Grid Development, Operation & Connections within EU Legal Framework Michael Walsh 17 th May 2013
Feb 25, 2016
Grid Development, Operation & Connections within EU Legal
FrameworkMichael Walsh17th May 2013
Overview
• Grid Development - Context and Challenges
• Constraints Reports and ATRs
• Gate 3 Offer Execution
• DS3 Update
Wind Development - Context
Grid Development Strategy to:
• Support energy policies: security of supply, sustainability, competitiveness, efficiency
• Facilitate economic growth in all regions
• Connect renewable and conventional generation
• Increase interconnectivity with other systems
• More than 300 projects
• €3.2bn expenditure
RI NAWADE
STRATFORDBALLYBEG
TIPPERARY
GLENLARA
ATHY
PROSPECT
NENA GH
M ONREAD
TRIEN
DRUMLINE
AHANE
LIMERICK
CASTLEFARM
SEALROCK
TYNAGH
DERRYBRIEN
AGANNYGAL
AUGHINISH
WEXFORD
KIL TEEL
BALLYWATER
GREAT ISLAND
CULLENAGH
TURLOUGHHILL
MAYNOOTH
INCHICORE
CARRICKM INES
NORTH WAL L
SHELL YBANKS
IRISHTOWN
OLDSTREET
FINGLAS
DUNSTOWN
BARODA
HUNTSTOWN
KELLIS
PLATIN
KNOCKUMBER
GORMAN
BALTRASNA
GLASM ORE
CORDUFF
WOODLAND
ATHLONE
GALWAY
LANESBORO
THORNSBERRY
CLOON
SOMERSET
CUSHALING
DALTON
KINNEGAD
BANDON
DUNMANWAY
MACROOM
BRINNY
KILBARRY
M ARINA
CARRIGADROHIDCOOL ROE
TRABEG
HARTNETTS
BALLYLICKEY
’SCROSS
CLONKEEN
COOMAGEARLAHY
GARROW
INNISCARRA
CLASHAVOON
BARRYMOREKNOCKEARAGH
DUNDALK
TANDRAGEE
STRABANE
OMAGH
DUNGANNON
COLERAINE
LOGUESTOWN
LIMAVADY
MAGHERAFELT
TAMNAMORE
KILROOT
MOYLE INTERCONNECTOR
RATHGAEL
NEWTOWNARDS
BALLYNAHINCH
NEWRY
BANBRIDGE
KELLS
BALLYMENA
CREAGH
ANTRIM
DRUMNAKELLYWARINGSTOWN
COOLKEERAGH
BALLYLUMFORDLARNE
LISAGHMORE
LISBURN
CASTLEREAGH
ENNISKILLEN
KNOCKROSEBANK
BALL YVAL LAGH
BC
CG
DG
PW
HT
FINAGHY
GG
CREDEN
KILTOY
CATHALEEN'SFALL CLIFF
BINBANE
GOLAGH
DRUMKEEN
SORNEHILL
TRILLICK
DRYBRIDGE
LOUTHMULLAGHARLIN
SLIGO
TA WNAGHMORE
MOY
RICHMOND
CARRICK
- ON -SHANNON
BELLACORICK
GILRA
GORTAWEE
ARIGNA
TONROE
CORRACLASSY
CUNGHILL
CORDERRY
SHANKILL
ARVA
RATRUSSAN
ENNIS
DALLOW
PORTLAOISE
CARLOW
KILKENNY
THURLES
CAHIRDOON
ANNER
BALLYDINE
MALLOW
CHARLEVILLE
RATHKEALE
TARBERT
BUTLERSTOWN
DUNGARVAN
BLAKE
TULLABRACK
MUNGRETMONETEEN
FASSAROE
POLLAPHUCA
IKERRIN
LISHEEN
OUGHTRAGH
TRALEE
DUNFIRTH
KILLOTERAN
KILLONAN
CASHLA
MEATHHILL
TIEVEBRACK
ARDNAGAPPARY
SHANNONBRIDGE
TURLEENAN
KINGSCOURT
LISDRUM
NORTH KERRY
CLAHANE
ATHEA
LOUGHTEEOG
BALLYRAGGET
DERRYIRON
MONE YPOINT
TARBERT REFURBI SHM ENT PROJ ECT
KNOCKRAHA
BANOGE
LODGEWOOD
CASTLEBAR
ARKLOW
SALTHILL
WATERFORD
GARVAGH
CRANE
CLOGHBOOLA
GLANLEE
CORDAL
FINNSTOWN
NAVAN
CASTLEDOCK RILL
BOOLTIAGH
ARDNACRUSHA
MULLINGAR
LETTE RKENNY
MEENTYCAT
BALGRIFFIN
EAST KERRY & NORTH W EST CORK
SRANANAGH
FLAGFORD
GL ANAGOW
BRACKLONE
POOLBEG
AGHADA
DROMADA
RAFFEEN
NEWBRIDGE
CARROWBEG
CAMUS
BOGGERAGH
KEELDERRY
KNOCKACUMMER
BALLYCUMMIN
Planned Transmission System400 kV, 220 kV and 110 kV
MILLSTREET
Programme Progress2010 Actual• New Line - 130km completed• Line Uprates - 340km completed
2011 Actual • New Line - 80km completed• Line Uprates - 300km completed
2012 Actual• New Line -130km completed• Line Uprates - 215km completed
2013/14/15 Forecast• New Line –200 km due for completion• Line Uprates – 860 km due for completion14 major station projects in the same period
Capital Expenditure
Transmission Capex Spend
-
50.0
100.0
150.0
200.0
250.0
300.0
350.0
2006 2007 2008 2009 2010 2011 2012 2013F 2014F
Actual Forecast
Annu
al S
pend
[€m
]
-
200.0
400.0
600.0
800.0
1,000.0
1,200.0
1,400.0
1,600.0
1,800.0
Cum
ulat
ive
Spen
d [€
m]
Annual Capex Spend Cumulative Capex Spend
Challenges
• Ensuring Public Acceptance
• Land access
• Legal challenges
• Legislation changes
• Uncertainty of volume of Gate 3 work
Response
• EirGrid/ESB Networks coordination on multi-Year Regional Programme Planning
• Project Development & Consultation Roadmap
• Stakeholder Engagement (local/national)
• Community Gain
• New Technologies
Overview
• Grid Development - Context and Challenges
• Constraints Reports and ATRs
• Gate 3 Offer Execution
• DS3 Update
FAQs ConstraintsATRs
3 pieces of the ‘information jigsaw’…..
Published Dec 2012 Published April-July 2013
Published April-July 2013
FAQs and ATRs
• Firm Access Quantities for all Gate 3 Wind were published in December 2012
• Determination of Associated Transmission Reinforcements is now complete
• ATRs will be issued alongside the constraint reports
Constraint Reports
• Studies for Gate 3 constraint reports have been completed following the publication of a final tie-break decision by the SEM Committee
• High-level results available• Some general trends have been
observed in the results• Detailed Area reports to be issued
Area Estimated Date Range for Issue
K 24 Apr – 3 May
D 8 May- 31 May
H2 8 May- 31 May
H1 8 May- 31 May
B 4 Jun – 28 June
F 4 Jun – 28 June
J 4 Jun – 28 June
E 10 Jun – 5 Jul
A 17 Jun – 12 Jul
G 24 Jun – 12 Jul
C 24 Jun – 12Jul
I 24 Jun – 12 Jul
Non-Wind 1 Jul – 19 Jul
Scenarios
• Two scenarios covered:– 33% uptake of Gate 3
• This is achieved by derating all Gate 3 projects to 33% of their MEC.
– 100% uptake of Gate 3• The build-out rate is the same for both scenarios
– This included project size, shallow connection leadtime, planning permission status etc
15
1934 2112 21162564 2564 2564 2564 2564
45
333 466
13691662
3385 35453999
553
607761
839
961
10121122
1306
0
1000
2000
3000
4000
5000
6000
7000
8000
2013 2014 2015 2016 2017 2018 2019 2020
Inst
alle
d W
ind
Capa
city
(MW
)
Year
Pre Gate 3 Gate 3 Northern Ireland
Build-out rate: 100% Gate 3
Large projects with planning assumed to connect ~4 years from offer acceptance
Projects without planning take an extra 2 years
1934 2112 21162564 2564 2564 2564 2564
15110 154
452 5491117 1170 1320
553607
761
839961
1012 11221306
0
1000
2000
3000
4000
5000
6000
7000
8000
2013 2014 2015 2016 2017 2018 2019 2020
Inst
alle
d W
ind
Capa
city
(MW
)
Year
Pre Gate 3 Gate 3 Northern Ireland
Build-out rate: 33% Gate 3
Average installation rate in Ireland of ~275MW/year
Overall 100% Gate 3 results
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
2014 2015 2016 2017 2018 2019 2020 2021
Redu
ction
a as
a %
of a
vaila
ble
cont
rolla
ble
win
d
Curtailment Constraint and Curtailment Constraint
Overall 33% Gate 3 results
19
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
2014 2015 2016 2017 2018 2019 2020 2021
Redu
ction
a as
a %
of a
vaila
ble
cont
rolla
ble
win
d
Curtailment Constraint and Curtailment Constraint
Observations on constraint results
• Average levels are low for all years• There are some nodes that will have high
constraints:– During uprate outages– Until uprates or new builds are delivered– Inside a constraint group
• There are constraint groups – higher levels of constraint– Donegal – South West
Observations on curtailment results• High levels of curtailment if all of Gate 3
connects• Low levels of curtailment in the 33% Gate 3 case
assuming:– Exporting of excess wind on the EWIC and Moyle– DS3 can deliver 75% SNSP*– No additional operational constraints to those
modelled in the study
*System Non-Synchronous Penetration
40%
45%
50%
55%
60%
65%
70%
75%
80%
2013 2014 2015 2016 2017 2018 2019 2020
SNSP Limit
Overview
• Grid Development - Context and Challenges
• Constraints Reports and ATRs
• Gate 3 Offer Execution
• DS3 Update
Gate 3 Offer Validity Period • Offer Validity Period is 50
Business Days and commences on receipt of Constraint Report
• No Extensions to Validity Period
– Modifications do not extend the validity period
TSO Offer Execution
• To execute an Offer the Applicant must meet the conditions precedent which include:
– Make First Stage Payment– Put in place MEC Bond (where applicable)– Sign the offer
• After signing the applicant will receive an offer acceptance letter
– Contains information including Long Stop Dates• 36 Months post Scheduled Consents Issue Date• 30 Months post Scheduled Operational Date
• A Kick Off Meeting will be scheduled within 20 Business Days of Execution
Executing TSO Offer:First Stage Payment• The First Stage Payment (FSP) Mechanism* applies
to Gate 3 Transmission Renewable Generators– This may be different to what is currently in your offer
• A Sliding Scale Mechanism now applies to FSP– Full amount of the FSP may not be due on execution. – Amount due on execution depends on Scheduled Consents Issue Date– The remaining amount is due 12 months prior to your Scheduled Consents Issue
Date.
• First Stage Payments are non-refundable
*CER/11/083
TSO First Stage Payment
• Renewable Projects:– Contested
• FSP = €10,000 per MW– Non Contested
• FSP = Greater of [X and 10% of the connection charge] where – X = Lesser of [€10,000 per MW of contracted capacity (MEC);
50% of the connection charge]
Sub Groups
• Project Starts when critical mass have signed– When enough MW has signed to warrant the connection works to go ahead– Members of same sub-group will have aligned validity period expiry date
• Sub-Group Agreement is required for any modification that may change connection works– One party cannot unilaterally hold up progress on connection works by
requesting a modification– If one or more parties wants to change the connection works e.g. AIS to GIS
all parties must agree and seek to modify their agreements accordingly – Splits, Mergers, Relocations can all impact on connection works
Sub Groups - Continued
• We proceed with connection works as set out in contract until a contract modification is signed – We cannot act on the basis of general discussions or hearsay
– We must have contractual basis for progressing works/planning for something different from what is in the offer
– This is for the protection of all parties within the subgroup and for the TUoS customer
• COPP is a good source of information about sub-groups
Overview
• Grid Development - Context and Challenges
• Constraints Reports and ATRs
• Gate 3 Offer Execution
• DS3 Update
DS3 ProgrammeShaping the power system of the future
System ServicesPerformance MonitoringGrid CodeDemand Side Management
Frequency ControlVoltage ControlRenewable dataRate of Change of Frequency
Studies & Model DevelopmentControl Centre ToolsWind Security Assessment Tool
DS3 Programme: Workstream Update (1)• System Services Review
– Paper on Financial Arrangements submitted to RAs
• Grid Code– All RoCoF Modifications submitted to RAs - Dec 2012
• Demand Side Management– WPDRS Phase Out, DSUs, Demonstration Projects
• Renewable Data– 2012 Curtailment Report Drafted and submitted to Regulator
• Performance Monitoring and Testing – Deadline for receiving Operational Certificates is 1st of December 2013– Performance Monitoring Workshops: Belfast and Dublin on 6th and 11th
of June
WFPS Controllability Update
Status Update1-2 slides
Feb-12 Mar-12Apr-12May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12Dec-12 Jan-13 Feb-13Mar-130
200
400
600
800
1000
1200
1400
Categories of Controllability Ireland
Category (1) Category (2) Category (3)
Mar-13 MWCategory (1) 72.95Category (2) 1218.8Category (3) 62.1
DS3 Programme Outlook• Project will evolve over the coming months
– Enhanced role for the RAs– Progress for certain workstreams is dependent on other parties e.g. RAs,
DSOs– Progress is dependent on decisions on System Services, RoCoF etc.– Move toward implementation of change in operational policies
• Challenge of aligning all island position– Different Grid Codes– 2 Regulatory Authorities
Supporting Meitheal na Gaoithe (1)• Gate 3 Customer Meetings
– Opportunity to meet with EirGrid in advance of signing your offer
– Available to both TSO and DSO Customers – contact relevant SO
– 18th June, 18th July, 1st August
• Gate 3 Frequently Asked Questions– On Gate 3 Section of EirGrid Website
http://www.eirgrid.com/gate3/frequentlyaskedquestions/
Supporting Meitheal na Gaoithe (2)
• Customer Forums– Last forum took place on 16th April
– Presentation available on the Events page of EirGrid website
• Customer Connections Update– Regular Bulletins issued by EirGrid
– Also available in Gate 3 section of EirGrid Website
• Register for EirGrid Updates– Email [email protected] to be added to circulation list
Summary• Grid Development
– Network Development Update and build out– Significant challenges and TSO Response
• Constraint Reports & ATRs– Progressing the issuance of all area reports– Constraint levels low for all years
• Gate 3 Offer Execution– First Stage Payments– Processing of Sub Groups
• DS3– Multiple workstreams ongoing– Regulatory Input and decisions due over coming months