Project Name Gorontalo 2x50MW Coal-Fired Steam Power Plant – Turnkey Project Technical Requirements Power Block 2x50MW (NET) Low Calorie Fuel ; 3,000GAR Boiler Type : CFB Net Performance Heat Rate : 3,000 kcal / kwh Balance Of Plant • BEP • Jetty (10,000 DWT) + Conveyor Systems (+500 meter) • Water Intake + Water Treatment (Closed System) • Switchyard Transmission Line 150 kVA + 13 km Total Area + 7 Ha • Temporary Facilities (existing 2x12.5MW) Level +40meter above sea level orontalo 2x50MW CFSPP – Technical & Financial Financial Requirements IRR : +15% Financial Scheme : L/C Crash Period : 3 years • Financial for Existing 2x12.5MW : PT SMI & CIMB Niaga (USD 28 Million) Project’s Schedule Feasibility Study Final Negotiation : August 2014 • PPA : September 2014 (already state in RUPTL 2011 - 2022 by PLN) COD Unit #1 : March 2018 COD Unit #2 : June 2018 Negotiation Step 1. Technical Agreement (prefer Korean / Japan Companies) DIRECT NEGOTIATION 2. Financial Agreement DIRECT NEGOTIATION 3. Sign MOU 4. Construction
5

Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

Dec 11, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

Project NameGorontalo 2x50MW Coal-Fired Steam Power Plant – Turnkey Project

Technical Re-quirements

• Power Block 2x50MW (NET)• Low Calorie Fuel ; 3,000GAR• Boiler Type : CFB• Net Performance Heat Rate : 3,000 kcal / kwh• Balance Of Plant• BEP• Jetty (10,000 DWT) + Conveyor Systems (+500 meter)• Water Intake + Water Treatment (Closed System)• Switchyard• Transmission Line 150 kVA + 13 km• Total Area + 7 Ha• Temporary Facilities (existing 2x12.5MW)• Level +40meter above sea level

Gorontalo 2x50MW CFSPP – Technical & Financial

Financial Re-quirements

• IRR : +15%• Financial Scheme : L/C

• Crash Period : 3 years• Financial for Existing 2x12.5MW : PT SMI & CIMB

Niaga (USD 28 Million)

Project’s Schedule

• Feasibility Study • Final Negotiation : August 2014• PPA : September 2014 (already state in RUPTL 2011

- 2022 by PLN)• COD Unit #1 : March 2018• COD Unit #2 : June 2018

Negotiation Step

1. Technical Agreement (prefer Korean / Japan Companies) – DIRECT NEGOTIATION

2. Financial Agreement – DIRECT NEGOTIATION3. Sign MOU4. Construction

Page 2: Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

Location of existing 2x12.5 MW and Expansion 2x50MW PT Tenaga Listrik

Gorontalo

Gorontalo 2x50MW CFSPP – LOCATION

Page 3: Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

TLG : Tenaga Listrik GorontaloRUPTL 1st Plant : 2x10 MWActual : 2x12.5 MW NET

Gorontalo 2x50MW CFSPP – TLG Plan in PLN’s RUPTL

Sources : RUPTL PLN 2011 - 2022

Page 4: Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

Gorontalo 2x50MW CFSPP – PLN’s Transmission Line

Sources : RUPTL PLN 2011 - 2022

Page 5: Gorontalo 2x50MW CFSPP_Turnkey Project_Feb 21 2014_2nd meeting.pptx

Project NameGorontalo 2x50MW Coal-Fired Steam Power Plant – Turnkey Project

Project Location Molutabu - Gorontalo, South of Sulawesi

Project Owner / Client

PT Tenaga Listrik Gorontalo

Map Location

Gorontalo 2x50MW CFSPP – Turnkey Project

Technical Re-quirements

• Low Calorie Fuel ; 3,000GAR• Boiler Type : CFB• Net Performance Heat Rate : 3,000 kcal / kwh• Capacity NET : 2x50 MW

Project’s Scope of Works

• Power Block 2x50MW• BOP• Jetty + Conveyor• Water Intake• Switchyard• Transmission Line 150 kVA + 13 km• Temporary Facilities (existing 2x12.5MW)

Project’s Status

• PPA , waiting for signing• Feasibility Study • Land Status : Owned by PT TLG • Permit : DONE• Coal Supply : PT TLG Owned mining• Existing : Operate unit #1 from 2x12.5MW