Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

Jun 10, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Getting to Grips with Deepwater Handling Operations

Mark Wood, Regional Manager SE Asia, First Subsea Ltd

Thursday, 18 October 12

Page 2: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

First Subsea

Trends in Offshore Handling

Deepwater Handling Challenges

Ball and Taper Technology

Case Study 1 - Riser Handling

Case Study 2 - TAD Lashing

Case Study 3 - MODU Mooring

Agenda

Thursday, 18 October 12

Page 3: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

First Subsea is a specialist in the development and supply of subsea mooring, riser connector and tubular handling systems

World leading, patented ball and taper connection technology

Full design, build and testing capability

Based in Lancaster, UK with representatives in Aberdeen; Kuala Lumpur, Malaysia; Perth, Australia; United States and Brazil

Over 50 employees, mostly qualified engineers

First Subsea

Thursday, 18 October 12

Page 4: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Greater development of seabed structures

Longer tie-backs to production platform

Growing importance of deepwater exploration and production

Renewable energy - offshore wind farms and current turbines

Decommissioning

Trends in Offshore Handling

Thursday, 18 October 12

Page 5: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Further offshore, lack of infrastructure

Environmental Risk

Engineering Challenge- water depth- mooring rather than fixed structures- greater subsea equipment payload

Handling Safety

Cost of vessel time

Deepwater Handling Challenges

Thursday, 18 October 12

Page 6: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Flexible deployment: dedicated offshore installation barge through to anchor handling vessels

Ability to withstand high loads

Avoid damaging payload

Easy and quick connection

Ease of recovery

Handling Tool Requirements

Thursday, 18 October 12

Page 7: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Ball and Taper Technology

Patented 'Ball and Taper' Ballgrab® technology

Self aligning, Self activating

Simple mechanical mechanism

Grip elements in compression, proportional to load

No release under load - zero failures

Ability to connect and reconnect

Thursday, 18 October 12

Page 8: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Characterised by: powerful yet gentle grip, high load resistance, speed of deployment

Shallow water and deepwater mooring connectors

ROV-lies and diverless bend stiffener connectors: riser and umbilical connections

Pipeline handling tools

Buoy pull-in

Drilling pipe handling tools

Ball and Taper Applications

Thursday, 18 October 12

Page 9: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Problem: deployment of risers to Tweedmuir (2005), Galley & Duart, AUK North and now Arkwright fields, North Sea

Handling requirement for multiple risers in main caisson during welding operations

Case Study - Riser Handling

Thursday, 18 October 12

Page 10: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Solution:

Riser Handling Tool developed:

- grip proportional to load- pure mechanical mechanism

No modification to risers required

No damage to risers

Ability to independently move each riser within main caisson

Ability to purge lines / inspection cameras through the riser handling tool

Case Study - Riser Handling

Thursday, 18 October 12

Page 11: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Case Study - Riser Handling

Next caisson section is prepared with Ballgrab riser handling tool engaged in each riser

Riser handling tool allows independent lifting and positioning of risers for welding to lower caisson section supported on the drill floor

Risers are welded out. A purge line can be connected through the tools

Once weld is complete riser handling tool can be disconnected ready for repeat procedure with next caisson section

Thursday, 18 October 12

Page 12: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia

First use of semi-submersible Tender Assist Drilling Unit (TADU) alongside Spar

TADU - reduces weight and cost of Spar topsides and increases drilling efficiency

Semi-submersibles for TAD include West Setia, West Alliance and West Menang for up to 3 years

Case Study - TAD/SPAR Lashing System

Thursday, 18 October 12

Page 13: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Case Study - TAD/SPAR Lashing System

Problem:

- Reduce cost of installation- Optimise mooring processes

Solution:

- Ballgrab connectors- Faster installation- Ease of changes in mooring line deployment- Greater connector integrity- Convenience and dependability

Thursday, 18 October 12

Page 14: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Case Study - TAD/SPAR Lashing System

Ballgrab connections:

TAD Bow mooringTAD Lashing connection in DTU SparDTU mooring

Ballgrab male connectors removed and serviced between TAD moorings

Thursday, 18 October 12

Page 15: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

100 subsea wells in 18 drill centers at 700 - 1435m

Drill centers in close proximity to optimise subsea architecture

Conventionally moored MODUs selected by field operator, up to four rigs operating simultaneously

Taut-leg mooring to allow MODU to moor safely over three drill centers

Case Study - MODU mooring

Thursday, 18 October 12

Page 16: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Problem:

Risk of damage to subsea infrastructure

Needed easy to deploy and recover mooring tool, without dragging along seabed

Solution:

Permanent, pre-set moorings

Sepla anchor and Ballgrab mooring connectors

Case Study - MODU mooring

Thursday, 18 October 12

Page 17: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Case Study - MODU mooring

Anchor prohibits ‘normal’ pile mounted Ballgrab receptacle

Ballgrab receptacle held in mudmat

Ballgrab connector (and mooring line) lowered from AHV to receptacle to complete mooring

Mooring connector disconnected at end of drilling schedule - retrieved to surface

Ballgrab receptacle returned to mudmat

Thursday, 18 October 12

Page 18: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Offshore handling becoming more complex, more challenging

Ball and taper tools provide a flexible approach to many offshore handling tasks

Simplicity of operation - dependable in-service

Broad offshore handling experience: subsea mooring, riser handling, TAD Lashing

Pipeline recovery, drill pipe handling, buoy retrieval, riser connections...

Ball and Taper - Simplicity over Complexity

Thursday, 18 October 12

Page 19: Getting to Grips with Deepwater Handling Operations · 2015. 3. 31. · Kikeh field - Spar - 4,364 ft (1,330 m) water depth, offshore Malaysia First use of semi-submersible Tender

First Subsea - Always Part of the Solution

Engineering House, Lune Industrial Estate, New Quay Road, Lancaster, LA1 5QP, UKT: +44 (0)1524 387 777 F: +44 (0)1524 387 778 Email: [email protected] site: www.firstsubsea.com