1 DG MOVE Seminar – Brussels, 12.07.2012 Guidance material on common projects for SESAR deployment
33

Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

Jun 05, 2018

Download

Documents

doannguyet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

1

DG MOVE Seminar – Brussels, 12.07.2012

Guidance material

on common projects for SESAR deployment

Page 2: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

2

14:30 – 14:45

Welcome & introduction DG MOVE

14:45 – 15:30

Presentation of DG MOVE's orientations on "Guidance material on common projects

for SESAR deployment" DG MOVE

15:30 – 16:00

Coffee break

16:00 – 17:50

Stakeholders' views ICB, EUROCONTROL, Military, PRB, EASA, PSO

17:50 – 18:20

Discussion / Q&A

18:20 – 18:30

Conclusions DG MOVE

Today's agenda

Page 3: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

3

• Renewed approach

• Deployment instruments

• SESAR deployment setup sequence

• Executing SESAR deployment

• Next steps

Content of the seminar

• Conclusions

Page 4: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

A renewed approach Preparing a legislative proposal

4

Page 5: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

Discussion paper

DG MOVE orientations Master plan's central role

Common projects: appropriate SES implementation tools

3 level governance OK

Deployment programme – project view of deployment

Deployment manager – sole accountable leader in level 2

European Commission – sole politically accountable leader in level 1

A renewed approach 5

Page 6: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

6

Deployment instruments Creating the right conditions

Page 7: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

7

• Updated ATM Master plan

• Guidance material

• Deployment governance

• Common projects

• Deployment manager

• Deployment programme

• Implementation projects

Deployment instruments

• Incentives

Page 8: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

8

Guidance material an EU framework for SESAR deployment

• Establishes the deployment governance

• Further develops the definition of common projects

• Defines the overall scope & characteristics of implementation projects

• Defines incentives for common projects

Deployment instruments

Page 9: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

9

Political

Management

Implementation

P1 P2 P3 Pn …

project managers

TEN-TEA

European Commission

Deployment manager

Single Sky Committee

NSA

Network Manager

SESAR JU

Experts group on SES social dimension

ICB

EASA

PRB

Eurocontrol (DSS)

EDA /military coordination

Deployment governance

Deployment instruments

Page 10: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

10

Common projects Defining EU agreed deployment objectives

ESSIP objectives related to Master plan essential operational changes or from other sources

Technological maturity

Requiring synchronisation

Significant contribution to performance

Further scoping (geographical, stakeholder, planning)

Airspace users-endorsed global CBA

Relevant incentives

Relevant regulatory actions

Safety compliance

Global interoperability

+

Deployment instruments

Page 11: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

11

Incentives

EU funding through TEN-T CEF

Grants, procurement Equity instruments (funds)

Loans, guarantees

Other incentives

Charging & performance scheme Modulation of charges Unit rate adjustment

Revenues from charges

Focussed intervention

Deployment instruments

Page 12: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

12

SESAR deployment setup sequence

Step by step

Page 13: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

ATM Master plan

Oct. 2012

SESAR Key features >

Deployment sequence

13

Page 14: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

SESAR Key features >

Guidance material Deployment governance

Definition of Common projects Definition of incentives

Oct. 2012

< June 2013

ATM Master plan

Deployment sequence

14

Page 15: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

1 2

3 Guidance material Deployment governance

Definition of Common projects Definition of incentives

SESAR Key features >

Oct. 2012

< June 2013

ATM Master plan

Deployment sequence

15

Page 16: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

1 2

3

SESAR Key features >

Common projects

Guidance material Deployment governance

Definition of Common projects Definition of incentives

+ R&D Validation (SESAR Releases) + Solid CBA + Further scoping + Contribution to performance + Coherence with performance plans + Safety case + Interoperability - ICAO blocks + Stakeholder consensus + Stability + Regulatory measures (IR,CS,…) + Relevant incentives

Oct. 2012

< June 2013

End 2013 ATM Master plan

Essential changes

Synchronisation

Maturity

Pilot

Deployment sequence

16

Page 17: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

Selection of deployment manager & of implementation projects

Common projects

SESAR Key features >

Pilot

Call

Draft deployment programme >

1 2

3 Guidance material Deployment governance

Definition of Common projects Definition of incentives

Oct. 2012

< June 2013

End 2013

Early 2014

ATM Master plan

+ R&D Validation (SESAR Releases) + Solid CBA + Further scoping + Contribution to performance + Coherence with performance plans + Safety case + Interoperability - ICAO blocks + Stakeholder consensus + Stability + Regulatory measures (IR,CS,…) + Relevant incentives

Essential changes

Synchronisation

Maturity

Deployment sequence

17

Page 18: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

End 2014

SESAR Key features >

Draft deployment programme >

Call

Selection of deployment manager & of implementation projects

Pilot

1 2

3

Common projects

Guidance material Deployment governance

Definition of Common projects Definition of incentives

Oct. 2012

< June 2013

End 2013

Early 2014

ATM Master plan

P1 P2 Pn …

Implementation projects Deployment programme

DP

Deployment manager

+ R&D Validation (SESAR Releases) + Solid CBA + Further scoping + Contribution to performance + Coherence with performance plans + Safety case + Interoperability - ICAO blocks + Stakeholder consensus + Stability + Regulatory measures (IR,CS,…) + Relevant incentives

Essential changes

Synchronisation

Maturity

Deployment sequence

18

Page 19: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

Oct. 2012

< June 2013

End 2013

SESAR Key features >

Common projects

Call

Selection of deployment manager & of implementation projects

Pilot

Draft deployment programme >

1 2

3 Guidance material Deployment governance

Definition of Common projects Definition of incentives

Execution End 2014

ATM Master plan

+ R&D Validation (SESAR Releases) + Solid CBA + Further scoping + Contribution to performance + Coherence with performance plans + Safety case + Interoperability - ICAO blocks + Stakeholder consensus + Stability + Regulatory measures (IR,CS,…) + Relevant incentives

Essential changes

Synchronisation

Maturity

P1 P2 Pn …

Implementation projects Deployment programme

DP

Deployment manager

Early 2014

Deployment sequence

19

Page 20: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

20

The "pilot" common project A first approach….

ATM Master plan Inc. ESSIP plan 2012

Moving from airspace to 4D trajectory management

Network Collaborative management and

Dynamic/Capacity Balancing

Airport Integration and Throughput

BASELINE (1)

• PRNAV (NAV03) • APV (NAV10) • A/G DL (ITY-AGDL) • Advance airspace

management (AOM19)

• Collaborative flight planning (FCM03)

• Ground-ground automated co-ordination processes (ITY-COTR)

• Airport CDM (AOP05)

STEP 1 • I4D • Free routing (AOM20)

• Extended AMAN (ATC17)

Network strategy plan SESAR JU’s validation results

(1) Based on the 7 core priorities agreed by the IDSG

Essential changes

Synchronisation

Maturity

Deployment sequence

Page 21: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

21

Adoption as Commission Implementing Regulation

Endorsement by Airspace Users

Deployment sequence

Page 22: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

22

Select proposals for implementation projects

Select the consortium for the deployment manager

Establish a draft deployment programme

Deployment sequence

Deployment manager, deployment programme & implementation projects

One call three objectives

Page 23: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

23

Commits to deploy common projects through the deployment programme & implementation projects

Strong cooperation with Network manager & SESAR JU support from manufacturing industry

Is not delegated the management if EU funds

Deployment manager "Owner" of the deployment programme

Deployment sequence

Page 24: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

24

Deployment manager "Owner" of the deployment programme

Single & accountable leader of level 2

Selected by the Commission (Level 1)

Consortium of civil & military operational stakeholders needed to deploy common projects

A “critical mass” of ANS, ATS, CNS, MET Service providers

Airport operators & Airspace users

Deployment sequence

Page 25: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

25

Deployment programme A comprehensive project view of deployment activities

A binding & "living" work programme for the deployment manager

Initially proposed by the candidate deployment manager

Approved by the Commission with input from the Network manager, the SESAR JU, EDA, TEN-TEA

Identifies implementation projects & coordination mechanisms

Deployment sequence

Page 26: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

26

Implementation projects Synchronised & coordinated deployment of SESAR

Specific coordinated activities to deploy common projects in accordance with the deployment programme

Proposed & executed by members of the deployment manager or

by non-members that accept its overall coordination

Selected by the Commission & Can be co-funded by the EU

Deployment sequence

Page 27: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

27

Executing SESAR deployment

Implementing the deployment programme

Page 28: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

28

Coordination of the execution of the implementation projects

Monitoring the execution of the implementation projects

& reporting to the Commission

Deployment programme management

maintenance revisions impacts of new common projects

Executing SESAR deployment

Page 29: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

29

Industrialisation Bridging between validation & implementation

Role of the manufacturers between industrialisation & implementation

Open & fair competition within manufacturing industry

Advisory role in all 3 levels on industrialisation processes, transition & risks

Ensure timely delivery of products

Support to deployment manager on organising coordination & financial engineering

Standardisation & certification Regulatory & standardisation roadmaps

Natural roles for Eurocae & EASA

SESAR JU facilitation of R&D certification & standardisation

Executing SESAR deployment

Page 30: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

30

Next steps Launching the formal consultation & adoption process

Page 31: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

31

Fine tuning mechanisms & processes

Proposal for guidance material

Start drafting a proposal for a Commission Implementing Regulation

Formal consultation process

Adoption sought before June 2013

Next steps

Page 32: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

32

Stakeholders' views

Page 33: Guidance material on common projects for SESAR deployment · on common projects for SESAR deployment . 2 ... on "Guidance material on common projects for ... PRB, EASA, PSO 17:50

33

Conclusions

Presentations can be found at: http://ec.europa.eu/transport/air/events/2012-07-12-sesar-deployment_en.htm