Germany’s Energiewende – Current and imminent challenges for the Transmission System Operator in Germany Jens Jacobs Transmission System Operation Brauweiler Budapest, 04 December 2014
Germany’s Energiewende –
Current and imminent challenges for the
Transmission System Operator in Germany
Jens Jacobs
Transmission System Operation Brauweiler
Budapest, 04 December 2014
Transmission System Operation Amprion | 04 December 2014 | © Amprion 2
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
Far-reaching changes due to the goals of the EU
and the German Federal Government
EU
– Completion of the European internal electricity market
– Integration of renewable energy sources (RES)
– „EU 20-20-20“:
-20% energy consumption; -20% greenhouse gas emission; +20% energy efficiency
– European Legislation – Network Codes – to guarantee system security and
establish harmonized market rules
Federal Government Germany
– Nuclear phase-out till 2022
– 35% power generation from RES till 2020 (80% till 2050)
– 40% reduction of greenhouse gases till 2020 (80% till 2050)
– 20% reduction of primary energy consumption till 2020 (80% till 2050)
3 Transmission System Operation Amprion | 04 December 2014 | © Amprion
Germany, quo vadis?
Road to “Green Revolution”
4 Transmission System Operation Amprion | 04 December 2014 | © Amprion
Transmission System Operation Amprion | 04 December 2014 | © Amprion 5
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
6
UCI
Bahnhof
Bahnhof
UCI
extra high voltage network 380 kV /220 kV
high voltage network 110 kV medium voltage network 20 kV
low voltage network 0,4 kV
Substation
Transformer station
From power plant to households
380-kV / 220-kV:
- large-scale PPs - transits
110-kV:
- Industry PPs - Industry - RES Infeed
Distribution level:
- cutomers - distributed PPs
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Transmission System Operation Amprion | 04 December 2014 | © Amprion 7
The electrical System “Transmission Grid”
Physical Unit (Lines, Transformer, Substation, Power Plant, Consumer
Installation, etc.)
International meshed system
Sensitive “real time” - System
Electrical Energy is not directly storable
Production and Consumption have to be balanced at any time
The Electrical System is operated in Real time (24h/365d)
EU Legislation and National laws (EnWG/EEG) define the Market
Rules and the legal framework
The Transmission System Operator (TSO) is in charge of security of
supply (§ 13 EnWG)
The Transmission Grid (380/220kV-Grid)
8
Structure of the German electrical power supply
TSO
380 kV
220 kV
110 kV
20/10 kV
380 V
Industry
Households
Utilities
TS
O-G
rid
D
SO
-Gri
d
Bulk-Industry
DSO
Dispersed
Generation
Conventional
Generation
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e :
Am
pri
on
Gm
bH
Transmission System Operation Amprion | 04 December 2014 | © Amprion 9
Security of Supply:
Backbone of Electricity Supply
Largest transmission system in Germany with a circuit
length of approx. 12,000 km at the 380/220 kV level and 165
substations
Connects the generation units of the lignite-fired power
plants on the lower Rhine with the hydroelectric stations in
the Alps: installed capacity of power plants approx. 40 GW
Through its central position in Europe, Amprion’s
transmission system is an important hub for electricity
trading between north and south as well as east and west:
approx. 4,000 schedule nominations per day
Interconnectors to eight foreign transmission system
operators in five countries (NL, L, F, CH, A) enables
Amprion to meet the specific transmission requirements of
European power traders at an utmost level of transmission
reliability
Amprion’s electricity network is part of the European
interconnected ENTSO-E system
380/220 kV Network of Amprion
Lower Saxony
Netherlands
North Rhine-
Westphalia
Hesse Belgium
Rhineland
Palatinate
France
Switzerland
Bavaria
Austria
380 kV extra high- voltage
transmission line
220 kV extra high-voltage
transmission line
Important switchgear
Baden
Wuerttemberg
So
urc
e:
Am
pri
on
Gm
bH
Transmission System Operation Amprion | 04 December 2014 | © Amprion 10
Amprion
50Hertz
Transmission
Transnet BW
TenneT
Operational Areas of German Transmission System
Operators
* in Germany
** Renewable Energy Act load compensation 2005
Amprion TenneT 50Hertz Transnet
BW
Network length [km] (380 kV) 5.300 5.800 6.870 1.970
Network length [km] (220 kV) 6.100 5.300 2.870 1.721
Served area [km²]* 73.100 140.000 109.000 34.600
Annual transmission [TWh] 27 20 18 11
Share load [%]** 35 32 19 14
Source : Amprion GmbH
Transmission System Operation Amprion | 04 December 2014 | © Amprion 11
The main control room: system control and system management
Tasks for Amprion (TSO Responsibility)
Tasks for the German TSOs (National Responsibility)
Coordination Center ENTSO-E RG CE North (International Responsibility)
Security first:
Transmission System Operation Amprion (I)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 12
TSO Responsibility
system control and system management of the transmission grid 380/220 kV
disturbance management
congestion management (preventive und curative)
planning and acquisition of ancillary services
Load-Frequency-Control and managing controlling power range of the
Amprion control zone
management of Wind and PV and prediction of system load
system balancing
process technology and –data management
Security first:
Transmission System Operation Amprion (II)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 13
Nationale Responsibilities
coordination of the power exchange programs between the German TSOs
and with foreign TSOs
pluralistic Load-Frequency-Control of the German control block
national quantity balancing of the German control block
Security first:
Transmission System Operation Amprion (III)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 14
Internationale Responsibilities
international coordination of the power exchange programs RG CE North /
South with Swissgrid
international quantity balancing of ENTSO-E RG CE North
congestion forecast (DACF)
Data management and clearance for the ENTSO-E ITC Process
Hosting and server operation of process technology for CWE Market Coupling
Hosting and server operation of process technology for international security
analysis within TSC Security initiative (11 TSOs)
Hosting of the Security Service Center (Germany / The Netherlands)
Security first:
Transmission System Operation Amprion (IV)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 15
Use of Balancing
Power
Forecast deviation
set point
frequency
50 Hz
Generation loss
Consumption Production
Forecast deviation (RES)
Tripped Load
Load interference
Load Frequency Control and Power Balance
Transmission System Operation Amprion | 04 December 2014 | © Amprion 16
DSO
Customer
TSO 2 TSO 1
n-1
Security of Supply: the „(n-1) - Criterion“
"N-1" CRITERION:
Any probable single event leading to a loss of Power System elements (generating set, transmission line, transformer, etc.) should not endanger the security of interconnected operation:
Loss of Consumption
Interconnected System Stability
Violation of limit values (Current, Voltage, Frequency Deviation)
Cascade of Tripping
Transmission System Operation Amprion | 04 December 2014 | © Amprion 17
“N-1” Security Criterion: Regional Approach
Observability area of Amprion
responsibility area
(Amprion)
165 substations
observability area
435 substations
Source: Amprion GmbH
Dramatic extended
data volume for
On-line Calculations
• Load flow Analysis
• (n-1)-Security
Calculations
Transmission System Operation Amprion | 04 December 2014 | © Amprion 18
Founded 19 December 2008 and fully
operational since 1 July 2009
Represents 42 TSOs from 34 countries
525 million citizens served
828 GW generation
305,000 km of transition lines managed by the TSOs
3,400 TWh/year demand
400 TWh/year exchanges
5 synchronous areas
Replaces former TSO organisations: ATSOI, BALTSO, ETSO, NORDEL, UCTE, UKTSOA
The European Interconnected System
ENTSO-E
Source: ENTSO-E
525 Million
Transmission System Operation Amprion | 04 December 2014 | © Amprion 19
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
Directly Effected power plants
Biblis A 1167 MW
Neckarwestheim 645 MW
Philippsburg 1 890 MW
Unterweser 1345 MW
Isar 1 878 MW
Biblis B 1240 MW
Brunsbüttel 771 MW
Krümmel 1345 MW
Total 8 281 MW
Nuclear phase out in Germany, March 2011
20 20
Nuclear power plants in Germany
Transmission System Operation Amprion | 04 December 2014 | © Amprion
2015:
Grafenrheinfeld 1275 MW
2017:
Gundremmingen B 1284 MW
2019:
Philippsburg 2 1402 MW
2021:
Brokdorf 1410 MW
Grohnde 1360 MW
Gundremmingen C 1288 MW
2022:
Emsland 1329 MW
Isar 2 1410 MW
Neckarwestheim 1310 MW
Total 12.068 MW
Nuclear phase out in Germany till 2022
21 21
Nuclear power plants in Germany
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Additional loss of 4000 MW in
the South in the next 5 years!
others5%
gas11%
renewables23%
lignite26%
cole20%
nuclear power15%
others5%
gas11%
renewables23%
lignite26%
cole20%
nuclear power15%
wind
biomass
PV
hydro
7,9%
7,6%
4,5%
3,4%
Generation mix in Germany 2013
Share of renewable energy 23%
22
Total
629 Bil. kWh
Source: BDEW 01/2014
Systemführung Netze Brauweiler | 24.03.2014 | © Amprion
RES in Hungary: ≈ 7 − 8%
0%
5%
10%
15%
20%
25%
30%
2010 2011 2012 2013
Others
Gas
Renewables
Lignite
Hard coal
Nuclear
Development of Generation Capacity in Germany
since 2010 (share of primary energy)
23
Total generation in
Germany [Bil. kWh]:
2010 605
2011 612
2012 617
2013 629
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
24
Renewable Generation leads to an inharmonic and unusual power flow in the
Grid:
In Germany Wind generation is installed in the northern and eastern part
of the country
High Wind power leads to bulk energy flows from North to South because
most industry is concentrated in southern part of Germany
Impacts of Renewable Generation on
Grid Security (1)
Transmission System Operation Amprion | 04 December 2014 | © Amprion
25
Renewable Generation leads to an inharmonic and unusual power flow in the
Grid:
In Germany PV generation is installed in the southern part of the country
High PV power leads to bulk energy flow in DSO grid and from DSO to
TSO
Impacts of Renewable Generation on
Grid Security (2)
Transmission System Operation Amprion | 04 December 2014 | © Amprion
4.162
6.201
8.144
7.473
8.445
18.321
22.796
31.038
59.882
75.324
4.772
7.698
8.551
8.254
10.531
20.150
22.959
34.660
61.108
91.413
4.855
8.526
8.586
8.592
11.180
21.262
22.970
36.488
61.946
98.588
Denmark
Canada
Italy
France
UK
India
Spain
Germany
USA
China
2014 (1st half) 2013 2012
26
Top 10 Countries by Total Wind Capacity [MW]
2012 to 2014 (first half)
So
urc
e:
Wo
rld
Win
d E
ne
rgy A
sso
cia
tio
n
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Hungary: ≈ 𝟓𝟎𝟎 𝑴𝑾 (2013)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 27
Source: IWES, TSOs
Wind Power Development in Germany
42 74155
309
505428
534
793
1.5681.665
2.659
3.247
2.645
2.037
1.871
1.200
1.800
1.600
1.880
1.357
1.913
2.500
2.055
1.880
110 193 334 643 1.1371.5462.0822.875
4.445
6.095
8.754
12.061
14.60916.629
18.500
19.700
21.500
23.100
24.980
26.387
28.300
30.800
32.855
34.735
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
0
500
1.000
1.500
2.000
2.500
3.000
3.500
1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 2013
Development of Capacity
Accummulated Capacity(End of Year)
MW MW
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000J
an
Feb
Ma
r
Ap
r
Ma
y
Ju
ne
Ju
ly
Au
g
Sep
t
Oct
No
v
Dec
2006
2007
2008
2009
2010
2011
2012
2013
2014*
Average
28 Transmission System Operation Amprion | 04 December 2014 | © Amprion
Monthly Production of Wind Energy in Germany 2006 to 2014 (1st half)
GWh
2014*: 1st half Source: Online Extrapolation German TSO
29
Top 10 Countries by Total PV Capacity [MW]
2011 to 2013
2.088
1.377
905
4.260
2.974
3.959
4.914
12.807
3.300
24.858
2.772
2.415
1.831
4.538
4.090
7.328
6.632
16.454
6.800
32.462
3.009
3.226
3.377
4.640
4.733
12.079
13.599
18.074
19.720
35.766
Belgium
Australia
UK
Spain
France
USA
Japan
Italy
China
Germany
2013 2012 2011
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Hungary: ≈ 𝟏𝟓 𝑴𝑾 (2013)
Transmission System Operation Amprion | 04 December 2014 | © Amprion 30
PV Development in Germany
Source: BNetzA, TSOs
3.806
5.515
7.200
8.654
4.630
1.2295.979
9.785
15.300
22.500
31.154
35.78437.013
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
10.000
2008 2009 2010 2011 2012 2013 2014*
Development of Capacity
Accummulated Capacity(End of Year)
MW MW
2014*: 1st half
31 Transmission System Operation Amprion | 04 December 2014 | © Amprion
0
1.000
2.000
3.000
4.000
5.000
6.000
Jan
Feb
Mar
Ap
r
Ma
y
Ju
n
Ju
l
Au
g
Sep
Okt
No
v
De
c
2010
2011
2012
2013
2014*
Average
GWh
2014*: 1st half
Monthly Production of PV Energy in Germany 2010 to 2014 (1st half)
Source: Online Extrapolation German TSO
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000Ja
n 1
0F
eb
10
Mrz
10
Ap
r 1
0M
ai 10
Ju
n 1
0Ju
l 10
Au
g 1
0S
ep
10
Okt 1
0N
ov 1
0D
ez 1
0Ja
n 1
1F
eb
11
Mrz
11
Ap
r 1
1M
ai 1
1Ju
n 1
1Jul 11
Au
g 1
1S
ep
11
Okt 1
1N
ov 1
1D
ez 1
1Ja
n 1
2F
eb 1
2M
rz 1
2A
pr
12
Ma
i 1
2Ju
n 1
2Ju
n 1
2A
ug
12
Sep 1
2O
kt 1
2N
ov 1
2D
ez 1
2Ja
n 1
3F
eb
13
Mrz
13
Apr
13
Ma
i 1
3Ju
n 1
3Ju
l 13
Au
g 1
3S
ep
13
Okt 1
3N
ov 1
3D
ez 1
3
onshore Wind Solar
Wind / PV – installed capacity in Amprion grid
32
MW
Transmission System Operation Amprion | 04 December 2014 | © Amprion
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
Wind D
Installiert Wind D
max. Wind: 25.741MW
approx. 78% of the inst. capacity
(05.12.2013, 18:00)
min. Wind: 126MW
approx. 0,4% of the inst. capacity
(04.09.2013, 14:00)
MW
PDE
Transmission System Operation Amprion | 04 December 2014 | © Amprion 33
Wind Energy: Installed Capacity and Production (2013)
h-Values for 2013 0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
Windgeneration
Installed capacity
So
urc
e :
Am
pri
on
Gm
bH
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
PV D
Installiert PV D
max. PV : 23.952MW
approx. 72% of the inst. capacity
(21.07.2013, 14:00)
MW
PDE
34 Transmission System Operation Amprion | 04 December 2014 | © Amprion
PV Energy: Installed Capacity and Production (2013)
h-Values for 2013
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
PV generation
Installed capacity
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
EE D
Installiert EE D
Jahres-Mittel EE
max. RES*: 35.768MW
Wind: 16.698MW
PV: 19.070MW
approx. 56% of the inst. capacity
(18.04.2013, 13:00)
min. RES*: 148MW
Wind: 148MW
PV: 0MW
approx. 0,5% of the inst. capacity
(17.02.2013, 04:00)
MW
PDE
35 Transmission System Operation Amprion | 04 December 2014 | © Amprion
RES Energy: Installed Capacity and Production (2013)
h-Values for 2013
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
RES generation
Installed capacity
Average generation
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
EE D
Installiert EE D
Jahres-Mittel EE
MW
PDE
max. RES: 35.768 MW
Wind: 16.698 MW
PV: 19.070 MW
approx. 56% (18.04.2013)
min. RES: 148 MW
Wind: 148 MW
PV: 0 MW
approx. 0,5% (17.02.2013)
36 Transmission System Operation Amprion | 04 December 2014 | © Amprion
RES Energy: Installed Capacity and Production (since 2011)
h-Values 2014*: 1st half
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
RES generation
Installed capacity
Average generation
So
urc
e :
Am
pri
on
Gm
bH
Transmission System Operation Amprion | 04 December 2014 | © Amprion 37
Wind Power Forecast Optimization (1/2)
Example: 25.05.14 forecast of 26.05.14 – total German wind
Forecast Combination
So
urc
e :
Am
pri
on
Gm
bH
Transmission System Operation Amprion | 04 December 2014 | © Amprion 38
Wind Power Forecast Optimization (2/2)
Example: 26.05.14 – total German wind
Forecast Combination
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Summe Wind+PV*
Last Deutschland**
MW
Wind and Solar Infeed vs. Load in Germany
Time: Thursday, 10 April 2014 (day with lowest share of renewable energy covering load)
39
10 April 2014 , 21:00 h
Load approx. 65.900MW
Wind+PV-Infeed approx. 240MW
Data Source: * Netz-Transparenz ** ENTSO-E h-values
Transmission System Operation Amprion | 04 December 2014 | © Amprion
approx. 0,4% of load covered by renewables
more than 65.000 MW conventional generation and Import!
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Sum Wind+PV*
Load Germany**
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Summe Wind+PV*
Last Deutschland**
Wind and Solar Infeed vs. Load in Germany
Time: Sunday, 11 May 2014 (day with highest share of renewable energy covering load)
40
h-values
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Data Source: * Netz-Transparenz ** ENTSO-E
11 May 2014, 14:00 h
Load approx. 53.200MW
Wind+PV-Infeed approx. 36.600MW
MW
approx. 69% of load covered by renewables
approx. 17.000 MW conventional generation and Import!
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Sum Wind+PV*
Load Germany**
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Summe Wind+PV*
Last Deutschland**
Wind and Solar Infeed vs. Load in Germany
Time: Saturday, 12 April 2014 (day with lowest renewable infeed)
41
h-values
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Data Source: * Netz-Transparenz ** ENTSO-E
12 April 2014 , 06:00 h
Load approx. 46.819MW
Wind+PV-Infeed approx. 180MW
MW
approx. 0,4% of load covered by renewables
more than 46.500 MW conventional generation and Import!
So
urc
e :
Am
pri
on
Gm
bH
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Sum Wind+PV*
Load Germany**
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Summe Wind+PV*
Last Deutschland**
Wind and Solar Infeed vs. Load in Germany
Time: Monday, 14 April 2014 (day with highest renewable infeed)
42
h-values
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Data Source: * Netz-Transparenz ** ENTSO-E
14 April 2014 , 15:00 h
Load approx. 70.600MW
Wind+PV-Infeed approx. 37.600MW
MW
approx. 53% of load covered by renewables
approx. 33.000 MW conventional generation and Import!
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV*
Wind*
Sum Wind+PV*
Load Germany**
So
urc
e :
Am
pri
on
Gm
bH
0,0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1,0
0 1000 2000 3000 4000 5000 6000 7000 8000
Duration curve of load covering with
Wind und PV in 2012
43
So
urc
e :
Am
pri
on
Gm
bH
PRES
PLoad,D
Hours
Transmission System Operation Amprion | 04 December 2014 | © Amprion
0,0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1,0
0 1000 2000 3000 4000 5000 6000 7000 8000
Duration curve of load covering with
Wind und PV in 2013
44
Hours
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e :
Am
pri
on
Gm
bH
PRES
PLoad,D
-200
-160
-120
-80
-40
0
40
80
120
160
200
-25.000
-20.000
-15.000
-10.000
-5.000
0
5.000
10.000
15.000
20.000
25.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV D
Trafo1
Trafo 2
45
Power flow (h-values) h
Influence of Dispersed Generation on the TSO (Low infeed in PV)
MW MW
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
DS
O
TS
O
TS
O
DS
O
-200
-160
-120
-80
-40
0
40
80
120
160
200
-25.000
-20.000
-15.000
-10.000
-5.000
0
5.000
10.000
15.000
20.000
25.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PV D
Trafo1
Trafo 2
46
MW
h
MW
Power flow (h-values)
Influence of Dispersed Generation on the TSO (High infeed in PV)
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
DS
O
TS
O
TS
O
DS
O
-200
-150
-100
-50
0
50
100
150
0 5.000 10.000 15.000 20.000 25.000
PV-Generation ↔ Reverse Flow on Transformer
400/110 KV (measurement values Amprion)
47
Trend
PV Generation Germany [MW]
MW
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
DS
O
TS
O
TS
O
DS
O
-12.000
-10.000
-8.000
-6.000
-4.000
-2.000
0
2.000
4.000
6.000
8.000
10.000
12.000
0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 40.000
Correlation Wind+PV Energy Production ↔ Control Program DE (h-values 2013)
P
MW
PDE
Trend
+ E
xp
ort
-
Imp
ort
Transmission System Operation Amprion | 04 December 2014 | © Amprion 48
So
urc
e:
Am
pri
on
Gm
bH
Peak Load vs. Capacity of all German pump
storage power plants
49
JAN FEB MAR JUN MAY APR NOV OCT SEP AUG JUL DEC
Lo
ad
in
GW
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
Could pump storage power
plants solve the problem? Capacity of all German
pump storage power plants
Peak load: 85,4 GW
Pump storage capacity: 6,4 GW
Annual consumption: 536,8 TWh
Storage capacity: 0,037 TWh Source: NEP 2013
Transmission System Operation Amprion | 04 December 2014 | © Amprion 50
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
-100
-80
-60
-40
-20
0
20
40
60
-50
-40
-30
-20
-10
0
10
20
30
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Wind D
PV D
Spot-Price Day Ahead
Hourly average Intraday
RES-Infeed and impacts on thermal generation
(1/2)
51
GW €/MWh
Sunday, 16.06.2013
Hour
- 6,3 GW
Transmission System Operation Amprion | 04 December 2014 | © Amprion
So
urc
e:
Am
pri
on
Gm
bH
, E
PE
X S
po
t
+ 4,6 GW
52
So
urc
e:
Am
pri
on
Gm
bH
, E
PE
X S
po
t
-100
-80
-60
-40
-20
0
20
40
60
-50
-40
-30
-20
-10
0
10
20
30
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
conv. Generation
Import
Spot-Price Day Ahead
Hourly average Intraday
GW €/MWh
Sunday, 16.06.2013
Hour
+ 3,9 GW ≈ 17%
Transmission System Operation Amprion | 04 December 2014 | © Amprion
RES-Infeed and impacts on thermal generation
(2/2)
-250
-200
-150
-100
-50
0
50
100
150
200
250
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Transmission System Operation Amprion | 04 December 2014 | © Amprion 53
P ______
Pinstall %
EPEX
Spot (DE,AT)
€/MWh
Trend
Correlation Wind+PV Energy Production ↔ Day-ahead PX h-values since 2011
So
urc
e:
Am
pri
on
Gm
bH
-250
-200
-150
-100
-50
0
50
100
150
200
250
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
Einspeisung Wind und PV
Spot-Preis
Trendlinie Einspeisung Wind und PV
Trendinie Spot-Preis
Spot-Price Day Ahead vs. RES Generation since 2011
54
High Renewable
generation
negative
Spot-Prices:
up to -240€/MWh
Christmas 2012
Spot-Price Day Ahead
Renewable generation
Trend Spot-Price Day Ahead
Trend Renewable generation
Transmission System Operation Amprion | 04 December 2014 | © Amprion
MW €/MWh
So
urc
e:
Am
pri
on
Gm
bH
RES push conventional power plants out of the market
Increasing share of renewables
(Germany: approx. 37 GW PV and
35 GW Wind installed)
conventional power plants become
unviable because of low prices
Steadily decreasing time of
operation of conventional power
plants
just minor peak loads, thereby
exposure of the profitability of
energy storage
The shutdown of thermal generation capacity in the grid
endanger system stability!
55 Transmission System Operation Amprion | 04 December 2014 | © Amprion
Transmission System Operation Amprion | 04 December 2014 | © Amprion 56
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
In case of (n-1)- security violations in the EHV-grid due to high dispersed generation TSO and DSO
collaborate to lower the infeed of renewable generation in DSOs grid. TSO initiates and DSOs operate
these measures according following cascade:
Cooperation of TSO and DSO:
Cascade in Generation Dispatching of Renewables
57
So
urc
e:
BD
EW
Transmission grid TSO
Generation Load Grid area
Distribution grid 1. Level DSO DSO
Distribution grid 2. Level DSO DSO
Distribution grid n. Level DSO DSO
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Prevent incorrect voltage augmentation caused by decentralized generation
Coordination of a large amount of small generation utilities without an adequate
communication network
Handling reversed load flows
*GL: Grid Level
Challenges for DSOs
58 Transmission System Operation Amprion | 04 December 2014 | © Amprion
TSO Extra-high
Voltage 220 / 380 kV GL* 1
DSO
High Voltage 110 kV GL 2
Regional
Distributors
Medium
Voltage 20 kV
GL 3
GL 4
Low Voltage 400V
(230 V)
GL 5
GL n
Operator Grid level of Energy system
Number of
generation units
Level
of automation
• TSO monitoring the overall
system
• Responsibility for SoS*
• Operative contact to DSOs /
generators on TSO-Level
• Requests support by the DSOs TSO
59 Transmission System Operation Amprion | 04 December 2014 | © Amprion
Responsibilities within the cascade
DSO
• Monitoring
own system
• Operative contact to
generators on DSO-Level
• Support of TSO to operate the
cascade
Cascade
• Support of TSO / DSO to SoS
through decreasing /
increasing the power of
generation units
Generation
facilities
• Support of industrial
customers to SoS
through decreasing /
increasing load
• End user can be
disconnected
Consumers
*SoS = Security of Supply
Transmission System Operation Amprion | 04 December 2014 | © Amprion 60
Agenda
Germany’s Energiewende - Framework
Transmission System Operation
Major Challenge: Transition of the Electricity System due RES
Impacts of RES on Conventional Generation and the Market
Cooperation of TSO and DSO: Cascade in Generation Dispatching
Outlook and Conclusion
61
What is now the influence of
wind and pv generation
and
power trading
on the grid ?
Huge Load Flows
Transmission System Operation Amprion | 04 December 2014 | © Amprion
Connection of wind farms in the north
to a powerful, regional east-west-grid
wind-busbar
Integration of solar energy in the
south by the use of regional grid
reinforcement
solar-busbar
Connection of the buspars via HVDC-
lines
Depending on the existing situation
north-, central- or south Germany can
be supplied with power from
renewable energy sources
X X
X
What are the key elements of
the German grid expansion?
62
Source: Amprion
Transmission System Operation Amprion | 04 December 2014 | © Amprion
63
German Grid Development Plan (NEP)
Optimizing of the existing corridors:
AC- expansion: 2.800 km
AC- reinforcement and
additional lines: 1.300 km
DC- lines: 1.300 km
Grid expansion
New AC- lines: 1.700 km
4 DC-corridors:
Transmission capacity: 10 GW
New DC- lines: 2.100 km
Investments: approx. 20 billion €
Transmission System Operation Amprion | 04 December 2014 | © Amprion
about 20 Billion €
invest one time
Conclusion
64
The current Challenges for Transmission System Operators are:
Stimulation of the European Electricity Market Integration
Integration of Renewable Energy Sources (Wind and Solar Power)
Changes in Generation Patterns (Shutdown of Nuclear PPs and Conventional PPs)
Congestion Management and Management of Critical Grid Situations
The current and future Challenges for Thermal Power Plants are:
Permanently decreasing load utilization due to high priority infeed of RES
Flexibility needs and growing load gradients
Reliable and flexible thermal generation capacity is essential for security of supply
and stability of the transmission grid
Transmission System Operation Amprion | 04 December 2014 | © Amprion
The „Energiewende“ consists of many components –
To achieve this goal all parties need to work together
Thank you for your attention.