GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

Jul 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel
Page 2: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

GREEN HYSLAND

Deployment of a H2 Ecosystem on

the Island of MallorcaMr. Jesús Manuel Gil Jiménez

Director of the Innovation and New Energies Dept. of Enagás

E-mail: [email protected]

• Lloseta

Page 3: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

GREEN HYSLAND – Mallorca’s context

Hydrogen pipeline proposal

Redexis’ natural gas network: primary gas pipelinesEnagás’ Transport Network: backbone network

Germany UK Spain Nordic countries

Benelux France Italy Others

11,947,382 tourists visited Mallorca in 2018

Development of a “H2 ecosystem” which can be replicated across other islandsand remote territories in UE and beyond

Source: “El turismo a les Illes Balears. Annuari 2018”. AEITB.

Source: Red Electrica Annual report 2018. Avaiable at https://www.ree.es/en/publications/annual-report-2018

Source: Enagás

Page 4: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

GREEN HYSLAND project schematic

Page 5: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

Location of GREEN HYSLAND project deployment sites

Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid

Page 6: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel

GREEN HYSLAND – key figures

Avoided carbonfootprint: more than

21,000 tpy

New direct and indirect employment ecosystem associated to hydrogen

Development of a sustainablelarge-scale island-based H2

hub in Mallorca

Development a long-term roadmap to lay the path for a

local & regional based economy towards 2050

Scalabilityand

Replicability

Estimated investment ≈ 50 M€

Page 7: GREEN HYSLAND Jimenez...Site 1: Lloseta Green H2 plant Site 2: Lloseta Municipal building FC Site 3: Cas Tresorer H2/NG mixing station & connection to NG gas grid Site 4: Palma hotel