Top Banner
© 2015 Chevron Corporation. All rights reserved. Gorgon Project Update July 31, 2015
6

Gorgon Project Update - Chevron

Feb 03, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

Gorgon Project Update July 31, 2015

Page 2: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

Train 1 Utilities Functional

Utilities required for the commissioning and operation of Train 1 are now operational.

2

Firewater

Fuel Gas Tempered

Water

Nitrogen Generation Plant Air

Diesel Distribution

Freshwater Reverse Osmosis Plant

Page 3: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

Subsea Verification Testing Underway

Commissioning is underway on the subsea gas gathering system at Janz-Io field. Both electric and hydraulic elements of the control system have been activated. Subsea valves are being tested, paving the way for first gas to the plant site.

3

Page 4: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

LNG Jetty

All eight LNG and two condensate loading arms are now installed on the jetty—the final major components before commissioning activities take place.

4

Page 5: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

Monoethylene Glycol (MEG) Delivery

Two cargos of MEG have been delivered to Barrow Island and imported to the MEG storage tanks. Preparations are underway to fill the Jansz-Io MEG pipeline.

5

MEG Tanks

Page 6: Gorgon Project Update - Chevron

© 2015 Chevron Corporation. All rights reserved.

LNG Trains

All LNG Train 1 and common modules required for first LNG are on their foundations. The final LNG Train 2 module has been placed on its foundations. Delivery of LNG Train 3 modules continues with five of the 13 on Barrow Island.

6

LNG Train 2

LNG Train 1