GLAST LAT Project November 17, 2004 AntiCoincidnce Detector 1 GLAST Large Area GLAST Large Area Telescope: Telescope: Face to Face Meeting November 17, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard Space Flight Center Subsystem Manager/Instrument Manager [email protected][email protected]Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope
12
Embed
GLAST LAT ProjectNovember 17, 2004 AntiCoincidnce Detector 1 GLAST Large Area Telescope: Face to Face Meeting November 17, 2004 AntiCoincidence Detector.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 1
GLAST Large Area Telescope:GLAST Large Area Telescope:Face to Face MeetingNovember 17, 2004AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6
David J. ThompsonThomas E. JohnsonNASA Goddard Space Flight CenterSubsystem Manager/Instrument Manager
4.1.6.2 Safety and Mission Assurance 817.7 585.0 223.9
4.1.6.3 Tile Shell Assembly 3723.0 3552.0 181.0
4.1.6.4 Base Electronics Assembly 5598.4 5242.0 356.4
4.1.6.4 BEA (SLAC) 684 640 44
4.1.6.5 Micrometeoroid Shield/Thermal Blanket
578.2 335.0 243.2
4.1.6.6 Mech Qual & Calibration Unit 160 108.0 52.0
4.1.6.7 Integration and Test 639.0 368.0 271.0
4.1.6.8 LAT Integration and Test 66.8 36.0 30.8
4.1.6.B Ground Support Equipment 951.2 799.0 152.2
TOTAL 17,340.6 15,595.0 1745.6
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 4
Lien ListLien List
Lien Description FY05 Liens*
EGSE SW Support $60K
FY05 portion of grassroots estimate (4-04) $226K
MS/TB $113K
Reduce Efficiency verif. Test duration ($20K)
Reduce shipping time ($10K)
Schedule Delay (including 2.5 month fab phase delay) $1230.6K
Streamline conformal coating FREE boards ($4K)
SLAC ASIC variance $44K
LAT I&T Support (½ time technician) $31K
Science Support for FY05 and ½ of FY06 (Grad Student) $75K
TOTAL $1745.6K* Updated Lien list from the lien list provided by Jay Doubrava on 10/13/04
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 5
Manpower PlanManpower Plan
• The following table provides both the Contractor and Civil Servant manpower plan for FY05-FY07
• Assumptions:– ACD RFI and integration to the LAT date is 5/17/04.– ACD Support Team ramps down significantly after 5/17/04.– From July – September, 1.8 FTE’s are for Science Support and the
remaining support is for Systems Engineering and Management.
Total TotalNov Dec Jan Feb Mar Apr May Jun Jul Aug Sep FY06 FY07 FY05