm  life  cycle  

Woodlands  

Four   (4)   significant  woodlands   are   located  within   the   Zone   of   Investigation.   None   of   the  woodlands  will  be  directly  impacted  by  the  Project.  There  will  be  no  impacts  to  woodlands  from  Operation  of  the  wind  farm,  so  there  were  no  mitigation  measures  suggested  for  this  period  of  the  wind  farm  life  cycle.  

Potential Effects

No   direct   effects   are   anticipated   to   significant   woodlands   as   a   result   of   operation   or  maintenance  activities.      

Indirect  impacts  may  occur  to  significant  woodlands  due  to  erosion.      

During   operation   and  maintenance   of   the   facility,   some  materials   such   as   lubricating   oils  and  other  fluids  associated  with  turbine  maintenance  have  the  potential  for  discharge  to  the  on-­‐site  environment  through  accidental  spills.      

Mitigation Measures

Mitigation  measures  related  to  erosion  and  accidental  spills  are  outlined  in  the  Construction  Plan  Report.    

Net Effects

Indirect  impacts  are  expected  to  be  short-­‐term  in  duration,  and  highly  localized.    Accidental  spills   would   be   spatially   limited   and   of   short   duration   and   protocols   to   minimize   their  impact  would  be  provided  in  the  Emergency  Preparedness/Response  Plan.  

Significant  Wildlife  Habitat  

The  following  significant  wildlife  habitats  were  identified  within  the  Zone  of  Investigation.  These  wildlife  habitat   are   all   potentially   significant   and   required   further  pre-­‐construction  surveying  to  accurately  determine  their  significance.  

• Bat  Maternity  Colonies  (2  locations)  

• Amphibian  Wetland  Breeding  (1  location)  

Potential Effects

The   potential   effects   to   amphibian   species   from   the   Project   are   primarily   from   the  Construction  period  when   increased   traffic  will   be   on   site.   Traffic   from  maintenance  may  pose  a  risk  if  this  habitat  is  determined  to  be  significance.  These  species  are  at  risk  of  harm  from  vehicular  traffic  as  the  habitat  area  is  adjacent  to  an  access  road.  If  these  species  cross  or  rest  on  the  road,  they  are  at  risk  from  maintenance  crews  travelling  to  the  turbines.  

The  candidate  Bat  Maternity  Colony  is  at  risk  from  the  turbine  operation  as  the  habitats  are  adjacent   to   the   location   of   a   proposed   turbine.   The   bats   are   at   risk   of   collision   with   the  turbine  or  avoidance  of  their  habitat  if  the  turbine  is  a  disturbance.  

Page 20: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

16

Mitigation Measures

Pre-­‐construction   surveys   for   all   of   the   above   potential   significant   wildlife   habitat   will   be  conducted   in   the   upcoming   seasons.   If   any   of   the   habitats   are   found   to   be   significant,  mitigation  measures  will  be  put  in  place.    

Mitigation  measures  for  amphibian  species  will  include  silt  fencing  located  between  habitat  feature  and  wind  farm  infrastructure  and  education  of  construction  and  maintenance  crews  about  the  risks  at  each  particular  site.    

Mitigation   measures   for   bat   maternity   roosts   will   include   additional   post-­‐construction  mortality  monitoring  to  evaluate  impacts  to  local  populations  as  outlined  below:  

• Bat  mortality  monitoring  at  all  turbines  will  be  conducted  twice-­‐weekly  (3-­‐4  day  intervals)  at  all   turbines   from  May  1st   -­‐  October  31st   for  three  years   following  start  of  operations.    

• Searcher   efficiency   and   carcass   removal   trials   will   be   conducted   seasonally  (spring,  summer,  and  fall)  between  May  1  and  October  31,  and  repeated  for  each  searcher.   Searcher  efficiency  and  carcass   removal   rates  are  known   to  be  more  variable   for  bats   than   for  birds   throughout   the  year   and  depending  on  habitat  (in  part  due  to  the  relative  size  of  the  species).      

• Regular   reporting   that   includes  analysis   and   submission  of   results   to   the  MOE  and  MNR.  

If  significant  mortality  events  do  occur,  mitigation  measures  such  as   feathering  the  blades  or  increasing  the  cut-­‐in  speed  of  the  turbines  may  be  enacted.  

Net Effects

Given   the   agricultural   land   use   in   the   area   and   the   low   potential   for   significant   wildlife  habitat  in  this  area,  effects  are  likely  to  be  low.  With  the  application  of  proposed  mitigation,  minimal  net  effects  are  predicted  for  amphibian  and  bat  habitats.    

Consultation  with  the  MNR  will  be  ensured  should  significant  impacts  to  any  species  in  the  area  be  identified.  

Generalized  Significant  Wildlife  Habitat  

In  addition  to  the  significant  wildlife  habitats,  the  following  Generalized  Significant  Wildlife  Habitats  were  identified  within  the  Zone  of  Investigation:    

• Species  of  Conservation  Concern  –  River  Bluet  (Damselfly)  (2  locations)  

• Terrestrial  Crayfish  (4  locations)  

• Seeps  and  Springs  (1  locations)  

Potential Effects

Potential   effects   to   Species   of   Conservation  Concern   –  River  Bluet,   Terrestrial   Crayfish   or  Seeps   and   Springs   from   the   Construction,   Operation   and   Maintenance   and  Decommissioning   periods   of   the  wind   farm   life   cycle   include   general   habitat   disturbance  such  as  soil  erosion,  vegetation  removal,  surface  water  contamination.  

Page 21: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

17

Mitigation Measures

The   primary  mitigation  measure   is   to   locate   project   activities   away   from   these   habits   as  best  as  possible.   IF  construction  activities  are   located  within  30  m  of   the  of  habitat  areas,  siltation   fencing   or   straw   bales   will   be   used   to   protect   the   features   from   overland   flow  causing  erosion,  and  contamination.    

In  the  unlikely  case  that  vegetation  is  required  to  be  removed,  the  area  will  be  rehabilitated  with  similar  vegetation  species.  

Net Effects

Given  the  agricultural  land  use  in  the  area,  effects  are  likely  to  be  low.  With  the  application  of  proposed  mitigation,  minimal  net  effects  are  predicted  for  generalized  wildlife  habitat.    

2.4.4. WATER BODIES AND AQUTIC RESOURCES

It  is  not  anticipated  that  operation  of  the  Project  will  adversely  affect  groundwater  quality,  quantity  or  movement.  Some  materials,  such  as  fuel,  lubricating  oils  and  other  fluids  associated  with  turbine  maintenance  have  the  potential  for  discharge  to  the  on-­‐site  environment  through  accidental  spills  

Water  contamination  is  possible,  although  unlikely,  due  to  accidental  spills  associated  with  maintenance  activities.    A  spill  response  plan  will  be  developed  and  an  emergency  spill  kit  will  be  kept  on  site.  In  addition,  the  Ministry  of  the  Environment  and  the  local  municipalities  will  be  notified  of  any  spills.  

Eight   REA   water   bodies   were   identified   within   the   Zone   of   Investigation.   Two   will   be  crossed  by  underground  collector  lines  and  five  will  be  crossed  by  overhead  feeder  line.  One  Water   Body   is   more   than   30   m   from   the   overhead   feeder   line   and   does   not   require  environmental  effect  and  mitigation  measures  analysis.  No  access  roads  are  located  within  120  m  of  a  water  body.  

Potential Effects

The  potential  for  effects  on  watercourses  during  operation  exists  from  soil  erosion  resulting  from   maintenance   activities   (removal   of   stabilizing   vegetative   cover).   Erosion   can   cause  downstream   sediment   transport   and   a   short-­‐term   increase   in   surface   water   turbidity,  including   associated   impacts   to   fish   and   fish   habitat.   The   magnitude   and   duration   of  potential  effects  to  watercourses  depend  on  the  specific  characteristics  of  each  watercourse  (e.g.  flow  regime,  water  velocity,  bed  substrates,  bank  conditions,  local  soils  and  the  extent  and   duration   of   exposure).   In   addition,   some  materials,   such   as   fuel,   lubricating   oils   and  other   fluids   associated   with   turbine   maintenance   have   the   potential   for   release   to   the  environment  in  the  event  of  accidental  spills.    

Mitigation Measures

Mitigation  measures  related  to  sedimentation  and  erosion  would  be  the  same  as  discussed  in  Section  5.10  and  5.9  respectively  of  the  Construction  Plan  Report.    

The   Emergency   Preparedness/Response   Plan   (Section   4.2.1)  will   contain   procedures   for  spill   contingency  and   response  plans,   spill   response   training,  notification  procedures,   and  necessary   cleanup  materials   and   equipment.   As   per   S.13   of   the  Environmental  Protection  Act,   all   spills   that   could  potentially   have   an   adverse   environmental   effect,   are   outside   the  

Page 22: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

18

normal  course  of  events,  or  are  in  excess  of  prescribed  regulatory  levels  will  be  reported  to  the  MOE’s  Spills  Action  Centre.  

Construction  activities   located  within  120  m  of   fish  habitat  will  consider  the  sensitive   fish  spawning  and  rearing  period  of  March  15  to  June  30,  if  possible,  

Net Effects

Provided   that   maintenance   activities   are   performed   properly,   no   adverse   net   effects   on  surface  water  features  and  fish/fish  habitat  are  anticipated  during  operation  of  the  Project.  

2.4.5. Emissions to Air

Maintenance  vehicles  may  create  dust  and  increase  emissions  to  air.  To  reduce  the  amount  of   dust   generated,   the   speed   of   maintenance   vehicles   will   be   limited.   All   construction  vehicles  will  meet  provincial  emissions  regulations.  

2.4.6. Noise

The   operation   of   turbines   and   the   substation   may   increase   noise   levels   experienced   by  some   residents.   Turbines  will   be   set   back   at   least   550  m   from   all   residents  who   are   not  leasing   their   land   for   the   Project   to   avoid   or   lessen   the   effects.   Noise  modeling  was   also  conducted   to   predict   and   ensure   that   noise   levels   from   the   operating   turbines   and  substation  will   not   be   greater   than   limits   set   by   the  Ministry   of   Environment.   Any   noise-­‐related  complaints  will  be  tracked  and  follow-­‐up  monitoring  will  occur  as  required.  

2.4.7. Local Interests, Land Use and Infrastructure

Turbines,  access  roads,  and  the  substation  will  result  in  a  minor  reduction  in  usable  agricultural  land.  To  avoid  or  lessen  these  effects,  the  length  of  access  roads  will  be  minimized  where  possible.  

2.4.8. Surveying and Geotechnical Studies

Potential   effects   on   human   health   and   safety   could   occur   from   ice   shed   (ice   falling   from  turbine  blades).  To  avoid  or  mitigate  these  effects,  all  setback  distances  will  be  adhered  to.  Shadow   flicker   (a   “flicker”   caused   when   rotating   turbine   blades   are   directly   between   a  viewer   and   the   sun)   represents   a   potential   annoyance   to   some   residents   under   certain  conditions   and   the   effect   is   reduced   by   adhering   to   the   required   setback   distances.   Any  safety  or  other  complaints  will  be  tracked  and  follow-­‐up  monitoring  will  occur  as  required.  

 2.4.9 Conclusions

The   overall   conclusion   of   the   Design   and   Operations   Report   is   that   this   Project   can   be  operated  without  any  remaining  effects  that  could  harm  the  environment.  Post-­‐construction  monitoring   related   to   effects   on   wildlife,   including   birds   and   bats,   will   be   undertaken   to  confirm  this  conclusion.  

     

Page 23: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

19

3. CONSTRUCTION PLAN

The  purpose  of  the  Construction  Plan  Report  is  to  describe  all  activities  that  are  part  of  the  Project’s   construction   phase   so   that   possible   negative   environmental   effects   can   be  identified.   The   report   also   presents   mitigation   measures,   monitoring   commitments   and  residual  effects,  if  any.  Residual  effects  are  “left  over”  effects  once  mitigation  measures  have  been  applied.  

The  Construction  Plan  Report  was  prepared  in  accordance  with  the  requirements  outlined  in   Ontario   Regulation   359/09,   the   regulation   governing   renewable   energy   projects   in  Ontario.  

The   land  proposed  to  host   the  wind  turbines,  buried  cable,  access  roads  and  substation   is  bounded  by  Firehall  Road  to  the  north,  Oxford  Road  14  to  the  east,  Gunn’s  Hill  Road  to  the  south   and   Oxford   Road   59   to   the   west.     This   land   is   privately   owned,   agricultural   land  neighbouring   the  Hamlets  of  Oxford  Centre   and  Curries,  Ontario;   located   southeast  of   the  City  of  Woodstock,  Ontario.  The  overhead  cable  is  proposed  within  municipal  road  Right-­‐of-­‐Ways  within  The  Township  of  Norwich  and  the  City  of  Woodstock.  

3.1. CONSTRUCTION ACTIVITIES

In   general   terms,   the   construction   phase   of   a   wind   project   consists   of   site   preparation,  construction  and   installation  of  project   infrastructure,  and  site   rehabilitation.  All  of  which  can  be  ongoing  concurrently  as  work  progresses  across  the  project  area.  

All   project   activities   will   be   undertaken   according   to   current   guidelines   provided   by  governmental   agencies,   Township   of   Norwich,   City   of   Woodstock,   Electrical   Safety  Authority,  Hydro  One,  Woodstock  Hydro  and  the  turbine  manufacturer.  

3.1.1. Surveying and Geotechnical Studies

Surveys   are   required   to   identify   locations   of   major   Project   components;   this   involves  surveyors  walking   around   the   sites   and  marking   locations   using   stakes.     Surveying  work  will  be  carried  out  by  a  crew  in  one  or  two  four-­‐wheel  drive  pickup  trucks.  

Geotechnical   sampling   is   required   to   locate   turbine   foundations;   this   involves   drilling  boreholes  to  collect   information  on  the  type  of  soil  below  ground.  Boreholes  will   likely  be  drilled  using  a  truck  mounted  drill  rig  (~30  ton).  Should  field  conditions  be  prohibitive  for  the  use  of  a  truck  mounted  drill  rig,  a  drill  rig  mounted  to  a  tracked  vehicle  will  be  used.  The  tracked  vehicle  will  be  transported  the  site  on  a  16  m  flatbed  trailer.  

 

3.1.2. Land Clearing And Construction Of Access Roads

Land   clearing   is   necessary   to   prepare   the   land   surface   to   facilitate   further   construction  activities.  As  the  project  is  located  in  intensively  cultivated  agricultural  fields,  there  is  little  vegetation  clearing  required  and  land  clearing  will  mostly  entail  the  removal  of  topsoil  from  work  areas  and   the  preparation  of   the  subsoil.  First,   the   land   is   cleared  and   the   topsoil   is  removed,  stored  for  later  use  and  replaced  with  a  layer  of  gravel.    

Page 24: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

20

Land  clearing  will  occur  for  the  construction  of  access  roads,  tower  foundations,  crane  pads,  lay-­‐down   areas,   and   some   of   the   underground   electrical   network.   The   turbines   will   be  located  within  existing  agricultural   fields,  with  the  crane  pads  and   lay-­‐down  areas   located  next  to  each  foundation.  Access  roads  are  placed  along  field  edges  and  existing  farm  roads  where   possible   to   minimize   disruption   to   agricultural   practices,   in   discussion   with   the  landowners.    The  electrical  cabling  will  be  placed  adjacent  to  access  roads  where  possible  and  within  the  municipal  road  allowance  along  Middletown  Line  and  Firehall  Rd  which  will  minimize   land   clearing   requirements.     The   equipment   used   for   land   clearing   will   be   the  same  equipment  used  to  construct  access  roads.  

Access  roads  and  crane  paths  will  be  11  m  wide  during  the  construction  phase  and  are  required  to  transport  equipment  to  the  turbine  location  construction  sites.    

The  access  road  layout  has  been  designed  to  minimize  impacts  to  the  natural  environment  and   farming   practices   while   utilizing   existing   entrances   to   the   greatest   extent   possible.  Access  roads  will  be  built  on  private  land  and  will  be  privately  maintained.  Maintenance  of  the  roads,  including  snow  removal,  is  the  responsibility  of  the  wind  farm  operator  and  will  be   contracted   to   a   local   service   provider.   There   is   potential   for   entrances   from   public  roadways  to  be  gated,  pending  detailed  consultation  with  local  emergency  services  and  the  landowners.    

Access   roads  will  have  a   foundation  of   ‘grade  B’  gravel  and  a   finished  surface  of   ‘grade  A’  gravel,  sourced  from  a  local  aggregate  quarry  and  delivered  to  the  site  in  dump  trucks.    The  access  roads  will  be  built  to  a  width  of  6  m  and  be  slightly  graded  to  self-­‐drain  toward  each  edge.  Access  roads  will  be  built  such  that  the  edge  of  the  road  is  roughly  flush  with  the  field  surface  to  maintain  existing  drainage  patterns  and  farming  operations.  

Any  culverts  at  entrances  along  Curries  Rd,  Middletown  Line,  and  Firehall  Rd  may  require  upgrading   to   accommodate   the   increased   turning   radius   and   load   capacity   needed   for  delivery   of   turbine   components   and   construction   equipment.   The   design   of   upgraded  culvert   installation   will   comply   with   local   municipal   and/or   conservation   authority  regulations  and  will  prevent  impacts  to  upstream  and  downstream  landowners.    Upgraded  culverts   will   only   be   required   for   entrances   to   span   the   roadside   ditch;   no   natural  watercourses  will  be  crossed  by  access  roads.  

3.1.3. Construction Of Crane Pad and Laydown Areas

A  turbine  component  “lay-­‐down”  area  covering  approximately  1  hectare  (100  m  x  100  m)  will  be  required  around  each  turbine  during  the  construction  phase.  This  area  is  required  to  store  tower  sections,  blades,  nacelle  and  rotor  hub  during  the  construction  process.    It  may  also  host  a  portable  field  office  trailer  and/or  a  portable  storage  container.      

The  lay-­‐down  area  will  be  cleared  and  the  topsoil  may  be  stockpiled  and  seeded  with  native  quick-­‐sprouting  grass  and/or  covered  with  a  geo-­‐textile  to  prevent  wind  erosion.  Stockpiles  will   be   located   outside   of   the   floodplain,   if   applicable.   The   lay-­‐down   area   will   then   be  covered   with   gravel   sourced   from   a   local   supplier   and   transported   to   the   site   via   dump  truck.  

The  crane  pad  will  be  located  within  the  lay-­‐down  area.  The  surface  area  of  the  crane  pad  will   be   approximately   20   m   x   40   m   (800   m2)   at   each   location.   The   crane   pad   will   be  constructed  of  the  same  gravel  material  as  the  access  roads.  

Page 25: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

21

At  the  end  of  the  construction  period,  the  gravel  will  be  removed  from  the  lay-­‐down  area  with  the  exception  of  the  crane  pad  and  the  topsoil  will  be  returned.    The  topsoil  will  be  returned  to  the  area  to  enable  farming  activity  to  resume.  

3.1.4. Transport Of Turbine Components

The  wind  turbine  and  related  hardware  will  be  transported  to  the  site  via  transport  truck  and  trailer.  Oversized  trucks  will  be  necessary  to  transport  turbine  components  and  some  construction  equipment.    

Not   including   the   foundation  construction,  each   turbine  will   require  12  heavy-­‐haul   trucks  listed  below  for  transportation  of  the  plant  components  listed  below:    

• 5  for  tower  sections    • 1  for  the  hub    • 1  for  the  nacelle    • 1  for  the  parts  container  • 1  for  miscellaneous  components    • 3  for  the  rotor  blades  

These  components  will  be  stored  within  the  designated  lay-­‐down  area  until  assembly.    The  only   chemicals   required   for   this   phase   are   oils,   gasoline,   and   grease   used   to   operate  construction  equipment.  Fuel-­‐handling  will  be  conducted  in  compliance  with  the  mitigation  measures  outlined  below.  

The  load  restrictions  on  the  municipal  roads  during  March  and  April  will  be  respected  for  all  traffic  related  to  the  wind  farm  construction  

3.1.5. Construction Of Turbine Foundations

Turbine   foundation   construction   begins   with   the   removal   and   stockpiling   of   topsoil.    Excavated   topsoil   will   be   stockpiled   in   low-­‐lying  windrows   and   used   for   back-­‐filling   and  grading   operations   once   the   foundation   construction   is   complete   and   the   site   is  rehabilitated.      

Typically,  shallow  spread  foundations  are  18  m  in  diameter  and  2  m  deep.  A  reinforced  steel  frame  is  constructed  first  and  then  concrete  will  be  poured  for  each  foundation.    

3.1.6. Wind Turbine Assembly And Installation

Once  turbine  foundations  are  complete  and  the  concrete  has  set,  the  turbines  will  be  constructed,  usually  in  five  lifts  by  a  crane  (three  for  the  towers,  one  for  the  nacelle  -­‐  which  houses  the  main  components  of  the  wind  turbine  such  as  the  rotor  shaft,  control  panel,  generator,  etc.  -­‐  and  one  for  the  rotor  with  the  blades  already  mounted).    

The   cranes   will   be   moved   from   turbine   to   turbine   via   wind   farm   access   roads   where  possible   and   will   be   disassembled,   loaded   onto   flatbed   trailers   and   re-­‐assembled   when  driving  the  crane  from  turbine  to  turbine  is  not  possible.  

3.1.7. Construction Of Electrical Network

The  electrical  collection  system  is  used  to  collect  and  deliver  the  power  generated  from  the  turbines   to   a   common   point   and   subsequently   the   provincial   distribution   grid.     A  combination  of  underground  and  overhead  wires  will  be  installed.      

Page 26: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

22

The  collection  system  consists  of  three  electrical  cables  running  at  a  system  voltage  of  27.6  kV,  a  neutral  ground,  and  a  fibre  optic  cable.  The  fibre  optic  cable  is  used  for  communication  between  turbines.  

The   collection   system   cables   connect   to   the   transformer   at   the   base   of   each   turbine   and  subsequently  connect  to  the  other  turbines  along  the  collection  system  route.    A  T-­‐Junction  box  will  be  used   to   join   radial  arms  of   the  collection  system  and   to   splice   cables   together  where  required.    

The   cables   running   along   Middletown   Line   and   Firehall   Road   will   be   buried   within   the  municipal  road  allowance.  Road  easement  permits  will  be  obtained  from  the  municipality,  where  necessary.  The  underground  collection   system  will   terminate  at   the  project-­‐owned  substation  on  Firehall  Rd.    

A  feeder  line  will  be  used  to  connect  the  project  to  the  existing  provincially  controlled  grid.  The  routing  of  the  feeder  line  was  selected  to  follow  the  most  direct  path  that  has  existing  hydro  poles  back   to   the  point  of   common  coupling  with   the  provincial  electrical  grid.  The  selected  route  follows  Hydro  One’s  M4  feeder  to  the  low  voltage  bus  of  the  Woodstock  TS.  Where  the  M4  feeder  traverses  the  Cedar  Creek  Golf  Club,  alternate  routes  were  considered  along   Juliana   Dr,   Norwich   Ave,   and   Parkinson   Rd,   as   well   as   through   other   nearby  residential  streets.  However,  the  route  through  the  golf  course  was  deemed  preferable.  

The  feeder  line  will  be  buried  for  a  length  of  approximately  350  m  from  the  substation  west  to  the  existing  overhead  Hydro  One  poles.  The  line  will  share  the  Hydro  One  and  Woodstock  Hydro  poles  up  to  the  point  of  common  coupling  at  or  adjacent  to  the  Woodstock  TS.    The  overhead  wires  will  have  a  rated  voltage  of  27.6  kV.  Hydro  One  and  Woodstock  Hydro  will  determine   whether   upgrades   are   needed   to   the   existing   poles   to   support   the   additional  cables   and   perform   the   upgrades   at   the   cost   of   the   proponent   Appropriate   permits   and  agreements  will  be  obtained  prior  to  the  construction  phase.  

The   portion   of   the   feeder   line   that  will   traverse   the   Cedar   Creek   Golf   Club   lands  may   be  overhead   or   underground   depending   on   the   needs   of   the   golf   course   owners   and   Hydro  One.  

3.1.8. Construction Of Substation

The  substation  will  be  located  on  the  south  side  of  Firehall  Road  approximately  60  m  east  of  the   buried   cable   line   coming   from  Turbine   1.     Construction  will   involve   the   removal   and  storage   of   topsoil   from   a   40   m   x   80   m   area.   This   will   be   performed   using   an   excavator  and/or  bulldozer.  The  displaced  top  soil  will  be  applied  to  adjacent  land  of  the  same  owner.  The   substation   area   will   then   be   leveled   and   covered   with   a   layer   of   engineered   gravel  delivered  by  approximately  6  dump  trucks.    Concrete  slab  foundations  will  then  be  poured  on   top   of   the   engineered   gravel   to   form   platforms   for   electrical   cabinets   and   the  transformer.   Concrete   for   the   platforms   will   arrive   onsite   via   approximately   3   concrete  trucks.  

Substation   electrical   components   typically   consist   of   switchgear,   SCADA,   fuses   and   other  protection   and   control   systems,   a   metal   lattice   tower   or   wooden   utility   pole   with   an  antenna,  (there  is  no  transformer  present  at  the  substation).    This  equipment  is  housed  in  grey  electrical  cabinets  bolted  to  a  concrete  foundation.    This  equipment  will  be  brought  to  the  site  on  flatbed  trucks  that  may  be  equipped  with  a  boom  to  unload  the  equipment.  

Page 27: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

23

A  chain  link  fence  will  be  installed  around  the  substation  for  safety  and  security  purposes.  The   fencing  material   will   be   sourced   from   a   local   building   supplies   provider   and  will   be  delivered  in  approximately  3  loads  from  a  flatbed  truck  with  a  boom.    

3.1.9. Construction Of Operation And Maintenance Building

An   Operations   and  Maintenance   building  may   be   constructed   to   support   the   operational  phase   of   the   project.     The   building   will   have  maximum   dimensions   of   16  m   x   32  m   and  would   host   office   space,   parking   for   approximately   4   vehicles,   tools,   spare   parts,   and  equipment  for  the  wind  farm.  Both  new  and  waste  fluids  would  also  be  temporarily  stored  at   the   facility   before   and   after   use   respectively.   Waste   fluids   would   be   stored   until   a  qualified   service   provider   can   remove   them.   A   physical   spill   containment   area   would   be  constructed  within  the  building  for  the  fluids.      

3.1.10. Clean Up And Site Reclamation

Site  clean-­‐up  will  occur  throughout  the  construction  phase  and  site  reclamation  will  occur  after  construction  has  been  completed.    

Materials  will  be  recycled  as  much  as  possible  and  waste  will  be  removed  from  the  site  and  disposed  of  at  an  appropriate  facility.    

All  disturbed  areas  will  be  restored  with  the  stockpiled  soil  and  reseeded,  as  appropriate.      

3.2. CONSTRUCTION AND INSTALLATION SCHEDULE

The  proposed  construction  and  installation  schedule  is  listed  below.  Due  to  factors  such  as  weather  and  equipment  availability,  wind  farm  construction  schedules  are  subject  to  minor  variation.      Construction  activity  is  proposed  to  occur  between  the  hours  of  7:00  –  21:00  up  to  7  days  per  week  as  a  maximum  scenario.  More  typically,  construction  will  occur  between  7:00   –   17:00,   6   days   per   week.   Based   on   community   feedback,   activities   producing   high  levels   of   noise   will   be   limited   to   08:00   –   20:00.   The   likely   start   time   for   construction   is  January  2014.  

3.2.1. Schedule

Activity   Days  Surveying   4  Land  Clearing   14  Access  Road  Construction   14  Crane  Pad  Construction   12  Electrical  Network  Installation   60  Substation  Construction   14  Foundation  Construction   90  Turbine  Installation   30  Turbine  Commissioning   20  Site  Rehabilitation   12    

Page 28: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

24

3.2.2. Timeline

A   general   timeline   of   the   construction   and   installation   activities   is   depicted   below.     This  timeline  represents  a  conservative  estimate  for  construction  duration.    

Page 29: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

June 2013

25

4. DECOMMISSIONING

The   purpose   of   the   Decommissioning   Plan   Report   is   to   describe   all   activities   involved   in  dismantling   or   decommissioning   of   the   Project   at   the   end   of   the   operations   phase.   The  report  also  explains  how  the  Project  owner  will  restore  the  land  and  manage  excess  water  or  waste.  

The   Decommissioning   Plan   Report   was   prepared   in   accordance   with   the   requirements  outlined  in  Ontario  Regulation  359/09,  the  regulation  governing  renewable  energy  projects  in  Ontario.    Corresponding  section  references  are  provided  below  to  assist  with  reviewing  the  associated  reports.  

The   anticipated   life   of   the   Project   is   approximately   20   years.   Decommissioning   typically  occurs  following  the  operations  phase.  

At   the   end   of   the   Project   life,   the   wind   turbines   may   be   ‘re-­‐powered’,   meaning   turbine  components   could   be   replaced   to   extend   the   life   of   the   Project   and   delay   any  decommissioning   activities.   Alternatively,   the   wind   turbines   may   be   decommissioned.  Project  decommissioning  will   follow  the  Ontario  Occupational  Health  and  Safety  Act  along  with  any  applicable  municipal,  provincial  and  federal  regulations  and  standards.  

 The  following  components  will  be  removed  during  dismantling:  

1.  Turbines;  2.  Overhead  lines  and  poles  (including  point  of  connection);  3.  Substation;  4.  Partial  removal  of  wind  turbine  foundations;  and  5.  Removal  of  turbine  access  roads,  if  required  by  landowners.  

4.1. RESTORATION OF LAND AND WATER

All  areas,  including  the  access  roads,  transformer  pads  and  crane  pads  will  be  restored  as  much  as  practical  to  their  original  condition  with  native  soils  and  seeding.    

Page 30: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

Gunn’s Hill Wind Farm Executive Summary  

                             

APPENDIX A

PROJECT LAYOUT MAP

Page 31: Gunn's Hill Wind Farm Executive Summary June 2013-1€¦ · GUNN’S HILL WIND FARM EXECUTIVE SUMMARY FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A

>

>

>

>

>

>>

>

>

>

CURRIES ROAD

OLD STAGE ROAD

PATTULLO AVENUE

HIGHWAY 59

GUNNS HILL ROAD

FIREHALL ROAD

HIGHWAY 401

OXFORD 14

HIGHWAY 403

CEDAR LINE

OXFORD CENTRE ROAD

ORIEL LINE

PARKINSON ROAD

JULIANA DRIVE

MIDDLETOWN LINE

SWEA

BURG

ROA

D

OLD 14 LINE

COMMERCE WAY

FINKLE STREET

SUBSTATION ROADRIVERS ROAD

HORN ROAD

ATHL

ONE A

VENU

E

DODGE LINE

BEARDS LANE

RIDGEWAY ROAD

DOVER STREET KEYES DRIVEPAVEY STREET

GREENLY LINE

MIDDLETOWN LINE

HIGHWAY 403

MIDDLETOWN LINE

MIDDLETOWN LINE

4

3

8

2 7

1

6

9

5

10

Gunn's Hill Wind Farm Proposed Project Layout

May 29, 2013Prowind Canada Inc.NAD 83 Zone 171:40,000

!(^̂

0 250 500 750 1,000Meters

^ Gunn's HillOttawa

!( TorontoOntario

Key Map to Project Area´

LegendZone of Investigation (50 m)

Zone of Investigation (120 m)

> Turbine

Blade Swept Area

Access Roads (5 m)

Overhead Cable

Buried Cables

Substation/O&M Building/Parking

Laydown Area

OHN Waterbody (LIO)

OHN Watercourse (LIO)

Wooded Area (LIO)

Existing Roads

Existing Transmission Line

Municipal Boundaries

Participating PropertiesNoise Receptors

! Participating

" Non-Participating (Occupied)

X Non-Participating (Vacant)