Top Banner
31

Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Dec 22, 2015

Download

Documents

Peter Knight
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.
Page 2: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.
Page 3: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.
Page 4: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.
Page 5: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Geotechnical investigation and risk assessment at Budapest metro line 4

Dr. Tibor HorváthGeovil Ltd.

INTERNATIONAL SOCIETY FOR SOIL MECHANICSAND GEOTECHNICAL ENGINEERINGHUNGARIAN NATIONAL COMMITTEE

24th -25th September 2010, Budapest ISSMGE TC 302

“Failures, Disputes, Causes and Solutions in Geotechnics”

Page 6: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

MAIN FEATURES OF METRO LINEMAIN FEATURES OF METRO LINE 4 4

Length of line: 12.7 km

Phase I: 7.4 km

Phase II: 3.2 km

Phase III: 2.1 km

Number of stations: 16

Phase I: 10 stations

Phase II: 4 stations

Phase III: 2 stations

Extensions:

Phase II currently holds licences from both railway and environmental authorities as far as Bosnyák tér, while the planned Phase III would extend as far as the Budaörs Flower Market.

Page 7: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

The route proceeds at a relatively shallow depth, at a rail-top level of 16-22 metres below the surface on average, the depth of 32-34 metres under the Danube, passing beneath an almost entirely built-up area and through extremely varied geological strata.

Buda section Danube Pest section

Page 8: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Enginner geological profile of Buda side

Kiscelli marly clay stone, weathered

Kiscelli marly clay stone, fissured

Page 9: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Engineering geological profile of river Danube crossing

Page 10: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Engineering geological profile of Pest side

Pleisztocene, river sediments

Miocéne, litoral facies of of a mediterrain sea

Page 11: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Risk Classification by Likelihood „L „

1 – FrequentAn effect derived in the frame of a survey from any risk successively experienced/monitored during the project and

supported statistics derived, if applicable, from the project and other relevant events.

2 – Likely An effect derived in the frame of a survey from any risk often experienced/monitored during the project and supported

statistics derived, if applicable, from the project and other relevant events.

3 – OccasionalAn effect derived in the frame of a survey from a risk occasionally experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events.

4 – Unlikely An effect derived in the frame of a survey from an unlikely risk during the project and supported statistics derived, if

applicable, from the project and other relevant events.

5 – ImprobableAn effect derived in the frame of a survey from an improbable risk often experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events.

Risk Classification by Severity „S „

1 – Catastrophic

Several immediate or deferred fatality cases attributable to injuries or illness. Loss of production for more than seven days.

(Total loss €5 millions)

2 – HighA single immediate or deferred fatality case attributable to injuries or illness. Loss of production of one to seven days due

to damage to work or equipment. (Total loss above €1 million, but below €5 millions)

3 – Significant

Injury, illness or dangerous circumstance subject to reporting.The loss of production due to injury exceeds one shift.Max. one day’s loss of production due to damage to work or equipment.(Total loss of more than €25,000 but less than €1 million)

4 – Low

Minor injury. No loss of time or the person can return, after receiving medical attention, to work yet in the same shift. Damage not causing a significant delay in work performance or equipment.

(Total loss of max. €25,000)

Page 12: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Risk Assessment Classification Matrix ”RI” (Risk Index)

Risk Severity / Likelihood

1 – Catastrophic 2 – High 3 – Significant 4 – Low

1 – Frequent1 2 3 4

2 – Likely2 4 6 8

3 – Occasional3 6 9 12

4 – Unlikely 4 8 12 16

5 – Improbable5 10 15 20

Risk Index (R) Risk classification Marking

1 – 4Very high V (Very high)V (Very high)

5 – 9High H ( High )H ( High )

10 – 14 Medium M (Medium)M (Medium)15 – 29 Low L (Low)L (Low)

Risk Index, Classification and Marking

• After determining the likelihood and severity of the risk we determined the risk index by means of the assessment matrix.

Risk index = Likelihood of occurrence x Severity of risk

RI = L x S

• The risk index has been calculated for the “starting/initial” cases and the cases yet remaining despite the efforts made to alleviate severity of the risks involved.

Page 13: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Elements of Risk Assessment Arise from Geology, Hydrogeology and Geotechnical features

• General risk from the level of geotechnical investigation, • Personal risk• Third party risk• Environmental risk• Risk of equipments• Risk of program and delay

Annex "A1.": Geotechnical risk level matrix table of Rákóczi Square Station with the section to be built by installing a diaphragm wall

Initial conditions, risks Residual conditions, risks  

Risk L S RI RR Reduction L S RI RR Comments

GENERAL RISK FROM THE LEVEL OF GEOTECHNICAL SURVEYING                    

The geotechnical and hydrogeological data available for the preparation of working drawings and for construction are not reliable and insufficient.

2 1 2 VSupplementary geotechnical and hydrogeological surveys. Continuous geotechnical service during construction.

4 4 16 LIn order to reduce risk, we suggest 2 "dry land" bores and a hydrogeological survey.

The supplementary geotechnical surveys are not suitably assessed. 4 3 12 MConsultation with the specialist geotechnical service, continuous presence of the specialist service during construction.

5 4 20 LThe geotechnical specialist service maps the strata found during excavation continuously and provides information about it to construction management.

River water level 0.5 m higher than the highest flood level of the Danube. 3 3 9 HDuring the preparation of construction drawings, protection shall be planned. Continuous assessment of water level reports, a technical and personnel protection plan shall be prepared.

4 4 16 L  

Groundwater level exceeds the estimated nominal design level 2 3 6 HContinuous monitoring and evaluation of data from groundwater monitoring wells and the Danube water levels. Preparation of a technical and personnel plan for protection against high groundwater levels.

4 4 16 L  

Soil and rock conditions differ from those established by the supplementary geotechnical survey.

3 4 12 MConsultation with the specialist geotechnical service and the designer, additional geotechnical and hydrogeological tests and surveys to be performed as required.

4 4 16 L  

Page 14: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

0,00

10,00

20,00

30,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

very high

high

medium

low

Geotechnical general risk from the level of geotechnical investigation, at Buda side

At the time of GBR After additional investigation and monitoring

Page 15: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Geotechnical General Risk from the Level of Geotechnical Investigation, at Danube River Crossing

Page 16: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Geotechnical General Risk from the Level of Geotechnical Investigation at Pest side

Page 17: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Volume of Geotechnical Investigation

Page 18: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Total Volume of the Investigation at the End of Construction Work

Page 19: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Length of boring versus length of tunnel (stations with SCL method)

Page 20: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Length of boring versus boring length / tunnell length

Length of boring (m)

Page 21: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Length of boring versus length of tunnell

Recommended rate of USTNC/TT=1,2 *

* U.S. National Committe on Tunnelling Technology, 2005

Page 22: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Cost of geotechnical investigation / cost construction at SCL tunnells

Page 23: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4, Kelenföld station, portal land slip

Page 24: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Fővám station

Due to the detailed investigation and monitoring the tunneling work has been safe and successful in very dangerous – difficult geotechnical conditions.

Page 25: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Rákóczi station SCL tunnell collapse – wash out

Page 26: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Rákóczi station SCL tunnell collapse – wash out

Page 27: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Rákóczi station SCL tunnell collapse – wash out

Page 28: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Rákóczi station SCL tunnell collapse – wash out

Page 29: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Budapest metro 4 Rákóczi station SCL tunnel collapse – wash out

Page 30: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Conclusions and recommendations

• The Geotechnical Risk Assessment comes from a suitable site investigation and the consequent building of an appropriate and coherent Engineering Geological model.

• It is desirable to create an international standard for the Geotechnical Risk Assessment, and to agree the parameters and guidelines for these recommendations.

• The Geotechnical Risk Assessment has a relationship to the quantity of meters of site investigation holes bored and the excavated length of tunnel. For the SCL tunnel ( soft tunneling at shallow depth ) the ratio of site investigation / excavated tunnel length should be 1.2 .

• For the Budapest metro 4 project, the recommended ratio was followed. This resulted in a project which was very safe, in geological, geotechnical terms also the project had very few disputes related to the geotechnical risk clauses

Page 31: Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Thank you for your kind attention!