Green IT Data Center Case Study: Modeling, Selection, and Virtualization Or “What I learned on summer vacation in The Matrix...”
11

Green Data Centers ECUC Presentation 2012

Jul 22, 2015

Download

Technology

Jeffrey Riegle
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Green Data Centers ECUC Presentation 2012

Green IT Data Center Case Study:Modeling, Selection, and Virtualization

Or “What I learned on summer vacation in The Matrix...”

Page 2: Green Data Centers ECUC Presentation 2012

22

Presentation Summary

Status Quo Reduction Pressures Growth Pressures

Modeling TileFlow Low-Cost/No-Cost Changes Phased Approach Placement

Hardware Selection Energy Star Right-sizing – Cost/TB

Virtualization 3:1 or 15:14

Page 3: Green Data Centers ECUC Presentation 2012

33

Red pill or Blue Pill?Status Quo – A Place to Start, not end

Existing 157 racks – 485 kW (99% heat steady state) Tier 1 Data Center

Constraints UPS Electrical Mechanical Space

PATH OF LEAST RESISTANCE Extrapolation

Cost/sf ~ kW/sf Expansion – Add 230 racks Loss of mission? Reliability?

What EROS got instead Reduction

638kW avoided - $202,881 saved annually $615k cost avoidance Tier 2 Data center

Master plan

Page 4: Green Data Centers ECUC Presentation 2012

44

Am I Bill or Ted? Wait, nope, I am Neo…TileFlow Modeling

Investigation Understanding constraints, needs, and existing conditions

Modeling Input status quo into system Determine “Hot Spots” Average Temperature range Under Floor Velocities What happens if redundant unit fails?

Shift racks

Increase plenum space

Increase/decrease floor perforations

Install Overhead Return air

Install CRAC unit redundancy software

Hypothesize additional rack space

Engineer highly likely variables and confirm (WAG)

Page 5: Green Data Centers ECUC Presentation 2012

55

Am I an Elf or An Agent?: Agent ElrondPhased Approach

Lessen Mission Impact

Reduce First Costs

“Just-In-Time” or Extra Redundancy Depending on Expectations and Budgets

Allows technology improvements

Phase 0 – Low-cost/No-cost (Buys Time)

Phase 1 – Replace small HVAC (Prepare for Upswing)

Phase 2 – Move CRACs (Let projects finish, then move)

Phase 3 – Upgrade large HVAC (Big savings)

Phase 4 – Install “nice to haves” (additional savings/reliability)

Page 6: Green Data Centers ECUC Presentation 2012

66

Loop it!Hardware Selections and Virtualization

Energy Star Rated Hardware 75% percentile 80% more efficiency minimum

– Idle Power Consumption – 50% standard

–Operational Power Consumption – Drop-in replacements for older power

Solid State Drive (SSD)Technologies Multi-Cell Levels

Enterprise Management Systems

Virtualization 3:1 ratio potential 15:14; due to accounting/project constraints Right Sizing Cost/PB

Page 7: Green Data Centers ECUC Presentation 2012

77

Mr. AndersonExisting

Page 8: Green Data Centers ECUC Presentation 2012

88

My name is NeoProposed

Page 9: Green Data Centers ECUC Presentation 2012

99

Difference between knowing the path and walking the path

Other avenues

Set house in order

Tighten up envelope Infiltration Reflectivity

Get Reliability Up

Then think about options Solar Hydro Wind Human Potential

Page 10: Green Data Centers ECUC Presentation 2012

1010

Was Ist Lost? Soul Patrol…. Free your mindConclusion

Status Quo Reduction Pressures Growth Pressures

Modeling TileFlow Low-Cost/No-Cost Changes Phased Approach Placement

Hardware Selection Energy Star Right-sizing – Cost/TB

Virtualization 3:1 or 15:14

Meet Goals, Expectations, change the world, or at least you little piece of it.

Page 11: Green Data Centers ECUC Presentation 2012

Shaping the Future

Any More Questions?

Hang around after.

Thanks to Innovative Research, StellCo

Industries, and the EROS Data Center Staff

What we do now is up to you…