Understanding Major Project Escalation Graham M Winch Centre for Infrastructure Development Manchester Business School Jubilee Professor Chalmers University 1
23
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Graham Winch

Understanding Major Project Escalation

Graham M Winch Centre for Infrastructure Development Manchester Business School Jubilee Professor Chalmers University

1

Page 2: Graham Winch

Understanding escalation on major projects

• What is a major project?

• Four perspectives on escalation on major projects – Future-perfect thinking

– Strategic misrepresentation

– Escalation of commitment

– Contractor scapegoating

• Towards a model of escalation

• Policies for de-escalation

• Concluding thoughts

2

Page 3: Graham Winch

What is a major project?

• Size matters – > $1bn US

• The heroic definition – “master builders”

• A proposed definition

3

Page 4: Graham Winch

What is a major project: a definition

• The synergistic elements of a major project or programme – They are organisational endeavours producing complex

product systems

– They combine bespoke elements with different technological trajectories

– They mobilise large human and financial resources

– They shape their environment, spatially and organisationally

– They are managed as a single or closely coupled entity

4

Page 5: Graham Winch

Future-perfect strategies

• Sydney waste water project case – Experiment in alliancing

• Designer culture – Representations of the completed project – CAD fly-thrus – Artists impressions – Virtual reality

• Endgaming – Orientating action around completion dates

• Tinker Bell effect (Tim Smit) – Projects only exist if you believe in them

(Clegg and colleagues)

5

Page 6: Graham Winch

Strategic misrepresentation (Flyvbjerg and colleagues) • 258 transportation projects (1927-1998)

– Mean budget escalation 28% – Systematic tendency to underperform estimates – Cannot be explained by chance alone – If based on incompetence would expect secular improvement

• Most plausibly explained by “lying” about costs and benefits – This is a client-side phenomenon by project promoters.

• Strategic misrepresentation – Socio-economic struggle for resources under uncertainty – Perverse incentives in investment policies e.g. 10 cent dollar

• Optimism bias – Psychological tendency to give the benefit of the doubt under uncertainty

6

Page 7: Graham Winch

Strategic misrepresentation: explanations

• Technical explanations – Forecasting errors – Exogenous events

• Economic explanations – Stakeholder self-interest – Strategic misrepresentation

• Psychological explanations – Optimism bias

• Political explanations – Local elites and national funds – Urban transit projects the classic case

7

Page 8: Graham Winch

Escalation of commitment (Staw and colleagues) • Social-psychological experiments

– Post-hoc justification of selected courses of action – Attribution of negative outcomes to exogenous events – A retrospective, not prospective rationality – The tendency to throw good money after bad – Cultural norms of consistency in leadership

• Hindsight case studies – Expo 86 and Shoreham nuclear power station – A dynamic interplay of determinants through time – Psychological determinants predominate earlier in life-cycle – Project determinants predominate later in life-cycle

8

Page 9: Graham Winch

Escalation of commitment: determinants

• Project determinants – Expected returns – Salvage value – Alternative courses of action

• Psychological determinants – Visibility – Self-justification

• Social determinants – Cultural norms of consistency in leadership

• Structural determinants – Political support – Symbolic aspects

9

Page 10: Graham Winch

Contractor scapegoating

• Contractors obliged to provide bids complying with promoters expectations or project cancelled

• Competitive bidding generates further “low-balling” by contractors – Reliance on claims then drives escalation

• Escalation inevitable during delivery as costs exceed estimates

• Contractors set up to fail by their clients

• They thereby provide a convenient scapegoat for project promoters.

10

Page 11: Graham Winch

Complementarities and differences

• The expected utility (EU) paradigm dominates investment appraisal and risk management – Net present value

– Cost-benefit analysis

– Probability/impact matrix

– A heroic model in terms of information requirements

• In practice the EU norms are not applied – Strategic misrepresentation and bad faith

– Escalation of commitment and good faith

11

Page 12: Graham Winch

Complementarities and differences

• What enables strategic misrepresentation? – Not personal gain

– Not masochism

– Rather future-perfect thinking

• What enables escalation of commitment? – Norms of leadership supported by future perfect thinking

– Availability of exogenous actor (scapegoat)

– “getting the concrete on the table”

• A proposed model

12

Page 13: Graham Winch

A model of escalation on major projects

ContractorScapegoating

ProjectOutcome

Escalation of

Commitment

StrategicMisrepresent-

ation

Future PerfectState

13

Page 14: Graham Winch

Policies for de-escalation

• Develop rigorous project assurance

• Ensure an external view

• Invest in front end definition

• Mitigate optimism bias

• Develop client capabilities

14

Page 15: Graham Winch

Project assurance

• Stage-gates provide clear points of reflection and decision in the project process – They provide formal opportunities for the “outside view” – They break the momentum of strategic misrepresentation – Gates review progress to date and plan next phase – Gates provide opportunities for peer review – Gates provide opportunities for senior management review

• For example – UK Office of Government Commerce Gateway Process – Norwegian Government Quality at Entry Process

15

Page 16: Graham Winch

A basic stage gate process

16

appraise select define execute operate opportunity

Gate 1

Is the business case

sound?

Gate 3

Are we ready to execute the

project?

Gate 2

Is scope complete?

(full funds authorisation)

1%-2% 3%-4% 95%

Developed from Merrow (2011)

Page 17: Graham Winch

An external view

• Industry cost indices – e.g. Building Cost Information Service

– But very context-specific

• Inter-client process benchmarking – e.g. Independent Project Analysis (IPA)

– High quality processes should achieve good outcomes

• Peer review – The input of independent experts is invaluable

17

Page 18: Graham Winch

Front end definition

• excellent project definition work brings multiple returns – Treat it as an investment in the success of the project

• Economising on high impact/ low proportion of total cost services is a false economy – e.g. engineering services

• Projects go wrong from the head – Just like fish!!

18

Page 19: Graham Winch

t

low

high

Actual project outcome

Ability to

influence project

outcome

appraise select define execute operate opportunity

high

low

Front end definition

19

Page 20: Graham Winch

Develop client capabilities

• The outsourcing trend – Projects and engineering capability

• The emergence of the ignorant client

• Clients need to understand the implications of what their suppliers are telling them

• The key issue is oversight – Do too little and you get unpleasant surprises

– Do too much and you generate costs and restrict innovation

20

Page 21: Graham Winch

The client capability sine wave (Railtrack effect)

21

OUTTURNS

Engineeringis Core

SeniorManagement

Attitude

All engineering can be

outsourced

excellent

Project Success

disasterous

SMATTITUDE

Source: Prof Bernard Kelly, UoM

Page 22: Graham Winch

Concluding thoughts

• Major projects need leadership and vision – Future-perfect thinking is vital but needs tempering

• Quality of front-end work is crucial – Stakeholder management – Investment in dispassionate analysis

• Avoid perverse incentives in investment policies – e.g. UK Private Finance Initiative

• Be prepared to cancel projects at gates – A cancelled project is testimony to good project assurance

• Invest in client capabilities – High quality front end work requires client-side engineering and

project management competencies – It requires own-employees committed to the organisation’s goals

22

Page 23: Graham Winch

Thank- you for your attention