Top Banner

of 86

Geotechnical Report

Oct 07, 2015

Download

Documents

mamandawe

Geotechnical Report
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

  • File No.494-64 Page 2 March 24, 2007 10,000 Santa Monica Blvd.

    EXECUTIVE SUMMARY

    An evaluation of the proposed construction of a multi-story condominium building over several levels of subterranean parking was performed by this office. The evaluation consisted of historical aerial photographic research, review of geotechnical reports for surrounding buildings, an extensive subsurface investigation including laboratory testing, geologic analysis of seismic hazards, and soil engineering analysis of potential settlement and liquefaction effects on the proposed building. Based on our findings the site is free from hazards associated with landsliding, slippage, soil erosion, subsidence, and liquefaction. The Design Basis Earthquake and estimated peak ground acceleration for the site are average and will not necessitate unusual structural design. Affects from typical settlement or seismic hazards can be mitigated with standard foundation design. There are no known active faults located close to the property. Heavy seepage was encountered at depths between 35 and 50 feet (227 to 216 elevation) below the ground surface and is likely representative of groundwater. The shallowest seepage (closest to the ground surface) was encountered along the south side of the site. If the below grade portion of the building is proposed deeper than the current groundwater level then permanent dewatering of the site or a special foundation and slab design will be required. Based on the geometry of the surrounding building foundations and the depth of the groundwater there will be no detrimental affect to adjacent structures during permanent or temporary dewatering (if it is needed). Although dependant upon the final building design, preliminary analysis indicates that the new condominium building will be founded on a conventional mat foundation.

  • File No.494-64 Page 3 March 24, 2007 10,000 Santa Monica Blvd. 1.0 INTRODUCTION 1.1 PURPOSE The purpose of this investigation was to evaluate the existing geotechnical conditions at the subject site and to provide design and construction criteria for the construction of a multi-story condominium tower of approximately forty stories in height with approximately four subterranean levels of parking. 1.2 SCOPE OF SERVICES

    The scope of work performed during this investigation involved the following; Research and review of available pertinent geotechnical literature; Subsurface exploration consisting of the excavation of four borings (B1, B2, B3, B4) and advancing four CPT (CPT1, CPT2, CPT3, CPT4); Sampling and logging of the subsurface soils; Laboratory testing of selected soil samples collected from the subsurface exploration to determine the engineering properties of the soil; Engineering and geologic analysis of the field and laboratory data; and Preparation of this report presenting our findings, conclusions and recommendations for the proposed construction. 1.3 SITE DESCRIPTION The project site is located in the City of Los Angeles just north of Beverly Hills High School at the southwest corner of Moreno Drive and Santa Monica Boulevard (Figure 1). An aerial photograph is included as Figure 2 and a topographic map is included as Figure 3. Figure 3 also shows the locations of a storm drain line and a sewer line easement located along the east side of the property. The site is currently vacant following demolition of the previous office building. Santa Monica Boulevard descends gently to the east and Moreno Drive descends to the south. From the northwest corner to the southeast corner of the property the site elevation varies by 15 feet. 1.4 PROPOSED CONSTRUCTION

    It is our understanding that conceptually, site development will consist of construction that may include approximately four subterranean levels of parking and a condominium tower of approximately forty stories in height.

  • File No.494-64 Page 4 March 24, 2007 10,000 Santa Monica Blvd.

    Figure 1. Location map of the site.

  • File No.494-64 Page 5 March 24, 2007 10,000 Santa Monica Blvd.

    Figure 2. Aerial Photograph of subject lot and surrounding area.

  • File No.494-64 Page 6 March 24, 2007 10,000 Santa Monica Blvd.

    Figure 3. Topographic map of the subject site and surrounding area. The red star is located on the subject property. The location of the storm drain is shown by the blue line and the sewer line easement is shown by the red hachured area.

  • File No.494-64 Page 7 March 24, 2007 10,000 Santa Monica Blvd. Previous Reports Research at the Los Angeles City Building and Safety Department yielded geological and soil reports for several of the surrounding high-rise developments and for the subject property. The reports for the surrounding properties indicated that the natural alluvium is relatively uniform, dense, and can support high structural loads. None of the boring logs that were reviewed and none of the reports indicated that there were any environmental concerns in the area. The reports for the surrounding buildings indicate that they are all founded on conventional foundations consisting of spread footings, driven piles, or cast-in-place caissons. The original soil and geology report prepared by Leroy Crandall and Associates for the subject property in 1958 was obtained. The report stated that old, dense, alluvium underlies the majority of the subject site except for the eastern side along Moreno Drive where 15 feet of loose fill was found. The old fill contained trash and oil saturated sand. The report stated that the older fill would be partially removed during excavation for a basement and recommended that the remaining fill be removed and new fill compacted during development. Conventional spread footings were recommended for the building foundation and caissons were used under the perimeter, property-line block wall. In 1960, a report was issued for the foundation of a proposed 14-story tower that was to be constructed along the north side of the property. Because the construction of the office building was already underway and grading for the tower foundation was not possible, cast-in-place caissons up to 48 feet in depth were reportedly going to be installed. However, the towers were never constructed and the pile clusters that were proposed were never constructed and were not found during the recent site demolition. A methane report included within the due diligence documents stated that groundwater was encountered 5 feet below the bottom of a probe drilled to 45 feet (no logs of the drilling were provided within the report); a call to the principal engineer for the project verified that groundwater was encountered at 50 feet below the ground surface. Site Demolition A site visit was conducted on May 26th, 2006. Discussion with the demolition contractor, Holcomb Engineering Contractors, Inc., revealed that no unusual subsurface conditions were encountered. Mr. Holcomb stated that the 14-story towers were never constructed and he has searched for but has not found any pile clusters.

  • File No.494-64 Page 8 March 24, 2007 10,000 Santa Monica Blvd. 2.0 INVESTIGATION

    2.1 GENERAL

    Our field investigation was performed on January 18-20, 2007, and consisted of a review of site conditions and exploration involving excavation of four borings; advancing four CPT soundings and soil sampling. Our investigation also included laboratory testing of selected soil samples. A brief summary of these various tasks are provided below. 2.2 FIELD EXPLORATION The subsurface investigation performed at the site consisted of excavating four borings by use of a hollow-stem auger drill rig and four electronic piezocone soundings (CPT). The purpose of the borings and CPT soundings was to determine the existing subsurface conditions and to collect subsurface soil in the areas of the proposed construction and throughout the site. The borings were excavated to a maximum depth of 100.5 below the existing ground surface. The CPTs were pushed to a maximum depth of 100.21 below the existing ground surface. The soil materials encountered in Borings 1-4 consisted of fill over Older Alluvium. A review of geological maps1,2 indicates that the material underlying the subject site is comprised of Alluvium of Quaternary age (Figure 4). The borings were logged by our field geologist using both visual and tactile means. Both bulk and relatively undisturbed soil samples were obtained. The approximate locations of the borings are shown on the attached site plan included in Appendix A. Detailed boring and CPT logs are presented in Appendix B. 2.3 LABORATORY TESTING Laboratory testing was performed on representative samples obtained during our field exploration. Samples were tested for the purpose of estimating material properties for use in subsequent engineering evaluations. Testing included in-place moisture and density, maximum density, optimum moisture content, hydro-response-swell/collapse, and shear strength testing. A summary of the laboratory test results is included in Appendix C. The physical properties of the soils were tested at Soil Labworks, LLC. The undersigned geologist and engineer have reviewed the data and concur and accept it.

    1 Dibblee, Thomas, 1991, Geologic Map of the Beverly Hills and Van Nuys (south ) Quadrangles, Los Angeles County, California Map #DF-31. 2Hoots, H.W., 1931, Geology of the eastern part of the Santa Monica Mountains, Los Angeles County, California: United States Geological Survey Professional Paper 165-C.

  • File No.494-64 Page 9 March 24, 2007 10,000 Santa Monica Blvd.

    Figure 4. Portion of Dibblee Geologic Map. Site is designated by a red star.

  • File No.494-64 Page 10 March 24, 2007 10,000 Santa Monica Blvd. 3.0 SITE GEOLOGY, SEISMICITY, POTENTIAL HAZARDS 3.1 SITE GEOLOGY Regional geologic maps and the subsurface exploration indicated that the property is underlain by Quaternary Age Older Alluvium (Figure 4) overlain by variable amounts of fill. Descriptions of the materials encountered in our exploratory borings are described below. 3.2.1 Fill The fill consists of fine to coarse grained silty and gravelly sand with minor amounts of clay. The color varies from light brown to brown. The fill is medium dense, moist and contains occasional construction spoils. The fill on site varied from between 2 to about 6 feet with the exception of boring four where it was found down to a depth of about thirteen feet; this is consistent with the findings of the previous site investigation reports. 3.2.2 Quaternary Alluvium The alluvium consists of admixtures of gravel, sands, silts and clays which vary from light to dark brown, gray, greenish-gray, orange-brown. The alluvium was moist to saturated, medium dense to dense, firm to stiff, containing caliche and mica. The alluvium is generally weakly horizontally layered with no significant structural planes. 3.2.3 Groundwater Groundwater was encountered during the recent excavations and soundings at depths ranging from 35 to 50 feet below the ground surface. Historically, the highest groundwater in this area of Los Angeles is estimated to be about 25 feet below the ground surface Figure 5 (Plate 1.2, Historically Highest Groundwater Contours and Borehole Log Data Locations, Beverly Hills 7 Minute Quadrangle in Seismic Hazard Zone Report for the Burbank Quadrangle, SHZR-023).

    Feffer Boring Designation

    Elevation of Boring

    Depth to Groundwater

    Groundwater Elevation

    B-1 272 50 222 B-2 261 45 216 B-3 262 35 227 B-4 261 35 226

    A monitoring well/piezometer has been installed within Boring 4 so that groundwater levels can be monitored over time. A measurement taken on February 27, 2007 indicated that groundwater was 35 below the surface level at B-4.

  • File No.494-64 Page 11 March 24, 2007 10,000 Santa Monica Blvd.

  • File No.494-64 Page 12 March 24, 2007 10,000 Santa Monica Blvd. 3.3 SEISMICITY A risk common to all areas of Southern California that should not be overlooked is the potential for damage resulting from seismic events (earthquakes). The site is located within a seismically active area, as is all of Southern California. Although we are not aware of any active faults on or within the immediate vicinity of the site, earthquakes generated on large regional faults such as the San Andreas and Santa Monica-Hollywood, Verdugo, Newport Inglewood and Raymond Faults could affect the site. The closest known potentially active faults to the site are the east-west trending Santa Monica-Hollywood, Newport Inglewood, Verdugo and Raymond Faults. The Santa Monica Fault is located within two kilometers of the site. Since no active faults cross the property, the surface rupture hazard at the site is very low. Due to the distance from the coastline the site is not susceptible to the effects of tsunamis and seiches. Figure 3.3 of the Seismic Hazard Zone Report for the Beverly Hills Quadrangle contains ground motion values assigned by the California Geological Survey (CGS) for this area of Los Angeles. The Design Basis Earthquake (10% Exceedance in 50 years) for the study area is peak ground acceleration (PGA) of about 0.50g. The de-aggregated predominant earthquake magnitude (Mw) is 6.5. These values are average and will not necessitate unusual structural design. Groundwater maps within the referenced report indicate that historical groundwater is deeper than 25 feet.

    Liquefaction Liquefaction is a process that occurs when saturated sediments are subjected to repeated strain reversals during an earthquake. The strain reversals cause increased pore water pressure such that the internal pore pressure approaches the overburden pressure and the shear strength approaches zero. Liquefied soils may be subject to flow or excessive strain, which can cause settlement. Liquefaction occurs in soils below the groundwater table. Soils commonly subject to liquefaction include loose to medium dense sand and silty sand that are normally consolidated and Holocene in age. Predominantly fine-grained soils, such as silts and clay, are less susceptible to liquefaction. Generally, soils with a clay content of greater than 15 percent and/or a fines content (percent passing the 200 sieve) greater than 30 percent, are not considered subject to liquefaction. The subject property is not included within a State of California Seismic Hazard Zone for earthquake liquefaction or seismic ground deformation. This investigation has determined the clay content of the soils too high for liquefaction. Therefore, the liquefaction potential of the site is low. Similarly, hazards associated with liquefaction, such as lateral spreading, ground failure and dynamic settlement are considered low to nil. Mitigation of the liquefaction hazards are not indicated for the site.

  • File No.494-64 Page 13 March 24, 2007 10,000 Santa Monica Blvd. 4.0 GEOTECHNICAL CONSIDERATIONS

    4.1 SUBSURFACE SOIL CONDITIONS

    Subsurface materials at the site consist of older alluvium below variable amounts of fill. On the subject property there was up to thirteen feet of fill over older alluvium. Laboratory testing indicates that the alluvium at a shallow depth has a moderate to high potential for consolidation and hydrocollapse. The older alluvium at the depth of the lowest level of the subterranean garage has a low potential for consolidation and hydrocollapse. The alluvium at the subject site is competent and not subject to liquefaction or earthquake induced ground deformation. The following paragraph provides general discussions about settlement and expansive soil activity. 4.2 SETTLEMENT Our investigation indicated that the consolidation and hydrocollapse potential of the older alluvium at the depth of the proposed subterranean garage is low. The dry densities and blow counts were high for the samples taken at depth and it is our experience that these soils have a very low potential for consolidation. Recommendations are presented below to mitigate the settlement hazard associated with consolidation of the near surface soils. 4.3 EXPANSIVE SOIL

    The on-site, near surface soil was found to possess low to moderate expansive characteristics based upon expansion index testing and field soil classifications.

  • File No.494-64 Page 14 March 24, 2007 10,000 Santa Monica Blvd. 5.0 CONCLUSIONS AND RECOMMENDATIONS 5.1 BASIS

    Conclusions and recommendations contained in this report are based upon information provided, information gathered, laboratory testing, engineering and geologic evaluations, experience, and judgment. Recommendations contained herein should be considered minimums consistent with industry practice. More rigorous criteria could be adopted if lower risk of future problems is desired. Where alternatives are presented, regardless of what approach is taken, some risk will remain, as is always the case.

    5.2 SITE SUITABILITY

    The site is within an area including completed housing and building developments. Geotechnical exploration, analyses, experience, and judgment result in the conclusion that the proposed development is suitable from a geotechnical standpoint.

    It is our opinion that the site can be improved without hazard of landslide, slippage, or settlement, and improvement can occur without similar adverse impact on adjoining properties. Realizing this expectation will require adherence to good construction practice, agency and code requirements, the recommendations in this report, and possible addendum recommendations made after plan review and at the time of construction. 5.3 SEISMIC DESIGN CONSIDERATION It is not known if the proposed structures are going to be designed using dynamic or static analyses. Feffer Geological has not performed a site-specific seismic ground motion study or produced seismic response spectra. The following recommendations may be used for static design. As discussed before, the nearest known potentially active seismic source are the Santa Monica-Hollywood, Newport Inglewood, Verdugo and Raymond Faults. These faults are Type B faults. The soil profile of the site is characterized as SD (stiff soil). The following seismic design parameters are recommended according to Chapter 16 of the 2002 Edition of the County of Los Angeles Building Code. Soil Profile Type : SD Seismic Zone Factor (z) : 0.4 Seismic Source Type : B Near-Source Factor, Na : 1.3 Near-Source Factor, Nv : 1.6 Seismic Coefficient, Ca : 0.44Na Seismic Coefficient, Cv : 0.64Nv

    TomRectangle

    TomRectangle

  • File No.494-64 Page 15 March 24, 2007 10,000 Santa Monica Blvd.

    It should be realized that the purpose of the seismic design utilizing the above parameters is to safeguard against major structural failures and loss of life, but not to prevent damage altogether. Even if the structural engineer provides designs in accordance with the applicable codes for seismic design, the possibility of damage cannot be ruled out if moderate to strong shaking occurs as a result of a large earthquake. This is the case for essentially all structures in Southern California.

    5.4 EARTHWORK 5.4.1 General Demolition of the previous structures disturbed the upper five to fifteen feet of existing fill and

    alluvium; all foundations should be founded on firm undisturbed older alluvium. Remedial grading is not anticipated for subterranean levels that penetrate the existing disturbed earth materials and are founded in competent older alluvium. Portions of the proposed floor slabs and structures that penetrate the surficial materials may be founded on firm undisturbed older alluvium. Where a compacted fill cap is used it should extend at least two feet below the building slabs. If it is anticipated that the proposed construction may require grading of the site, it should be done in accordance with good construction practice, minimum code requirements and recommendations to follow. Grading criteria are included within Appendix E.

    5.4.2 Site Preparation and Grading Based on our understanding of the proposed development, we recommend that footings be founded

    in firm older alluvium. Prior to the start of grading operations, utility lines within the project area, if any, should be located and marked in the field so they can be rerouted or protected during site development. All debris and perishable material should be removed from the site. No permanent cut and fill slopes should be constructed steeper than a 2:1 gradient.

    If fill is to be placed the upper six to eight inches of surface exposed by the excavation should be scarified; moisture conditioned to two to four percent over optimum moisture content, and compacted to 95 percent relative compaction3. If localized areas of relatively loose soils prevent proper compaction, over-excavation and re-compaction will be necessary.

    3 Relative compaction refers to the ratio of the in-place dry density of soil to the maximum dry density of the same material as obtained by the "modified proctor" (ASTM D1557) test procedure.

  • File No.494-64 Page 16 March 24, 2007 10,000 Santa Monica Blvd. 5.5.1 New Structures All proposed footings shall be embedded within approved firm older alluvium, in accordance with the recommendations below. Formal design parameters, such as the anticipated structural loads and the depth of the basement have not been provided. Foundations loads are anticipated to be very high. The following design parameters assume that the lower subterranean level will extend 40 feet below existing grade. Based on the anticipation of high structural loads conventional column foundations and slabs are not feasible and a mat foundation is likely. Based upon the recently measured groundwater levels of 35 to 50 feet below grade, and the historically highest groundwater reported for the site of 25 feet, either permanent dewatering or a hydrostatic design will be required. Since it is not likely tenable to permanently pump groundwater to maintain the static level below the elevation of the deepest foundation and slab, a hydrostatic design is appropriate.

    Mat Foundations

    A mat foundation may be used to distribute concentrated loads to the bearing soils to mitigate differential settlement. The thickness of the mat should be determined by the structural engineer. For capacity of the mat, a net dead-plus-live load pressure of 6,000 pounds per square foot may be assumed for the native alluvium at the basement level. A increase may be used for wind or seismic loads. For bearing calculations, the weight of the concrete in the footing may be neglected.

    A coefficient of subgrade reaction of 335 kips per cubic foot may be used for the mat to compute deflections. The recommended subgrade modulus has already been factored to reflect the anticipated size.

  • File No.494-64 Page 17 March 24, 2007 10,000 Santa Monica Blvd. 5.6 RETAINING WALL AND SHORING

    Retaining Wall

    Cantilevered retaining walls up to 20 feet high that support older alluvium and approved retaining wall backfill, may be designed for an equivalent fluid pressure of 45 pounds per cubic foot (calculations included within Appendix D). Restrained basement walls that are pinned at the top by a non-yielding floor should be designed for a trapezoidal distribution of pressure. The design earth pressure on restrained basement wall is 30H psf, where H is the height of the basement wall in feet. Retaining walls should be provided with a subdrain or weepholes covered with a minimum of 12 inches of inch crushed gravel.

    28H Basement retaining walls surcharged by existing foundations or vehicular traffic should be designed to withstand the surcharge. Feffer Geologic would be happy to assist the structural engineer in evaluating the magnitude of the surcharge pressure and the point of application.

    Backfill

    Retaining wall backfill should be compacted to a minimum of 90 percent of the maximum density as determined by ASTM D 1557-02. Where access between the retaining wall and the temporary excavation prevents the use of compaction equipment, retaining walls should be backfilled with inch crushed gravel to within 2 feet of the ground surface. Where the area between the wall and the excavation exceeds 18 inches, the gravel must be vibrated or wheel-rolled, and tested for compaction. The upper 2 feet of backfill above the gravel should consist of a compacted fill blanket to the surface. Retaining wall backfill should be capped with a paved surface drain or a concrete slab.

    It should be pointed out that the use of heavy compaction equipment in close proximity to retaining walls can result in excess wall movement and/or soil loadings exceeding design values. In this regard, care should be taken during backfilling operations.

  • File No.494-64 Page 18 March 24, 2007 10,000 Santa Monica Blvd. Waterproofing Where retaining walls form portions of the building interiors, very special consideration should be given to waterproofing the walls to prevent damage to the building interior. Unless dampness is acceptable on exterior wall faces, waterproofing should also be incorporated into the exterior retaining wall design. Although the project architect is the party who should provide actual waterproofing details, it is suggested the waterproofing consist of a multi-layered system such as an initial generously applied layer of hot-mopped asphalt over which a layer of construction felt could be applied, then thoroughly mopped again with hot asphalt. In the case of all retaining walls, it is suggested that a layer of 10-mil Visqueen be placed as a finish layer. The multi-layered system should be covered with protective foam board, or similar, to prevent damage during the backfilling operation.

    Extreme care should be exercised in sealing walls against water and water vapor migration. Where retaining walls are planned against interior space, continuity should be provided between the aforementioned wall moisture-proofing on the back of the retaining wall and the moisture barrier typically placed under slab areas. This waterproofing is necessary to prevent the foundation concrete from acting as a wick through which moisture migrates to the interior space despite wall moisture proofing. As aforementioned, the architect or structural engineer should develop the actual waterproofing details. 5.6.2 TEMPORARY EXCAVATIONS

    Temporary excavations will be required to construct the proposed subterranean levels. The excavations could be up to 50 feet in height and will expose scattered fill over Older Alluvium. Where not surcharged by existing footings or structures, the Older Alluvium is capable of maintaining vertical excavations up to 5 feet. Where vertical excavations in the Older Alluvium exceed 5 feet in height, the upper portion should be trimmed to 1:1 (45 degrees). Vertical excavations removing lateral or vertical support from existing structures or the public right-of-way will require the use of temporary shoring. Any excavation that encroaches within a 1:1 plane projected downward from the edge of the footing is considered to remove lateral support from the footing.

    Shoring

    Shoring may consist of drilled, cast-in-place concrete piles with wood lagging. Shoring piles should be a minimum of 24 inches in diameter and a minimum of 8 feet into native soils below the base of the excavation. Piles may be assumed fixed at 3 feet below the base of the excavation. The concrete placed in the soldier pile excavations may be a lean-mix concrete. However, the concrete used in that portion of the soldier pile, which is below the planned excavated level, should be of sufficient strength to adequately transfer the imposed loads to the surrounding soils.

    Cantilevered shoring up to a height of 20 feet may be designed for an equivalent fluid pressure of 35 pcf. The recommended design pressure on shoring in excess of 20 feet is 40 pcf. For the vertical forces, piles may be designed for a skin friction of 200 pounds per square foot for that portion of pile

  • File No.494-64 Page 19 March 24, 2007 10,000 Santa Monica Blvd. in contact with the soil. Soldier piles should be spaced a maximum of 8 feet on center. Due to arching on the soils, the design fluid pressure should be multiplied by the pile spacing.

    Shoring that is restrained by tie-back anchors, rakers or struts should be designed for a trapezoidal distribution of soil pressure. The design earth pressure on restrained shoring wall is 22H psf, where H is the height of the shored excavation wall in feet. The recommended soil pressures do not include surcharge pressures from traffic or existing structures. The shoring engineer should add appropriate surcharge pressures to account for existing structures, property line retaining walls and vehicular traffic. Feffer Geological can assist the shoring engineer in determining the surcharge pressure and the point of application.

    Lateral Design of Shoring

    The friction value is for the total of dead and frequently applied live loads and may be increased by one third for short duration loading, which includes the effects of wind or seismic forces. Resistance to lateral loading may be provided by passive earth pressure within the Older Alluvium below the base of the excavation.

    Passive earth pressure may be computed as an equivalent fluid having a density of 300 pounds per cubic foot. The maximum allowable earth pressure is 6,000 pounds per square foot. For design of isolated piles, the allowable passive and maximum earth pressures may be increased by 100 percent. Piles spaced more than 2 pile diameters on center may be considered isolated.

    Lagging Lagging is required between shoring piles. The lagging should be designed for a maximum pressure of 400 pounds per square foot.

    Earth Anchors

    Earth anchors (tie backs) may be employed to assist the shoring system. Pressure grouted friction anchors are recommended. For design purposes, it is assumed that the active wedge adjacent to the shoring is defined by a plane drawn at 30 degrees with the vertical through the bottom excavation. Friction anchors should extend at least 20 feet beyond the potential active wedge, or to a greater length if necessary to develop the desired capacities. The capacities of the anchors should be determined by testing of the initial anchors as outlined in a following section.

    For shallow conventional, straight-shaft friction anchors (less than 15 feet of over-burden) the estimated skin friction is 300 pounds per square foot. Deeper anchors will develop an average value of 550 to 750 pounds per square foot. Post-grouted anchors are expected to achieve capacities of 3 to 8 kips/ft, depending on the depth. Only the frictional resistance developed beyond the active wedge would be effective in resisting lateral loads. If the anchors are spaced at least six feet on center, no reduction in the capacity of the anchors need be considered due to group action.

    The anchors may be installed at angles of 20 to 40 degrees below the horizontal. Caving and sloughing of the anchor hole should be anticipated and provisions made to minimize such caving and

  • File No.494-64 Page 20 March 24, 2007 10,000 Santa Monica Blvd. sloughing. To minimize chances of caving and sloughing, that portion of the anchor shaft within the active wedge should be backfilled with sand before testing the anchor. This portion of the shaft should be filled tightly and flush with the face of the excavation. The sand backfill should be placed by pumping; the sand may contain a small amount of cement to facilitate pumping.

    The frictional resistance between the soldier piles and the retained earth may be used in resisting a portion of the downward component of the anchor load. The coefficient of friction between the soldier piles and the retained earth may be taken as 0.25. (This value is based on the assumption that uniform full bearing will be developed between the steel soldier beam and the lean-mix concrete and between the lean-mix concrete and the retained earth). In addition, the soldier piles below the excavated level may be used to resist downward loads. The downward frictional resistance between the concrete soldier piles and the soils below the excavated level may be taken as equal to 200 pounds per square foot.

    The initial anchors should be performance tested to verify the design assumptions and capacities. The shoring engineer should specify a testing program that is acceptable to the geotechnical engineer. The following may be used as a guide. Three of the initial anchors should be scheduled for a 24-hour 200 percent test and 10 percent of the remaining anchors for quick 200 percent tests. The specific anchors selected for the 200 percent test should be representative and acceptable to the geotechnical engineer. The purpose of the 200 percent tests is to verify the friction value assumed in design and the bond length. Anchor rods of sufficient strength should be installed in these anchors to support the 200 percent test loading. Where satisfactory tests are not achieved on the initial anchors, the anchor diameter and/or length should be increased until satisfactory test results are obtained. The total deflection during the 24-hour 200 percent test should not exceed 12 inches. During the 24-hour test, the anchor deflection should not exceed 0.75 inches, measured after the 200 percent test load is applied. If the anchor movement after the 200 percent load has been applied for 12 hours is less than 0.5 inches, and the movement over the previous four hours has been less than 0.1 inches, the 24-hour test may be terminated.

    For the quick 200 percent tests, the 200 percent test load should be maintained for 30 minutes. The total deflection of the anchor during the 200 percent quick tests should not exceed 12 inches; the deflection after the 200 percent test load has been applied should not exceed 0.25 inch during the 30-minute period.

    All of the anchors should be proof tested to at least 150 percent of the design load. Total deflection during the test should not exceed 12 inches. The rate of creep under the 150 percent test should not exceed 0.1 inch over a 15-minute period for the anchor to be approved for the design loading.

    After a satisfactory test, each anchor should be locked-off at the design load. The locked-off load should be verified by rechecking the load in the anchor. If the locked-off load varies by more than 10 percent from the design load, the load should be reset until the anchor is locked-off within 10 percent of the design load.

    The installation of the anchors and the testing of the completed anchors should be observed by a representative of the geotechnical engineer.

  • File No.494-64 Page 21 March 24, 2007 10,000 Santa Monica Blvd. Deflection Monitoring

    Some deflection is expected for a well designed and constructed shoring system. Where offsite structures or the public right-of-way are located within 10 feet of the shored excavation, it is recommended that the deflection be limited to inch or less. Where offsite structures and the public right-of-way are located within more than 10 feet of the shored excavation, it is recommended that the deflection be limited to 1 inch or less.

    Prior to construction and excavation for the subterranean levels, it is recommended that the existing conditions along the property line be documented and surveyed. Documentation should include photographs and descriptions of the offsite structures and conditions. Survey monuments should be affixed to representative structures and to points along the property line and offsite. The survey points should be measured prior to construction to form a baseline for determining settlement or deformation. Upon installation of the soldier piles, survey monuments should be affixed to the tops of representative piles so that deflection can be measured.

    The shored excavation and offsite structures should be visually inspected every day. Survey monuments should be measured once a month during the construction process. Should the surveys reveal offsite deformation or excessive deflection of the shoring system, the shoring engineer and geotechnical engineer should be notified. Excessive deflection may require additional anchors, post-grouting and re-tensioning or internal bracing to restrain the shoring system. Excavation Characteristics

    The borings and CPT soundings did not encounter hard, cemented bedrock. Groundwater was encountered at depths of 35 to 50 feet and should be anticipated for drilled shafts and deep excavations. Drilled foundations and anchors below the groundwater level may be subject to caving and casing, drilling muds or special drilling techniques may be required. Water should be pumped from foundation excavations prior to placing concrete. As an alternative, water may be displaced from drilled foundation shafts by placing the concrete from the bottom up. The compressive strength of concrete placed below the water table should be increased by 1,000 psi over the design strength. A dewatering consultant should be retained to evaluate the feasibility of lowering the groundwater table to facilitate construction.

    5.7 EXTERIOR FLATWORK

    Whenever planned, the exterior flatwork should be placed over at least a two foot blanket of approved compacted fill. Five inch net sections with #4 bars at 18 inches o.c.e.w. are also advised. Control joints should be planned at not more than twelve foot spacing for larger concrete areas. Narrower areas of flatwork such as walkways should have control joints planned at not greater than 1.5 times the width of the walkway. Recommendations provided above for interior slabs can also be used for exterior flatwork, but without a sand layer or Visqueen moisture barrier. Additionally, it is also recommended that at least 12-inch deepened footings be constructed along the edges of larger concrete areas.

  • File No.494-64 Page 22 March 24, 2007 10,000 Santa Monica Blvd. Movement of slabs adjacent to structures can be mitigated by doweling slabs to perimeter footings. Doweling should consist of No. 4 bars bent around exterior footing reinforcement. Dowels should be extended at least two feet into planned exterior slabs. Doweling should be spaced consistent with the reinforcement schedule for the slab. With doweling, 3/8-inch minimum thickness expansion joint material should be provided. Where expansion joint material is provided, it should be held down about 3/8 inch below the surface. The expansion joints should be finished with a color matched, flowing, flexible sealer (e.g., pool deck compound) sanded to add mortar-like texture. As an option to doweling, an architectural separation could be provided between the main structures and abutting appurtenant improvements. 5.8 CONCRETE

    Based on our experience soils at the site have low levels of sulfates. As such, no special sulfate resistant cure mix design is required for the project. However, we recommend that the low permeable concrete be utilized at the site to limit moisture transmission through slab and foundation. For this purpose, the water/cement ratio to be used at the site should be limited to 0.5 (0.45 preferred). Limited use (subject to approval of mix designs) of a water reducing agent may be included to increase workability. The concrete should be properly cured to minimize risk of shrinkage cracking. The code dictates at least seven days of moist curing. Two to three weeks is preferred to minimize cracking. One-inch hard rock mixes should be provided. Pea gravel mixes are specifically not recommended but could be utilized for relatively non-critical improvements (e.g., flatwork) and other improvements provided the mix designs consider limiting shrinkage. Contractors/other designers should take care in all aspects of designing mixes, detailing, placing, finishing, and curing concrete. The mix designers and contractor are advised to consider all available steps to reduce cracking. The use of shrinkage compensating cement or fiber reinforcing should be considered. Mix designs proposed by the contractor should be considered subject to review by the project engineer.

    5.9 DRAINAGE

    Drainage should be directed away from structures via non-erodible conduits to suitable disposal areas. Two percent drainage is recommended directly away from structures. Two percent minimum is recommended for drainage over soil areas. In pipes or paved swales, one percent should be adopted as the minimum unless otherwise recommended by the project civil engineer. For area drains, a six inch minimum pipe diameter is recommended because experience has shown that three and four-inch pipes tend to clog. All enclosed planters should be provided with a suitably located drain or drains and/or flooding protection in the form of weep holes or similar. Preferably, structures should have roof gutters and downspouts tied directly to the area drainage system.

    5.10 PLAN REVIEW

    When detailed grading and structural plans are developed, they should be forwarded to this office for review and comment.

  • File No.494-64 Page 23 March 24, 2007 10,000 Santa Monica Blvd.

    5.11 AGENCY REVIEW All soil, geologic, and structural aspects of the proposed development are subject to the review and approval of the governing agency(s). It should be recognized that the governing agency(s) can dictate the manner in which the project proceeds. They could approve or deny any aspect of the proposed improvements and/or could dictate which foundation and grading options are acceptable.

    5.12 SUPPLEMENTAL CONSULTING

    During construction, a number of reviews by this office are recommended to verify site geotechnical conditions and conformance with the intentions of the recommendations for construction. Although not all possible geotechnical observation and testing services are required by the governing agencies, the more site reviews requested, the lower the risk of future site problems. The following site reviews are advised, some of which will probably be required by the agencies. Preconstruction/pregrading meeting ................................................ Advised Continuous observation and testing during any grading.................Required Shoring Observation .......................................................................Required Reinforcement for all foundations ................................................... Advised Slab subgrade moisture barrier membrane ...................................... Advised Slab subgrade rock placement ......................................................... Advised Presaturation checks for all slabs in primary structure areas..........Required Presaturation checks for all slabs for appurtenant structures........... Advised Slab steel placement, primary and appurtenant structures............... Advised Compaction of utility trench backfill ............................................... Advised

    Unless otherwise agreed to in writing, all supplemental consulting services will be provided on an as-needed, time-and-expense, fee schedule basis.

    5.13 PROJECT SAFETY The contractor is the party responsible for providing a safe site. This consultant will not direct the contractor's operations and cannot be responsible for the safety of personnel other than his own representatives on site. The contractor should notify the owner if he is aware of and/or anticipates unsafe conditions. If the geotechnical consultant at the time of construction considers conditions unsafe, the contractor, as well as the owner's representative, will be notified. Within this report the terminology safe or safely may have been utilized. The intent of such use is to imply low risk. Some risk will remain, however, as is always the case.

  • File No.494-64 Page 24 March 24, 2007 10,000 Santa Monica Blvd. 6.0 REMARKS Only a portion of subsurface conditions have been reviewed and evaluated. Conclusions, recommendations and other information contained in this report are based upon the assumptions that subsurface conditions do not vary appreciably between and adjacent to observation points. Although no significant variation is anticipated, it must be recognized that variations can occur. This report has been prepared for the sole use and benefit of our client. The intent of the report is to advise our client on geotechnical matters involving the proposed improvements. It should be understood that the geotechnical consulting provided and the contents of this report are not perfect. Any errors or omissions noted by any party reviewing this report, and/or any other geotechnical aspect of the project, should be reported to this office in a timely fashion. The client is the only party intended by this office to directly receive the advice. Subsequent use of this report can only be authorized by the client. Any transferring of information or other directed use by the client should be considered "advice by the client." Geotechnical engineering is characterized by uncertainty. Geotechnical engineering is often described as an inexact science or art. Conclusions and recommendations presented herein are partly based upon the evaluations of technical information gathered, partly on experience, and partly on professional judgment. The conclusions and recommendations presented should be considered "advice." Other consultants could arrive at different conclusions and recommendations. Typically, "minimum" recommendations have been presented. Although some risk will always remain, lower risk of future problems would usually result if more restrictive criteria were adopted. Final decisions on matters presented are the responsibility of the client and/or the governing agencies. No warranties in any respect are made as to the performance of the project.

  • File No.494-64 Page 25 March 24, 2007 10,000 Santa Monica Blvd. REFERENCES

    1. Blake, T., 2000, EQFault, Version 3.00b, Program for Deterministic Estimation of Peak Acceleration from Digitized Faults.

    2. Blake, T., 2000, EQSearch, Version 3.00b, Program for Estimation of Peak Acceleration from California Earthquake Catalogs.

    3. Blake, T., 2000, UBCSEIS, Version 1.03, Program for Computation of 1997 Uniform Building Code Seismic Design Parameters.

    4. Jennings, C.W., 1994, Fault Activity Map of California and Adjacent Areas, Scale 1:750,000, California Division of Mines and Geology, California Geologic Map Data Series.

    5. State of California, Seismic Hazard Zone Mapping, 1998, Beverly Hills Quadrangle.

  • APPENDIX A

    Site Plan

  • LARGE GRAVEL PILE

    CPT-1

    B-1

    B-2

    CPT-2

    B-3CPT-3

    B-4

    CPT-4

    JB: NAME: BY:

    DATE: SCALE: SITE:

    REF:

    SITE PLAN

    494-64 SUNCAL CO. YH

    3/24/07 1=3010000 SANTA

    MONICA BLVD

    BASE MAP FROM S.E.C. CIVIL ENGINEERS SURVEY

    LEGEND

    B-4 LOCATION OF BORING

    CPT-4 LOCATION OF CPT

    FILL OVER OLDER ALLUVIUM

    PROPOSED FORTY-STORY BUILDING OVER

    FOUR LEVELS OF SUBTERRANEAN PARKING

    TomRectangle

    TomRectangle

    TomRectangle

  • APPENDIX B

    Boring Logs &

    CPT Logs

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    5

    10

    15

    20

    25

    30

    35

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 1 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    40

    Silty sand with gravel, mg-cg

    8

    9

    11

    brown medium

    dense

    moist

    Silty sand, with gravel, fg-mg, clay binder4

    7

    11

    10

    12

    16

    4

    5

    8

    7

    12

    14

    7

    11

    14

    17

    20

    22

    Silty sand to clay sand, fgmottled

    orange, brown

    greenish-gray

    dense to firm

    Sandy silt, fg

    Interbedded silty sand and silty clay, fg

    SPT

    dense

    Silty sand, fg-mg, with gravel brown

    red-brown

    Clayey silt, fg

    SPT

    SPT

    1

    See Site Plan for locationSun Cal Co

    1/20/07 8 Hollow Stem Rig

    494-64

    mottled

    brown, gray

    Fill:

    Silty sand, fg

    brown slightly

    moist

    Alluvium:dense

    orange

    gray-brown

    TomRectangle

    TomRectangle

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    45

    50

    55

    60

    65

    70

    75

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 2 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    80

    Silty clay to clay silt, fg

    16

    22

    25

    dense moist

    Water, interbeded gravelly sand and

    silty sand, mg-fg

    6

    10

    11

    4

    5

    8

    5

    8

    13

    22

    50

    5

    10

    13

    21

    27

    30

    Gravelly sand, cg, cohesionless brownmedium

    dense

    Interbeded silty sand, fg, and gravelly

    sand, cg, gravelly sand is cohesionless

    sandy clay, fg, calche

    SPT

    Silty sand to sandy silt, fg-mg, with

    occasional gravel, calche

    mottled

    orange-brown

    gray-brown

    Silty sand to sandy silt, fg, calche

    SPT

    SPT

    1

    See Site Plan for locationSun Cal Co

    1/20/07 8 Hollow Stem Rig

    494-64

    40 6

    9

    10

    SPT brownSilty sand, mg-cg, with clay binder

    brown

    red-brownsaturated

    gray

    mottled

    brown

    green-brown

    medium

    dense to

    dense

    moiststiff

    dense

    mottled

    brown

    gray-green

    TomRectangle

    TomRectangle

  • RR

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    85

    90

    95

    100

    105

    110

    115

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 3 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    120

    Interbeded sandy clay and sand, fg,

    calche

    25

    50

    dense moist

    13

    15

    17

    7

    8

    15

    Clay, fg, poor recovery brown

    Silty clay, fg

    SPT

    SPT

    1

    See Site Plan for locationSun Cal Co

    1/20/07 8 Hollow Stem Rig

    494-64

    80 12

    15

    22

    SPT brownSandy silt to silty sand, fg, calche

    gray

    brown

    mottled

    gray-green

    brown

    End at 100 Fill to 10

    Water at 50, No Caving

    22

    50

    Sandy silt, fg, calche

    stiff

    TomRectangle

    TomRectangle

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    5

    10

    15

    20

    25

    30

    35

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 1 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    40

    Interbedded sandy silt and silty sand with

    gravel, fg-mg, clay binder

    10

    15

    17

    brown,

    gray brown,

    green brown

    dense moist

    Silty clay, fg firm to stiff5

    6

    9

    9

    12

    15

    4

    5

    7

    8

    12

    15

    14

    18

    30

    20

    22

    28

    Silty sand, fg, clay bindermottled

    orange-brown

    greenish-gray

    brown

    dense

    Sandy silt, fgmedium

    dense

    Sandy silt to clayey silt, fg, occasional

    gravel & slate chips

    SPT

    dense

    Silty sand grades into gravelly sand,

    mg-cg, gravel up to 1/2

    brown

    Silty sand to sandy silt, fg, occasional

    gravel

    SPT

    SPT

    2

    See Site Plan for locationSun Cal Co

    1/19/07 8 Hollow Stem Rig

    494-64

    brown

    orange-brown

    Fill:

    Alluvium:

    Silty sand, fg

    brown slightly

    moist

    TomRectangle

    TomRectangle

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    45

    50

    55

    60

    65

    70

    75

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 2 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    80

    Water, No recovery

    14

    20

    28

    dense moist

    Gravelly sand, cg, rock fragments up to 1

    50

    for

    6

    23

    30

    15

    18

    25

    25

    55

    10

    15

    19

    20

    23

    28

    Gravelly sand, mg, grades into sandy clay,

    mg

    green-gray dense to firm

    Silty sand to clay sand, fg-mg

    dense

    Gravelly sand, cg, clay binder, slate chips

    up to 3/4

    SPT

    Silty sand with gravel, mg-cg, slate chips,

    calche

    brown

    Silty sand to clay sand with gravel up to

    1/16, calche

    SPT

    SPT

    2

    See Site Plan for locationSun Cal Co

    1/19/07 8 Hollow Stem Rig

    494-64

    40 6

    8

    11

    SPT mottled

    orange-brown

    gray-green

    brown

    Clayey silt, fg, occasional gravel

    brown

    red-brownsaturated

    moist

    mottled

    green-gray

    red-brown

    brown

    red-brown

    gray-brown

    brown

    dense to stiff

    TomRectangle

    TomRectangle

  • RR

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    85

    90

    95

    100

    105

    110

    115

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 3 of 3

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    120

    Silty sand, fg-mg

    17

    20

    23

    dense moist

    Silty sand, fg-mg, calche, occasional

    gravel

    12

    14

    19

    29

    50

    Silty sand to sandy silt, fg mottled

    green-gray

    brown

    Interbeded silty sand, fg, and gravelly

    sand, cg

    SPT

    SPT

    2

    See Site Plan for locationSun Cal Co

    1/19/07 8 Hollow Stem Rig

    494-64

    80 13

    19

    20

    SPT brown

    green-brownSandy silt to silty sand, fg, clay binder

    mottled

    orange-brown

    gray-green

    brown

    brown saturated

    End at 100 Fill to 5

    Water at 45, No Caving

    TomRectangle

    TomRectangle

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    5

    10

    15

    20

    25

    30

    35

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 1 of 2

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    40

    Gravelly sand, cg, gravel up to

    26

    55 orange-brown

    gray, brown

    dense moist

    Interbeded clay sand and silty sand15

    17

    19

    10

    12

    15

    13

    15

    17

    17

    19

    20

    14

    17

    18

    20

    21

    23

    Silty clay, fg, with occasional gravelmottled

    orange-brown

    green-brown

    gray

    Silty clay, fg

    Clayey silt to silty clay, fg

    Silty sand to sandy silt, fg-mg, with gravel

    up to 3/4

    mottled

    red-brown

    black, gray

    Water, Gravely sand, mg-cg, clay binder,

    gravel up to 3/4

    3

    See Site Plan for locationSun Cal Co

    1/20/07 8 Hollow Stem Rig

    494-64

    brown

    red-brown

    R

    R

    R

    Fill:

    Silty sand with gravel

    mottled

    orange-brown

    brown

    green-gray

    dense

    saturated

    brown firm to dense

    Alluvium:

    firm to stiff

    TomRectangle

    TomRectangle

  • RLOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    45

    50

    55

    60

    65

    70

    75

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 2 of 2

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    80

    Gravely sand, cg, cohesionless, clay

    inclusions, gravel up to no recovery,

    9

    15

    18

    dense saturated

    Clay sand, cg, with gravel

    14

    16

    20

    3

    See Site Plan for locationSun Cal Co

    1/20/07 8 Hollow Stem Rig

    494-64

    40 21

    24

    28

    Gravely sand, cg, cohesionless, clay

    inclusions, gravel up to 1/2 brownR

    R

    End at 50, Fill to 5

    Water at 35, No Caving

    dense to stiff

    TomRectangle

    TomRectangle

  • RR

    R

    R

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    5

    10

    15

    20

    25

    30

    35

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 1 of 2

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    40

    Gravelly sand, cg, cohesionless

    14

    15

    17

    brown, tan dense moist

    Gravelly sand, cg, cohesionless, concrete

    debris

    26

    50

    12

    14

    17

    14

    15

    16

    8

    10

    11

    7

    12

    14

    17

    23

    28

    Silty sand, mg-cg, with gravellight brown

    gray

    Sandy silt, fg, with clay binder

    Clayey silt, fgdense

    to firm

    Gravely sand, mg-cg, cohesionless, clay

    inclusions

    brown

    black

    orange

    Water, Gravely sand, mg-cg, cohesionless,

    gravel up to 1/4

    4

    See Site Plan for locationSun Cal Co

    1/19/07 8 Hollow Stem Rig

    494-64

    brown

    R

    R

    R

    Fill:

    Silty sand with gravel

    Alluvium:slightly

    moist to

    moist

    mottled

    orange

    brown

    gray brown

    moist

    greenish

    gray-brown

    dense

    saturated

    TomRectangle

    TomRectangle

  • RR

    LOG OF EXPLORATORY BORING

    Job Number: B No:oring

    Project: Boring Location:

    Date Performed: Drill Type:

    Din

    Fe

    et

    ep

    th

    Blo

    ws

    pe

    rF

    oo

    t

    Un

    dis

    turb

    ed

    Bu

    lk

    45

    50

    55

    60

    65

    70

    75

    Figurer GeologicalFeffe Consulting

    Sample

    Type

    Sheet 2 of 2

    Bedrock/ Soil Description

    Colo

    r

    Density

    Mo

    istu

    re

    80

    Gravely sand, cg, cohesionless, poor

    recovery in rings, bag sample only

    9

    15

    18

    dense saturated

    Gravely sand, cg, cohesionless, clay

    inclusions, poor recovery in rings, bag

    sample only

    14

    16

    20

    14

    17

    22

    14

    15

    19

    Gravelly sand, mg-cg, ,

    cohesionless

    clay inclusions

    Gravelly sand, mg-cg, clay inclusions,

    cohesionless

    4

    See Site Plan for locationSun Cal Co

    1/19/07 8 Hollow Stem Rig

    494-64

    40 21

    24

    28

    Gravely sand, mg-cg, cohesionless,

    gravel up to 1/4 brownR

    R

    R

    End at 60, Fill to 15

    Water at 35, No Caving

    TomRectangle

    TomRectangle

  • Maximum depth: 100.09 (ft)Page 1 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-1Project: LosAngeles

    Test ID: CPT-1File: Z18J0707C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    Sand Mix

    Silt Mix

    ClayOrganics

    Clay

    Silt Mix

    Clay

    Sand MixSilt Mix

    Clay

    Silty Clay

    Clay

    Silty Clay

    Silt Mix

    Interbedded

    D

    e

    p

    t

    h

    (

    f

    t

    )

    0 0

    10 10

    20 20

    30 30

    40 40

    50 50

    TomRectangle

    TomRectangle

  • Maximum depth: 100.09 (ft)Page 2 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-1Project: LosAngeles

    Test ID: CPT-1File: Z18J0707C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    Silt Mix

    Silty Sand

    Sand

    Sandy Silt

    Silt MixVS Fine Gr

    Silt Mix

    Sandy Silt

    VS Fine GrSilt Mix

    Sandy Silt

    Sandy Silt

    Silt Mix

    D

    e

    p

    t

    h

    (

    f

    t

    )

    50 50

    60 60

    70 70

    80 80

    90 90

    100 100

    TomRectangle

    TomRectangle

  • Maximum depth: 100.09 (ft)Page 3 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-1Project: LosAngeles

    Test ID: CPT-1File: Z18J0707C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    D

    e

    p

    t

    h

    (

    f

    t

    )

    100 100

    110 110

    120 120

    130 130

    140 140

    150 150

    TomRectangle

    TomRectangle

  • Maximum depth: 100.14 (ft)Page 1 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-2Project: LosAngeles

    Test ID: CPT-2File: Z18J0703C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    Silt Mix

    ClaySilty Clay

    Sandy Silt

    Silty ClaySandy Silt

    Silt Mix

    Silty Clay

    Silt Mix

    Silty Clay

    Silt Mix

    Silty ClayClay

    Silt Mix

    Clay

    Silt Mix

    Silty Clay

    Silt Mix

    Sandy Silt

    Gr Sand

    Sandy Silt

    Sand

    Interbedded

    D

    e

    p

    t

    h

    (

    f

    t

    )

    0 0

    10 10

    20 20

    30 30

    40 40

    50 50

    TomRectangle

    TomRectangle

  • Maximum depth: 100.14 (ft)Page 2 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-2Project: LosAngeles

    Test ID: CPT-2File: Z18J0703C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)Sand

    Silt Mix

    Sandy Silt

    Silt MixSandy Silt

    Silt Mix

    VS Fine Gr

    Silt Mix

    Sandy Silt

    Silt Mix

    Sandy Silt

    Silt Mix

    Sandy Silt

    D

    e

    p

    t

    h

    (

    f

    t

    )

    50 50

    60 60

    70 70

    80 80

    90 90

    100 100

    TomRectangle

    TomRectangle

  • Maximum depth: 100.14 (ft)Page 3 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-2Project: LosAngeles

    Test ID: CPT-2File: Z18J0703C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    D

    e

    p

    t

    h

    (

    f

    t

    )

    100 100

    110 110

    120 120

    130 130

    140 140

    150 150

    TomRectangle

    TomRectangle

  • Maximum depth: 100.21 (ft)Page 1 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-3Project: LosAngeles

    Test ID: CPT-3File: Z18J0705C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    Sand

    Sandy Silt

    ClaySand MixSilty ClaySandy Silt

    Silt MixSandy SiltSilty Clay

    Silty Clay

    Silt Mix

    Silty Clay

    Silty Sand

    Sandy Silt

    Silty Clay

    Silt Mix

    Clay

    Silty Clay

    ClaySand Mix

    Silty Sand

    Sand Mix

    Silty Sand

    Clay

    Silt Mix

    D

    e

    p

    t

    h

    (

    f

    t

    )

    0 0

    10 10

    20 20

    30 30

    40 40

    50 50

    TomRectangle

    TomRectangle

  • Maximum depth: 100.21 (ft)Page 2 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-3Project: LosAngeles

    Test ID: CPT-3File: Z18J0705C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)Silt MixSand

    VS Fine Gr

    Clay

    Sand

    VS - Sandy

    Silty SandGr Sand

    Sand

    Silt Mix

    Sandy Silt

    Silt Mix

    Sandy Silt

    Silt Mix

    D

    e

    p

    t

    h

    (

    f

    t

    )

    50 50

    60 60

    70 70

    80 80

    90 90

    100 100

    TomRectangle

    TomRectangle

  • Maximum depth: 100.21 (ft)Page 3 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-3Project: LosAngeles

    Test ID: CPT-3File: Z18J0705C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    D

    e

    p

    t

    h

    (

    f

    t

    )

    100 100

    110 110

    120 120

    130 130

    140 140

    150 150

    TomRectangle

    TomRectangle

  • Maximum depth: 100.17 (ft)Page 1 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-4Project: LosAngeles

    Test ID: CPT-4File: Z18J0706C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)Silt Mix

    Clay

    Silty Clay

    Sand MixVS - Sandy

    VS Fine Gr

    Silty Clay

    Clay

    VS Fine Gr

    Silty Sand

    Sand Mix

    VS - Sandy

    VS Fine Gr

    VS - Sandy

    Silty Sand

    VS Fine Gr

    Silty SandVS Fine Gr

    D

    e

    p

    t

    h

    (

    f

    t

    )

    0 0

    10 10

    20 20

    30 30

    40 40

    50 50

    TomRectangle

    TomRectangle

  • Maximum depth: 100.17 (ft)Page 2 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-4Project: LosAngeles

    Test ID: CPT-4File: Z18J0706C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)VS Fine GrSilty Sand

    Sandy Silt

    Silt Mix

    VS Fine Gr

    Silt Mix

    Sandy Silt

    Silt Mix

    Sandy Silt

    Silt Mix

    D

    e

    p

    t

    h

    (

    f

    t

    )

    50 50

    60 60

    70 70

    80 80

    90 90

    100 100

    TomRectangle

    TomRectangle

  • Maximum depth: 100.17 (ft)Page 3 of 3

    Kehoe Testing & EngineeringOffice: (714) 901-7270Fax: (714) [email protected]

    CPT Data 30 ton rig

    Customer: Feffer GeologicalJob Site: Vacant Lot

    Date: 18/Jan/2007Test ID: CPT-4Project: LosAngeles

    Test ID: CPT-4File: Z18J0706C.ECP

    0 700Tip Stress COR

    (tsf) 0 10Sleeve Stress

    (tsf) -1 30Pore Pressure

    (tsf) 0 8Ratio COR

    (%) 2 12SBT FR

    (Rob. 1986)

    D

    e

    p

    t

    h

    (

    f

    t

    )

    100 100

    110 110

    120 120

    130 130

    140 140

    150 150

    TomRectangle

    TomRectangle

  • APPENDIX C

    Laboratory Testing

  • TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

    TomRectangle

  • TomRectangle

    TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

    TomRectangle

  • TomRectangle

    TomRectangle

  • TomRectangle

    TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • TomRectangle

  • APPENDIX D

    Engineering Calculations

  • IC: 494-64 CONSULT: JAICLIENT: SUNCAL COMPANIES

    GRAPH # 1

    24.073 1.492 0.47128.675 2.861 1.42624.334 2.26 1.82514.66 1.019 2.562

    13.211 0.678 3.41310.214 0.433 3.4212.815 0.485 3.73413.529 0.599 4.024

    69.104 1.432 3.758101.477 0.449 -3.528

    NAVFAC DENSITY

    ESTIMATED COMPACTNESS FROM SPT BLOW COUNTSMODIFIED FROM NAVFAC FIG. 1 7.1-14

    0

    20

    40

    60

    80

    100

    120

    140

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0VERTICAL EFFECTIVE STRESS (tsf)

    N60

    BLO

    W C

    OU

    NTS

    (blo

    ws/

    ft)

    CPT-1

    CPT-2

    CPT-3

    CPT-4

    VERY DENSE

    DENSE

    MEDIUM

    LOOSE

    VERY LOOSE

    30 F

    EET

    40 F

    EET

    TomRectangle

  • JN: 494-64 CONSULT: JFCLIENT: SUNCAL COMPANIES

    GRAPH #

    SHEAR WAVE VELOCITY

    INTERNAL SHEAR WAVE VELOCITY

    300

    500

    700

    900

    1100

    1300

    1500

    1700

    0 20 40 60 80 100DEPTH (feet)

    S-W

    AVE

    VEL

    OC

    ITY

    (ft/s

    ec)

    CPT-2 - SEISMIC

    SOIL PROFILE TYPE SD

    SOIL PROFILE TYPE SC

    TomRectangle

  • IC: 494-64 CONSULT: JAICLIENT: SUNCAL COMPANIES

    CORRELATION SHEET # 1

    CPT/SPT BLOW COUNT

    SPT N60 BLOW COUNT CORRELATION

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 20 40 60 80 100

    DEPTH (feet)

    BLO

    W C

    OU

    NTS

    (N60

    )

    CPT-1Boring 1

    TomRectangle

  • IC: 494-64 CONSULT: JAICLIENT: SUNCAL COMPANIES

    CORRELATION SHEET # 2

    CPT/SPT BLOW COUNT

    SPT N60 BLOW COUNT CORRELATION

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 20 40 60 80 100

    DEPTH (feet)

    BLO

    W C

    OU

    NTS

    (N60

    )

    CPT-2Boring 2

    TomRectangle

  • IC: 494-64 CONSULT: JAICLIENT: SUNCAL COMPANIES

    CALCULATION SHEET #

    FOUNDATION SETTLEMENT

    TOTAL SETTLEMENT-CONSTRAINED MODULUSMAT FOUNDATION (40' DEEP - 6,000 PSF)

    0.00

    0.10

    0.20

    0.30

    0.40

    0.50

    0.60

    0.70

    0.80

    0 20 40 60 80 100DEPTH (feet)

    TOTA

    L SE

    TTLE

    MEN

    T (in

    ches

    )

    CPT-1

    CPT-2

    CPT-3

    CPT-4

    TomRectangle

  • IC: 494-64 CONSULT: JFCLIENT: FEFFER/SUNCAL COMPANIES

    CALCULATION SHEET # 1

    CALCULATION PARAMETERSEARTH MATERIAL: ALLUVIUM WALL HEIGHT 20 feetSHEAR DIAGRAM: BACKSLOPE ANGLE: 0 degreesCOHESION: 280 psf SURCHARGE: 1000 poundsPHI ANGLE: 27 degrees SURCHARGE TYPE: P PointDENSITY 125 pcf INITIAL FAILURE ANGLE: 10 degreesSAFETY FACTOR: 1.5 FINAL FAILURE ANGLE: 70 degreesWALL FRICTION 0 degrees INITIAL TENSION CRACK: 4 feetCD (C/FS): 186.7 psf FINAL TENSION CRACK: 40 feetPHID = ATAN(TAN(PHI)/FS) = 18.8 degreesHORIZONTAL PSEUDO STATIC SEISMIC COEFFICIENT (kh) 0 %gVERTICAL PSEUDO STATIC SEISMIC COEFFICIENT (kv) 0 %g

    CRITICAL FAILURE ANGLE 56 degreesAREA OF TRIAL FAILURE WEDGE 130.3 square feetTOTAL EXTERNAL SURCHARGE 1000.0 poundsWEIGHT OF TRIAL FAILURE WEDGE 17288.1 poundsNUMBER OF TRIAL WEDGES ANALYZED 2257 trialsLENGTH OF FAILURE PLANE 19.7 feetDEPTH OF TENSION CRACK 3.7 feetHORIZONTAL DISTANCE TO UPSLOPE TENSION CRACK 11.0 feetCALCULATED HORIZONTAL THRUST ON WALL 8773.4 poundsCALCULATED EQUIVALENT FLUID PRESSURE 43.9 pcfDESIGN EQUIVALENT FLUID PRESSURE 45.0 pcf

    RETAINING WALL

    THE CALCULATION INDICATES THAT THE PROPOSED CANTILEVERED RETAINING WALLS MAY BE DESIGNED FOR AN EQUIVALENT FLUID PRESSURE OF 45 POUNDS PER CUBIC FOOT.

    CALCULATED RESULTS

    CALCULATE THE DESIGN MINIMUM EQUIVALENT FLUID PRESSURE (EFP) FOR PROPOSED RETAINING WALLS. THE WALL HEIGHT AND BACKSLOPE AND SURCHARGE CONDITIONS ARE LISTED BELOW. ASSUME THE BACKFILL IS SATURATED WITH NO EXCESS HYDROSTATIC PRESSURE. USE THE MONONOBE-OKABE METHOD FOR SEISMIC FORCES.

    B-1

    TomRectangle

  • APPENDIX E

    Grading Specifications

  • STANDARD GRADING SPECIFICATIONS

    These specifications present the usual and minimum requirements for grading operations performed under

    our supervision.

    GENERAL

    1) The Geotechnical Engineer and Engineering Geologist are the developer's representative on the project.

    2) All clearing, site preparation or earth work performed on the project shall be conducted by the contractor

    under the supervision of the Geotechnical Engineer.

    3) It is the contractor's responsibility to prepare the ground surface to receive the fills to the satisfaction of

    the Geotechnical Engineer and to place, spread, mix, water, and compact the fill in accordance with the

    specifications of the Geotechnical Engineer. The contractor shall also remove all material considered unsatisfactory

    by the Geotechnical Engineer.

    4) It is the contractor's responsibility to have suitable and sufficient compaction equipment on the job site to

    handle the amount of fill being placed. If necessary, excavation equipment will be shut down to permit completion

    of compaction. Sufficient watering apparatus will also be provided by the contractor, with due consideration for the

    fill material, rate of placement and time of year.

    5) A final report shall be issued by our firm outlining the contractor's conformance with these

    specifications.

    SITE PREPARATION

    1) All vegetation and deleterious materials such as rubbish shall be disposed of off-site. Soil, alluvium or

    rock materials determined by the Geotechnical Engineer as being unsuitable for placement in compacted fills shall

    be removed and wasted from the site. Any material incorporated as a part of a compacted fill must be approved by

    the Geotechnical Engineer.

  • Page 2

    Standard Grading Specifications

    Feffer Geological Consulting

    2) The Engineer shall locate all houses, sheds, sewage disposal systems, large trees or structures on the site

    or on the grading plan to the best of his knowledge prior to preparing the ground surface.

    Any underground structures such as cesspools, cisterns, mining shafts, tunnels, septic tanks, wells, pipe

    lines, or others not located prior to grading are to be removed or treated in a manner prescribed by the Geotechnical

    Engineer.

    3) After the ground surface to receive fill has been cleared, it shall be scarified, disced or bladed by the

    contractor until it is uniform and free from ruts, hollows, hummocks or other uneven features which may prevent

    uniform compaction.

    The scarified ground surface shall then be brought to optimum moisture, mixed as required, and compacted

    as specified. If the scarified zone is greater than twelve inches (12") in depth, the excess shall be removed and

    placed in lifts restricted to six inches (6").

    Prior to placing fill, the ground surface to receive fill shall be inspected, tested and approved by the

    Geotechnical Engineer.

    PLACING, SPREADING AND COMPACTION OF FILL MATERIALS

    1) The selected fill material shall be placed in layers which when compacted shall not exceed six inches

    (6") in thickness. Each layer shall be spread evenly and shall be thoroughly mixed during the spreading to insure

    uniformity of material and moisture of each layer.

    2) Where the moisture content of the fill material is below the limits specified by the Geotechnical

    Engineer, water shall be added until the moisture content is as required to assure thorough bonding and thorough

    compaction.

    3) Where the moisture content of the fill material is above the limits specified by the Geotechnical

    Engineer, the fill materials shall be aerated by blading or other satisfactory methods until the moisture content is

    adequate.

    TomRectangle

  • Page 3

    Standard Grading Specifications

    Feffer Geological Consulting

    COMPACTED FILLS

    1) Any material imported or excavated on the property may be utilized in the fill, provided each material

    has been determined to be suitable by the Geotechnical Engineer. Roots, tree branches or other matter missed

    during clearing shall be removed from the fill as directed by the Geotechnical Engineer.

    2) Rock fragments less than six inches (6") in diameter may be utilized in the fill, provided:

    a) They are not placed in concentrated pockets.

    b) There is a sufficient percentage of fine-grained material to surround the rocks.

    c) The distribution of the rocks is supervised by the Geotechnical Engineer.

    3) Rocks greater than six inches (6") in diameter shall be taken off-site, or placed in accordance with the

    recommendations of the Geotechnical Engineer in areas designated as suitable for rock disposal. Details for rock

    disposal such as location, moisture control, percentage of rock placed, will be referred to in the "Conclusions and

    Recommendations" section of the geotechnical report.

    If the rocks greater than six inches (6") in diameter were not anticipated in the preliminary geotechnical and

    geology report, rock disposal recommendations may not have been made in the "Conclusions and

    Recommendations" section. In this case, the contractor shall notify the Geotechnical Engineer if rocks greater than

    six inches (6') in diameter are encountered. The Geotechnical Engineer will than prepare a rock disposal

    recommendation or request that such rocks be taken off-site.

    4) Representative samples of materials to be utilized as compacted fill shall be analyzed in the laboratory

    by the Geotechnical Engineer to determine their physical properties. If any materials other than that previously

    tested is encountered during grading, the appropriate analysis of this material shall be conducted by the Geotechnical

    Engineer as soon as possible.

    Material that is spongy, subject to decay or otherwise considered unsuitable shall not be used in the

    compacted fill.

    5) Each layer shall be compacted to ninety percent (90%) of the maximum density in compliance with the

    testing method specified by the controlling governmental agency (ASTM D-1557-02).

    TomRectangle

  • Page 4

    Standard Grading Specifications

    Feffer Geological Consulting

    If compaction to a lesser percentage is authorized by the controlling governmental agency because of a

    specific land use or expansive soil conditions, the area to receive fill compacted to less than ninety percent (90%)

    shall either be delineated on the grading plan or appropriate reference made to the area in the geotechnical report.

    6) Compaction shall be by sheeps foot roller, multi-wheeled pneumatic tire roller, or other types of

    acceptable rollers. Rollers shall be of such design that they will be able to compact the fill to the specified density.

    Rolling shall be accomplished while the fill material is at the specified moisture content. The final surface of the lot

    areas to receive slabs-on-grade should be rolled to a smooth, firm surface.

    7) Field density tests shall be made by the Geotechnical Engineer of the compaction of each layer of fill.

    Density tests shall be made at intervals not to exceed two feet (2') of fill height provided all layers are tested. Where

    the sheeps foot rollers are used, the soil may be disturbed to a depth of several inches and density readings shall be

    taken in the compacted material below the disturbed surface. When these readings indicate the density of any layer

    of fill or portion thereof is below the required ninety percent (90%) density, the particular layer or portion shall be

    reworked until the required density has been obtained.

    8) Buildings shall not span from cut to fill. Cut areas shall be over excavated and compacted to provide a

    fill mat of three feet (3').

    FILL SLOPES

    1) All fills shall be keyed and benched through all top soil, colluvium, alluvium, or creep material into

    sound bedrock or firm material where the slope receiving fill exceeds a ratio of five (5) horizontal to one (1) vertical,

    in accordance with the recommendations of the Geotechnical Engineer.

    2) The key for side hill fills shall be a minimum of fifteen feet (15') within bedrock or firm materials, unless

    otherwise specified in the geotechnical report.

    3) Drainage terraces and subdrainage devices shall be constructed in compliance with the ordinances of the

    controlling governmental agency, or with the recommendations of the Geotechnical Engineer.

    4) The Contractor will be required to obtain a minimum relative compaction of ninety percent (90%) out to

    the finish slope face of fill slopes, buttresses, and stabilization fills. This may be achieved by either over-building

    TomRectangle

  • Page 5

    Standard Grading Specifications

    Feffer Geological Consulting

    the slope and cutting back to the compacted core, or by direct compaction of the slope face with suitable equipment,

    or by any other procedure which produces the required compaction.

    5) All fill slopes should be planted or protected from erosion by methods specified in the geotechnical

    report and by the governing agency.

    6) Fill-over-cut slopes shall be properly keyed through topsoil, colluvium, or creep material into rock or

    firm materials. The transition zone shall be stripped of all soil prior to placing fill.

    CUT SLOPES

    1) The Engineering Geologist shall inspect all cut slopes excavated in rock, lithified, or formation material

    at vertical intervals not exceeding ten feet (10').

    2) If any conditions not anticipated in the preliminary report such as perched water, seepage, lenticular or

    confined strata of a potentially adverse nature, unfavorably inclined bedding, joints, or fault planes, are encountered

    during grading, these conditions shall be analyzed by the Engineering Geologist and Geotechnical Engineer; and

    recommendations shall be made to treat these problems.

    3) Cut slope that face in the same direction as the prevailing drainage shall be protected from slope wash by

    a non-erosive interceptor swale placed at the top of the slope.

    4) Unless otherwise specified in the geological and geotechnical report, no cut slopes shall be excavated

    higher or steeper than that allowed by the ordinances of the controlling governmental agencies.

    5) Drainage terraces shall be constructed in compliance with the ordinances of controlling governmental

    agencies, or with the recommendations of the Geotechnical Engineer or Engineering Geologist.

    GRADING CONTROL

    1) Inspection of the fill placement shall be provided by the Geotechnical Engineer during the progress of

    grading.

    2) In general, density tests should be made at intervals not exceeding two feet (2') of fill height or every

    five hundred (500) cubic yards of fill placed. These criteria will vary depending on soil conditions and the size of

    the job. In any event, an adequate number of field density tests shall be made to verify that the required compaction

    is being achieved.

    TomRectangle