This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
RECOMMENDED GEOTECHNICAL PARAMETERS FOR MSE WALL DESIGN
Material
Type
Total Unit
Weight
(pcf)1
Effective Stress (Drained)
Parameters1
c′, psf ′, degrees
Reinforced Zone
(ODOT Type “A”) 125 N/A2 34
Alternate 110 N/A 34
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 5
RECOMMENDED GEOTECHNICAL PARAMETERS FOR MSE WALL DESIGN
Material
Type
Total Unit
Weight
(pcf)1
Effective Stress (Drained)
Parameters1
c′, psf ′, degrees
Reinforced Zone
(ASTM C-33 #57 Stone)
Retained/Foundation Zone
(Fill: Lean clay or clayey
sand) (near RW3-8 & C-6)3
120 50 26
Foundation Zone
(lean clay) (near C-6)3 120 50 26
Foundation Zone
(Weathered Sandstone) (B-1
to B-4)
125 0 36
1. The geotechnical parameters provided for the foundation soil are based on average correlated
values. 2. C=2000 psf used for global analysis to represent grid strength and force potential failure planes
outside of the reinforced zone. 3. Due to the presence of fill near the bearing level at borings RW3-8 and C-6, we recommend
overexcavating the subgrade within the proposed retaining wall areas to a depth of about 3 feet
below the retaining wall foundation. The overexcavation should extend laterally a minimum of 5
feet beyond the front of the retaining wall toe to a minimum distance behind the wall facing
equal to the width of the reinforced zone. The overexcavation should be backfilled to the
foundation base elevation with approved ODOT Type “A” structural fill placed in lifts of 9 inches
or less in loose thickness and should be compacted to at least 98 percent of the material’s
maximum standard Proctor dry density (AASHTO T-99) within 2 percent of its optimum value.
Based on the subsurface conditions encountered in the soil test borings, listed below are the
resistance and load factors based on AASHTO’s LRFD Bridge Design Specification, 5th Edition,
2010 that should be used by the retaining wall designer in the design of the retaining wall.
Load Factor for vertical earth pressure, EV, from Table 3.4.1-2 and Figure C11.5.5-2:
Sliding and Eccentricity p-EV = 1.00
Bearing Capacity p-EV = 1.35
Load Factor for live load surcharge, LS, from Table 3.4.1-2 and Figure C11.5.5-3b:
Bearing Capacity, Sliding and Eccentricity p-EV = 1.75
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 6
Load factor for active earth pressure, EH, from Table 3.4.1-2 and Figure C11.5.5-2:
p-EH = 1.50
Resistance factor for shear resistance along common interfaces from table 10.5.5.2.2 -1:
Reinforced Soil and Foundation = 0.9
Resistance factor for bearing capacity of a shallow foundation from table 10.5.5.2.2-1:
b = 0.45
Please note that we have determined reinforcement lengths for the MSE wall based on our
experience with MSE wall design and the parameters listed in the report. Actual design
embedment lengths in the contractor supplied design could vary from those used in our
analyses.
4.2 Retaining Wall Stability Analyses
Based on the plans, profiles, and cross sections provided by Leidos Engineering, Inc., we have
analyzed four different cross sections of the anticipated design profile of the retaining wall. The
cross sections were taken at stations 273+50, 274+50, 278+00 and 282+00. The maximum
design wall height will be up to about 35 feet. We understand that the retaining wall contractor
will perform internal and external stability analyses as part of the contractor supplied design of
the wall.
Our engineering analyses of the MSE wall has considered the following:
Foundation bearing capacity (with water level at the base of the foundation)
Settlement of the reinforced zone and differential settlement along the wall fascia
Direct sliding at the base of the reinforced zone
Horizontal grade at the toe of the proposed wall
4H:1V and 3H:1V grade at the back of the proposed wall
Minimum wall embedment of 3 feet
Global stability of the reinforced zone for both circular and horizontal block slip
surfaces, considering the reinforced zone to act as a rigid block
Reinforcement will consist of extensible geogrid
4.2.1 Foundation Bearing Capacity
The factored bearing resistance qR was evaluated using the following equation, which is
dependent on various soil properties and the design grid length.
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 7
qR = b qn (Equation AASHTO 10.6.3.1.1-1)
where: b = resistance factor
qn = nominal bearing resistance, which is defined as
qn = c Ncm + 0.5 B Nm Cw
where: c = cohesion
= unit weight
Ncm and N = dimensionless bearing capacity coefficients
B = total length of reinforcement
Cw = correction factors to account for the location of groundwater table
Based on the subsurface conditions encountered in the soil test borings and the proposed wall
geometry, the reinforcement grid lengths required varied from 11 to 45 feet (about 73 to 130
percent) in order to satisfy the LRFD Capacity to Demand Ratio (CDR). It is important to note
that for our analyses, we have considered that the ground water level will affect the ultimate
bearing capacity of the foundation soils. This assumption was made based on the 24 hour
water level readings and the geometry of the analyses. We also assumed that the wall near
boring RW3-8 will bear on approximately 5 feet of the remaining existing fill.
Based on the subsurface conditions, the retaining wall foundation can be analyzed using the
geotechnical design parameters presented in the Recommended Geotechnical Design
Parameters section of this report.
4.2.2 Settlement of Reinforced Zone
The wall settlement will depend upon the variations within the subsurface soil profile, the
structural loading conditions and the quality of the past and future earthwork operations.
Because of the variations associated with these parameters, Terracon cannot accurately
estimate settlements under all design scenarios. Assuming that the foundation bearing
conditions are similar to our subsurface data beneath all sections of the wall, it is our opinion
that the maximum total settlement experienced along the retaining wall will be less than 1
inch with maximum differential settlements not expected to exceed a slope of 1:200. These
values should be evaluated by the wall designer/manufacturer to confirm that the wall will be
able to tolerate this magnitude of total and differential settlement.
4.2.3 Direct Sliding
Our analyses indicate that with reinforcement lengths required to meet bearing capacity and
global stability requirements (on the order of 73 to 130 percent of the wall height) have a
CDR against direct sliding at the foundation equal to or greater than 1.0. Sliding may control
the design where the bearing surface consists of bedrock (shale or sandstone) support,
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 8
such as near borings B-1, B-2, B-3 and B-4. The factored resistance against failure by
sliding was determined using the following equation.
RR = R (Equation AASHTO 10.6.3.4-1)
where: = resistance factor for shear resistance between soil and foundation
R = nominal sliding resistance between soil and foundation
Based on the subsurface conditions, the wall designer should use the geotechnical design
parameters presented in the Recommended Geotechnical Design Parameters section of
this report when analyzing the external sliding resistance.
4.2.4 Global Stability of Reinforced Zone
We have performed global stability analyses for conceptual wall sections at borings RW3-8, C-
6, B-2 and B-4. Drained soil, foundation, and backfill geotechnical parameters were used in
our analyses. A resistance factor, , of 0.65, as outlined in section 11.6.2.3 of AASHTO’s
LRFD Bridge design Specification, 5 th Edition, 2010 was applied when analyzing the global
stability. Circular failures were analyzed using the modified Bishop method and sliding block
failures were analyzed using the modified Janbu method. All global stability analyses indicated
a CDR of 1.0 or greater.
We constrained the analysis of sliding block slip surfaces to the interface between the
reinforced zone and upper portion of the foundation soils by limiting shear surface development
in the reinforced zone. Our analysis focused on developing the minimum reinforced zone that
would satisfy a minimum global stability CDR of 1.0.
The stability analyses were performed on wall sections with reinforced zone length-to-height
ratio (i.e., the ratio of length of the reinforced zone to total wall height) of 0.7 to 1.3 as
determined to meet bearing capacity or sliding requirements. If the wall geometry is changed
(deeper penetration, shorter grids, etc), then additional global stability analyses should be
performed to confirm that the CDR is greater than 1.0.
Please note that the preceding discussion related so external global stability and not compound
stability of the retaining wall. Compound stability should be considered in the design analysis
conducted by the wall design engineer.
4.3 Global Stability of Temporary Excavation Slopes
Based on the drawings provided by Leidos Engineering, Inc., it is anticipated that up to 35 feet
of cut will be required for constructing the retaining wall. A slope stability analysis was
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 9
conducted for a typical section for temporary construction excavations. We have assumed no
surcharge in our analysis for these excavations.
A resistance factor, , of 0.75, as outlined in section 11.6.2.3 of AASHTO’s LRFD Bridge
design Specification, 5th Edition, 2010 was applied when analyzing the global stability for
maximum temporary excavation slopes.
Excavations deeper than 4 feet should meet all OSHA and other applicable safety
regulations.
Slopes for temporary excavations for subsurface conditions similar to those encountered at this
project should be constructed at 3H:1V or flatter. In areas where weathered bedrock is
encountered, the slopes for temporary excavation on weathered bedrock could be steepened
to 2H:1V.
We anticipate that excavations for the retaining wall may extend into weathered bedrock.
Rock formations that have standard penetration test results of 4 or more inches per 50
blows can usually be excavated with heavy excavation equipment equipped with ripping
teeth. Rock formations that have standard penetration test results of 3 inches or less per 50
blows usually require either pneumatic equipment or blasting for rock break-up and removal.
However, variations in hardness of rock can occur with depth and distance from the borings.
4.4 Wall Drainage Recommendations
Care should be taken in the design and during construction to develop and maintain rapid,
positive drainage away from the retaining wall area. Water should not be allowed to pond
adjacent to either the upslope or downslope sides of the retaining wall. We recommend that
drainage swales with sufficient gradients be constructed along both the upslope and downslope
sides of the wall to direct surface water away from the wall. Proper surface drainage is needed
to prevent water from flowing over the face of the wall and saturating either the fill behind the
wall or the subgrade soils at the base of the wall.
If Oklahoma Department of Transportation (ODOT) Type “A” aggregate base material is
used to construct the reinforced zone, we recommend that a backslope drain, comprised of
a geocomposite drainage blanket, such as Miradrain, be attached to the face of the cut
backslope and extend down to a collector drain pipe placed along the bottom of the
reinforced zone at the base of the cut slope. The collector drain should consist of a
perforated PVC pipe that is placed in free-draining aggregate such as ASTM No. 57 stone,
with the stone wrapped in a geotextile filter fabric. The collector drain should be sloped to
drain out beyond one or both ends of the retaining wall. The geocomposite drainage blanket
should be cut off at a depth of 2 feet below the finished ground surface at the back of the
reinforced backfill zone to allow a minimum cover of 2 feet of compacted clayey soil over the
drain to prevent the infiltration of surface water into the backslope drain.
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 10
Alternatively, select drainable aggregate fill material consisting of crushed No. 57 stone could
be imported to construct the entire reinforced zone. If the crushed No. 57 stone is used to
construct the reinforced backfill zone, we recommend that a geotextile filter fabric, such as
Mirafi 140N be placed between the face of the retained soil and the reinforced backfill zone to
prevent the migration of fines from the native soils or proposed fill into the free-draining No. 57
stone.
4.5 Construction Considerations
The construction specifications should provide the backfill material specifications and design
strength parameters that are required for the different fill zones so that unsuitable materials
are not used in the reinforced backfill zone during construction.
We recommend that any fill with debris encountered at the time of construction be removed
and replaced with ODOT Type “A” structural fill.
Any overexcavations for compacted backfill placement below the retaining wall should
extend laterally a minimum of 5 feet beyond the front of the retaining wall (or edge of the
embankment) toe to a minimum distance behind the wall facing equal to the width of the
reinforced zone. The overexcavation should then be backfilled to the foundation base
elevation with approved ODOT Type “A” structural fill placed in lifts of 9 inches or less in
loose thickness and compacted to at least 98 percent of the material's maximum standard
Proctor dry density (ASTM D-698) at a moisture content between 2 percent below to 2
percent above the material’s optimum moisture content.
Prior to starting construction of the MSE wall, fill material proposed to be used in
constructing the reinforced zone for the wall should be sampled and tested in the laboratory
to confirm that the engineering properties of the backfill satisfy the specified properties used
in design. Observation and field testing during construction of the MSE wall by qualified
geotechnical personnel is also recommended.
We anticipate that excavations for the retaining wall will extend into weathered bedrock.
Rock formations that have standard penetration test results of 4 or more inches per 50
blows can usually be excavated with heavy excavation equipment equipped with ripping
teeth. Rock formations that have standard penetration test results of 3 inches or less per 50
blows usually require either pneumatic equipment or blasting to remove. However,
variations in hardness of rock can occur with depth and distance from the borings.
Based on the groundwater conditions encountered during our subsurface exploration,
excavations for the retaining wall may encounter groundwater. Therefore, the contractor
should anticipate dewatering will be required during the construction of the walls.
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable 11
5.0 GENERAL COMMENTS
Terracon should be retained to review the final design plans and specifications so
comments can be made regarding interpretation and implementation of our geotechnical
recommendations in the design and specifications. Terracon also should be retained to
provide observation and testing services during grading, excavation, wall construction and
other earth-related construction phases of the project.
The analysis and recommendations presented in this report are based upon the data
obtained from the borings performed at the indicated locations and from other information
discussed in this report. This report does not reflect variations that may occur between
borings, across the site, or due to the modifying effects of construction or weather. The
nature and extent of such variations may not become evident until during or after
construction. If variations appear, we should be immediately notified so that further
evaluation and supplemental recommendations can be provided.
The scope of services for this project does not include either specifically or by implication
any environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or
identification or prevention of pollutants, hazardous materials or conditions. If the owner is
concerned about the potential for such contamination or pollution, other studies should be
undertaken.
This report has been prepared for the exclusive use of our client for speci fic application to
the project discussed and has been prepared in accordance with generally accepted
geotechnical engineering practices. No warranties, either express or implied, are intended
or made. Site safety, excavation support, and dewatering requirements are the
responsibility of others. In the event that changes in the nature, design, or location of the
project as outlined in this report are planned, the conclusions and recommendations
contained in this report shall not be considered valid unless Terracon reviews the changes
and either verifies or modifies the conclusions of this report in writing.
APPENDIX A
FIELD EXPLORATION
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable Exhibit A-2
Field Exploration Description
A total of four additional test borings were drilled at the site on April 2, 2014. The borings were
drilled to depths ranging from approximately 10 to 15 feet below the ground surface at the
approximate locations shown on the attached Boring Location Diagram, Exhibit A-1. Subsurface
information collected from borings RW3-8 and C-6 provided in our geotechnical report No’s
03115012 dated 8/30/2011 and 03115101 dated 4/15/2011 was also used in developing our
recommendations.
Terracon personnel located the borings in the field by taping distances and estimating right
angles based on information from the site plan provided by Leidos Engineering, LLC. The boring
locations should be considered accurate only to the degree implied by the methods used to
define them. Terracon determined the approximate ground surface elevations at the borings
using an engineer’s level. These elevations were referenced to the benchmark shown in the
following table. Based on the benchmark, the ground surface elevations at the boring locations
ranged from 1123.3 to 1149.7 feet. The elevations shown on the logs have been rounded to the
nearest 0.1 foot. The boring locations and elevations should be considered accurate only to the
degree implied by the methods used to define them.
Bench Mark Description Northing/Easting Elevation, ft.
13 “V” T/C by F.H. @ N.W.
50th & Sewell 190386.14 / 2112582.36 1142.57
An all-terrain truck mounted, rotary drill rig equipped with continuous flight augers was used to
advance the boreholes. Representative samples were obtained by the split -barrel sampling
procedures.
The split-barrel sampling procedure uses a standard 2-inch O.D. split-barrel sampling spoon
that is driven into the bottom of the boring with a 140-pound drive hammer falling 30 inches.
The number of blows required to advance the sampling spoon the last 12 inches, or less, of a
typical 18-inch sampling interval or portion thereof, is recorded as the standard penetration
resistance value, N. The N value is used to estimate the in-situ relative density of cohesionless
soils and, to a lesser degree of accuracy, the consistency of cohesive soils and the hardness of
sedimentary bedrock. The sampling depths, penetration distances, and the N values are
reported on the boring logs. The samples were tagged for identification, sealed to reduce
moisture loss and returned to the laboratory for further examination, testing and classification.
An automatic Standard Penetration Test (SPT) drive hammer was used to advance the split -
barrel sampler. The automatic drive hammer achieves a greater mechanical efficiency when
compared to a conventional safety drive hammer operated with a cathead and rope. We
considered this higher efficiency in our interpretation and analysis of the subsurface information
provided with this report.
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable Exhibit A-2
The drill crew prepared field logs as part of the dr illing operations. These boring logs included
visual classifications of the materials encountered during drilling and the driller’s interpretation of
the subsurface conditions between samples. The final boring logs included with this report
represent the engineer’s interpretation of the field logs and include modifications based on
observations and tests of the samples in the laboratory.
As required by the Oklahoma Water Resources Board, any borings deeper than 20 feet, or
borings that encounter groundwater or contaminated materials must be grouted or plugged in
accordance with Oklahoma State statutes. One boring log must also be submitted to the
Oklahoma Water Resources Board for each 10 acres of project site area. Terracon grouted the
borings and submitted a log in order to comply with the Oklahoma Water Resources Board
requirements.
APPENDIX B
LABORATORY TESTING
Geotechnical Engineering Report Proposed Retaining Wall 44ARW-1 ■ Oklahoma City, Oklahoma May 8, 2014 ■ Terracon Project No. 03145071
Responsive ■ Resourceful ■ Reliable Exhibit B-1
Laboratory Testing
Samples retrieved during the field exploration were taken to the laboratory for further
observation by the project geotechnical engineer and were classified in accordance with the
Unified Soil Classification System (USCS) described in Appendix C. Samples of bedrock were
classified in accordance with the general notes for Sedimentary Rock Classification. At that
time, the field descriptions were confirmed or modified as necessary and an applicable
laboratory testing program was formulated to determine engineering properties of the
subsurface materials.
Laboratory tests were conducted on selected soil and bedrock samples and the test results are
presented in this appendix. The laboratory test results were used for the geotechnical
engineering analyses, and the development of foundation and earthwork recommendations.
Laboratory tests were performed in general accordance with the applicable ASTM, local or other
accepted standards.
Selected soil and bedrock samples obtained from the site were tested for the following
engineering properties:
In-situ Water Content
Atterberg Limits
Sieve Analysis
APPENDIX C
SUPPORTING DOCUMENTS
01 - 1011 - 30
> 30
RELATIVE PROPORTIONS OF FINES
Descriptive Term(s)of other constituents
Percent ofDry Weight
Hand Penetrometer
Torvane
Standard PenetrationTest (blows per foot)
Photo-Ionization Detector
Organic Vapor Analyzer
Texas Cone Penetrometer
TraceWithModifier
Water Level Aftera Specified Period of Time
GRAIN SIZE TERMINOLOGYRELATIVE PROPORTIONS OF SAND AND GRAVEL
TraceWithModifier
Standard Penetration orN-Value
Blows/Ft.
Descriptive Term(Consistency)
Loose
Very Stiff
Exhibit C-1
Standard Penetration orN-Value
Blows/Ft.
Ring SamplerBlows/Ft.
Ring SamplerBlows/Ft.
Medium Dense
Dense
Very Dense
0 - 1 < 3
4 - 9 2 - 4 3 - 4
Medium-Stiff 5 - 9
30 - 50
WA
TE
R L
EV
EL
Auger
Shelby Tube
Grab Sample
FIE
LD
TE
ST
S
DESCRIPTION OF SYMBOLS AND ABBREVIATIONS
Descriptive Term(Density)
Non-plasticLowMediumHigh
BouldersCobblesGravelSandSilt or Clay
10 - 18
> 50 15 - 30 19 - 42
> 30 > 42
_
Water levels indicated on the soil boringlogs are the levels measured in theborehole at the times indicated.Groundwater level variations will occurover time. In low permeability soils,accurate determination of groundwaterlevels is not possible with short termwater level observations.
CONSISTENCY OF FINE-GRAINED SOILS
(50% or more passing the No. 200 sieve.)Consistency determined by laboratory shear strength testing, field
visual-manual procedures or standard penetration resistance
DESCRIPTIVE SOIL CLASSIFICATION
> 8,000
Unless otherwise noted, Latitude and Longitude are approximately determined using a hand-held GPS device. The accuracyof such devices is variable. Surface elevation data annotated with +/- indicates that no actual topographical survey wasconducted to confirm the surface elevation. Instead, the surface elevation was approximately determined from topographicmaps of the area.
Soil classification is based on the Unified Soil Classification System. Coarse Grained Soils have more than 50% of their dryweight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils haveless than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, andsilts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may beadded according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are definedon the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
Plasticity Index
8 - 15
Split Spoon
Rock Core
PLASTICITY DESCRIPTION
Term
< 1515 - 29> 30
Descriptive Term(s)of other constituents
Water InitiallyEncountered
Water Level After aSpecified Period of Time
Major Componentof Sample
Percent ofDry Weight
(More than 50% retained on No. 200 sieve.)Density determined by Standard Penetration Resistance
Includes gravels, sands and silts.
Hard
Very Loose 0 - 3 0 - 6 Very Soft
7 - 18 Soft
10 - 29 19 - 58
59 - 98 Stiff
less than 500
500 to 1,000
1,000 to 2,000
2,000 to 4,000
4,000 to 8,000> 99
LOCATION AND ELEVATION NOTES
SA
MP
LIN
G
< 55 - 12> 12
No Recovery
RELATIVE DENSITY OF COARSE-GRAINED SOILS
Particle Size
Over 12 in. (300 mm)12 in. to 3 in. (300mm to 75mm)3 in. to #4 sieve (75mm to 4.75 mm)#4 to #200 sieve (4.75mm to 0.075mmPassing #200 sieve (0.075mm)
ST
RE
NG
TH
TE
RM
S Unconfined CompressiveStrength, Qu, psf
4 - 8
GENERAL NOTES
Texas Cone
(HP)
(T)
(b/f)
(PID)
(OVA)
(TCP)
Pressure Meter
Exhibit C-2
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A Soil Classification
Group Symbol
Group Name B
Coarse Grained Soils: More than 50% retained on No. 200 sieve
Gravels: More than 50% of coarse fraction retained on No. 4 sieve
Clean Gravels: Less than 5% fines C
Cu 4 and 1 Cc 3 E GW Well-graded gravel F
Cu 4 and/or 1 Cc 3 E GP Poorly graded gravel F
Gravels with Fines: More than 12% fines C
Fines classify as ML or MH GM Silty gravel F,G,H
Fines classify as CL or CH GC Clayey gravel F,G,H
Sands: 50% or more of coarse fraction passes No. 4 sieve
Clean Sands: Less than 5% fines D
Cu 6 and 1 Cc 3 E SW Well-graded sand I
Cu 6 and/or 1 Cc 3 E SP Poorly graded sand I
Sands with Fines: More than 12% fines D
Fines classify as ML or MH SM Silty sand G,H,I
Fines classify as CL or CH SC Clayey sand G,H,I
Fine-Grained Soils: 50% or more passes the No. 200 sieve
Silts and Clays: Liquid limit less than 50
Inorganic: PI 7 and plots on or above “A” line J CL Lean clay K,L,M
PI 4 or plots below “A” line J ML Silt K,L,M
Organic: Liquid limit - oven dried
0.75 OL Organic clay K,L,M,N
Liquid limit - not dried Organic silt K,L,M,O
Silts and Clays: Liquid limit 50 or more
Inorganic: PI plots on or above “A” line CH Fat clay K,L,M
PI plots below “A” line MH Elastic Silt K,L,M
Organic: Liquid limit - oven dried
0.75 OH Organic clay K,L,M,P
Liquid limit - not dried Organic silt K,L,M,Q
Highly organic soils: Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-inch (75-mm) sieve B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name. C Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well-graded sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
6010
2
30
DxD
)(D
F If soil contains 15% sand, add “with sand” to group name. G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
H If fines are organic, add “with organic fines” to group name. I If soil contains 15% gravel, add “with gravel” to group name. J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay. K If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,”
whichever is predominant. L If soil contains 30% plus No. 200 predominantly sand, add “sandy” to
group name. M If soil contains 30% plus No. 200, predominantly gravel, add
“gravelly” to group name. N PI 4 and plots on or above “A” line. O PI 4 or plots below “A” line. P PI plots on or above “A” line. Q PI plots below “A” line.