Project NameGorontalo 2x50MW Coal-Fired Steam Power Plant – Turnkey Project
Technical Re-quirements
• Power Block 2x50MW (NET)• Low Calorie Fuel ; 3,000GAR• Boiler Type : CFB• Net Performance Heat Rate : 3,000 kcal / kwh• Balance Of Plant• BEP• Jetty (10,000 DWT) + Conveyor Systems (+500 meter)• Water Intake + Water Treatment (Closed System)• Switchyard• Transmission Line 150 kVA + 13 km• Total Area + 7 Ha• Temporary Facilities (existing 2x12.5MW)• Level +40meter above sea level
Gorontalo 2x50MW CFSPP – Technical & Financial
Financial Re-quirements
• IRR : +15%• Financial Scheme : L/C
• Crash Period : 3 years• Financial for Existing 2x12.5MW : PT SMI & CIMB
Niaga (USD 28 Million)
Project’s Schedule
• Feasibility Study • Final Negotiation : August 2014• PPA : September 2014 (already state in RUPTL 2011
- 2022 by PLN)• COD Unit #1 : March 2018• COD Unit #2 : June 2018
Negotiation Step
1. Technical Agreement (prefer Korean / Japan Companies) – DIRECT NEGOTIATION
2. Financial Agreement – DIRECT NEGOTIATION3. Sign MOU4. Construction
Location of existing 2x12.5 MW and Expansion 2x50MW PT Tenaga Listrik
Gorontalo
Gorontalo 2x50MW CFSPP – LOCATION
TLG : Tenaga Listrik GorontaloRUPTL 1st Plant : 2x10 MWActual : 2x12.5 MW NET
Gorontalo 2x50MW CFSPP – TLG Plan in PLN’s RUPTL
Sources : RUPTL PLN 2011 - 2022
Gorontalo 2x50MW CFSPP – PLN’s Transmission Line
Sources : RUPTL PLN 2011 - 2022
Project NameGorontalo 2x50MW Coal-Fired Steam Power Plant – Turnkey Project
Project Location Molutabu - Gorontalo, South of Sulawesi
Project Owner / Client
PT Tenaga Listrik Gorontalo
Map Location
Gorontalo 2x50MW CFSPP – Turnkey Project
Technical Re-quirements
• Low Calorie Fuel ; 3,000GAR• Boiler Type : CFB• Net Performance Heat Rate : 3,000 kcal / kwh• Capacity NET : 2x50 MW
Project’s Scope of Works
• Power Block 2x50MW• BOP• Jetty + Conveyor• Water Intake• Switchyard• Transmission Line 150 kVA + 13 km• Temporary Facilities (existing 2x12.5MW)
Project’s Status
• PPA , waiting for signing• Feasibility Study • Land Status : Owned by PT TLG • Permit : DONE• Coal Supply : PT TLG Owned mining• Existing : Operate unit #1 from 2x12.5MW