Top Banner
100

Greg Smith-tennessee parking 2-2013.ppt

Jan 05, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Greg Smith-tennessee parking 2-2013.ppt
Page 2: Greg Smith-tennessee parking 2-2013.ppt

Parking lot constructionParking lot construction

• Why Concrete?Why Concrete?– Competitive pricing 

Good fit with new environmental designs– Good fit with new environmental designs

• Why Parking lots?

• Design is out of whack!

• Construction Practices Today

Page 3: Greg Smith-tennessee parking 2-2013.ppt

Why Concrete?

• Pricing of concrete is more competitive than ever.

• Concrete ‐ Numerous sustainability benefits (sri, reflectance i i f h l d PAH )savings, savings from heat load, no PAHs).

• Concrete lasts and requires little to no maintenance.

• Owners see overall job costs savings when concrete is• Owners see overall job costs savings when concrete is specified along with asphalt (equivalent designs).  

• By always specifying concrete designed per ACI 330 R‐08 you are saving your client money!

Page 4: Greg Smith-tennessee parking 2-2013.ppt
Page 5: Greg Smith-tennessee parking 2-2013.ppt
Page 6: Greg Smith-tennessee parking 2-2013.ppt
Page 7: Greg Smith-tennessee parking 2-2013.ppt

51,000 sq ft on red clay51,000 sq ft on red clay

Page 8: Greg Smith-tennessee parking 2-2013.ppt

NOW THAT CONCRETE IS COMPARIBLE ON INITIAL COST, LONG TERM BENEFITS ARE FREE

L T N t P t V l ($I iti l t C i Long Term Net Present Value ($ K)

Concrete is 9.5% Lower

$137.0

Initial cost Comparison

Historical = 60-80% Difference

Current = 2% Difference

$137.0

$124.0$141$154

$118 $120

$76

2004 2010“Over designed” Concrete Pavement

Asphalt Pavement Asphalt Pavement“ACI 330 designed” Concrete Pavement

Inflation rate – 4.0%, Discount Rate = 8.0%Seal coat and stripe application every 5 years, cost $1.50/SYConcrete cleaning and re-striping every 10 years, cost $0.50/SY

Asphalt Pavement

“ACI 330 designed” Concrete Pavement

Page 9: Greg Smith-tennessee parking 2-2013.ppt

CONCRETE PARKING LOTS CAN BE CONSTRUCTED IN SIMILAR TIME AS ASPHALT

Major Construction Tasks and Production Rates

Concrete Surface (5” thick)

Expected Days of Construction

ConcreteConcrete Surface (5 thick)

• Form work (800-1200 SY/day)

• Paving (1100 – 1600 SY/day)1,2

12

16

12

15Asphalt

Concrete

Asphalt Surface (2” Asphalt / 6”Base)

• Granular base preparation (150 - 250 tons/day, minimum 2 day)

• Asphalt paving (500 - 100 tons/day)

9

12

10

12

Asphalt paving (500 - 100 tons/day)

• Curb and gutter (250 - 350 LF/day)

Min Days Avg Days Max Days

1. Based on paving two 25’ wide x 250 ft long sections/dayAsphalt Design: 2” AC / 6” Granular on compacted subgrade Concrete Design: 5” Jointed concrete on compacted subgrade

2. Curb & gutter are integral to concrete paving and included in paving and form work

Page 10: Greg Smith-tennessee parking 2-2013.ppt

Sealer abrasionSealer abrasionFall of 07  Spring of 08

Page 11: Greg Smith-tennessee parking 2-2013.ppt

Oils and antifreeze degradationOils and antifreeze degradationThe problem The fix?

Page 12: Greg Smith-tennessee parking 2-2013.ppt
Page 13: Greg Smith-tennessee parking 2-2013.ppt
Page 14: Greg Smith-tennessee parking 2-2013.ppt
Page 15: Greg Smith-tennessee parking 2-2013.ppt
Page 16: Greg Smith-tennessee parking 2-2013.ppt
Page 17: Greg Smith-tennessee parking 2-2013.ppt

Dollar General –

Page 18: Greg Smith-tennessee parking 2-2013.ppt

Dollar StoresDollar Stores

Page 19: Greg Smith-tennessee parking 2-2013.ppt

SonicsSonics

Page 20: Greg Smith-tennessee parking 2-2013.ppt
Page 21: Greg Smith-tennessee parking 2-2013.ppt
Page 22: Greg Smith-tennessee parking 2-2013.ppt
Page 23: Greg Smith-tennessee parking 2-2013.ppt
Page 24: Greg Smith-tennessee parking 2-2013.ppt
Page 25: Greg Smith-tennessee parking 2-2013.ppt
Page 26: Greg Smith-tennessee parking 2-2013.ppt
Page 27: Greg Smith-tennessee parking 2-2013.ppt

Lighting cost comparison

Page 28: Greg Smith-tennessee parking 2-2013.ppt
Page 29: Greg Smith-tennessee parking 2-2013.ppt
Page 30: Greg Smith-tennessee parking 2-2013.ppt
Page 31: Greg Smith-tennessee parking 2-2013.ppt
Page 32: Greg Smith-tennessee parking 2-2013.ppt
Page 33: Greg Smith-tennessee parking 2-2013.ppt
Page 34: Greg Smith-tennessee parking 2-2013.ppt

Spring Street Fire Station LouisvilleSpring Street Fire Station Louisville

Page 35: Greg Smith-tennessee parking 2-2013.ppt

Henderson Learning CenterHenderson Learning Center

Page 36: Greg Smith-tennessee parking 2-2013.ppt
Page 37: Greg Smith-tennessee parking 2-2013.ppt
Page 38: Greg Smith-tennessee parking 2-2013.ppt

ACI 330R‐08The Gold Standard for ConcreteThe Gold Standard for Concrete 

Parking Lot Design

Page 39: Greg Smith-tennessee parking 2-2013.ppt

Why Use It?‐Economical 20 Year DesignEconomical 20 Year Design

‐Addresses Many Aspects of Concrete Parking Lot Construction

B d S d E i i‐Based on Sound Engineering‐Created Just for Concrete Parking 

Lots! 

Page 40: Greg Smith-tennessee parking 2-2013.ppt

Overview of the Document:

‐Pavement Design – CH 3

‐Materials – CH 4Materials  CH 4

‐Construction – CH 5

I i d T i CH 6‐Inspection and Testing – CH 6

‐Maintenance and Repairs – CH 7Specifying and requiring the contents of ACI 330 R‐08 gives a designer confidence that many aspects of 

a concrete parking lot are addressed.p g

Page 41: Greg Smith-tennessee parking 2-2013.ppt

What do designers currently use for concrete parking lots?concrete parking lots?Usually follow DOT

• Nothing – No concrete design; Only design in asphaltasphalt 

• AASHTO Design Guide – ‘72, ‘86, ’93

• DOT guidelines for roadway design – usually one of the AASHTO guides  

• “What we’ve always used”

• ACI 330!ACI 330!

Page 42: Greg Smith-tennessee parking 2-2013.ppt

If AASHTO is good enough for the g ghighway, why not the parking lot?

O i it?Or is it?

‐Gary Sharpe, P.E., AASHTO Chairperson, 6/23/2004

Page 43: Greg Smith-tennessee parking 2-2013.ppt

Source of Much of What We Know About Pavement Design

• AASHO Road Test• Late 50’s and early 60’s• Ottawa, Illinois

WWW. NRMCA.ORG

Page 44: Greg Smith-tennessee parking 2-2013.ppt

The AASHO road test and AASHTO method

PSI⎡ ⎤⎡ ⎤ΔStandard OverallStandard Deviation D th

Change in Serviceability

PSI⎡ ⎤⎡ ⎤ΔPSI⎡ ⎤⎡ ⎤ΔStandard OverallStandard DeviationStandard Standard OverallStandard DeviationOverallStandard Deviation D thD th

Change in Serviceability

Log(ESALs) Z *s +7.35*Log(D +1) - 0.06R o=

( )

+Log PSI

4.5 - 1.5

1+1.624*10

D

7

⎡⎣⎢

⎤⎦⎥

+

⎢⎢⎢⎢⎢

⎥⎥⎥⎥⎥

Δ

1 8 46.

Normal DeviateStandard Deviation Depth

DrainageModulus of

Log(ESALs) Z *s +7.35*Log(D +1) - 0.06R o=

( )

+Log PSI

4.5 - 1.5

1+1.624*10

D

7

⎡⎣⎢

⎤⎦⎥

+

⎢⎢⎢⎢⎢

⎥⎥⎥⎥⎥

Δ

1 8 46.( )

+Log PSI

4.5 - 1.5

1+1.624*10

D

7

⎡⎣⎢

⎤⎦⎥

+

⎢⎢⎢⎢⎢

⎥⎥⎥⎥⎥

Δ

1 8 46.

Normal DeviateStandard Deviation

Normal DeviateNormal DeviateStandard DeviationStandard Deviation DepthDepth

DrainageDrainageModulus ofModulus ofModulus of ( )D +⎣⎢ ⎦⎥1

( )+ 4.22 - 0.32pt * [ ]Log

S' C D 1.132c d0.75 −

⎡ ⎤

⎡⎢⎢⎢

⎤⎥⎥⎥

* *

Terminal Serviceability

DrainageCoefficient

Rupture ( )D +⎣⎢ ⎦⎥1( )D +⎣⎢ ⎦⎥1

( )+ 4.22 - 0.32pt *( )+ 4.22 - 0.32pt * [ ]Log

S' C D 1.132c d0.75 −

⎡ ⎤

⎡⎢⎢⎢

⎤⎥⎥⎥

* *[ ]Log

S' C D 1.132c d0.75 −

⎡ ⎤

⎡⎢⎢⎢

⎤⎥⎥⎥

* *

Terminal ServiceabilityTerminal Serviceability

DrainageCoefficientDrainageCoefficient

RuptureRuptureRupture

( )pt

( )

g

215.63*J * D -18.42

E /k0.75

c

⎣⎢⎢

⎦⎥⎥⎣

⎢⎢⎢

⎥⎥⎥0 25.

Load Transfer Modulus

of ElasticityModulus ofSubgrade

( )pt( )pt

( )

g

215.63*J * D -18.42

E /k0.75

c

⎣⎢⎢

⎦⎥⎥⎣

⎢⎢⎢

⎥⎥⎥0 25.( )

g

215.63*J * D -18.42

E /k0.75

c

⎣⎢⎢

⎦⎥⎥⎣

⎢⎢⎢

⎥⎥⎥0 25.

Load TransferLoad Transfer Modulus

of ElasticityModulus of ElasticityModulus of Elasticity

Modulus ofSubgrade Modulus ofSubgrade y gReaction

yyy gReaction

gReaction

AASHTO design equations:

Empirical – reproduce actual road test performance datap p pUse the “ESAL” concept to quantify loads / repetitionsDeveloped Serviceability Factors

Page 45: Greg Smith-tennessee parking 2-2013.ppt

AASHO Test Traffic

Max Single Axle

Max Tandem AxleMax Tandem Axle

Page 46: Greg Smith-tennessee parking 2-2013.ppt

Typical AASHO Pavement Sections

Page 47: Greg Smith-tennessee parking 2-2013.ppt

AASHTO DESIGN ServiceabilityAASHTO DESIGN Serviceability

P t S i bilit

Serviceability ‐the pavement’s ability to 5.0

Present Serviceability Index (PSI)         

the pavement s ability to serve the type of traffic (automobiles and trucks) th t th f ilit

Very Good4.0

3 0that use the facility Good

Fair

3.0

2.0

Poor

Very Poor

1.0

0.0

WWW. NRMCA.ORG

Page 48: Greg Smith-tennessee parking 2-2013.ppt

AASHO Road Test Results

Page 49: Greg Smith-tennessee parking 2-2013.ppt

AASHO Road Test Results

Page 50: Greg Smith-tennessee parking 2-2013.ppt

CONVENTIONAL PAVEMENT DESIGN USES THE 1993 AASHTO PAVEMENT DESIGN GUIDE

Based On Old Technology

•AASHTO Guide was developed based on AASHO Road Test in 1950’s

– Pavement surface: jointed plain or jointed reinforced concrete with dowels (3500 psi)

Many of the 1993 AASHTO Inputs are not measureable

• Initial serviceability

• Terminal serviceabilitye o ced co c ete t do e s (3500 ps )– Utilized 1 subgrade and 1 base type (highly 

erodible)• PCC pavements failed by pumping

– Maximum 1.1 million ESAL applications over 2 yrs– Based on 1 climatic zone ‐ Illinois (wet/freeze)

• Equivalent Single Axle load ‐ ESAL

• Load transfer coefficient ‐ J‐factor

• Drainage factor

• Structural number( / )

– Pavement performance measured by human perception of ride quality

• Layer coefficient

Page 51: Greg Smith-tennessee parking 2-2013.ppt

MEPDG ‐ BASED ON ACTUAL PAVEMENT PERFORMANCE AND LATEST PAVEMENT DESIGN MODELS 

The New Technology for Roads and Highways:

•FHWA monitored 2,400 test sections through LTPP program – 1,250 test sections constructed for specific studies

Test Section Locations

1,250 test sections constructed for specific studies• Structural factors for asphalt pavements• Structural factors for concrete pavements• Rehabilitation of asphalt pavements• Rehabilitation of concrete pavements• Environmental effects in absence of heavy• Environmental effects in absence of heavy 

loads– Performance measured annually

• Concrete: Cracking, faulting, pumping, roughness

• Asphalt: Rutting, cracking, roughnessp g, g, g– Each section is 10‐20 yrs old and still counting

Pavement Stresses From Traffic LoadingAll Vehicles Considered Individually

11109

8765

1312

Page 52: Greg Smith-tennessee parking 2-2013.ppt

AASHTO PAVEMENT DESIGN GUIDE IS NOT RECOMMENDED FOR CONCRETE PARKING LOT PAVEMENTS

•AASHTO Guide is intended for use on highway pavementshighway pavements

– Highway pavements are different than parking lots

• High speed traffic

• One‐directional traffic patterns

• Loading near edge of pavementpavement

• Mixed vehicle types

• Water drains rapidly from pavement

• Light poles, Islands are not on highways

•AASHTO Guide is currently being revised based on current technology of pavement design

Page 53: Greg Smith-tennessee parking 2-2013.ppt

FOLLOWING ACI 330 GUIDELINES RESULTS IN COMPARABLE,  SUPERIOR PERFORMING CONCRETE DESIGNS

•ACI has developed recommended design procedure  specifically for parking lots

Determines:Given:

•Soil Strength

•Concrete Strength

•Traffic Demand

Determines:

•Thickness 

•Jointing

•Reinforcing (opt.)

( )

‐ Recognizes construction integrity of rigid pavement materials. Recommends reduction or elimination of granular base:

•Subbase (opt.)

base: 

‐ Potential Savings = 25‐35% of total cost.

•ACI 330 recognizes parking lots are differentACI 330 recognizes  parking lots are different than a street/roadway.

– Load is in the Interior

– Primary purpose is to store & move vehicles

– Lot may be a water collector

– May need to accommodate lighting, islands, landscaping

Page 54: Greg Smith-tennessee parking 2-2013.ppt

Actual NRMCA National Account i Si iDesign Situation:

Large Account Default Requirement Requested AASHTO Design Methodology:

St d d D t 7” 6” b dStandard Duty: 7” over 6” subgradeHeavy Duty: 8” over 6” subgrade

Revised Project Criteria using ACI 330 R 08Revised Project Criteria using ACI 330 R‐08 Guideline:

Standard Duty: 5” – no subgradey gHeavy Duty: 6” over 4” subgrade

Substantial Cost Savings !!!

Page 55: Greg Smith-tennessee parking 2-2013.ppt

Keeping thickness in perspective…• “Rules of thumb” work fine for 

many small projects.• Actual fatigue failures are rare.Actual fatigue failures are rare.• Most thickness design is 

conservative for assumed loads.• More critical issues:

– Subgrade / subbase uniformity– Drainage & maintenance

Page 56: Greg Smith-tennessee parking 2-2013.ppt

STEEL REINFORCEMENT IS NOT NECESSARY FOR CONCRETE PAVEMENTS

• Steel reinforcement has minor effect on a pavement’s load-carrying capacity or thickness

• It does effect the joint design of the pavement

• Joints are placed according to the system selected and identifies the “concrete pavement type”

• For all paving applications, industry does not recommend using mesh reinforcing

Xnot recommend using mesh reinforcing steel

• Not enough mesh to add strength• It is rarely placed at the correct depth

• Cost impact – 7 to 12%p• Save money with tighter joint spacing

instead of spending money on reinforcing for similar performance

X

Page 57: Greg Smith-tennessee parking 2-2013.ppt

Steel reinforcement

When used, the purpose of secondary steel reinforcement is  to keep cracks from opening.  To do this, it must be located above the mid‐thickness.  

Page 58: Greg Smith-tennessee parking 2-2013.ppt

Steel reinforcement

It is almost impossible to place rolled wire mesh in the upper thickness where it can function. Rebar on chairs or welded rigid mats perform better if  steel is called for.Secondary steel reinforcement is often misunderstood and can rarely be justified inmisunderstood and can rarely be justified in flatwork that is properly jointed.

If steel is used, it should ll b t t ll j i t !generally be cut at all joints!

Page 59: Greg Smith-tennessee parking 2-2013.ppt
Page 60: Greg Smith-tennessee parking 2-2013.ppt
Page 61: Greg Smith-tennessee parking 2-2013.ppt
Page 62: Greg Smith-tennessee parking 2-2013.ppt

JOINTED REINFORCED CONCRETE PAVEMENTS (JRCP) ARE NOT RECOMMENDED FOR PARKING LOTS

Plan

Profile30’ to 90’ joint spacing

Profile

Page 63: Greg Smith-tennessee parking 2-2013.ppt

PROPER JOINTING PRACTICES AFFECT LONG TERM PERFORMANCE MORE THAN THICKNESS

• Match existing joints or cracks• Isolate fixed structures

• Slabs < 1 ft. wide• Slabs > 15 ft. wide

Things to avoidThings to do

• Take into account aggregate type• Joint locations can be adjusted in the field• Match joints in curb• Be practical

• Angles < 60º • Creating interior corners• Odd Shapes (keep slabs square)• Avoid “T” joint p

• Detail Jointsj

Diagonal

Inlet - None

Isolation joint

Isolationjoint

Page 64: Greg Smith-tennessee parking 2-2013.ppt

WHY ARE JOINTS NECESSARY?

• The concrete will crack after placement• Joints tell the concrete where to

crack• Why does concrete crack after placement?

Proper jointing provides a series of saw cuts (joints) spaced to

• Concrete drying shrinkage• Changes in temperature and

moisture• Ambient (contraction)

(joints) spaced to control crack formation

• Gradient (curling)• Subbase restraint (friction or bond)• First applied loads

Pavement thickness, in.

Spacing range, ft

Recommended Maximum Joint Spacing (2 x thickness)

4 to 4.5 6-10

5 to 5.5 7.5 -12.5

6 or greater 10-15

Erratic crack patterns due to no joints

6 or greater 10 15

Page 65: Greg Smith-tennessee parking 2-2013.ppt

THE CRITICAL STRESS FOR PARKING LOT DESIGN IS IN THE INTERIOR

Edge Loadings are used for Highway Design

Loadings at pavement corners are most

Edge Loadings are used for Highway Design

1 Loadings at pavement corners are most severe

Loadings at pavement edges are next most severe

1

2

Parking lot thickness design assumes the loads at some distance from pavement corners and edges

32

3

Pavement edge without integral curb may need thickened edge

Joint design must provide for the proper

32

Joint design must provide for the proper level of load transfer or a condition approaching free edge loading will occur at joints / cracks.

1

Page 66: Greg Smith-tennessee parking 2-2013.ppt

Expansion JointsExpansion Joints

Page 67: Greg Smith-tennessee parking 2-2013.ppt
Page 68: Greg Smith-tennessee parking 2-2013.ppt

Expansion JointsExpansion Joints

Page 69: Greg Smith-tennessee parking 2-2013.ppt

ACI 330R‐08 – The Gold StandardACI 330R 08  The Gold StandardACI 330 is preferred because:

• AASHTO 93 – for roads and highways NOT parking lotsp g

• AASHTO 93 – outdated methodology (1950s)

• AASHTO 93 doesn’t offer construction• AASHTO 93 doesn t offer construction methodology standards for concrete parking lotslots

• AASHTO 93 doesn’t allow for cost competitive d i fdesigns for concrete

Page 70: Greg Smith-tennessee parking 2-2013.ppt

70 cubic yards per day pipeper day pipe screed

Page 71: Greg Smith-tennessee parking 2-2013.ppt

City of Frankfort Public Works Department Pl d h P i CPlaced the Pervious Concrete

Page 72: Greg Smith-tennessee parking 2-2013.ppt
Page 73: Greg Smith-tennessee parking 2-2013.ppt

Porous Concrete Installation May 10 200510, 2005

2/7/20132/7/2013 7373

Page 74: Greg Smith-tennessee parking 2-2013.ppt

InstallationInstallation

Page 75: Greg Smith-tennessee parking 2-2013.ppt

Radcliff – using KRMCA Pervious Concrete Equipment

Page 76: Greg Smith-tennessee parking 2-2013.ppt

Dry Ridge, KYDry Ridge, KY

Page 77: Greg Smith-tennessee parking 2-2013.ppt

60‐70 cu yds / day60 70 cu yds / day

Page 78: Greg Smith-tennessee parking 2-2013.ppt
Page 79: Greg Smith-tennessee parking 2-2013.ppt
Page 80: Greg Smith-tennessee parking 2-2013.ppt
Page 81: Greg Smith-tennessee parking 2-2013.ppt
Page 82: Greg Smith-tennessee parking 2-2013.ppt
Page 83: Greg Smith-tennessee parking 2-2013.ppt
Page 84: Greg Smith-tennessee parking 2-2013.ppt
Page 85: Greg Smith-tennessee parking 2-2013.ppt

700 cubic yards laser screed one night Breckinridge County Kentucky700 cubic yards laser screed one night Breckinridge County Kentucky

Page 86: Greg Smith-tennessee parking 2-2013.ppt
Page 87: Greg Smith-tennessee parking 2-2013.ppt
Page 88: Greg Smith-tennessee parking 2-2013.ppt
Page 89: Greg Smith-tennessee parking 2-2013.ppt

660 cu yds 9 hours660 cu yds 9 hours

Page 90: Greg Smith-tennessee parking 2-2013.ppt
Page 91: Greg Smith-tennessee parking 2-2013.ppt
Page 92: Greg Smith-tennessee parking 2-2013.ppt
Page 93: Greg Smith-tennessee parking 2-2013.ppt
Page 94: Greg Smith-tennessee parking 2-2013.ppt
Page 95: Greg Smith-tennessee parking 2-2013.ppt

Menards store, OhioMenards store, Ohio

Page 96: Greg Smith-tennessee parking 2-2013.ppt

RW Brick, Genoa City, WI, y,

Page 97: Greg Smith-tennessee parking 2-2013.ppt
Page 98: Greg Smith-tennessee parking 2-2013.ppt

124,750 sq ft 3 days124,750 sq ft 3 days

Page 99: Greg Smith-tennessee parking 2-2013.ppt
Page 100: Greg Smith-tennessee parking 2-2013.ppt

Questions?