Top Banner
Andy Szatko [email protected] City of Omaha Environmental Quality Control Tech I Green Infrastructure Lessons Learned: Experiences from Omaha
78
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Green Infrastructure in Omaha 4 22-15

Andy Szatko [email protected] City of Omaha Environmental Quality Control Tech I

Green Infrastructure Lessons Learned: Experiences from Omaha

Page 2: Green Infrastructure in Omaha 4 22-15

Green Infrastructure: Defined

Preservation, connecting, & mimicking of natural

processes that slow, sink, & spread rain where it lands

3 Scales: 1. Watershed 2. Neighborhood 3. Site

Page 3: Green Infrastructure in Omaha 4 22-15

Site Specific GI Project Types § Bioretention system § Rain gardens § Bioswales § Xeric gardens § Soil Conditioning § Green roofs § Porous/pervious

pavement § Rain barrels § Urban forest § Wet & dry ponds § Wetlands § Filter strips and

level spreaders § Sand filters

Page 4: Green Infrastructure in Omaha 4 22-15

Post-Construction BMPs in Omaha

1,158

Page 5: Green Infrastructure in Omaha 4 22-15

Post-Construction BMPs in Omaha

339

157 147

122

81 67

53 36 34

23 17 16 14 12 9 9 5 5 4 4 4 0

50

100

150

200

250

300

350

400

PCSMP BMP Type Distribution - all status

Total BMPs = 1,158

Page 6: Green Infrastructure in Omaha 4 22-15

Bioretention System

• Infiltration ‘Trench’: Bioretention Soil Mix (BSM) & washed aggregate

• Conditioned soil outside ‘trench’

• Valve

Omahastormwater.org/ORSDM – Chapter 8

Page 7: Green Infrastructure in Omaha 4 22-15

Bioretention is not a…

• Pond • Wetland • Swamp • Mosquito breeding ground

• Just a landscape bed • Bio-pond, -garden, etc… • Bioswale

Page 8: Green Infrastructure in Omaha 4 22-15

Bioretention System – Upturned Elbow

Omahastormwater.org/ORSDM – Chapter 8

Page 9: Green Infrastructure in Omaha 4 22-15

5-29-09

Infiltration cell

Clean-outs High flow structure

Valve

Bioretention: In the field

Overflow

Page 10: Green Infrastructure in Omaha 4 22-15

Prairie Lane Park When bioretention “doesn’t work”

Page 11: Green Infrastructure in Omaha 4 22-15

The site as it was being constructed…

Page 12: Green Infrastructure in Omaha 4 22-15

Soil conditioning BEFORE infiltration cell installation

Protect infiltration cell after installation

Sequencing & protecting infiltration cell key

Page 13: Green Infrastructure in Omaha 4 22-15

2” clay lens at top

‘Clean’ BSM below

“Poor design”, “doesn’t work”…upon further review

Page 14: Green Infrastructure in Omaha 4 22-15

Drains great below lens

Clay lens

Clay, in-situ soil tilled into BSM clogged system

Page 15: Green Infrastructure in Omaha 4 22-15

Troweled into pipe during paving MH floor

1 7/8” concrete ‘plug’ in underdrain tap to MH

Don’t make things harder than they need to

Page 16: Green Infrastructure in Omaha 4 22-15

Remove top 2”, place new BSM, & new sod

Page 17: Green Infrastructure in Omaha 4 22-15

Works great now

Page 18: Green Infrastructure in Omaha 4 22-15

Elmwood Park Green Infrastructure Part of the Aksarben Village Sewer Separation Project

Page 19: Green Infrastructure in Omaha 4 22-15

Elmwood Park Green Infrastructure – just installed

Page 20: Green Infrastructure in Omaha 4 22-15

Offline bioretention = less stress on system

Page 21: Green Infrastructure in Omaha 4 22-15

Elmwood Park Diversion – Adaptations • Gardens holding up

great but can handle more volume

• Gardens not level • Bottom 0.1’ lower

than notch

Install a bracket around low-flow notch & stop logs to increase capacity & provide flexibility

Page 22: Green Infrastructure in Omaha 4 22-15

4/18/15 After rain, better capacity & slower flow

Page 23: Green Infrastructure in Omaha 4 22-15

QC is key, 2 of 7 ScourStop failing; early in 2014

Page 24: Green Infrastructure in Omaha 4 22-15

QC is key, 6 of 7 failing by end of season 2014

Page 25: Green Infrastructure in Omaha 4 22-15

Repaired 12/2014

Page 26: Green Infrastructure in Omaha 4 22-15

Benson Gateway Bioretention A project full of learning

Page 27: Green Infrastructure in Omaha 4 22-15

Originally a street…

Page 28: Green Infrastructure in Omaha 4 22-15

Catch street runoff into conveyance

Page 29: Green Infrastructure in Omaha 4 22-15

Test the system after install

Page 30: Green Infrastructure in Omaha 4 22-15

Poor drainage instantly

Page 31: Green Infrastructure in Omaha 4 22-15

Anticipated flows like this...

Page 32: Green Infrastructure in Omaha 4 22-15

Failure 1: …but we got this slow flow instead

FYI, this is first flush of some dirt in underdrain

Page 33: Green Infrastructure in Omaha 4 22-15

Failure 1: Slotted pipe with dirty drainage aggregate

Page 34: Green Infrastructure in Omaha 4 22-15

Fix1: Remove the infiltration cell & replace

Page 35: Green Infrastructure in Omaha 4 22-15

Fix 1: Install 4” PVC w/¼” perf, washed ¾” rock

Page 36: Green Infrastructure in Omaha 4 22-15

Fix 1: Geotextile as separation, only on top*

* - note the return up the sides; this was not intended

Page 37: Green Infrastructure in Omaha 4 22-15

Fix 1: Replace the soil mix & finish the project

Page 38: Green Infrastructure in Omaha 4 22-15

Plant everything up

Page 39: Green Infrastructure in Omaha 4 22-15

Right away we get a ‘natural’ test of the garden

Page 40: Green Infrastructure in Omaha 4 22-15

Slow flow once again…

Page 41: Green Infrastructure in Omaha 4 22-15

Failure 2: Flat geotextile created ‘perched water table’

Page 42: Green Infrastructure in Omaha 4 22-15

Cut slit at corner, pulled back, & drained fast

Page 43: Green Infrastructure in Omaha 4 22-15

Fix 2: Remove fabric, mound rock, separate w/burlap • Burlap is recycled coffee bean sacks • 1” gap on either side of burlap

Page 44: Green Infrastructure in Omaha 4 22-15

Test it again before Ribbon Cutting event…

Page 45: Green Infrastructure in Omaha 4 22-15

…but once valve opened, drained at same slow rate

Page 46: Green Infrastructure in Omaha 4 22-15

Gotta be something else – time to look inside…

Page 47: Green Infrastructure in Omaha 4 22-15

Cleaned out mulch from underdrain &…

Page 48: Green Infrastructure in Omaha 4 22-15

…filled it once more for the Ribbon Cutting…

Page 49: Green Infrastructure in Omaha 4 22-15

…& it finally worked (first flow of 2014)

Page 50: Green Infrastructure in Omaha 4 22-15

Still working & looking good

Page 51: Green Infrastructure in Omaha 4 22-15

Sewer Maintenance Demonstration EPA ORD, USGS, UNL, City of Omaha Collaboration

Page 52: Green Infrastructure in Omaha 4 22-15

Project Partners § Collaborative project that

includes: § EPA Office of Research

& Development § US Geologic Service

(USGS) § University of Nebraska § City of Omaha CSO &

Stormwater Programs § Designed by: Olsson &

Associates § Installed by: Sudbek

Home Builders

Page 53: Green Infrastructure in Omaha 4 22-15

Basic function of the project

Infiltration Cell (trench) w/1 ingredient – pea gravel

Weather Station

Inflow flume

Inflow flume

Infiltration Cell

Storage area

Outflow flume

Page 54: Green Infrastructure in Omaha 4 22-15

Planting Plan by Steve Rodie, Associate Professor UNO

Create an “Omaha aesthetic” Utilize grasses, sedges & shrubs for simple maintenance

Page 55: Green Infrastructure in Omaha 4 22-15

Bioretention System: 1-ingredient (no soil mix)

Page 56: Green Infrastructure in Omaha 4 22-15

Bioretenetion site before

Page 57: Green Infrastructure in Omaha 4 22-15

West swale set, work stops for season – late 2013

Page 58: Green Infrastructure in Omaha 4 22-15

Infiltration cell installation continued

Page 59: Green Infrastructure in Omaha 4 22-15

Lesson learned: Ensure system is watertight at underdrains & utility crossings

Pea Gravel

Permeable pavement storage area

Page 60: Green Infrastructure in Omaha 4 22-15

Buffalo sod, beds mulched, & irrigating plants

Page 61: Green Infrastructure in Omaha 4 22-15

PaveDrain = 2,170 gallons of designed capacity

Page 62: Green Infrastructure in Omaha 4 22-15

Bioretention = 39,085 gallons of designed capacity

Page 63: Green Infrastructure in Omaha 4 22-15

Demo pavement cleaning w/jet-vac truck 4/7/15

Page 64: Green Infrastructure in Omaha 4 22-15

Time lapse camera for rain events & plant growth

Page 65: Green Infrastructure in Omaha 4 22-15

50th & Pine Porous concrete parking lot, bioretention, real-time controls, & monitoring 50th & Pine

Page 66: Green Infrastructure in Omaha 4 22-15

Bioretention System

Drainage Area ~10,000 sf

Drainage area ~10,500 sf

Concrete Porous

Omaha Fire Dept Education Center

Page 67: Green Infrastructure in Omaha 4 22-15
Page 68: Green Infrastructure in Omaha 4 22-15
Page 69: Green Infrastructure in Omaha 4 22-15

storage for incoming storms

Ultrasonic Depth Sensors

Valve

Valve

Real time controls: • Slide gate valve • Monitor weather

forecasts to open or close valve

• Ability to draw down to create

Page 70: Green Infrastructure in Omaha 4 22-15

Antecedent Dry Conditions ~ 5 days (1.0 inch storm)

Page 71: Green Infrastructure in Omaha 4 22-15

48 hour QPF > 0.5, valve

opens

6 hour QPF > 0.1, valve

closes

Page 72: Green Infrastructure in Omaha 4 22-15

§ Valves greatly improve efficiency of system & give flexibility, i.e. put peak ahead of storm § Learning curve w/real-time controls but

provide significant benefits § This was a retrofit; maximize the storage

you have § Infiltration possible in poor soils § Winter performance good, warmer temps

at depth

Conclusions

Page 73: Green Infrastructure in Omaha 4 22-15

24th St Bioretention Case study in design approach & costs

Page 74: Green Infrastructure in Omaha 4 22-15

Design approach: offline vs. online?

• 5 inlets • 2 large gate inlets • 6” underdrain, valves, & clean outs • 2’ bioretention soil mix (BSM) • 3 layers of aggregate

• 1 inlets • 2 type A inlets • 4” underdrain, valve, & clean outs • Narrow 18” BSM & underdrain • 1 layer of washed aggregate

Cost savings approx. 51%

Page 75: Green Infrastructure in Omaha 4 22-15

Initial Take-aways…

• Targeted “over-engineering” • Bioretention is not a traditional curb inlet • Public education critical

Page 76: Green Infrastructure in Omaha 4 22-15

Overall take-away points…

• Bioretention Systems • Follow details & don’t take shortcuts • Design approach sets the stage, set

appropriately • Cost savings w/simple & functional design • Don’t lay geotextile flat in profile • If geotextile used, use open weave & light • Avoid using slotted underdrain • Use washed rock • Think about maintenance during design • Plants are integral, value them

Page 77: Green Infrastructure in Omaha 4 22-15

Overall take-away points…

• Permeable pavements • Simple maintenance, just different • Excellent benefits in winter • Significant volume benefits w/valves & real-

time controls (50th & Pine project) • General

• Put in once site is stabilized • Sequencing/staging important • Have fun & enjoy it!

Page 78: Green Infrastructure in Omaha 4 22-15

It’s more than just landscaping

Green Infrastructure