© 2015 Chevron Corporation. All rights reserved. Gorgon Project Update July 31, 2015
© 2015 Chevron Corporation. All rights reserved.
Train 1 Utilities Functional
Utilities required for the commissioning and operation of Train 1 are now operational.
2
Firewater
Fuel Gas Tempered
Water
Nitrogen Generation Plant Air
Diesel Distribution
Freshwater Reverse Osmosis Plant
© 2015 Chevron Corporation. All rights reserved.
Subsea Verification Testing Underway
Commissioning is underway on the subsea gas gathering system at Janz-Io field. Both electric and hydraulic elements of the control system have been activated. Subsea valves are being tested, paving the way for first gas to the plant site.
3
© 2015 Chevron Corporation. All rights reserved.
LNG Jetty
All eight LNG and two condensate loading arms are now installed on the jetty—the final major components before commissioning activities take place.
4
© 2015 Chevron Corporation. All rights reserved.
Monoethylene Glycol (MEG) Delivery
Two cargos of MEG have been delivered to Barrow Island and imported to the MEG storage tanks. Preparations are underway to fill the Jansz-Io MEG pipeline.
5
MEG Tanks
© 2015 Chevron Corporation. All rights reserved.
LNG Trains
All LNG Train 1 and common modules required for first LNG are on their foundations. The final LNG Train 2 module has been placed on its foundations. Delivery of LNG Train 3 modules continues with five of the 13 on Barrow Island.
6
LNG Train 2
LNG Train 1