Top Banner
OSHA 1926 Subpart CC: Cranes and Derricks in Construction Summary Ray Feidt, Stephenson Equipment, Inc. Joel Oliva, National Commission for the Certification of Crane Operators (NCCCO
56
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Gin pole

OSHA 1926 Subpart CC:  Cranes and Derricks in Construction

Summary

Ray Feidt, Stephenson Equipment, Inc.

Joel Oliva, National Commission forthe Certification of Crane Operators(NCCCO

Page 2: Gin pole

TYPES OF EQUIPMENT COVEREDOSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 2

Page 3: Gin pole

1926.1400 Included Equipment• § 1926.1400 Scope.• (a) This standard applies to power‐operated 

equipment, when used in construction, that can hoist, lower and horizontally move a suspended load. Such equipment includes, but is not limited to: 

– articulating cranes (such as knuckle‐boom cranes); 

– crawler cranes; – floating cranes; – cranes on barges; – locomotive cranes; – mobile cranes (such as wheelmounted, 

rough‐terrain, all‐terrain, commercial truck‐mounted, and boom truck cranes); 

– multi‐purpose machines when configured to hoist and lower (by means of a winch or hook) and horizontally move a suspended load; 

– industrial cranes (such as carry‐deck cranes); dedicated pile drivers; service/ mechanic trucks with a hoisting device; 

– a crane on a monorail; – tower cranes (such as a fixed jib, i.e., 

“hammerhead boom”), luffing boom, and self‐erecting);

– pedestal cranes; – portal cranes; – overhead and gantry cranes; – straddle cranes; – sideboom cranes; – derricks; – and variations of such equipment. 

• Attachments. This standard applies to equipment included in this section when used with attachments. Such attachments, whether crane‐attached or suspended include, but are not limited to: hooks, magnets, grapples, clamshell buckets, orange peel buckets, concrete buckets, drag lines, personnel platforms, augers or drills and pile driving equipment.

Stephenson Equipment, Inc./Ray Feidt 3

Page 4: Gin pole

Exclusions• Exclusions. This subpart does not cover: 

– Machinery included in paragraph (a) of this section while it has been converted or adapted for a non‐hoisting/lifting use. Such conversions/adaptations include, but are not limited to, power shovels, excavators and concrete pumps.

– Power shovels, excavators, wheel loaders, backhoes, loader backhoes, track loaders. This machinery is also excluded when used with chains, slings or other rigging to lift suspended loads.

– Automotive wreckers and tow trucks when used to clear wrecks and haul vehicles.

– Digger derricks when used for augering holes for poles carrying electric and telecommunication lines, placing and removing the poles, and for handling associated materials to be installed on or removed from the poles. Digger derricks used in work subject to 29 CFR part 1926, subpart V, must comply with 29 CFR 1910.269. Digger derricks used in construction work for telecommunication service (as defined at 29 CFR 1910.268(s)(40)) must comply with 29 CFR 1910.268.

– Machinery originally designed as vehicle‐mounted aerial devices (for lifting personnel) and self‐propelled elevating work platforms.

– Telescopic/hydraulic gantry systems.– Stacker cranes.– Powered industrial trucks (forklifts), except 

when configured to hoist and lower (by means of a winch or hook) and horizontally move a suspended load.

– Mechanic’s truck with a hoisting device when used in activities related to equipment maintenance and repair. 

– Machinery that hoists by using a come‐a‐long or chainfall.

– Dedicated drilling rigs.– Gin poles when used for the erection of 

communication towers.– Tree trimming and tree removal work.– Anchor handling or dredge‐related operations 

with a vessel or barge using– an affixed A‐frame.– Roustabouts.– Helicopter cranes.

Stephenson Equipment, Inc./Ray Feidt 4

Page 5: Gin pole

Material Handlers• (Material Delivery)

– Articulating/knuckle‐boom truck cranes that deliver material to a construction site when used to transfer materials from the truck crane to the ground, without arranging the materials in a particular sequence for hoisting.

– Articulating/knuckle‐boom truck cranes that deliver material to a construction site when the crane is used to transfer building supply sheet goods or building supply packaged materials from the truck crane onto a structure, using a fork/cradle at the end of the boom, but only when the truck crane is equipped with a properly functioning automatic overload prevention device. Such sheet goods or packaged materials include, but are not limited to: sheets of sheet rock, sheets of plywood, bags of cement, sheets or packages of roofing shingles, and rolls of roofing felt.

– This exclusion does not apply when:• The articulating/knuckle‐boom crane is used to 

hold, support or stabilize the material to facilitate a construction activity, such as holding material in place while it is attached to the structure;

– The material being handled by the articulating/knuckle‐boom crane is a prefabricated component. Such prefabricated components include, but are not limited to: precast concrete members or panels, roof trusses (wooden, cold‐formed metal, steel, or other material), prefabricated building sections such as, but not limited to: floor panels, wall panels, roof panels, roof structures, or similar items;

– The material being handled by the crane is a structural steel member (for example, steel joists, beams, columns, steel decking (bundled or unbundled) or a component of a systems‐engineered metal building (as defined in 29 CFR 1926 subpart R).

– The activity is not specifically excluded under §1400(c)(17)(i) and (ii).

Stephenson Equipment, Inc./Ray Feidt 5

Page 6: Gin pole

SUBPART CC

OSHA 1926.1400 covers all equipment with a manufactured maximum  capacity of over 2000 pounds used in construction work.Subpart CC, effective date: November 8, 2010These cranes include….

6Stephenson Equipment, Inc./Ray Feidt

Page 7: Gin pole

Equipment Covered

Carry Deck Cranes

Rough Terrain Cranes

7Stephenson Equipment, Inc./Ray Feidt

Page 8: Gin pole

Equipment Covered

Telescopic Truck Cranes Lattice Crawler Cranes

8Stephenson Equipment, Inc./Ray Feidt

Page 9: Gin pole

Equipment Covered

Lattice Truck Crane Top Slew Tower Cranes

9Stephenson Equipment, Inc./Ray Feidt

Page 10: Gin pole

Equipment Covered

Self-Erecting Tower Cranes Non-Swing Cab Rough Terrain

10Stephenson Equipment, Inc./Ray Feidt

Page 11: Gin pole

Equipment Covered

Boom Trucks

Service Trucks with Cranes (Exception: If they are being used for equipment repair work they are exempt.)

11Stephenson Equipment, Inc./Ray Feidt

Page 12: Gin pole

Equipment Covered

Gantry Cranes when used in construction work

12Stephenson Equipment, Inc./Ray Feidt

Page 13: Gin pole

Equipment Covered

Stephenson Equipment, Inc./Ray Feidt 13

Tele‐handlers with winch attachments Tele‐handlers with forks are exempt

Page 14: Gin pole

EQUIPMENT EXEMPTOSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 14

Page 15: Gin pole

Digger Derrick

• Digger derrick machines are exempt if they are being used for augering holes for poles carrying electric or telecommunication lines and for handling the associated equipment that gets installed on these poles.

• If the digger derrick is used for any other purpose, it is not exempt.i.e. if the digger derrick is used to set poles in a parking lot, it is not exempt.

Stephenson Equipment, Inc./Ray Feidt 15

Page 16: Gin pole

Material Handlers

• If the knuckleboom crane is being used to deliver material to a jobsite from the truck to the ground, without arranging the materials in a particular sequence for hoisting, the crane is exempt.

Stephenson Equipment, Inc./Ray Feidt 16

Page 17: Gin pole

Material Handlers• Articulating/knuckle‐boom truck cranes are 

exempt if they are used to deliver material to a construction site when the crane is used to transfer building supply sheet goods or building supply packaged materials from the truck crane onto a structure, using a fork/cradle at the end of the boom, but only when the truck crane is equipped with a properly functioning automatic overload prevention device.

• This exclusion does not apply when:– The knuckle‐boom crane is used to hold, 

support or stabilize the material to facilitate a construction activity, such as holding material in place while it is attached to the structure; 

– The material being handled by the articulating/knuckle‐boom crane is a prefabricated component.

– The material being handled by the crane is a structural steel member (for example, steel joists, beams, columns, steel decking (bundled or unbundled) or a component of a systems‐engineered metal building

– The activity is not specifically excluded under §1400(c)(17)(i) and (ii).

Stephenson Equipment, Inc./Ray Feidt 17

Page 18: Gin pole

Excavators

• Excavators, wheel loaders, backhoes, power shovels are all exempt when being used for lifting.

Stephenson Equipment, Inc./Ray Feidt 18

Page 19: Gin pole

Tow Trucks

• Tow trucks are exempt if they are being used for auto wrecking.

• If they are being used to lift something on a construction project, they are not exempt.

Stephenson Equipment, Inc./Ray Feidt 19

Page 20: Gin pole

Bucket Truck

• Bucket trucks are exempt.

• They are manufactured as vehicle mounted aerial lifts.

Stephenson Equipment, Inc./Ray Feidt 20

Page 21: Gin pole

Manlifts

• Self propelled elevating work platforms are exempt.

Stephenson Equipment, Inc./Ray Feidt 21

Page 22: Gin pole

Telescopic Gantry System

• Telescopic gantry systems are exempt.

Stephenson Equipment, Inc./Ray Feidt 22

Page 23: Gin pole

Stacker Cranes

• Stacker cranes are exempt.

Stephenson Equipment, Inc./Ray Feidt 23

Page 24: Gin pole

Powered Industrial Trucks

• Powered industrial trucks (forklifts) are exempt if being used with forks and other attachments.

• Exception:• When the forklift is 

equipped with a winch that can hoist and lower a load and move the load horizontally, it is not exempt.

Stephenson Equipment, Inc./Ray Feidt 24

This machine is not exempt

These machines are exempt

Page 25: Gin pole

Mechanics Truck with Cranes

• Mechanics trucks with cranes are exempt when being used when maintaining or repairing equipment. 

• They are not exempt if they are being used to handle parts for a machine for the purpose of assembling the machine.

Stephenson Equipment, Inc./Ray Feidt 25

Page 26: Gin pole

Come‐a‐long or Chain falls

• Any machine or equipment that uses a come‐a‐long or chain fall to do lifting is exempt.

Stephenson Equipment, Inc./Ray Feidt 26

Page 27: Gin pole

Drill Rig

• Dedicated drill rigs are exempt.

Stephenson Equipment, Inc./Ray Feidt 27

Page 28: Gin pole

Gin Pole

• Gin poles are exempt when used to erect communication towers.

Stephenson Equipment, Inc./Ray Feidt 28

Page 29: Gin pole

Tree Work using Cranes

• Cranes used to trim or remove trees are exempt.

Stephenson Equipment, Inc./Ray Feidt 29

Page 30: Gin pole

Barge Mounted A‐Frame Hoists

• Barge mounted A‐frame hoists used in dredge related operations are exempt.

Stephenson Equipment, Inc./Ray Feidt 30

Page 31: Gin pole

Roustabouts

• Roustabouts are exempt.

Stephenson Equipment, Inc./Ray Feidt 31

Page 32: Gin pole

Helicopters

• Helicopter cranes are exempt.

Stephenson Equipment, Inc./Ray Feidt 32

Page 33: Gin pole

GROUND CONDITIONS §1926.1402OSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 33

Page 34: Gin pole

Ground Conditions §1926.1402

• Controlling entity:– Must assure that ground preparations are:

– Firm, drained and graded

– Sufficient to support crane (in conjunction with blocking, mats, etc.)

Stephenson Equipment, Inc./Ray Feidt 34

Page 35: Gin pole

Ground Conditions §1926.1402

– The Controlling Entity must Inform equipment user & operator of known underground hazards (voids, utilities, etc.)

Stephenson Equipment, Inc./Ray Feidt 35

Page 36: Gin pole

Controlling Entity• If there is no controlling entity for 

the project, this position must be met by the employer that has authority at the site to make or arrange for ground preparations needed.

• If the A/D director or the operator determines that ground conditions do not meet the requirements, that person’s employer must have a discussion with the controlling entity regarding the ground preparations that are needed so that, with the use of suitable supporting materials/devices (if necessary), the site meets necessary requirements.

Stephenson Equipment, Inc./Ray Feidt 36

Page 37: Gin pole

ASSEMBLY – DISASSEMBLY OSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 37

Page 38: Gin pole

Assembly ‐ Disassembly• When assembling or 

disassembling equipment (or attachments), the employer must comply with all applicable manufacturer prohibitions and must comply with either:– Manufacturer procedures 

applicable to assembly and disassembly, or

– Employer procedures for assembly and disassembly. Employer procedures may be used only where the employer can demonstrate that the procedures used have been developed and documented by a qualified person.

– Note: The employer must follow manufacturer procedures when an employer uses synthetic slings during assembly or disassembly rigging.

Stephenson Equipment, Inc./Ray Feidt 38

Page 39: Gin pole

Assembly – Disassembly Rigging• Rigging. The employer must 

ensure that:– The rigging work is done by a 

qualified rigger.– Synthetic slings are protected 

from: Abrasive, sharp or acute edges, and configurations that could cause a reduction of the sling’s rated capacity, such as distortion or localized compression. 

– Wire rope slings must be used following the manufacturer’s inspections and protection must be used where applicable.

– When synthetic slings are used, the synthetic sling manufacturer’s instructions, limitations, specifications and recommendations must be followed.

Stephenson Equipment, Inc./Ray Feidt 39

Page 40: Gin pole

A/D Director• When assembling or disassembling a 

crane, these general requirements must be met:

• There must be an A/D director who is in charge of the operation.

• A/D Director must be a “competent & qualified person”

• A/D Director must:• Understand procedures• Review procedures (unless A/D 

Director has used them before) • Check that crew members 

understand their tasks, hazards• Follow manufacturer’s prohibitions• All rigging work is done by a Qualified 

Rigger• When using outriggers ‐ fully extend 

or deploy as per the load chart.• Capacity limits of all assist cranes 

must not be exceeded.

Stephenson Equipment, Inc./Ray Feidt 40

Page 41: Gin pole

Assembly – Disassembly near Power Lines up to 350kV

• Before assembling or disassembling equipment, the employer must determine if any part of the equipment could get closer than 20 feet to a power line during the assembly/disassembly process. If so, the employer must meet the requirements in Option (1), Option (2), or Option (3):

• No assembly/disassembly operations are permitted under an energized power line.

Stephenson Equipment, Inc./Ray Feidt 41

Page 42: Gin pole

Assembly – Disassembly (Option 1)

• Deenergize and ground. Confirm from the utility owner/operator that the power line has been deenergized and visibly grounded at the worksite.

Stephenson Equipment, Inc./Ray Feidt 42

Off

Page 43: Gin pole

Assembly – Disassembly (Option 2)

• 20 foot clearance.• Ensure that no part of the 

equipment gets closer than 20 feet to the power line doing all of the following:– Conduct a planning meeting.– If tag lines are used they must 

be non‐conductive.– And one of the following must 

be done:• Use a dedicated spotter to 

watch for power line clearance.• Use a proximity device.• Use a range limiting device on 

the crane.• Erect an elevated warning line 

with high visibility flags.

Stephenson Equipment, Inc./Ray Feidt 43

Page 44: Gin pole

Assembly – Disassembly (Option 3)

• If you determine the actual power line voltage from the utility company in writing, the 20 foot clearance can be reduced to the distances listed in the “Table A”for clearances during operation and “Table T” for clearances during “in transit”.

• All other requirements of option 2 apply.

Stephenson Equipment, Inc./Ray Feidt 44

Page 45: Gin pole

OSHA 1926.1408 & ASME B30.5 Minimum OSHA 1926.1408 & ASME B30.5 Minimum Clearances during Operation Clearances during Operation –– ““TABLE ATABLE A””

Voltage  (Nominal, kV, Alternating Current Minimum Clearance in Feet

Up to 50 10

Over 50 to 200 15

Over 200 to 350 20

Over 350 to 500 25

Over 500 to 750 35

Over 750 to 1000 45

Over 1000  (as established by utility owner)

Stephenson Equipment, Inc./Ray Feidt 45

Page 46: Gin pole

OSHA 1926.1411 & ASME B30.5 Minimum OSHA 1926.1411 & ASME B30.5 Minimum Clearances in Transit Clearances in Transit –– ““TABLE TTABLE T””

Stephenson Equipment, Inc./Ray Feidt 46

Voltage  (Nominal, kV, Alternating Current Minimum Clearance in Feet

Up to 0.75 4

Over 0.75 to 50 6

Over 50 to 345 10

Over 345 to 750 16

Over 750 to 1,000 20

Over 1000  (as established by utility owner)

No load, boom lowered. Specifically when a crane is travelling under or near a power line on a construction site with no load. Cranes travelling with a load is governed by

the “in operation” minimum clearances in “Table A”.

Page 47: Gin pole

POWER LINE SAFETY ‐ OPERATIONOSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 47

Page 48: Gin pole

OSHA 1926.1412 ‐ Defining the Work Zone

• The work zone must be defined by either:– Option 1:

• Erecting boundary markings such as flags or,

• Setting and using a range limiting device on the crane,

• and prohibiting the operator from operating the crane past those boundaries.

– Option 2:• Defining the work zone as the area 360 degrees around the crane, up to the equipment’s maximum working radius.

Stephenson Equipment, Inc./Ray Feidt 48

20’ ≤ 350kV50’ > 350kV

360°

Page 49: Gin pole

OSHA 1926.1412 – Define Work Zone con’t.

• And……• Determine if any part of the 

crane, if operated up to the crane’s maximum working radius in the work zone, could get closer than:• 20 feet to a power line up to 

and including 350kV or …..• 50 feet over 350kV. 

• If so, the employer must meet the requirements in Option (1), Option (2), or Option (3) of this section, as follows:

Stephenson Equipment, Inc./Ray Feidt 49

Page 50: Gin pole

Stephenson Equipment, Inc./Ray Feidt 50

Is the maximum radius of the crane is within:

20 feet of a power line ≤ 350kV, or50 feet of a power line > 350kV, or

OPTION 3 - if the voltage level is known, the minimum distance listed in chart “A”?

YES NO

Option #1Deenergize & Ground

Encroachment Prevention Measures(Equipment Operations)

Option #3Ask Utility for Voltage and Use Table A to get the minimum clearance and maintain the clearance by doing these:

Option #2Maintain 20-foot clearance by doing these:

No further action

• Must do all of these:• Must have a planning meeting• If tag lines are used they must be Non-conductive• Elevated warning lines, barricade or line of signs must be positioned visible to the operator.

•PLUS one of these must be used (Choose one):

• Proximity alarm, dedicated spotter, warning device, range limiter, or insulating link

Page 51: Gin pole

Stephenson Equipment, Inc./Ray Feidt 51

Must Show:• Staying outside zone

is infeasible• Infeasible to deenergize and ground

Intentionally Working Closer Than Table A ZoneAll of the following are required:

1. Power line owner – sets minimum approach distance

2. Planning meeting – minimum procedures- Dedicated spotter- Elevated warning line or barricade- Insulating link/device- Nonconductive rigging- Range limiter (if equipped)- Nonconductive tag line (if used)- Barricades - 10 feet from equipment- Limit access to essential workers- Prohibit non-operator workers from touching above insulating link- Properly ground crane- Deactivate automatic re-energizer- Insulating line cover-up installed

Page 52: Gin pole

INSPECTIONSOSHA 1926.1400

Stephenson Equipment, Inc./Ray Feidt 52

Page 53: Gin pole

Inspections

Stephenson Equipment, Inc./Ray Feidt 53

Modified or repaired/adjusted

Qualified person

Post-assembly Qualified person

Shift Competent person

Monthly Competent person

Annual Qualified person

Type of Inspection: Who Inspects:

Page 54: Gin pole

Shift Inspection• The shift inspection is normally done 

by the operator. OSHA requires the person that does this inspection to be considered a “competent person”.

• Competent person means one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.

• This inspection does not need to be documented.

• The shift inspection must begin prior to the shift and be finished before the end of the shift.

Stephenson Equipment, Inc./Ray Feidt 54

Page 55: Gin pole

Monthly Inspections

• The monthly inspection is normally done by the operator. OSHA requires the person that does this inspection to be considered a “competent person”.

• This inspection needs to be documented (recorded in writing).

• The last three monthly inspections must be retained. These inspection reports must be made available to all people that are or will be inspecting the crane.

• Any deficiency found during the annual inspection that was recorded as needing monitored on a monthly basis must be inspected during the monthly inspection and recorded specifically  on the monthly inspection report.

Stephenson Equipment, Inc./Ray Feidt 55

Page 56: Gin pole

Annual Inspection

• The annual inspection is normally not done by the operator. OSHA requires the person that does this inspection to be considered a “qualified person”.

• Qualified person means a person who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, successfully demonstrated the ability to solve/resolve problems relating to the subject matter, the work, or the project.

• This inspection needs to be documented (recorded in writing).

• The last annual inspection must be retained. This inspection report must be made available to all people that are or will be inspecting the crane.

Stephenson Equipment, Inc./Ray Feidt 56